You are on page 1of 10

Tunnelling and Underground Space Technology 16 Ž2001.

225᎐234

Tunnelling of infrastructure: from non-considered to ill


considered ᎏ lessons from the Netherlands

Gerard ArendsU , Enne de Boer


Delft Uni¨ ersity of Technology, Delft, The Netherlands

Received 11 June 2001; accepted 13 July 2001

Abstract

In The Netherlands, tunnels are in much Žpublic. demand since approximately 1980. Infrastructure is less tolerated in the
urban environment, especially when it is elevated above ground. Three different projects for which the authors acted as scientific
consultants can serve to demonstrate how problematic it can be to neglect an underground option on the one hand and to make
it dogmatic on the other. Existing infrastructure is often seen as both environmentally and commercially damaging, suppressing
urban land values. Reconstruction is a difficult task, though, in spite of modern techniques. The Helmond case, where an elevated
part of a main road separates the town centre and historical castle and blocks revitalisation of the area, is an adequate
demonstration. The proposed replacement with a tunnel proved to be ill considered, i.e. both difficult and costly. Even worse:
perhaps the town might do without the road after all! In developing new infrastructure, like high speed train links, urban
alignments are avoided because of public resistance. Yet these may prove to be acceptable if tunnelled, whereas an alignment in
the rare open countryside is locally despised. This proved to be true in the case of the Amsterdam᎐Antwerp High-Speed Railway
Line ŽHSL., for the passage of Dordrecht, south of Rotterdam. An urban underground solution was not considered in the
government studies. A local proposal, which proved to be quite feasible, was rejected, mainly because it was presented late in the
planning process. New types of infrastructure may be developed explicitly for underground use. Lorries are an ever-bigger
problem in local distribution, both for the environment and congestion and for trade, dependent on these. Therefore,
underground logistic systems ŽULS. are proposed more frequently. Perhaps the best-studied one is the Schiphol Airport ULS,
intended predominantly to connect air and rail terminals and the world’s largest flower auction at Aalsmeer. It showed that the
choice for an underground solution can be too dogmatic, not affordable and only partly necessary. Mixed solutions, partly
underground, partly on the surface and partly elevated were quite feasible and economically more attractive. 䊚 2001 Elsevier
Science Ltd. All rights reserved.

Keywords: Alignment; Elevation; Decision making; Tunnelling technique; Urban environment

1. Introduction 1. The first motive is avoiding dangerous crossings in


roads and railways. For pedestrians and bicyclists
1.1. The demand for underground transport infrastructure viaducts are not thought to be an attractive option
in The Netherlands and therefore, many short tunnels have been built.
2. Longer tunnels were constructed for a second rea-
In the Dutch lowlands, tunnelling used to be an
son: crossing ‘standing mast’ shipways, being able
exception until approximately 1980. In fact, there were
to accommodate very tall ships. If transport on the
considered to be only three motives for constructing
Žrail. road crossing is intensive, movable bridges
tunnels.
are impractical. High bridges are very long and not
without danger in stormy weather. Tunnelling is
U the only feasible solution then.
Corresponding author. Tel.: q31-15-278-52-66; fax: 31-15-278-
78-28. 3. Tunnel systems are traditional in metropolitan ar-
E-mail address: G.Arends@CT.TUDelft.NL ŽG. Arends.. eas, where the competition for space is so heavy

0886-7798r01r$ - see front matter 䊚 2001 Elsevier Science Ltd. All rights reserved.
PII: S 0 8 8 6 - 7 7 9 8 Ž 0 1 . 0 0 0 4 3 - 8
226 G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234

