Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
UNIT-8 FDR-2
1 BBSR-1 BCDD-1 Chandaka UNIT-8 PTR-1 12.5
(RAJBHABAN)
UNIT-8 FDR-2
2 BBSR-1 BCDD-1 Chandaka UNIT-8 PTR-1 12.5
(RAJBHABAN)
UNIT-8 FDR-2
3 BBSR-1 BCDD-1 Chandaka UNIT-8 PTR-1 12.5
(RAJBHABAN)
UNIT-8 FDR-2
4 BBSR-1 BCDD-1 Chandaka UNIT-8 PTR-1 12.5
(RAJBHABAN)
UNIT-8 FDR-2
5 BBSR-1 BCDD-1 Chandaka UNIT-8 PTR-1 12.5
(RAJBHABAN)
UNIT-8 FDR-2
8 BBSR-1 BCDD-1 Chandaka UNIT-8 PTR-3 12.5
(RAJBHABAN)
UNIT-8 FDR-2
9 BBSR-1 BCDD-1 Chandaka UNIT-8 PTR-3 12.5
(RAJBHABAN)
UNIT-8 FDR-2
10 BBSR-1 BCDD-1 Chandaka UNIT-8 PTR-3 12.5
(RAJBHABAN)
FDR-2 (KHARABELA
21 BBSR-1 BCDD-1 Mancheswar A UNIT-3 PTR-1 12.5
NAGAR)
FDR-2 (KHARABELA
22 BBSR-1 BCDD-1 Mancheswar A UNIT-3 PTR-1 12.5
NAGAR)
FDR-2 (KHARABELA
23 BBSR-1 BCDD-1 Mancheswar A UNIT-3 PTR-1 12.5
NAGAR)
FDR-2 (KHARABELA
24 BBSR-1 BCDD-1 Mancheswar A UNIT-3 PTR-1 12.5
NAGAR)
FDR-2 (KHARABELA
25 BBSR-1 BCDD-1 Mancheswar A UNIT-3 PTR-2 8
NAGAR)
FDR-2 (KHARABELA
26 BBSR-1 BCDD-1 Mancheswar A UNIT-3 PTR-2 8
NAGAR)
FDR-2 (KHARABELA
27 BBSR-1 BCDD-1 Mancheswar A UNIT-3 PTR-2 8
NAGAR)
FDR-2 (KHARABELA
28 BBSR-1 BCDD-1 Mancheswar A UNIT-3 PTR-2 8
NAGAR)
FDR-1 (SAINIK
29 BBSR-1 BCDD-1 Mancheswar A UNIT-4 PTR-1 5
SCHOOL)
FDR-1 (SAINIK
30 BBSR-1 BCDD-1 Mancheswar A UNIT-4 PTR-1 5
SCHOOL)
FDR-1 (SAINIK
31 BBSR-1 BCDD-1 Mancheswar A UNIT-4 PTR-1 5
SCHOOL)
FDR-1 (SAINIK
32 BBSR-1 BCDD-1 Mancheswar A UNIT-4 PTR-1 5
SCHOOL)
FDR-1 (SAINIK
33 BBSR-1 BCDD-1 Mancheswar A UNIT-4 PTR-2 5
SCHOOL)
FDR-1 (SAINIK
34 BBSR-1 BCDD-1 Mancheswar A UNIT-4 PTR-2 5
SCHOOL)
FDR-1 (SAINIK
35 BBSR-1 BCDD-1 Mancheswar A UNIT-4 PTR-2 5
SCHOOL)
FDR-2 (KHARABELA
36 BBSR-1 BCDD-1 Mancheswar A SATYA NAGAR PTR-1 8
NAGAR)
FDR-2 (KHARABELA
37 BBSR-1 BCDD-1 Mancheswar A SATYA NAGAR PTR-1 8
NAGAR)
FDR-2 (KHARABELA
38 BBSR-1 BCDD-1 Mancheswar A SATYA NAGAR PTR-1 8
NAGAR)
FDR-2 (KHARABELA
39 BBSR-1 BCDD-1 Mancheswar A SATYA NAGAR PTR-1 8
NAGAR)
FDR-2 (KHARABELA
40 BBSR-1 BCDD-1 Mancheswar A SATYA NAGAR PTR-2 8
NAGAR)
FDR-2 (KHARABELA
41 BBSR-1 BCDD-1 Mancheswar A SATYA NAGAR PTR-2 8
