You are on page 1of 12

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/245294602

Reliability Analysis and Updating of Excavation-Induced Ground Settlement for


Building Serviceability Assessment

Article  in  Journal of Geotechnical and Geoenvironmental Engineering · October 2008


DOI: 10.1061/(ASCE)1090-0241(2008)134:10(1448)

CITATIONS READS

80 576

4 authors, including:

Evan C. L. Hsiao C.Hsein Juang


geoLyteca LLC, United States Clemson University
9 PUBLICATIONS   387 CITATIONS    282 PUBLICATIONS   8,151 CITATIONS   

SEE PROFILE SEE PROFILE

Gordon Tung-Chin Kung


National Cheng Kung University
19 PUBLICATIONS   788 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Multiscale regional liquefaction hazard mapping View project

All content following this page was uploaded by Gordon Tung-Chin Kung on 09 April 2014.

The user has requested enhancement of the downloaded file.


Reliability Analysis and Updating of Excavation-Induced
Ground Settlement for Building Serviceability Assessment
Evan C. L. Hsiao1; Matt Schuster2; C. Hsein Juang, F.ASCE3; and Gordon T. C. Kung4

Abstract: In this paper, the excavation-induced settlement determined by the KJHH model, a recently developed semiempirical model,
is used to assess the serviceability reliability of adjacent buildings. The calculated settlement, considered as the load in the context of
reliability analyses in this paper, is compared with a tolerable settlement, considered as the resistance herein. The reliability of the adjacent
building against “damage” 共defined herein as the violation of serviceability requirements such as having intolerable settlement兲 is first
analyzed and the probability of exceedance 共i.e., exceeding the tolerable settlement兲 is calculated. Furthermore, as the excavation
proceeds, observed settlement at the current excavation stage is used to update the prediction of settlement at subsequent stages, and the
probability of exceedance is updated accordingly.
DOI: 10.1061/共ASCE兲1090-0241共2008兲134:10共1448兲
CE Database subject headings: Reliability; Probability; Bayesian analysis; Excavation; Settlement; Serviceability; Damage.

Introduction “predicted settlement” or “prediction” is referred to an engineer-


ing calculation of settlement. Because the analyses performed
Construction of a braced excavation system inevitably causes herein all dealt with case histories 共“after-the-event” calculations兲,
wall deflections and ground movements, which can have detri- the term “prediction” used in this paper does not meet the strict
mental effects on adjacent buildings. In practice, the excavation- definitions given by Lambe 共1973兲. Nevertheless, the term “pre-
induced maximum ground surface settlement 共␦vm兲, and dicted settlement” is used herein as it goes well with the focus of
particularly, angular distortion 共␻兲, are often used as performance the paper, namely, the updating of settlement “prediction.”
indicators for estimating the damage potential of buildings adja- In this paper, a newly developed model for the excavation-
cent to an excavation. In the context of this paper, the term “dam- induced wall deflection and ground movements, called the KJHH
age” is synonymous with the state of a building where the model 共Kung et al. 2007b兲, is adopted for developing the
violation of serviceability requirements occurs. The serviceability reliability-based approach. For simplicity, the maximum ground
requirements are usually expressed in terms of some threshold surface settlement ␦vm is selected as an indicator to assess the
values 共or tolerable limits兲 of ground surface settlement or angu- excavation-induced building damage potential, although more ad-
lar distortion. In a deterministic approach, serviceability of a vanced evaluation criteria 共i.e., Boone 1996; Son and Cording
building adjacent to a braced excavation can be assumed if the 2005; and Finno et al. 2005兲 are available. The tolerable limits of
“predicted” ␦vm and/or ␻ are less than the specified tolerable lim- ␦vm, such as those proposed by Wahls 共1994兲, Simons and Men-
its. In reality, such tolerable limits and “predicted” ␦vm and ␻ are zies 共2000兲, and Zhang and Ng 共2005兲, are used as the evaluation
random variables in light of the presence of uncertainty. There- criterion. In the context of serviceability reliability of the build-
fore, the development of a reliability-based approach for estimat- ings adjacent to an excavation, the calculated ␦vm is the load and
ing the serviceability of a building adjacent to a braced the tolerable limit of ␦vm is the resistance. In a real-world prob-
excavation is desirable. lem, either or both the load and the resistance can be treated as a
It should be noted that in the context of this paper, the term random variable.
It is noted that the published tolerable settlements 共Skempton
1 and MacDonald 1956; Wahls 1994; Simons and Menzies 2000兲
Staff Engineer, Golder Associates Inc., Irvine, CA 92602. E-mail:
ehsiao@golder.com were primarily derived based on a limiting angular distortion of
2
Research Assistant, Dept. of Civil Engineering, Clemson Univ., 1 / 300 or equivalence. Thus, use of the maximum ground settle-
Clemson, SC 29634. E-mail: mschust@clemson.edu ment as an indicator for assessing the excavation-induced build-
3
Professor, Dept. of Civil Engineering, Clemson Univ., Clemson, ing damage potential is deemed acceptable as the “first-order”
SC 29634 共corresponding author兲. E-mail: hsein@clemson.edu; formerly, approximation. Total settlement is much easier to measure in the
Chair Professor, Dept. of Civil Engineering, National Central Univ., field than its more sophisticated counterparts such as angular dis-
Jungli, Taiwan. tortion and lateral strain; thus, it has the advantage of being easily
4
Assistant Research Fellow, Sustainable Environment Research adaptable into a Bayesian updating framework that utilizes
Center, National Cheng Kung Univ., Taiwan 70944. E-mail: tckung@ observations/measurements in a staged construction. It must be
mail.ncku.edu.tw
emphasized, however, that other more accurate indicators such as
Note. Discussion open until March 1, 2009. Separate discussions must
be submitted for individual papers. The manuscript for this paper was angular distortion and lateral strain should be adopted for assess-
submitted for review and possible publication on April 4, 2007; approved ing building damage potential within the Bayesian updating
on February 29, 2008. This paper is part of the Journal of Geotechnical framework if they can be measured and judged in the field.
and Geoenvironmental Engineering, Vol. 134, No. 10, October 1, 2008. In the reliability-based approach, the observed settlements at
©ASCE, ISSN 1090-0241/2008/10-1448–1458/$25.00. various stages of excavation may be used to update the KJHH