that traffic has to be processed at different levels. on underground construction has become more compli-
Elevated systems are a solution in less dense areas, cated because of technical developments on the one
but in central districts underground solutions are hand and societal ones on the other. The variety of
necessary for creating high capacity urban rail sys- technical possibilities has increased considerably and so
tems. In the Netherlands only the national capital, has the political context with numerous actors or stake-
Amsterdam and the giant port of Rotterdam devel- holders trying to influence the outcome of the planning
oped metro systems and only so in the second half process.
of the twentieth century. In response to these developments, the role of the
TU Delft in developing underground solutions is multi
The soft soils of the Dutch ‘waterland’ are the cause faceted as well. Of course, we participate in developing
of a certain reluctance to construct tunnels and tunnel new techniques, but increasingly we are involved in
systems on a large scale, although it led to a high multidisciplinary projects in which administrative, plan-
degree of expertise in immersed tunnel construction, ning and technical aspects are studied in order to find
which was developed in the realisation of a series of feasible solutions.
waterway crossings. Nowadays, more and more tunnels
under waterways are constructed with a drilling tech-
nique using modern TBMs, because of heavy water 2. The problem of existing elevated infrastructure in
traffic and little space on the river banks. For ‘inland central districts: the castle thoroughfare of Helmond as
tunnels’ too, less intrusive tunnelling techniques Žcut an ill-considered project
and cover or drilling. are in much demand.
The demand for ‘inlandtunnels’ as such is increasing The town of Helmond Žliterally: hell’s mouth., east
because the general public no longer accepts the da- of Eindhoven Žhometown of Philips electronics . devel-
mage inflicted by large infrastructural projects on their oped near a castle, that still is the pride of the town: a
environment. Policy makers traditionally looked for the classical square ground plan; high walls; and towers on
most economic solutions, but under public pressure every corner. The town flourished in the nineteenth
they accept underground options which create or main- century, profiting from a north᎐south shipping canal
tain a more sustainable environment, both from an with a parallel road and an east᎐west railway line ŽFig.
ecological and a societal perspective. Decision making 1., the two crossing near the castle ŽFig. 2.. In approxi-

Fig. 1. Map of Helmond.


G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234 227

Fig. 2. Helmond castle, view from the thoroughfare viaduct to the


south direction.
Fig. 4. View alongside the viaduct from the canal side to the city
mately 1960, the east᎐west through traffic congested centre.
the inner city. The movable bridge across the canal
augmented congestion. After an intensive debate, which
fully, a famous Italian architect, Boscotondo, was in-
divided the local community, the decision was made to
vited to design the quarter. The presence of the viaduct
build a road bypass with a high fixed bridge between
with its heavy load of traffic is thwarting further rede-
the town and the castle. It bridged the canal road and
velopment though. It separates the Boscotondo project
castle lane as well ŽFig. 3.. The view of the castle from
from the town centre and depresses land values.
the town was now spoiled thoroughly by a viaduct ŽFig.
The political opposition in the town council took the
4.. The opponents did accept the breakthrough as such,
initiative to ask the TU Delft to design a tunnel to
but wanted a tunnel instead of the bridge. The town
replace the viaduct.
could not afford it. However, in the zoning plan for the
In several discussions, field visits and studies of avail-
area a zone along the bridge was reserved for a possi-
able sources we developed a strategy for tackling the
ble future tunnel.
matter ŽDe Boer et al., 1999.. Positive conclusions
During the following decades the traffic increased
concerning the feasibility of a tunnel solution could be
continually. Therefore, the town tried to create by-
drawn only by answering the following questions:
passes for the canal and for the canal road. The canal,
which had lost most of its function for trade, was
1. The first question was whether the thoroughfare
by-passed in approximately 1995, the road is expected
had to stay where it was located. In fact, it served
to be by-passed before 2010. It implies that the original
as the main artery between Helmond and Eind-
reasons for constructing the high bridge will disappear.
hoven to the west and Deurne to the east. It is
Over the years a decline of local industry led to
quite unusual for trunk routes like this to be lo-
substantial decay in the canal and railway zones. A
cated in the middle of the town. The local opinion
process of redevelopment was started, first around the
was that the road was essential for the vitality of
railway station and later on along the canal, near the
the town centre.
castle. To exploit the potential of the historical site
2. The second question was what could or should be
gained by building the tunnel, both environmen-
tally and financially. The local opinion was that the
whole castle area had to be by-passed vertically in
order to create an attractive urban environment
with further redevelopment opportunities. It would
require a tunnel with a closed part of several
hundred meters in length. The area to be recov-
ered by removing the viaduct and by reconstructing
adjacent properties was quite modest though.
3. The third question was how to construct a tunnel.
Regarding its modest length boring was not a real-
istic option: the additional depth required for con-
struction in soft soil would cause a length far
greater than necessary. Therefore, the tunnel would
Fig. 3. The thoroughfare viaduct with a movable bridge behind it, have to be constructed from the surface, which
view from the castle᎐canal side to the north. would have to be cleared before. Alas, the zone
228 G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234