NAGAR)
FDR-2 (KHARABELA
42 BBSR-1 BCDD-1 Mancheswar A SATYA NAGAR PTR-2 8
NAGAR)
FDR-2 (KHARABELA
43 BBSR-1 BCDD-1 Mancheswar A SATYA NAGAR PTR-2 8
NAGAR)
FDR-3 (SHAHEED
44 BBSR-1 BCDD-1 Mancheswar A SAHID NAGAR PTR-1 12.5
NAGAR)
FDR-3 (SHAHEED
45 BBSR-1 BCDD-1 Mancheswar A SAHID NAGAR PTR-1 12.5
NAGAR)
FDR-3 (SHAHEED
46 BBSR-1 BCDD-1 Mancheswar A SAHID NAGAR PTR-1 12.5
NAGAR)
FDR-3 (SHAHEED
47 BBSR-1 BCDD-1 Mancheswar A SAHID NAGAR PTR-2 12.5
NAGAR)
FDR-3 (SHAHEED
48 BBSR-1 BCDD-1 Mancheswar A SAHID NAGAR PTR-2 12.5
NAGAR)
FDR-3 (SHAHEED
49 BBSR-1 BCDD-1 Mancheswar A SAHID NAGAR PTR-2 12.5
NAGAR)
FDR-3 (SHAHEED
50 BBSR-1 BCDD-1 Mancheswar A SAHID NAGAR PTR-2 12.5
NAGAR)
FDR-3 (SHAHEED
51 BBSR-1 BCDD-1 Mancheswar A Board Colony PTR-1 12.5
NAGAR)
FDR-3 (SHAHEED
52 BBSR-1 BCDD-1 Mancheswar A Board Colony PTR-1 12.5
NAGAR)
FDR-3 (SHAHEED
53 BBSR-1 BCDD-1 Mancheswar A Board Colony PTR-1 12.5
NAGAR)
FDR-3 (SHAHEED
54 BBSR-1 BCDD-1 Mancheswar A Board Colony PTR-1 12.5
NAGAR)
FDR-3 (SHAHEED
55 BBSR-1 BCDD-1 Mancheswar A Board Colony PTR-1 12.5
NAGAR)
FDR-3 (SHAHEED
56 BBSR-1 BCDD-1 Mancheswar A Board Colony PTR-2 12.5
NAGAR)
FDR-3 (SHAHEED
57 BBSR-1 BCDD-1 Mancheswar A Board Colony PTR-2 12.5
NAGAR)
FDR-3 (SHAHEED
58 BBSR-1 BCDD-1 Mancheswar A Board Colony PTR-2 12.5
NAGAR)
UNIT-8 GIS-
63 BBSR-1 BCDD-1 UNIT-8 GIS DELTA PTR-1 8
BARAMUNDA(FDR-3)
UNIT-8 GIS-
64 BBSR-1 BCDD-1 UNIT-8 GIS DELTA PTR-1 8
BARAMUNDA(FDR-3)
UNIT-8 GIS-
65 BBSR-1 BCDD-1 UNIT-8 GIS DELTA PTR-2 8
BARAMUNDA(FDR-3)
UNIT-8 GIS-
66 BBSR-1 BCDD-1 UNIT-8 GIS DELTA PTR-2 8
BARAMUNDA(FDR-3)
FDR-1 (SAINIK (UNIT 2)MATER
67 BBSR-1 BCDD-1 Mancheswar A PTR-1 8
SCHOOL) CANTEEN ODSSP
FDR-1 (SAINIK (UNIT 2)MATER
68 BBSR-1 BCDD-1 Mancheswar A PTR-1 8
SCHOOL) CANTEEN ODSSP
FDR-1 (SAINIK (UNIT 2)MATER
69 BBSR-1 BCDD-1 Mancheswar A PTR-2 8
SCHOOL) CANTEEN ODSSP
FDR-1 (SAINIK (UNIT 2)MATER
70 BBSR-1 BCDD-1 Mancheswar A PTR-2 8
SCHOOL) CANTEEN ODSSP
-1 - 11kV Feeder Loading
Individual 11kV Feeder Peak 11kV Feeder Peak Load 13th
Date of Load 13th April-2022 April-2022, 23:00