1448 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008


Table 1. Coefficients for Linear Transformation of Five Variables
Linear transformation equation
X = t共x兲 = b1x2 + b2x + b3
Variables x Applicable range b1 b2 b3
He 共m兲 0–30 −0.4 24 −50
ln共EI / ␥whavg
4
兲 艌0 11.5 −295 2,000
B / 2 共m兲 0 艋 B 艋 100 −0.04 4 90
su / ␴⬘v 0.2–0.4 3,225 −2,882 730
Ei / ␴⬘v 200–1,200 0.00041 −1 500

model for the predictions of settlement at the subsequent stages. strain triaxial test 共at a strain level of less than 10−5兲. The reader
Updating model parameters, such as parameters of a soil model in is referred to Kung et al. 共2007a兲 for discussion of the character-
a finite-element solution, based on the field observations is often istics of excavation-induced settlement as influenced by the small
adopted during the construction phase of a deep excavation strain soil behavior. The maximum lateral wall deflection ␦hm is
project 共Ou and Tang 1994; Calvello and Finno 2004; Hashash calculated as 共Kung et al. 2007b兲
et al. 2004; Finno and Calvello 2005兲. This approach of combin-
ing the numerical capability of the finite-element method with the ␦hm = a0 + a1X1 + a2X2 + a3X3 + a4X4 + a5X5
observational method has been used successfully in many exca-
vation projects. In this study, however, updating the KJHH model + a 6X 1X 2 + a 7X 1X 3 + a 8X 1X 5 共1兲
during construction is carried out with a different approach. Here,
the KJHH model is updated through the change in its model bias where X1 = t共He兲; X2 = t关ln共EI / ␥wh4avg兲兴; X3 = t共B / 2兲; X4 = t共su / ␴⬘v兲;
factor based on the recognition that the observed ground re- and X5 = t共Ei / ␴⬘v兲, and t = transformation function defined in
sponses reflect the effect of all factors in the field, not just soil Eq. 共2兲. The coefficients are as follows: a0 = −13.41973,
parameters in the model. a1 = −0.49351, a2 = −0.09872, a3 = 0.06025, a4 = 0.23766,
The reliability of the building against damage at each stage of a5 = −0.15406, a6 = 0.00093, a7 = 0.00285, and a8 = 0.00198. It is
excavation is first evaluated prior to excavation. As the excava- noted that variables Xi 共i = 1 , 5兲 are the transformed variables of
tion proceeds, the bias factor of the KJHH model is recalibrated at the five basic input variables defined as 共Kung et al. 2007b兲
the end of each stage and prior to the next stage of excavation
based on the observed settlements from the current stage. The X = t共x兲 = b1x2 + b2x + b3 共2兲
serviceability reliability of the building in subsequent stages can
then be reevaluated with the updated bias factor of the KJHH where x = each of the input variables 共He, ln共EI / ␥wh4avg兲, B / 2,
model. This serviceability reliability analysis procedure first in- su / ␴⬘v, and Ei / ␴⬘v兲; X = transformed variable; and the coefficients,
troduced by Hsiao et al. 共2007兲 is refined and extended herein. b1, b2, and b3 are listed in Table 1.
Kung et al. 共2007b兲 found that the deformation ratio R, the
ratio of the maximum ground settlement over the maximum wall
KJHH Model: Overview deflection, in clay-dominant sites is mainly influenced by three
parameters, ⌺Hclay / Hwall, su / ␴⬘v, and Ei / 1,000␴⬘v. The parameter
In general, an evaluation of excavation-induced wall and ground ⌺Hclay / Hwall is illustrated in Fig. 1. The deformation ratio R is
movements using empirical methods may proceed as follows: determined as
1. Determine the maximum lateral wall deflection ␦hm;
2. Estimate the deformation ratio R共=␦vm / ␦hm兲; and R = c 0 + c 1Y 1 + c 2Y 2 + c 3Y 3 + c 4Y 1Y 2 + c 5Y 1Y 3
3. Calculate the maximum surface settlement ␦vm.
The KJHH model 共Kung et al. 2007b兲 follows this general ap- + c6Y 2Y 3 + c7Y 33 + c8Y 1Y 2Y 3 共3兲
proach to predict the wall deflection and ground movement in an
excavation in soft to medium clays. For simplicity, the effect of where Y 1 = ⌺Hclay / Hwall, Y 2 = su / ␴⬘v, Y 3 = Ei / 1,000␴⬘v, and the
the presence of hard stratum is excluded in this study, although coefficients for Eq. 共3兲 determined through the least-square
the presence of hard stratum might restrain the displacement of regression, are as follows: c0 = 4.55622, c1 = −3.40151, c2 =
soil beneath and around the bottom of excavation as indicated −7.37697, c3 = −4.99407, c4 = 7.14106, c5 = 4.60055, c6 = 8.74863,
in Kung et al. 共2007b兲. Thus, five basic parameters are consi- c7 = 0.38092, and c8 = −10.58958.
dered essential for predicting the maximum wall deflection 共␦hm兲 The excavation-induced maximum settlement ␦vm can be ob-
caused by excavation in soft to medium clays. These parameters tained by multiplying ␦hm by R. The uncertainty of the entire
include the excavation depth 共He兲, the excavation width 共B兲, the model for ␦vm was previously characterized with a model bias
system stiffness 关EI / ␥wh4avg as defined in Clough and O’Rourke factor that follows a normal distribution with a mean of 1.0 and a
共1990兲, where E = Young’s modulus of wall material; I = moment standard deviation of 0.34 共Kung et al. 2007b兲. Including the bias
of inertia of the wall section; ␥w = unit weight of water; and factor, this model for maximum ground settlement ␦vm can be
havg = average support spacing兴, the ratio of shear strength over expressed as
vertical effective stress 共su / ␴⬘v兲, and the ratio of initial Young’s
tangent modulus over vertical effective stress 共Ei / ␴⬘v兲. It should ␦vm = BF · R · ␦hm 共4兲
be noted that the initial tangent modulus, Ei, is similar to that used
in the hyperbolic model 共Duncan and Chang 1970兲. However, in where BF= model bias factor. Because of the variation of all input
the KJHH model, this modulus should be measured with a small variables, the calculated ␦vm is a random variable.

JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008 / 1449


1974; Ang and Tang 1984兲 and the probability of exceedance
共i.e., the probability of exceeding a tolerable settlement兲 in
each stage of excavation.

