Professional Documents
Culture Documents
net/publication/273749544
CITATIONS READS
7 2,552
3 authors, including:
Some of the authors of this publication are also working on these related projects:
Modelización del Proceso Biológico de Biorreactores de Membrana Sumergida Aplicados a la Depuración de Aguas Residuales Urbanas View project
Estudio de Tecnologías Avanzadas para la Eliminación de Nutrientes y Xenobióticos en el Tratamiento de Aguas Residuales. View project
All content following this page was uploaded by Gloria Fernandez Alvarez on 16 May 2017.
Abstract: Aeration energy demand represents 45 to 80% of the total energy consumption of a wastewater treatment plant (WWTP).
In membrane bioreactor (MBR) technology, biological aeration requirements are higher than in conventional activated sludge (CAS) because
the transfer efficiency is lower. The evaluation of aeration transfer efficiency is imperative in order to find energy-saving opportunities and
to make MBR cost effective in comparison to CAS. The effect of increasing the reactor depth was revised through the study of different
scenarios from 3 to 9 m. Afterwards, the overall costs considering both capital and operating costs were studied. The results of this work
indicate that air consumption is reduced on average by 9.1% per meter increased. This decrease affects the aeration system and represents
capital savings in aeration equipment of 52%. Moreover, blower energy consumption shows a reduction of approximately 5% per meter
increased. However, regarding civil work, an increase in reactor depth implies an increase of 21% in the constructions costs, showing an
optimum depth of 5 m. When considering global costs, this optimum moves to 6.5 m, at which the total reduction is about 42%. From here the
tendency is to stay similar, so a further increase in reactor depth does not compensate for the increase in civil work costs, even if it leads to
lower operational costs. DOI: 10.1061/(ASCE)EE.1943-7870.0000829. © 2014 American Society of Civil Engineers.
Author keywords: Cost optimization; Membrane bioreactor (MBR); Oxygen transfer efficiency; Reactor depth; Standard oxygen transfer
efficiency (SOTE).
0.6 Tmin
Tmax
0.5
0.4
α .β.θ
0.3
0.2
0.1
0
0 2 4 6 8 10
Reactor depth,m
%sSOTE, %/m
Air compressors (%) 43.23 47.71 33.43
%SOTE
4
30 Total CAPEX (k€=year) 2,663.32 1,723.97 1,476.31
%SOTE
3 Maintenance (%) 3.22 3.22 2.86
20 Fixed power (%) 1.43 2.14 2.81
2 Depreciation civil work (%) 18.89 17.41 26.19
Tmean
10 1
Depreciation equipment (%) 49.48 50.06 39.87
Downloaded from ascelibrary.org by UGR/E.U ARQUITECTURA TECNICA on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.
Tmax
Tmin Energy consumption (%) 26.97 27.17 28.28
0 0 Total OPEX 344.22 230.28 175.20
0 1 2 3 4 5 6 7 8 9 10
Reactor depth, m
Capital Costs
In terms of the cost, the first factor to be analyzed was the capital
costs. As stated previously when analyzing CAPEX, the capital
costs of the equipment have been considered for both the air dif-
fusers and the air compressors. The capital costs of the civil work
were also included (Table 4).
Fig. 5 shows the evolution of the different contributions to total
costs as a function of the reactor depth. At higher reactor depths, the
Fig. 6. Evolution of capital costs versus reactor depth
capital cost for civil work grew by 21%, while the capital costs for
Qair, Nm3/h
4.0 1,937.50 13,933.09 3,990 5
5.0 1,550.00 10,812.89 3,128 5 2
6.0 1,291.67 8,748.92 2,496 5
7.0 1,107.14 7,287.32 2,184 3
8.0 968.75 6,201.30 1,872 3 1
9.0 861.11 5,364.94 1,632 3
Downloaded from ascelibrary.org by UGR/E.U ARQUITECTURA TECNICA on 05/16/17. Copyright ASCE. For personal use only; all rights reserved.
0
0 2 4 6 8 10
(Collado et al. 2012; Pöpel and Wagner 1994), as it is the depth at Reactor depth, m
which the civil work is cheapest. At this depth, the constructive
process is optimized because the quantity of formwork needed Fig. 7. Evolution of the AFR versus reactor depth
is minimal when using up-to-date commercial products. Increasing
the depth by 0.5 m means a change in the thickness of the walls,
which has an effect on the civil work costs. Due to a change in the
formwork, the capital costs for civil work decreased again at 6.5 m.
Aeration power supply
When the total capital costs were considered, this point was the 0.04
Conclusions