Name of 11kV Feeder
Charging Peak Load Time Peak Load Time
(in A) (hh:mm) (in A) (hh:mm)
ASSEMBLY
RAJ BHAWAN
OERC
CBI
DELTA
UNIT-5
OUAT
G.B NAGAR
TELEPHONE BHAWAN
ASHOK NAGAR
UNIT-1 FEEDER
MEDICAL FEEDER
SM-RMU-07
SM-RMU-16
UNIT-6 FEEDER
BM-RMU-19
SM-RMU-08
BAPUJI NAGAR
RAM MANDIR
UNIT-3 FEEDER
JP RMU-41 FEEDER
SM-RMU-05 FEEDER
UNIT-2 FEEDER
BM-RMU-07/SHASTRI NAGAR
FEEDER
BM-RMU-23
BM-RMU-05
MADHUSUDAN FEEDER/RMU-
06 FEEDER
BM-RMU-22
SM-RMU-14
SM-RMU-15
PRESS FDR
RAHUL CO.
JP-RMU-14 FEEDER
SPARE/JP RMU 13
JP-RMU-45 FEEDER
JP RMU 40
SAHEED NAGAR-2(FEEDER-
2,SATYA NAGAR)
SAHEED NAGAR-4 (FEEDER-
4,PLAZA ROAD)
JP RMU-35 FEEDER
JP RMU-03 FEEDER
FLAT FEEDER/UNIT-9
BM-RMU-01
BM-RMU-02
SM-RMU-01
AG COLONY /NEW AG
COLONY/jp rmu 37
ACHARYA VIHAR (DEAD)/ jp
rmu 36
SM-RMU-02
PALLASHAPALLI
GANGANAGAR
JP RMU 34
AIRPORT
SATABDI NAGAR
FIRE STATION
SIRIPUR
UNIT-8 (SPARE)
ASHOK NAGAR
MARKET BUILDING
SUCHANA BHAWAN
JANAPATH
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
BCDD-2 - 11kV Feeder Loa
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
BARANGA
6 BBSR-1 BCDD-2 Mancheswar A FEEDER-5 PTR-1 8
KALARAHANGA
BARANGA
7 BBSR-1 BCDD-2 Mancheswar A FEEDER-5 PTR-1 8
KALARAHANGA
BARANGA
8 BBSR-1 BCDD-2 Mancheswar A FEEDER-5 PTR-2 8
KALARAHANGA
BARANGA
9 BBSR-1 BCDD-2 Mancheswar A FEEDER-5 PTR-2 8
KALARAHANGA
CHANDAKA
17 BBSR-1 BCDD-2 Ransinghpur BARAMUNDA PTR-1 8
ODSSP
CHANDAKA
18 BBSR-1 BCDD-2 Ransinghpur BARAMUNDA PTR-1 8
ODSSP
CHANDAKA
19 BBSR-1 BCDD-2 Ransinghpur BARAMUNDA PTR-2 8
ODSSP
CHANDAKA
20 BBSR-1 BCDD-2 Ransinghpur BARAMUNDA PTR-2 8
ODSSP
PTR-
27 BBSR-1 BCDD-2 Chandaka C.S.PUR-1 CS PUR-2 8
1(DEAD)
Ransinghpur
82 BBSR-1 BCDD-2 Ransinghpur RANASINGHPUR PTR-1 5
(ODSSP)
Ransinghpur
83 BBSR-1 BCDD-2 Ransinghpur RANASINGHPUR PTR-1 5
(ODSSP)
Ransinghpur
84 BBSR-1 BCDD-2 Ransinghpur RANASINGHPUR PTR-1 5
(ODSSP)
Ransinghpur PTR-
85 BBSR-1 BCDD-2 Ransinghpur RANASINGHPUR 5
(ODSSP) 2(DEAD)
FDR-1 (SAINIK
89 BBSR-1 BCDD-2 Mancheswar A Sainik School PTR-1 8
SCHOOL)
FDR-1 (SAINIK
90 BBSR-1 BCDD-2 Mancheswar A Sainik School PTR-1 8
SCHOOL)
FDR-1 (SAINIK