Example Application
The Taipei National Enterprise Center 共TNEC兲 case 共Ou et al.
1998兲 is used as an example to illustrate the reliability assessment
of serviceability of an adjacent building. The TNEC is located
near the center of the Taipei basin. In general, the subsurface
deposit at the Taipei basin is represented by a thick alluvium
formation 共Sungshan formation兲 overlain by a gravel formation
共Chingmei formation兲. Typically, the Sungshan formation has six
alternating layers of silty sand and silty clay, but it mainly con-
sists of soft to medium, slightly overconsolidated clay with low
plasticity, and ⌺Hclay / Hwall is estimated to be 0.87. In this case,
the hard stratum is found at 46 m deep from the ground surface,
and thus it has negligible effect on ground deformation 共Kung
et al. 2007b兲. The excavation width is approximately 41.2 m; fur-
ther, a diaphragm wall, 0.9 m thick and 35 m deep, is employed
as the earth-retaining structure. As shown in Table 2, the excava-
tion was completed in seven stages to a maximum depth of
19.7 m. Also included in Table 2 is the system stiffness at differ-
Fig. 1. Determination of normalized clay layer thickness
ent stages of excavation. For the convenience of illustration, all
共兺Hclay / Hwall兲 for clay dominant site
input variables in the KJHH model are assumed to follow a nor-
mal distribution. A normal distribution requires the knowledge of
Reliability Analysis of Ground Surface Settlement the mean and standard deviation. For the TNEC case history, the
mean values of su / ␴⬘v and Ei / su are found to be 0.31 and 2,135,
respectively. The COV of both su / ␴⬘v and Ei / su are found to be
Analysis Steps
0.16 based on the statistical analysis of the data obtained from
In this study, reliability analysis of excavation-induced ground Kung 共2003兲. The COV of the model BF is 0.34 共Kung et al.
surface settlement for building serviceability assessment is con- 2007b兲. The COVs of other nonsoil variables in Eq. 共1兲 are gen-
ducted with the following steps: erally small and assumed herein to be 0.05.
1. Estimate the mean values and coefficients of variation Correlations among variables in the KJHH model are consid-
共COVs兲 for all input variables of the KJHH model. The mean ered in the reliability analysis. Based on statistical analysis of the
value for the nonsoil parameter can be determined from ex- data presented in Kung 共2003兲, the correlation coefficient between
cavation specifications. Unless specified, the COV of the su / ␴⬘v and Ei / ␴⬘v is estimated to be 0.3. As shown in Fig. 2, the
nonsoil parameters is assumed to be 0.05, an assumption that effect of the degree of correlation between su / ␴⬘v and Ei / ␴⬘v on the
is indirectly confirmed with sensitivity analysis presented calculated probability of exceedance is not significant. Other vari-
later. The mean value and COV of the soil parameters can be able pairs are assumed uncorrelated, as there is no evidence to
determined from small-strain triaxial tests 共Kung 2003兲 and suggest otherwise. The random variable which represents model
published literature including Duncan 共2000兲; bias factor, BF, is assumed to be uncorrelated with input variables
2. Calculate the excavation-induced maximum ground settle- in the model. In a recent study by Phoon and Kulhawy 共2005兲, the
ment ␦vm using the KJHH model; model bias factor is found to be weakly or moderately correlated
3. Define the performance function as g共 兲 = ␦lim − ␦vm, where with individual input variables. Further, the assumption of no cor-
␦lim = limiting tolerable settlement 共or tolerable settlement for relation between input variables and the model bias factor yields
short兲 and treated as the resistance, and ␦vm is treated as the an “upper bound” in the calculated probability of exceedance,
load. Thus, g共 兲 艌 0 defines a satisfactory performance re- when compared to those analyses with various degrees of corre-
gion, while g共 兲 ⬍ 0 defines an unsatisfactory performance lation. Thus, the assumption of no correlation is deemed accept-
region; and able in this study.
4. Perform analysis using the first-order reliability method As an example to illustrate the analysis procedure, the toler-
共FORM兲 to obtain the reliability index 共Hasofer and Lind able settlement is first set to be 75 mm as suggested by Skempton

Table 2. Mean Values of Excavation Depths and System Stiffness of TNEC Case History
Excavation sequence 共stage number兲
Factor 3 4 5 6 7
Depth, He 共m兲 8.6 11.8 15.2 17.3 19.7
System stiffness, EI / ␥whavg
4
1,023 966 1,109 1,115 1,294
Note: Mean of other factors required for determining maximum ground surface settlement using KJHH model: B / 2 = 20.6 m, su / ␴⬘v = 0.31 and Ei / ␴⬘v
= 650, 兺HcalyHwall = 0.87, model bias factor=1.0, and tolerable settlement 共␦lim兲 = 75 mm; COVs of He, EI / ␥whavg 4
, B / 2, and 兺Hclay / Hwall = 0.05; COVs of
su / ␴⬘v and Ei / ␴⬘v = 0.16; COV of BF= 0.34; COV of ␦lim = 0.0; and coefficient of correlation of su / ␴⬘v and Ei / ␴⬘v = 0.3.

1450 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008


Fig. 2. Probabilities of exceedance for various degree of correlation Fig. 3. Computed reliability indices at various excavation depths
between su / ␴⬘v and Ei / ␴⬘v

bution of the input variables are studied. Results of these analyses


and MacDonald 共1956兲, and Simons and Menzies 共2000兲. Other are presented herein. Although not presented herein, these sensi-
criteria may be used, including those by Burland and Worth tivity analyses were also performed using another quality case
共1975兲, Boscardin and Cording 共1989兲, Wahls 共1994兲, Boone history, the Formosa case 共Ou et al. 1993兲, and similar results
共1996兲, and Zhang and Ng 共2005兲. It should be stressed that the were obtained.
tolerable settlement criterion employed here is for general condi-
tions. For special cases, other criteria of tolerable settlement may
be more appropriate. Furthermore, the tolerable settlements rec- Effect of Magnitude and Variation of Limiting Tolerable
ommended for practice are often applied with an additional factor Settlement
of safety in a conventional deterministic approach 共Simons and To determine the effect of the tolerable settlement on the results
Menzies 2000兲. Thus, the criterion of 75 mm for the reliability of reliability analysis, the TNEC case history is reanalyzed using
analysis herein may be considered as being equivalent to a toler- different fixed values of tolerable settlement ranging from
able settlement criterion of 50 mm applied with a factor of safety 60 to 160 mm. As shown in Fig. 4, the reliability index increases
of 1.5. and the probability of exceedance decreases for the same loading
It should be noted that in principle, the total amount of allow- as the tolerable settlement increases. The results indicate that the
able settlement of the buildings adjacent to an excavation should calculated probability of exceedance depends on the choice of
remain the same before and after the excavation. Because the tolerable settlement.
buildings have already experienced settlement before the excava-
tion, the allowable settlement of these buildings caused by the
excavation should be smaller than the total amount specified in
the applicable building codes. However, many practitioners argue
that although some settlement of the buildings will occur due to
self-weights, the redistribution of the stresses in the structural
members over time will increase the capability of the buildings to
sustain additional settlement without serviceability problems.
Thus, the total amount of allowable settlement specified in the
building codes is considered applicable to assessing the service-
ability of buildings adjacent to an excavation.
With the knowledge of the statistical distributions of input
variables and the tolerable settlement, the reliability analyses can
be conducted using FORM. It is noted that the FORM analysis
can be easily implemented in a spreadsheet-based approach 共e.g.,
Low and Tang 1997; Phoon 2004兲. In these analyses, the adjacent
building is assumed to be located where the maximum
excavation-induced settlement occurred. As shown in Fig. 3, the
reliability index 关calculated based on the performance function,
g共 兲 = ␦lim − ␦vm兴 decreases as the excavation proceeds 共i.e., the ex-
cavation depth increases兲, indicating that adjacent buildings are
more likely to undergo settlement greater than the tolerable settle-
ment at the later stage of excavation.