reserved for a tunnel in the 1960s had been used gent. A modest road on ground level might handle
for the Boscotondo project. It meant that the tun- traffic that is of vital importance for the town centre,
nel should have exactly the same location as the which is perfectly compatible with the environment.
viaduct. In order to construct the tunnel, traffic Replacing an elevated solution with a depressed one,
would have to be diverted during the demolition an elevated bypass with an underground one, should be
and construction process. The viaduct was rather systematically compared with replacing it with a hori-
over-dimensioned: it had a cross section with four zontal bypass, maybe longer, but maybe cheaper as
lanes; two cycle lanes; and footpaths. Theoretically well.
one might demolish one half of the viaduct and In the Helmond case, the idea of a tunnel might be
build one half of the tunnel in its place. However, called ill considered.
the integrated construction of the viaduct made
this impossible. In a certain sense, we had to return
to the first question: where to leave the voluminous 3. The problem of new surface infrastructure through
traffic from the thoroughfare. We surveyed the rare and vulnerable landscape. The case of the High
municipal network and found various historical ef- Speed Link South through the vulnerable Devel area.
forts to develop bypasses to the north and to the An example of (sadly) non-considered
south, which could be used for traffic diversions.
The network as a whole, however, was developed In the Netherlands, expansion of the highway and
so haphazardly, that congestion would be unavoid- airport infrastructure is met with general rejection. In
able. Local street widening did not look impossible approximately 1990, large schemes for railway expan-
though. sion were developed instead. The most important lines
4. The fourth question was that of construction cost, a to be added are a trunk freight line to Germany The
most important one, certainly because financial ‘Betuwe route’ and a high-speed link to the French
benefits to be gained by redevelopment would be network, the ‘HSL South’, Fig. 5 shows the HSL line.
modest. The local ideal was to connect the tunnel Open country with qualities regarding landscape and
to underground parking garages, which of course nature has become rare and deserves protection be-
would have an impact on both profile and construc- cause of that. For the HSL South, linking Amsterdam,
tion cost. The best fitting tunnel for regional traffic Rotterdam and the Belgian town of Antwerp, a fast
without these ‘extra’s’ was estimated to cost and short route was designed. Upgrading the existing
$20 000 000 ᎏ disregarding temporary measures line was rejected as either too expensive or harmful for
for traffic. It was quite unlikely that the municipal- the environment. For the Amsterdam᎐Rotterdam part
ity would be able to afford this, even with national the new route implied an alignment through the so-
subsidies for urban reconstruction it was entitled called ‘Green Heart’ of the Dutch Randstad Žfringe
to. town.. This being taboo, a substantial part of it is
5. The last question, to be answered by local politics, tunnelled. It is to be constructed before 2010. The
was and still is whether there can be found a tunnel will be bored because of the sanctity of the area.
balance between accessibility of the town centre, South of Rotterdam the line will cross the ‘Devel
an attractive environment and the cost of combin- area’, a restful landscape along a river branch with
ing those. We developed systematically variants of distinct qualities, like a varied, typically Dutch diking
the tunnel regarding length and cross section with history. In a heavily urbanised area, it is the last
different effects on accessibility and amenity. The opportunity for rural recreation. Directly south of the
town is now developing scenarios for different Devel area, a waterway, the river Old Maas, has to be
courses of action regarding redevelopment, traffic crossed by means of a tunnel and after - 10 km a
recirculation and infrastructural adaptations. second tunnel has to be made across the next water-
way. The possibility of making the Old Maas tunnel
Creating a central artery, like the famous Boston longer, passing underneath the Devel area too, has
example had caused the problem in Helmond. It could been studied. It was rejected because of the additional
not do without grade crossings. The choice for partial cost that was thought to be politically unjustified.
elevation instead of suppression proved to be detrimen- The town of Zwijndrecht, to support a citizen group
tal to urban amenity and redevelopment. The most opposing the alignment, hired TU Delft Ži.e. the second
important reasons for grade crossings, the canal and author.. Citizen groups of some quality tend to attack
the canal road have disappeared or will disappear, the project as such, the alignment or the elevation. This
respectively. The fact that for construction of a tunnel, group decided to concentrate on local problems, i.e. to
predominantly for reasons of amenity, traffic has to be plea for a longer tunnel Žstudied in the project papers.,
diverted for quite some time makes the study of perma- to develop the argument against cutting the Devel area
nent bypassing of a substantial part of the traffic ur- into two pieces Žwhich the surface solution would do.
G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234 229

