Professional Documents
Culture Documents
Paralleling Operations / Synchronizations:-: Theory, Practices and Improvements
Paralleling Operations / Synchronizations:-: Theory, Practices and Improvements
Topics
• What is Synchronizing
• Types of Switching Operation
• Types of Synchronizing
• Concept of Slip frequency and Advance angle
• Load pick-up and Governor droop Characteristics
• Synchronizing methods
• Generator Synchronizing
• General criteria for Generator Synchronisation
• Manual Synchronizing
• Components used for Synchronisation
• Automatic Synchronizing
• Choice of Synchronization
( cont..)
1
Topics (cont…
(cont…)
THEME of Presentation
2
What is Synchronising ?
Overall operation of ensuring that the two power systems to
be interconnected THROUGH a Circuit Breaker.
3
Types of Synchronisation
1. System synchronising:
When two different parts of a system are connected together
(i.e. both Voltage Magnitude, Phase and Frequency cannot
be controlled like generator circuits)
For example Closing of a Bus coupler CB fed by two
Transformer feeders, the voltage magnitude can only be
varied through Tap changing mechanism
2. Generator synchronizing
Generator is connected to a Grid. The voltage magnitude,
Phase and frequency of the generator supply can be varied.
Synchronising methods
1) Manual synchronising
It is performed by the operator using following synchronizing
devices. This is generally used for both Generator
synchronisation and System synchronisation
• Synchroscope
• Check Synchronising Relay
• DV, DF Meters, Guard Relay
2) Automatic synchronising
It is performed through “Automatic Synchronising Relay”.
This provides closed loop control for adjusting Speed & Voltage
of the Generator during synchronization. This is used for
Generator synchronisation
4
Slip Frequency:
Difference between the incoming voltage and the running voltage
frequency is called Slip frequency. It is the measure of the rate
rate of
change of phase
Say (for 50Hz System)
12
Time period of Slip cycle:
5
Advance angle:
The angle in advance of the phase coincidence at the instant when
when the
switch closing impulse is generated
Aa = fs X 360 º X tc
Where, tc = Closing time of CB (0.15 sec)
5.40º electrical
= 5.40º
6° 6°
9 3
Load Pick-Up
% Slip Frequency ( fs )
pick-up ( lp )=
% load pick- X 100
% Speed droop ( nd )
Where, %fs = slip frequency
X 100
system frequency
No load Speed – Full load Speed
% Speed droop = X 100
No load Speed
% ( lp ) X % (nd) System frequency
Slip frequency = X
100 100
6
Criteria for Generator Synchronising
Generator synchronising is of two methods:
1) Super synchronously synchronising, with the incoming
frequency higher than the running frequency
2) Sub synchronously synchronising, with the incoming
frequency lower than the running frequency
8° (elec)
Phase error 8° (elec) 8° (elec)
7
Manual Synchronising for Generator
Synchronisation
To synchronize generator to a Grid the following steps shall be
adopted.
1. Voltage difference is brought within prescribed limits by
adjusting the excitation
8
Automatic Synchronising for Generator
Synchronisation
• Automatic synchronising relays monitor the voltages and the
frequencies of the incoming and the running supplies.
• Burdens
The total burden connected to the secondary of winding shall be
within 25% to 100% of rated burden
• Lead Resistance
The Cable Lead interconnecting VT and Synchronising panel
should not make any significant voltage drop.
9
Mechanism of Wrong Synchronisation in
Generator System
• To Synchronize a Generator with GRID,a load pick-up of 1% -
5% shall be considered.
• This results into a Slip frequency (i.e. fs = 0)
180°
180° : Due to interchange of R & Y at PT secondary
Phase – Phase method: Wiring
60°
60° : When R&Y & R&B of I/C & Running circuits
are compared at synchroscope / synchronising
relay
120°
120° : When R&Y & Y&B of I/C & Running circuits
are compared at synchroscope / synchronising
relay
150°
150° : When R&Y & B&R of I/C & Running circuits
are compared at synchroscope / synchronising
relay
10
Effect of Faulty Synchronising on
Generators
The effect of the disturbance on an turbine generator
1. Stator end windings, being the weakest part of the stator,
may distort and would damage the end insulation
2. Torsional oscillations stress the shaft system and in particular
the shaft couplings
3. The No.of force reversals is more important in determining the
failure of alternator windings
4. Even Protective Relay (50) picking-up instantaneously (20
msec) and Tripping the CB (40 msec) cannot protect the
Generator from the effect of Faulty Synchronisation as first two
cycle is sufficient enough to cause the damage.
5. Differential Protective Relays will sense only after Fault is
established by the Generator after damaging the winding.
11
Short fall in the Conventional Synchronising
Scheme
1. Basically Unsecured due to highly person dependent.
12
Conventional Scheme
Improvement Suggested
• TBs associated with VT signal for Synchronising circuits at
all locations / Tapping points shall be COLORED type and
it shall be SEALABLE.
• Terminals of Synchronising Instruments at the Respective
panels shall be of SEALABLE type.
• Connection from VT to Synchronising circuit shall be by
cable as DIRECT as possible.
• Connection from VT to Synchronising circuit shall be by
cable as DUPLICATED (i.e.redundancy).
• Auxiliary Synchronising panel with 3# incandescent lamps
and Voltage balance Relay
• Lamps are configured in Bright / Dark Lamp methods.
13
Improvement Suggested
THANK YOU
14