Sensitivity Analyses

A series of sensitivity analyses are performed using the TNEC


case history to study the effect of a number of assumptions
made during the reliability analysis. Particularly, the tolerable Fig. 4. Effect of various tolerable settlements at final depth of
settlement, the COV of su / ␴⬘v, and Ei / ␴⬘v, and the assumed distri- excavation on: 共a兲 reliability index; 共b兲 probability of exceedance

JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008 / 1451


Fig. 5. Gamma sensitivity index ␥i: 共a兲 tolerable settlement Fig. 6. Variation rate index at various COVs of su / ␴⬘v 共tolerable
= 75 mm; 共b兲 tolerable settlement= 123 mm with standard deviation settlement= 75 mm兲
␴ = 73 mm

Fig. 5共a兲 displays the gamma sensitivity indices for different


input variables when tolerable settlement is assumed to be fixed.
Since settlement is most likely an uncertain variable, a subse- Fig. 5共b兲, on the other hand, illustrates the gamma sensitivity
quent analysis is performed to examine the effect of this uncer- indices for different input variables when the tolerable settlement
tainty on the results of the reliability analysis. The same is assumed to be a random variable as suggested by Zhang and
conditions are employed in this analysis as those used previously Ng 共2005兲. Additionally, a number of other analyses were per-
except that the tolerable settlement is assumed to have a standard formed with different values of tolerable settlement and different
deviation of 73 mm as suggested by Zhang and Ng 共2005兲. Simi- levels of uncertainty. For example, one case involved a mean
lar to the results when the tolerable settlement was a fixed value, tolerable settlement of 75 mm with a standard deviation of
the reliability index increases and the probability of exceedance 45 mm. In all cases, similar results were observed. The analyses
decreases as the tolerable settlement increases as shown in Fig. 4. indicate the high importance of the model BF as the calculated
However, Fig. 4 also illustrates that for the range of tolerable reliability index is most sensitive to this input. Furthermore, the
settlements studied, the reliability index is generally lower and calculated reliability index is also shown to be sensitive, to a
the probability of exceedance is generally higher when the toler- slightly lesser degree, to the normalized shear strength 共su / ␴⬘v兲
able settlement is assumed to be a random variable. This result
and normalized Young’s modulus 共Ei / ␴⬘v兲, and to be insensitive to
demonstrates that the uncertainty in the tolerable settlement has a
excavation depth 共He兲, excavation width 共B / 2兲, system stiffness
significant effect and needs to be properly characterized.
共EI / ␥wh4avg兲, and 兺Hclay / Hwall. These findings are consistent with
the assumptions made previously based on different sensitivity
Relative Importance of Input Variables to Calculated analyses that the variations in excavation depth 共He兲, excavation
Reliability Index width 共B / 2兲, system stiffness 共EI / ␥wh4avg兲, and 兺Hclay / Hwall have
little effect on the reliability analysis.
The sensitivity of the reliability index to a given input variable is The above findings regarding the importance of input variables
also studied for the two scenarios where the tolerable settlement also support the conventional approach in the back-analysis of
is assumed to be a fixed and an uncertain 共random兲 variable. This excavation-induced wall and ground movements, in which only
sensitivity may be expressed in terms of the gamma sensitivity soil parameters are “updated” in an effort to match the “pre-
index 共Der Kiureghian and Ke 1985兲 defined as follows: dicted” responses with the “measured” responses. Other than the
model bias factor, only the variations in the soil parameters are
兩␣Jy,xD兩 found to have significant effects on the calculated reliability
␥i = 共5兲
储␣Jy,xD储 index.

where ␥i = gamma sensitivity index for input variable xi in Effect of Variation in Soil Properties
the KJHH model 共x1 = He, x2 = EI / ␥wh4avg, x3 = B / 2, x4 = su / ␴⬘v,
x5 = Ei / ␴⬘v, x6 = 兺Hclay / Hwall, and x7 = BF兲; ␣ = directional cosine; Since the reliability index is found to be sensitive to soil strength
Jy,x = Jacobian matrix with element of ⳵y / ⳵x; and y = T共x兲 with 共su / ␴⬘v兲 and stiffness 共Ei / ␴⬘v兲, it is important to study the effect of
T共.兲 being an orthogonal transformation function; and finally the variation 共expressed as COV兲 in su / ␴⬘v and Ei / ␴⬘v on the reli-
D = diagonal matrix of standard deviation of each random ability index. Thus, a subsequent study is performed to determine
variable. the effect that the COV of su / ␴⬘v and Ei / ␴⬘v has on the reliability
The gamma sensitivity index can be calculated for each input index. Fig. 6 demonstrates that the gamma sensitivity index for
variable with Eq. 共5兲 after the reliability index is calculated with su / ␴⬘v increases significantly as the COV of su / ␴⬘v increases. Simi-
FORM analysis. It should be noted that the gamma sensitivity larly, Fig. 7 shows that the gamma sensitivity index for Ei / ␴⬘v
index measures the relative contribution of each input variable to increases significantly as the COV of Ei / ␴⬘v increases. This indi-
the calculated reliability index. Therefore, the calculated reliabil- cates that the reliability index becomes increasingly sensitive to
ity index is most sensitive to the input variables with the highest su / ␴⬘v and Ei / ␴⬘v as the COV of su / ␴⬘v and Ei / ␴⬘v increase. As
gamma sensitivity indices. shown in Fig. 6, when the COV of su / ␴⬘v 共or Ei / ␴⬘v in the case of