Fig. 5. Alignment overview of the Zwijndrecht and Devel area.

and to look for possibilities to improve the existing makes a sharp curve that restricts operational speed.
railway line. We encouraged a search for alternative Residences are located so close to the tracks that noise
routes, putting the burden on adjacent areas. The TU nuisance and risk are serious problems and railway
Delft produced a report with two elements: widening is hardly feasible. A survey of the town quar-
ter within the curve showed that it was astonishingly
1. An analysis of the qualities of the area and; easy to make a shortcut. It proved that a corridor had
2. A proposal to remove the most problematic pas- been reserved for it in the past. The shortcut is indi-
sage of the existing railway line. cated in Fig. 5 as ‘Shortcut’. To prevent new environ-
mental problems, a tunnel of approximately 1.5 km
In the adjacent town of Dordrecht, the railway line would be required. This could be provided with a
230 G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234

station for intercity trains, to be connected with the old The boundary conditions for the tunnel showed large
railway station by way of a footpath or travelator. The differences:
worst environmental problems would have been solved
and Dordrecht would have kept its main line station, 䢇 In the northern section, a crossing and connection
which it will lose because intercity trains will use the to be made with the existing infrastructure Žeight
HSL bypass through the Devel area. lane highway and four track railway line..
The reaction of the town was not antagonistic. How- 䢇 In the middle section, residential buildings to be
ever, national government rejected the idea resolutely, avoided as much as possible.
predominantly because of an insufficient design speed. 䢇 In the southern section, a deep waterway crossing
It was an ideological reaction, because the time loss as with on both sides industrial areas and sensitive
compared with the government proposal was quite dike constructions.
modest.
We did not develop any proposal for a longer short- On the basis of these differences, various tunnelling
cut with a higher design speed through the town of techniques and combinations of those had to be con-
Zwijndrecht, because we thought it to be impossible. sidered with respect to cost, risk for the stability of
Half a year later, Mr Willem Bos, a civil engineer who existing structures and nuisance from construction and
had made it a hobby to study alignments for potential operation for the environment. The following tun-
improvement, drew such a shortcut though. At first nelling techniques and accompanying subjects can be
sight, a ridiculous one indeed, even if put into a tunnel distinguished:
as he proposed. A second effort looked more plausible
though and it drew the attention of national Parlia-
䢇 Bored tunnel. Regarding the sensitive environment
ment that valued the fact that both the Devel area and
and the length of the tunnel one tends to consider
a rural district south of the river Old Maas would gain
this technique. There are three problems though:
from it. It demanded an additional study of this alter-
native route. The Minister of Transport conceded, but 1.1. The relatively wide impact zone under-
under the condition, that developing and eventual con- ground with the risk of effecting pile founda-
structing would not slow down the project as a whole tions ŽFig. 6..
and would not be more expensive than the preferred 1.2. The flexibility of the tunnel construction with
Devel alternative, indicated in Fig. 5 as option Fn. the risk of passing vibrations to the pile
Strangely enough, the town of Zwijndrecht was posi- foundations.
tively interested in an alignment cutting through its 1.3. Because of the deep position under the river
built up area, albeit underground. It did not trust the Ž) 25 km below mean water level. the tunnel
Ministry to do an objective study and gave an assign- would be longer than necessary in the south-
ment to the TU Delft Žboth authors. for an indepen- ern section.
dent study in co-operation with Mr Bos ŽArends et al.,
1997.. Careful analysis and adaptation of the Bos align- 䢇 Cut and Cover tunnel to be applied at the land
ment showed that a tunnel could be fitted relatively sections. Of course construction nuisance is a prob-
easily into the urban fabric, ironically because it fol- lem. The impact zone is narrower though and the
lowed a substantial part of the dry former bed of the vibration risk is limited because of the possible
river Devel, of which the wet part was to be protected. rigidity construction ŽFig. 6..
Only one apartment house, a modest number of family 䢇 Immersed tunnel to be applied at and near the
homes and a few commercial buildings would be af- crossing with the river Old Maas. The long standing
fected. The Bos alignment is indicated in Fig. 5 as experience and the relatively low cost could make
option Fd Ž ds Drecht-towns.. this advantageous. The existing dock used for the