91 BBSR-1 BCDD-2 Mancheswar A Sainik School PTR-1 8
SCHOOL)
FDR-1 (SAINIK
92 BBSR-1 BCDD-2 Mancheswar A Sainik School PTR-2 8
SCHOOL)
FDR-1 (SAINIK
93 BBSR-1 BCDD-2 Mancheswar A Sainik School PTR-2 8
SCHOOL)
94 BBSR-1 BCDD-2 Chandaka BARANGA TRISULIA PTR-1 3.15
VANIVIHAR
97 BBSR-1 BCDD-2 Mancheswar A FDR-10 (VANI VIHAR) PTR-1 8
ODSSP
VANIVIHAR
98 BBSR-1 BCDD-2 Mancheswar A FDR-10 (VANI VIHAR) PTR-1 8
ODSSP
VANIVIHAR
99 BBSR-1 BCDD-2 Mancheswar A FDR-10 (VANI VIHAR) PTR-2 8
ODSSP
VANIVIHAR
100 BBSR-1 BCDD-2 Mancheswar A FDR-10 (VANI VIHAR) PTR-2 8
ODSSP
BARAMUNDA BDA
BARAMUNDA DELTA
CRPF FEEDER
BARAMUNDA RE-FEEDER
PATIA STATION
DHAWA
TANGI BANTA
INJANA
BHARATPUR RING/BHARAT
PUR
KHANDAGIRI
BHARATPUR BDA
SATELITE
SAMPUR
K-2
PHD
PATHARAGADIA
DASPUR
KUJI MAHAL
INDUSTRY
BDA
QUALITY CARE
DIST CENTER
SHREE VIHAR
RMRC & KH
ESIC HOSPITAL 1
BIDYADHARPUIR
MADHUBAN
TALAGARH
INDUSTRIAL/EPI CAST
NUAGAON
IIIT
PAIKRAYPUR
GODIBARI
JAYDEV VIHAR
NALCO
RENTAL
IRC-2
IRC-3
IRC-4
IRC-1
TRISULIA
ANDHARUA
-
NARANPUR
MADHUPUR
MUND MUHAN
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
BCDD-1 - 11kV Feeder Lo
Name of
Sl. Name of Name of
Name of Grid Name of 33kV Feeder Name of 33/11kV PSS 33/11kV
No. Circle Division
PTR
BHIMATANGI - II /
1 BBSR-1 BED Ransinghpur BADAGADA PTR-1
BARAGARH
BHIMATANGI - II /
2 BBSR-1 BED Ransinghpur BADAGADA PTR-1
BARAGARH
BHIMATANGI - II /
3 BBSR-1 BED Ransinghpur BADAGADA PTR-2
BARAGARH
BHIMATANGI - II /
4 BBSR-1 BED Ransinghpur BADAGADA PTR-2
BARAGARH
BHIMATANGI - II /
5 BBSR-1 BED Ransinghpur BADAGADA PTR-2
BARAGARH
BHIMATANGI - II /
6 BBSR-1 BED Ransinghpur BADAGADA PTR-2
BARAGARH
BHIMATANGI - II /
7 BBSR-1 BED Ransinghpur BADAGADA PTR-2
BARAGARH
8 BBSR-1 BED Kesura LAXMISAGAR (FDR-I) BADAGADA PTR-3
71 BBSR-1 BED
72 BBSR-1 BED
12.5 BRAHMESWAR
12.5 MAUSIMA
12.5 RAJARANI
12.5 CR-RMU 20
12.5 CR-RMU 21
12.5 BHUASUNI
10 WATER WORKS
10 B.J.B NAGAR/BJB
10 BADAGADA
10 SAI
10 CR-RMU -11
8 Dead
8 11kV Pokhariput-1
8 11kV Pokhariput-2
8 11kV Kalpana
5 TRINATH BAZAR
5 PAHAL
5 DPS
5 GOBINDPUR RE
12.5 JHARAPADA
12.5 LAXMISAGAR