1452 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008


Fig. 9. Probability of exceedance at various COVs of Ei / ␴⬘v

Fig. 7. Variation rate index at various COVs of Ei / ␴⬘v 共tolerable


settlement= 75 mm兲 except that the COVs of the input variables were assumed to vary
between 10 and 60%. When the COVs of these variables are
relatively low 共⬍20% 兲, the effect of the assumed distribution is
Fig. 7兲 exceeds a certain value, the reliability index becomes negligible 共⬍1 % 兲. When the COVs of these variables become
more sensitive to su / ␴⬘v 共or Ei / ␴⬘v兲 than it is to the model bias greater 共say at the level of 40–60%兲, the difference in the result-
factor. Therefore, it is important to accurately characterize the ing probability of exceedance becomes noticeable 共⬇5 % 兲 but not
COV of su / ␴⬘v and Ei / ␴⬘v. very significant 共⬍10% 兲. Overall, the effect of the assumed dis-
Figs. 8 and 9 illustrate the effect that the COV of su / ␴⬘v and tribution is quite modest 共⬇0 – 5 % 兲.
Ei / ␴⬘v has on the probability of exceedance. Generally, at a pre-
scribed tolerable settlement, the probability of exceedance in-
creases as the COV of su / ␴⬘v or Ei / ␴⬘v increases. However, the Updating Settlement Predictions and Serviceability
difference is less significant in the case of lower prescribed toler- Reliability
able settlement than in the case of higher prescribed tolerable
settlement. Therefore, limiting the variation in the soil properties As an excavation proceeds, the settlement may be observed at
共COV of su / ␴⬘v or Ei / ␴⬘v兲 will lead to a lower probability of ex- various stages of excavation, and thus these observed settlements
ceedance, especially when the prescribed tolerable settlement is at various stages of excavation may be used to update the KJHH
high. At a given COV level, the probability of exceedance de- model for the predictions of settlement at the subsequent stages
creases as the tolerable settlement increases. This trend is more using the Bayesian updating approach 共e.g., Ang and Tang 2006兲.
profound at lower COV levels than at higher COV levels, which Accordingly, the reliability analysis may be repeated or updated
demonstrates that the selection of an appropriate tolerable settle- using the updated settlement prediction.
ment is more important as the variation in the soil properties is As mentioned previously, engineers often adopt the approach
reduced. of combining the numerical capability of the finite-element
method with the observational method in excavation projects.
Effect of Assumed Distribution of Input Random This is usually carried out by updating soil parameters based on
Variables field observations during the construction. The soil parameters are
updated through back-analysis using the finite-element method so
Fig. 10 shows the effect of the assumed distribution 共normal ver-
sus lognormal兲 of input variables, mainly those of the soil
strength and stiffness 共su / ␴⬘v and Ei / ␴⬘v兲, on the probability of
exceedance. The input variables for both the normal and lognor-
mal distribution were determined based on the TNEC case history

Fig. 10. Probabilities of exceedance for various distributions under


Fig. 8. Probability of exceedance at various COVs of su / ␴⬘v assumption of fixed tolerable settlement

JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008 / 1453


Table 3. Mean Values of Excavation Depths and System Stiffness of Formosa Case History
Excavation sequence 共stage number兲
Factor 3 4 5 6 7
Depth, He 共m兲 6.9 10.2 13.2 16.2 18.45
System stiffness, EI / ␥whavg
4
1,757 2,043 1,456 1,367 1,320
Note: Mean of other factors required for determining maximum ground surface settlement using KJHH model: B / 2 = 16.7 m, su / ␴⬘v = 0.30, and Ei / ␴⬘v
= 510, 兺HclayHwall = 0.87, model bias factor=1.0, and tolerable settlement 共␦lim兲 = 75 mm; COVs of He, EI / ␥whavg 4
, B / 2, and 兺Hclay / Hwall = 0.05; COVs of
su / ␴⬘v and Ei / ␴⬘v = 0.16; COV of BF= 0.34; COV of ␦lim = 0.0; and coefficient of correlation of su / ␴⬘v and Ei / ␴⬘v = 0.3.

that the responses of the wall and soil match the field observa- In this paper, the updating of settlement is performed through
tions. In this study, however, the settlement calculated with the an updated model bias factor, as the model bias factor back-
KJHH model is updated through the change in its model bias calculated from the observed settlement reflects the overall effect
factor since the observed ground responses reflect the effect of all of all changes in the ground conditions during the excavation. To
factors in the field, not just soil parameters in the model. Thus, for fully illustrate the capabilities of this updating procedure, the For-
the same excavation case, the variable R and ␦hm in Eq. 共4兲 will mosa case history 共Ou et al. 1993兲 is selected here for application.
not be updated but the variable BF will be updated. Similar to the TNEC case history, the Formosa case involved a
Since the KJHH model is developed on the basis of the exten- seven-stage construction in the Taipei basin. Table 3 summarizes
sive artificial cases and real-world case histories, the model may the details about the Formosa case relevant to the procedure. Ad-
be treated as a global empirical correlation. Thus, the standard ditionally, it is assumed that the building adjacent to the excava-
deviation of the model BF may be attributable to the combined tion is located where the maximum settlement occurs. The
effects of the “within-site” variability and the “cross-site” vari- updating procedure described herein is applicable to other cases,
ability 共e.g., Zhang and Tang 2002兲. The sources of the within-site although the improvement in the updated “predictions” of the
variability 共␴w兲 of the predicted excavation-induced settlement settlement may not be as drastic as the one presented in the fol-
may include: inherent variability of soil properties and the uncer- lowing. After all, the degree of improvement resulting from the
tainty associated with construction effects such as dewatering ac- updating procedure also depends on the accuracy of the prediction
tivity and overexcavation prior to support installation. prior to the excavation, which in turn depends on the accuracy of
Furthermore, the sources of the cross-site variability 共␴o兲 may be the estimated soil parameters employed in the design analysis
generated from the differences in soil and construction details, among many other factors.
and other factors at the different sites. Therefore, the variance of As the excavation proceeds, observed maximum settlements at
the predicted settlement using the KJHH model at a particular site various stages of the Formosa excavation are used to update the
becomes: ␴BF 2
= ␴20 + ␴2w. model BF of the KJHH model using the Bayesian approach. As
noted previously, most site-specific uncertainty such as the varia-
tion of soil properties and construction effects shall be reflected
Bayesian Updating of Predicted Ground Settlement
in the field observations. Therefore, the model BF of the KJHH
and Serviceability Reliability
model at a particular stage of excavation of the Formosa case
In the reliability analysis, it is essential to incorporate the uncer- can be recalibrated by comparing the observed settlement with the
tainty not only in the input variables, but also in the predictive predicted settlement. In addition, in order to carry out Bayesian
model expressed in terms of a model bias factor. To increase the updating analysis, knowledge of prior distribution of the mean
confidence in the reliability assessment of the serviceability of of the model bias factor of the KJHH model first needs to
adjacent buildings, a more precise and accurate model is desir- be obtained. As discussed earlier, the model BF of the KJHH
able. As the excavation proceeds, the site-specific observed settle- model is found by Kung et al. 共2007b兲 to be normally distributed
ments become available. Using the observed settlements, the with a mean of 1.0 共␮BF = 1.0兲 and a standard deviation of 0.34
uncertainty in the predictions could be reduced with a Bayesian 共␴BF = 0.34兲. Thus, prior to excavation, the parameters of the prior
approach. Use of the Bayesian updating techniques in geotechni- distribution of the mean bias factor 共Zhang and Tang 2002兲 can be
cal engineering is of course not new 共e.g., Kay 1976; Baecher and determined with
Rackwitz 1982; Lacasse et al. 1990; Tang et al. 1999; Zhang and
Tang 2002; and Zhang et al. 2004兲. In particular, Zhang et al.
共2004兲 formalized procedures for three levels of uncertainty re- ␮⬘ = ␮BF 共6兲
duction associated with the use of the empirical predictive model
based on regional data and site-specific observations. In this
study, the procedures for Level 3 共Bayesian updating for a spe- ␴⬘ = 冑␴BF
2
− ␴2w 共7兲
cific site using limited observations兲 are employed for updating
the model bias factor of the KJHH model. The model bias factor where ␴w = within-site variability of BF. Based on the observed
represents the uncertainty of a predictive model and thus, ideally, settlements in the various stages of excavation in both the TNEC
it should not depend on the observations. However, the KJHH and Formosa cases, and other local experience in Taipei Basin,
model is a data-driven model, meaning that it is not a theoretical the within-site variability ␴w is estimated to be 0.20. This value is
model but rather, a semi-empirically model developed based on assumed to be a prior knowledge for similar excavations in the
observed data. Thus, the performance of the predictive model Taipei Basin. Now, suppose that at the end of the third stage of
such as the KJHH model could vary as the excavation proceeds excavation, the observed mean of the apparent model bias factor
and the model bias factor is more appropriately referred to herein is BF. Then, according to the Bayesian theory 共e.g., Ang and Tang
as the apparent model bias factor. 2006兲, the updated mean of apparent model bias factor 共␮⬙兲 and