Fig. 6. Settlement sensitive areas for three bored options compared to cut and cover construction.
G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234 231

construction of segments for a series of tunnels at port is expanded only reluctantly. Especially, the regio-
the town of Barendrecht is close by. nal network around the airport and the airport’s infras-
tructure itself are becoming continually more con-
Our proposal is shown in Fig. 5, alignment Fd. The gested ŽFig. 7..
problem of construction nuisance of a cut and cover Commercial enterprises in central business districts
tunnel was studied in a MSc thesis of one of our are suffering even more from inaccessibility. Especially,
students. It proved to be manageable ŽRiesebosch, for urban goods distribution, collective solutions are
1998.. sought. These may take different shapes:
The town of Zwijndrecht, which would suffer espe-
cially from tunnel construction in a residential area, 䢇 Distribution centres to which lorries deliver goods
showed a remarkably positive attitude and the resi- and smaller vehicles collect these for a specific
dents concerned proved to be far from hostile on a neighbourhood. In this way, the large vehicles will
neighbourhood meeting on the outcomes of our study. lose less time and the streets are relieved from
The fact that the natural part of the Devel area would them.
remain unaffected was the explanatory factor. The town 䢇 A more radical solution is the creation of an under-
of Dordrecht now was disapproving the Devel ŽFn. ground distribution system. Ideally, clients are con-
alignment without much argument, which made it the nected directly to the system. The investment re-
Minister of Transport easy to conclude that the Bos quired is so substantial though, that even in the
ŽFd. alignment did not comply with one of her condi- most prosperous districts only a few stations are
tions: no time losses. The Ministry of Transport stuck affordable.
to the alignment cutting the Devel area into two pieces,
too small to maintain its qualities. In the voluminous In the Netherlands, both types of solutions have
project papers, the area was recognised to be of con- been studied to some extent but neither one was yet
siderable value. Nevertheless, the Minister refused to realised.
make investments in a longer river tunnel which would The World’s largest flower auction at Aalsmeer, - 10
have left the area unaffected. km from Amsterdam Airport, is very dependent on
The Ministry could not be accused of developing too reliable transport connections, especially with the air-
few alternative alignments, but one might say, that it port. Fresh flowers should reach the flower shop within
did not use the right criteria for development. On the 24 h after leaving the auction. Flowers are imported
basis of the operational train speed chosen at 300 from countries like Colombia and exported to Hong
kmrh, only alignments avoiding urbanised areas were Kong and Russia for instance. Presently, the auction is
developed. It resulted in a very long bypass of the accessible by road only. The connecting regional road
towns of Dordrecht and Zwijndrecht with two costly is suffering from increasing congestion. The risk of
tunnels to pass major waterways. Sticking for longer to missing a plane is consequently growing. The flower
the existing straight main railway line and making a auction took the initiative of developing an Under-
tunnel bypass through these towns should have been ground Logistic System. It was supported by the Min-
investigated from the start of the planning process. It istries of Economic Affairs and Transport that share a
might have been chosen then. programme for research and development of under-
Meanwhile this type of exercise has been done in the ground construction.
case of another railway line, the Hanse line, in which The airport itself suffers from congestion both inter-
both authors were involved in different roles. nally and on the roads to its hinterland. Internally, it is
predominantly a problem of the connection between
cargo areas on both sides of the most important run-
4. The solutions of completely underground systems. way. Externally it is the common problem of increasing
The case of the Amsterdam Airport Underground traffic flows and reluctance to expand the road infras-
Logistic System. The problem of exaggeration tructure. According to national policy it has to become
more of a ‘rail airport’, discouraging both car traffic at
Amsterdam Airport is one of the most thriving air- the land side and short distance flights at the air side.
ports in Europe. For passenger transport, it is fourth in Its High-Speed Railway Line ŽHSL. passenger station
size, with only Frankfurt, London, Heathrow and Paris, is supposed to support this concept. The addition of a
Charles de Gaulle above it. For cargo, it is even more HSL cargo terminal is considered as shown in Fig. 7.
important. The development of hub airports like this The idea of an Underground Logistic System ŽULS.
may cause considerable ground transport congestion started as an underground transport route between
and environmental nuisance around it. Airport expan- flower auction and airport. In a first outline, a system
sion has a history of some forty years of conflict in the connecting the auction, different airfreight terminals
present case. The road infrastructure around the air- and the eventual railway terminal was sketched. The
232 G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234