12.5 KALPANA-2
12.5 BOMIKHAL
12.5 CR-RMU-6A/LS-RMU-6A
12.5 CR-RMU-5/LS-RMU-5
KALPANA-1/KALPANA
12.5
NAGAR
12.5 CR-RMU-6/LS-RMU-6
12.5 CR-RMU-14/LS-RMU-14
12.5 CR-RMU-15/LS-RMU-15
12.5 CR-RMU-16/LS-RMU-16
8 Balianta
8 Naharkanta
8 Atala
5 SBI COLONY
8 11kV Dhauli
8 11kV KEC
8 11kV Sardeipur
8 11kV Kausalya
5 GANGESWAR
5 BHINGARPUR
8 CUTTACK ROAD
8 BJB NAGAR
8 KALPANA FLAT
8 BARAGADA
8 MAHAVEER COTTAGE
8 KAPILESWAR
8 MULAPADIA
8 RATHA ROAD
8 CIFA/SAI MANDIR
8 GANGUA
8 SISHUPALA GADA
8 KUAKHAI/ LINGIPUR
8 PRACHI NAGAR
8 JAGANNATH
8 MANGARAJ POINT
8 PANDARA VILLAGE
5 RAJDHANI FEEDER
5 Hi-Tech Feeder
5 Panchagaon
5 PradhanSahi
5 Kalyani Plaza
V Feeder Peak Load 13th Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak
April-2022, 23:00 Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022
Time Peak Load Time Peak Load Time Peak Load Time
(hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm)
11kV Feeder Peak Load
23rd April-2022, 23:00
Peak Load Time
(in A) (hh:mm)
NED - 11kV Feeder Lo
Name of
Sl. Name of Name of
Name of Grid Name of 33kV Feeder Name of 33/11kV PSS 33/11kV
No. Circle Division
PTR
5 ANASARA
5 BALIDOKQAN
5 SIRIPUR
8 ODAP
8 KONARK O/H
8 KONARK U/G
8 Omfed
8 Charichhaka
8 Gop
8 Basantmala
Installed under DDUGJY ,
8
Presently remain idle
5 Bamanala
5 Dandipur
5 Payara
5 Gop
5 Begunia
5 Nagapur
3.15 Sundara
3.15 Jiunti
5 Astaranga
5 Satyabhamapur
5 Balakati
5 Balipatna
5 Budhipada
8 Narada
8 Banamalipur
5 Nuasantha
5 Bhanti
5 Davar
5 Banamalipur
5 Bhanara
5 Jaydev
5 Bangurigaon
5 Kolathakanta
5 Tikarapada
5 Dalanai
3.15 Charishree
5 Tulasipur
5 Binishpur
5 Nayahat
5 Mukundadaspur
5 Rajas (New)
5 Trahiachyuata nagar
5 Nayahat-1
5 Nayahat-2
5 Nilakanthapur
8 Kakatpur-11
8 Mangalapur-1
8 Mangalapur-2
8 Pipili Bazar
8 Rajas (Old)
5 Mallagaon
5 Nagapur Bazar
5 Madaranga
V Feeder Peak Load 13th Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak
April-2022, 23:00 Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022
Time Peak Load Time Peak Load Time Peak Load
(hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