1454 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008


Table 4. Apparent Model Bias Factors Used in Prediction of Formosa Case History
Excavation sequence
Prior to End of End of End of End of
excavation 3rd stage 4th stage 5th stage 6th stage
Mean of model bias factor 1.000 0.791 0.738 0.684 0.656
Standard deviation of model bias factor 0.340 0.257 0.236 0.227 0.221

the updated standard deviation of the apparent model bias factor It should be noted that the settlement readings for the first two
共␴⬙兲 at the end of the third stage can be computed as follows: stages of excavation are not used in this analysis because the
mechanism of the excavation-induced wall deflection and ground
␮⬘␴2w + BF␴⬘2 movement of the first stage, or the first two stages, of excavation
␮⬙ = 共8兲
␴2w + ␴⬘2 are generally different than those of the subsequent stages, which
is a well understood and observed phenomenon in a braced exca-
␴2w␴⬘2 vation. Fortunately, under normal construction conditions, the
␴⬙ = 共9兲 damage caused by the excavation-induced ground settlement in
␴2w + ␴⬘2
the first two stages of excavation has rarely been reported and is
The updated distribution 共or more precisely, mean ␮⬙ and stan- generally negligible.
dard deviation ␴⬙兲 of the apparent model bias factor BF based on To further examine the improvement of the updated settlement
the observation at the end of the third stage is then used for the predictions over the predictions made prior to excavation, the
prediction of settlements at the subsequent stages. As the excava- updated settlement predictions and their variations prior to each
tion proceeds and additional observed settlements are obtained, excavation stage are plotted. Fig. 11 shows the settlement predic-
the distribution of the apparent model BF is updated by treating tions at various excavation stages, Stages 4, 5, 6, and 7 共or their
the posterior result of the previous update as the prior result for corresponding target depths: 10.15, 13.20, 16.20, and 18.45 m兲.
the next update until the completion of excavation. Prior to the fourth stage of excavation, the observed data from
Table 4 shows the mean and standard deviation of the updated Stage 3 are available, and based on these data, the apparent model
apparent model bias factors that are used in the subsequent settle- bias factor is updated, and the settlements at various target depths
ment predictions. As the excavation proceeds, both the mean and 共10.15, 13.20, 16.20, and 18.45 m兲 are updated or recalculated.
standard deviation of the updated model bias factor decrease. These results 共i.e., settlements predicted at four target depths兲 are
However, it is interesting to note that the coefficient of variation represented with a “triangle” symbol as shown in Fig. 11. As the
of the updated model bias factor at various stages remains ap- excavation proceeds beyond Stage 4, there is no need to “predict”
proximately the same in this particular case. The implication of the settlement at the depth of 10.15 m, the target depth of Stage 4.
this result is that the “precision” of the KJHH model remains Thus, in Fig. 11, only one settlement prediction is made at the
constant throughout the updating process, which is expected. depth of 10.15 m. Similarly, prior to Stage 5 of the excavation,
Table 5 shows the observed maximum ground settlements and with the observed data from Stage 4, the settlements at the depths
the predicted mean maximum settlements at various stages of of 13.2, 16.2, and 18.45 m 共the target depths at Stages 5, 6, and 7兲
excavation using the updated apparent model bias factors. It is are recalculated based on the updated apparent model bias factor.
noted that the predictions made after the third stage and prior to The settlement predictions at these three target depths are also
the fourth stage of excavation are those based on the updated shown in Fig. 11. In a similar manner, two settlements predictions
apparent model bias factor that has incorporated the observed data are made at the target depths of 16.2 and 18.45 m prior to Stage 6
from the third stage of excavation. In other words, the mean of excavation, and one settlement prediction is made at the target
maximum settlement is still calculated from Eq. 共4兲 but with an depth of 18.45 m prior to Stage 7 of excavation. Also shown
updated apparent model actor BF. The predictions made at the in Fig. 11 is the observed settlement at the final stage 共Stage 7兲
end of subsequent stages are interpreted in the same way. The of excavation, which is at the depth of 18.45 m. The results
results 共Table 5兲 show that as the excavation proceeded and with shown in Fig. 11 indicate that as the excavation proceeds, and
each stage of observation and updating, the settlement predictions with more and more observed data, the settlement prediction be-
for the subsequent excavations became more accurate, compared comes more accurate compared to the final observed settlement at
to the observations. the depth of 18.45 m. Finally, it should be mentioned that the

Table 5. Observed and Predicted Maximum Settlements of Formosa Case History


Mean maximum settlement 共mm兲
Excavation Prediction
Depth Prior to End of End of End of End of
Stage 共m兲 Observation excavation 3rd stage 4th stage 5th stage 6th stage
3 6.9 12 18 — — — —
4 10.2 25 38 30 — — —
5 13.2 31 57 45 42 — —
6 16.2 40 72 57 53 49 —
7 18.45 47 78 62 58 53 51

JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008 / 1455


Fig. 13. Probabilities of exceedance updated with observed data

Fig. 11. Bayesian updating of settlement predictions 0 at the completion of the final stage of excavation. Thus, the
updating yielded more and more accurate estimates of the prob-
ability of exceedance. However, it should be noted that the “zero”
settlement predictions shown in Fig. 11 are the “mean” maximum probability would never be “predicted” prior to any stage of ex-
settlements. cavation, including the final stage of excavation, because of the
Fig. 12 shows the updated settlement predictions only at the within-site variability and the random nature of the input param-
target depth of 18.45 m prior to Stage 4, 5, 6, and 7 of excava- eters. Finally, it should also be noted that this probability of ex-
tions. Also shown in this figure are the settlement prediction at the ceedance depends in large part on the specified limiting tolerable
target depth of 18.45 m prior to Stage 3 of excavation 共i.e., before settlement.
any updating兲, and the observed settlement at the completion of
the final stage 共Stage 7兲 of excavation. The results shown in this
figure clearly demonstrate the improvement in the settlement pre- Conclusions
diction using the updated model bias factor.
Fig. 13 shows the probability of exceedance 共exceeding the 1. A simple reliability-based framework is established where
limiting tolerable settlement of 75 mm兲 predicted at the target the probability of exceedance 共i.e., exceeding the specified
depth of 18.45 m prior to Stages 4, 5, 6, and 7, respectively. tolerable settlement兲 can be calculated for buildings adjacent
These probabilities of exceedance were updated prior to Stages 4, to an excavation. This framework involves a simplified limit
5, 6, and 7 of excavations 共using the observed data at the end of state that relies only on the maximum ground settlement and
Stages 3, 4, 5, and 6, respectively兲. Also shown in this figure is a recently developed semiempirical model for the calculation
the probability of exceedance at the target depth of 18.45 m prior of ground settlement induced by an excavation. The results
to Stage 3 of excavation 共which is before any updating兲. It should presented in this paper show that this simple framework can
be noted that at the completion of the final stage 共Stage 7兲 of any yield meaningful assessments of the probability of exceed-
excavation, the probability of exceedance should be either 1 共yes兲 ance and building serviceability caused by an excavation,
or 0 共no兲. In this particular case, the probability of exceedance is although further study to adopt more advanced limit states in
the reliability analysis for assessing building serviceability is
warranted;
2. Sensitivity analyses are performed to determine the effects of
a number of assumptions, including the magnitude and varia-
tion of the limiting tolerable settlement, the apparent model
bias factor, COV of soil properties, and assumed distribution
of input variables. The results indicate that the calculated
probability of exceedance depends on the choice of tolerable
settlement, as expected. The results also showed that the un-
certainty in the limiting tolerable settlement has a significant
effect, and thus the limiting tolerable settlement needs to be
properly characterized for a given case with a given set of
conditions;
3. The calculated reliability index and probability of exceed-
ance is most sensitive to the model bias factor, which indi-
cates the importance of the accuracy and precision of
the deterministic settlement model adopted for reliability
analysis. Furthermore, the calculated reliability index is
Fig. 12. Updated settlement predictions at target depth of 18.45 m also sensitive, albeit to a lesser degree, to the normalized
prior to Stages 3, 4, 5, 6, and 7 of excavations shear strength 共su / ␴⬘v兲 and normalized Young’s modulus