Fig. 7. Network and alternative alignments of ULS.

network length might be up to 30 km, the number of In the design of a system like the ULS a number of
stations up to 10 km, serving important forwarders and questions have to be raised:
distribution centres too.
In order to get a better idea of possible qualities and 1. What is the function of the system: a logistic sys-
quantities of the system three prestigious institutions tem and not just a transport system? It implies that
were assigned to do a ‘definition study’: destinations, Žre.grouping of freight and inter-
change with other transport modes must be con-
1. The Dutch Economic Institute ŽNEI.; sidered.
2. The national institute for applied natural science 2. What mode of transport is needed? One might
ŽTNO. and; think of automated individual rail vehicles, fed by
3. The inter-university research school for transport an electric rail and with an electronic guidance, but
TRAIL. hardly any of these features are self-evident. Fig. 8
shows an inside-view of a possible ULS terminal
For TRAIL, the first author led the tunnel study and with Automated Guided Vehicles ŽAGV..
the second author the study of the system’s alignment. 3. What should be the maximum dimensions of the
G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234 233

than one transport module is in use: air containers;


road containers; flower wagons; and smaller packing
units. It proved to be a very hard discussion to decide
upon the normative packing because of the different
interests of the stakeholders. Every choice in tunnel
diameter had an impact on the logistic systems in use
by the various parties. Whilst the discussion concerning
the diameter continued, the study was performed for a
system with the inner diameters of 5 and 3 m ᎏ the
5-m system largely using a TBM drilling technique with
a segmented tunnel-lining and the 3-m system a pipe-
jackingrmicrotunnelling construction technique. As
could be expected, the 5-m choice involved an invest-
ment cost approximately twice as much as the 3-m
solution Ž$500 million as against $250 million. ŽArends
and Joustra, 1996..
Fig. 8. Inside view of an ULS terminal with AGVs ŽAutomated The total capacity of a 5-m system is by far exceeding
Guided Vehicles.. the total required transport capacity and as a conse-
quence, it is hard to finance. The 3-m solution is more
loads, i.e. the standard packing units to be used? promising. Nevertheless, the choice of diameter was
ŽFig. 9.. decided upon the 5-m option, mainly because of the
Aeroplane Topdeck Containers, obviously demanding a
These considerations have considerable conse- direct train-transport directly from aeroplane to far
quences for terminal design and especially for the away destinations, e.g. Paris or Milan, without repack-
tunnel profile. The discussion on the profile was most aging in smaller units.
intense. The opinions of the experts involved varied At the same time, Amsterdam Airport finds it more
widely. Some defended a profile allowing for the ac- and more difficult to organise effective transports on
commodation of aeroplane topdeck containers, leading both rail and road to the hinterland caused by an ever
to an internal tunnel diameter of approximately 5 m. increasing traffic volume on the roads surrounding the
The investment would be prohibitive though. Other airport. As a result in a combined effort by the Flower
experts pleaded for a modest profile based on the use Auction and Amsterdam Airport a study was made into
of the ‘Euro’ pallet, used widely in urban distribution. the possibilities of an underground logistic system con-
The tunnel diameter based on the Euro pallet would be necting Amsterdam Airport with the Flower Auction
approximately 3 m. Fig. 9 shows the tunnel diameter vs. and a soon-to-be-constructed High Speed Line Termi-
the freight size. It would make the project a realistic nal, see Fig. 7.
pilot for this interesting application, but required logis- The TU Delft was deeply involved regarding the
tic changes for the flower auction. It had an under- possible underground alignments, the required diame-
ground connection in mind and not so much a logistic ter and the consequential investment costs. One of the
system. boundary conditions was that the system had to be
It was clear from the beginning that the diameter of 100% underground. It became clear that the high cost
the pipe would have a tremendous effect on the invest- was largely the consequence of the exaggerated de-
ment costs. In the case of Amsterdam Airport, more mand for a total underground system. At present the

Fig. 9. Tunnel diameter vs. freight size.


234 G. Arends, E. de Boer r Tunnelling and Underground Space Technology 16 (2001) 225᎐234

project is still under development, whereby major route will be constructed: the internal network of the airport.
sections have been transferred from the subsurface to By relocating the HSL cargo terminal to the central
the surface, thus bringing the financing within the area of the airport it might be connected relatively
possibilities. cheaply with this core network.
In the alignment study, a number of aspects was The original idea that sparked the whole operation,
investigated: an underground connection between Flower Auction
and the airport, is not unlikely to be replaced with a
䢇 Creating an optimal network between the intended quite surprising solution. An old railway alignment,
terminals: a balance between short infrastructure shown in Fig. 8 as A3, is passing both the airport and
lines and short transport lines, i.e. serving heavier the Flower Auction at a relatively close distance. It is
flows with priority. reconstructed as a busway. In the definition study, we
䢇 Finding alignments that would be least conflicting considered to use the underground dimension of it for
with underground and surface structures: avoiding the ULS tube. Alas, it was used already for pipes and
the long piles of existing and planned buildings; and cables. Now the idea is to use the busway for the
crossing other infrastructures at right angles if pos- automated ULS vehicles as well.
sible. In the case of the Amsterdam airport ULS project,
䢇 Deciding, on the basis of present and foreseeable one could conclude that the exaggerated first demand
future land use, where an underground location of a 100% underground solution has hampered a speedy
would be necessary and where a cheaper elevated realisation of the project. A better approach would
or even a surface solution for the tubular system have been to study just the overall possibilities and
might be sufficient. requirements, both above and underground thus, avoid-
ing the well-known planning mistake of starting with
The 100% subterranean character of the system has solutions instead of problem analyses.
the advantage of being protected from external influ-
ences, like weather and theft. However, there are dis-
advantages too. The investment required can be justi- 5. Conclusions
fied only where and when land values are extreme. The
Studies such as those presented in this paper show
cost of interchanges and terminals are such that the
clearly that the underground option should be included
system should surface at the respective locations if
into the planning process of infrastructure, especially in
possible. The invisibility of the system might be called a
urbanised areas, but not only there. It may open oppor-
disadvantage too: if part of it were visible; it no doubt
tunities for different alignments and even for different
would attract more of the attention it deserves.
transport systems. However, it is not advisable to build
The alignment study led to a layout that differed
underground castles in the air. It may be just as coun-
strongly from the original one. Tunnelling was neces-
terproductive as thoughtlessly building on the ground.
sary especially in the core of the airport, across run-
ways and platforms. The business development around References
the airport has such a spacious layout that the addition
of an elevated tube would be an attractive addition. Arends, G., De Boer, E., Bos, W., 1997. De mogelijkheden voor een
The application of underground construction only in ´ door Zwijndrecht. TU Delft.
Fd-trace
Arends, G., Joustra, J., 1996. Tunnelconstructie OLS. In: Onder-
places where it is strictly necessary or less expensive gronds Logistiek Systeem ŽOLS. deelrapportage 2, CTT.
would enlarge the feasibility of the project consider- De Boer, E., Arends, G., Visser, W.M., Piepers, P.R., 1999. Een
ably, see Fig. 7 for two alternative examples named A1 Viaduct in de weg! Mogelijkheden voor ondertunneling van de
and A2 ŽDe Boer and Regt, 1996.. Kasteeltraverse in Helmond. TU Delft.
It proved that the combination of a large diameter De Boer, E., Regt, M.J.J., 1996. Tracering van het Ondergronds
Logistiek Systeem Bloemenveiling-Schiphol-Railterminal. In: On-
and an extended network was not affordable. The na- dergronds Logistiek Systeem ŽOLS. deelrapportage 2, CTT.
tional government refused to make the necessary con- Riesebosch, K., 1998. Wordt de Drechtstedevariant de grond in
tributions to construction cost. One part of the system geboord? TU Delft. March.

You might also like