1456 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008


共Ei / ␴⬘v兲, and to be insensitive to excavation depth 共He兲, ex- tests.” Int. J. Numer. Analyt. Meth. Geomech., 6共4兲, 409–424.
cavation width 共B / 2兲, system stiffness 共EI / ␥wh4avg兲, and Boone, S. J. 共1996兲. “Ground-movement-related building damage.”
兺Hclay / Hwall. However, the reliability index becomes increas- J. Geotech. Engrg., 122共11兲, 886–896.
Boscardin, M. D., and Cording, E. J. 共1989兲. “Building response to
ingly sensitive to su / ␴⬘v and Ei / ␴⬘v as the COV of su / ␴⬘v and
excavation-induced settlement.” J. Geotech. Engrg., 115共1兲, 1–21.
Ei / ␴⬘v increase relative to the other input variables. There- Burland, J. B., and Worth, C. P. 共1975兲. “Settlement of buildings and
fore, it is important to accurately characterize the COV of
associated damage.” Proc., Conf. on Settlement of Structures, Cam-
su / ␴⬘v and Ei / ␴⬘v; bridge Pentech Press, London, 611–654.
4. Excluding the model bias factor, which is not a “real” input Calvello, M., and Finno, R. J. 共2004兲. “Selecting parameters to optimize
variable in a given problem, the soil parameters, su / ␴⬘v in model calibration by inverse analysis.” Comput. Geotech., 31共5兲,
and Ei / ␴⬘v, are found to have most important effects on 411–425.
the calculated reliability index and probability of exceed- Clough, G. W., and O’Rourke, T. D. 共1990兲. “Construction-induced
ance. This finding supports the conventional approach in the movements of in-situ walls.” Proc., ASCE Conf. on Design and Per-
back-analysis of excavation-induced wall and ground move- formance of Earth Retaining Structure, Geotechnical Special Publica-
ments, in which only soil parameters are “updated” in an tion No. 25, ASCE, New York, 439–470.
effort to match the “predicted” responses with the “mea- Der Kiureghian, A., and Ke, J.-B. 共1985兲. “Finite-element-based reliabil-
sured” responses; ity analysis of framed structures.” Proc., 4th Int. Conf. on Structural
5. The effect of the assumed distribution of input variables on Safety and Reliability, Vol. 1, International Association for Structural
the probability of exceedance is found to be insignificant, Safety and Reliability, New York, 395–404.
particularly when the COVs of these variables are relatively Duncan, J. M. 共2000兲. “Factors of safety and reliability in geotechnical
low 共⬍20% 兲. Even at higher COV levels, the effect is still engineering.” J. Geotech. Geoenviron. Eng., 126共4兲, 307–316.
Duncan, J. M., and Chang, C. Y. 共1970兲. “Nonlinear analysis of stress and
quite modest. Consequently, the input variables can be as-
strain in soils.” J. Soil Mech. and Found. Div., 96共5兲, 1629–1651.
sumed to be normally distributed to simplify the reliability
Finno, R. J., and Calvello, M. 共2005兲. “Supported excavations: Observa-
analysis; and tional method and inverse modeling.” J. Geotech. Geoenviron. Eng.,
6. A new technique is presented by which the excavation- 131共7兲, 826–836.
induced settlement prediction and the probability of exceed- Finno, R. J., Voss, F. T., Jr., Edwin, R., and Blackburn, J. T. 共2005兲.
ance can be updated using the observed data from the prior “Evaluating damage potential in buildings affected by excavations.”
excavation stages. While the updating of information based J. Geotech. Geoenviron. Eng., 131共10兲, 1199–1210.
on newly observed data through Bayesian theorem is nothing Hashash, Y. M. A., Jung, S., and Ghaboussi, J. 共2004兲. “Numerical imple-
new, the proposed technique, in which the predicted settle- mentation of a neural network based material model in finite-element
ment and probability of exceedance are updated through the analysis.” Int. J. Numer. Methods Eng., 59共8兲, 989–1005.
model bias factor, is new and quite innovative. The imple- Hasofer, A. M., and Lind, N. C. 共1974兲. “Exact and invariant second-
mentation of this updating technique is straightforward and moment code format.” J. Engrg. Mech. Div., 100共1兲, 111–121.
Hsiao, E. C. L., Juang, C. H., Kung, G. T. C., and Schuster, M. J. 共2007兲.
can easily be carried out in a spreadsheet. The effectiveness
“Reliability analysis and updating of excavation-induced ground
of the updating technique that involves the model bias factor settlement for building serviceability evaluation.” Geotechnical Spe-
is demonstrated with the example presented. cial Publication No. 170, ASCE, Reston, Va.
Kay, J. N. 共1976兲. “Safety factor evaluation for single piles in sand.” J.
Geotech. Engrg. Div., 102共10兲, 1093–1108.
Acknowledgments Kung, G. T. C. 共2003兲. “Surface settlement induced by excavation with
consideration of small strain behavior of Taipei silty clay.” Ph.D.
dissertation, National Taiwan Univ. of Science and Technology,
The study on which the paper is based was supported by the
Taipei, R.O.C.
National Science Foundation through Grant No. CMS-0300198 Kung, G. T. C., Hsiao, E. C. L., and Juang, C. H. 共2007a兲. “Evaluation of
under Program Director Dr. Richard J. Fragaszy. This financial a simplified small-strain soil model for estimation of excavation-
support is greatly appreciated. The views and opinions expressed induced movements.” Can. Geotech. J., 44共6兲, 726–736.
in this paper, however, do not necessarily reflect the policies or Kung, G. T. C., Juang, C. H., Hsiao, E. C. L., and Hashash, Y. M. A.
views of the National Science Foundation. The fourth author 共2007b兲. “A simplified model for wall deflection and ground surface
wishes to acknowledge support by the National Science Council settlement caused by braced excavation in clays.” J. Geotech. Geoen-
of Taiwan through Grant No. NSC 96-2218-E-006-291. Dr. Eng viron. Eng., 133共6兲, 731–747.
Hui Khor of the Probabilistic Design and Optimization Group of Lacasse, S., Guttormsen, T. R., and Goulois, A. 共1990兲. “Bayesian updat-
ANSYS, Inc. is thanked for many helpful discussions on reliabil- ing of axial capacity of single pile.” Proc., 5th Int. Conf. on Structural
ity and sensitivity analysis. The journal reviewers are thanked for Safety and Reliability, H.-S. Ang, M. Shinozuka, and G. I. Schuller,
their thorough and constructive comments that have helped eds., ASCE, New York, 287–290.
sharpen this paper. Lambe, T. W. 共1973兲. “Prediction in soil engineering.” Geotechnique,
23共2兲, 149–202.
Low, B. K., and Tang, W. H. 共1997兲. “Efficient reliability evaluation
using spreadsheet.” J. Eng. Mech., 123共7兲, 749–752.
References Ou, C. Y., Hsieh, P. G., and Chiou, D. C. 共1993兲. “Characteristics of
ground surface settlement during excavation.” Can. Geotech. J.,
Ang, A. H.-S., and Tang, W. H. 共1984兲. Probability concepts in engineer- 30共5兲, 758–767.
ing planning and design. Design, risk and reliability, Vol. II, Wiley, Ou, C. Y., Liao, J. T., and Lin, H. D. 共1998兲. “Performance of diaphragm
New York. wall using top-down method.” J. Geotech. Geoenviron. Eng., 124共9兲,
Ang, A. H.-S., and Tang, W. H. 共2006兲. Probability concepts in engineer- 798–808.
ing: Emphasis on applications to civil and environmental engineering, Ou, C. Y., and Tang, Y. G. 共1994兲. “Soil parameter determination for
2nd Ed., Wiley, New York. deep excavation analysis by optimization.” J. Chin. Inst. Eng., 17共5兲,
Baecher, G. B., and Rackwitz, R. 共1982兲. “Factors of safety and pile load 671–688.

JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008 / 1457


Phoon, K. K. 共2004兲. “General non-Gaussian probability models for first Tang, W. H., Stark, T., and Angulo, M. 共1999兲. “Reliability in back analy-
order reliability method 共FORM兲: A state-of-the art report.” ICG Rep. sis of slope failures.” Soils Found., 39共5兲, 73–80.
No. 2004-2-4 共NGI Rep. No. 20031091-4兲, International Center for Wahls, H. E. 共1994兲. “Tolerable deformations.” Geotechnical Special
Geohazards, Oslo, Norway. Publication No. 40, ASCE New York, 1611–1628.
Phoon, K. K., and Kulhawy, F. H. 共2005兲. “Characterization of model
Zhang, L. M., and Ng, A. M. Y. 共2005兲. “Probabilistic limiting tolerable
uncertainties for laterally loaded rigid drilled shafts.” Geotechnique,
displacement for serviceability limit state design of foundations.”
55共1兲, 45–54.
Geotechnique, 55共2兲, 151–161.
Simons, N. E., and Menzies, B. K. 共2000兲. A short course in foundation
Zhang, L. M., and Tang, W. H. 共2002兲. “Use of load tests for reducing
engineering, 2nd Ed., Thomas Telford, London.
Skempton, A. W., and MacDonald, D. H. 共1956兲. “The allowable settle- pile length.” Deep Foundations 2002, Geotechnical Special Publica-
ment of buildings.” Proc.-Inst. Civ. Eng., 3共5兲, 727–768. tion No. 116, ASCE, Reston, Va., 993–1005.
Son, M., and Cording, E. J. 共2005兲. “Estimation of building damage due Zhang, L. M., Tang, W. H., Zhang, L. L., and Zheng, J. G. 共2004兲.
to excavation-induced ground movements.” J. Geotech. Geoenviron. “Reducing uncertainty of prediction from empirical correlations.”
Eng., 131共2兲, 162–177. J. Geotech. Geoenviron. Eng., 130共5兲, 526–534.

1458 / JOURNAL OF GEOTECHNICAL AND GEOENVIRONMENTAL ENGINEERING © ASCE / OCTOBER 2008

View publication stats

You might also like