ividual 11kV Feeder Peak 11kV Feeder Peak Load
Load 23rd April-2022 23rd April-2022, 23:00
Time Peak Load Time
(hh:mm) (in A) (hh:mm)
CDD-1 - 11kV Feeder Load
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
FDR-5
1 Cuttack CDD-1 Bidanasi SISUBHABAN PTR 1 12.5
(SISHUBHABAN)
FDR-5
2 Cuttack CDD-1 Bidanasi SISUBHABAN PTR 1 12.5
(SISHUBHABAN)
FDR-5
3 Cuttack CDD-1 Bidanasi SISUBHABAN PTR-2 12.5
(SISHUBHABAN)
FDR-5
4 Cuttack CDD-1 Bidanasi SISUBHABAN PTR-2 12.5
(SISHUBHABAN)
FDR-5
40 Cuttack CDD-1 Bidanasi DRDA PTR-1 8
(SISHUBHABAN)
FDR-5
41 Cuttack CDD-1 Bidanasi DRDA PTR-2 8
(SISHUBHABAN)
FDR-5
42 Cuttack CDD-1 DRDA PTR-2 8
(SISHUBHABAN)
High Court
Town Hall
Chandini Chowk
Ayakar Bhawan
CHOUDHURY BAZAR-I
CANTONEMENT -II
GORA KABAR
JNI STADIUM
LOWER GROUND
UPPER GROUND
CANTONMENT-I
CHOUDHURY BAZAR-II
HIGH COURT
SRIVIHAR
DOORDARSHAN OH
CHANDI MANDIR
TELEPHONE BHAWAN
RANIHAT BAZAR
MEDICAL-2
MANGALABAG
MEDICAL-1
KAZIBAZAR
GANESHGHAT
JOUDGE COURT
TREASERY
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
CDD-2 - 11kV Feeder Load
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
FDR-6(CHAULIGANJ-
15 Cuttack CDD-2 CUTTACK OGP PTR-1 12.5
II)
FDR-6(CHAULIGANJ-
16 Cuttack CDD-2 CUTTACK OGP PTR-1 12.5
II)
FDR-6(CHAULIGANJ-
17 Cuttack CDD-2 CUTTACK OGP PTR-2 8
II)
FDR-6(CHAULIGANJ-
18 Cuttack CDD-2 CUTTACK OGP PTR-2 8
II)
19 Cuttack CDD-2 CUTTACK FDR-8 (CRRI-I) CRRI PTR-1 8
JAGATPUR
31 Cuttack CDD-2 CHOUDWAR FDR-6(JAGATPUR) PTR-1 8
(IPICOL) ODSSP
JAGATPUR
32 Cuttack CDD-2 CHOUDWAR FDR-6(JAGATPUR) PTR-1 8
(IPICOL) ODSSP
JAGATPUR
33 Cuttack CDD-2 CHOUDWAR FDR-6(JAGATPUR) PTR-2 8
(IPICOL) ODSSP
FDR-9
34 Cuttack CDD-2 CUTTACK KANDARPUR PTR-1 5
(JAGATSINGHPUR)
FDR-9
35 Cuttack CDD-2 CUTTACK KANDARPUR PTR-1 5
(JAGATSINGHPUR)
FDR-9
36 Cuttack CDD-2 CUTTACK KANDARPUR PTR-2 5
(JAGATSINGHPUR)
FDR-9
37 Cuttack CDD-2 CUTTACK KANDARPUR PTR-2 5
(JAGATSINGHPUR)
FDR-9
38 Cuttack CDD-2 CUTTACK KISHAN NAGAR PTR-1 3.15
(JAGATSINGHPUR)
FDR-9
39 Cuttack CDD-2 CUTTACK KISHAN NAGAR PTR-2 3.15
(JAGATSINGHPUR)
FDR-9
40 Cuttack CDD-2 CUTTACK KISHAN NAGAR PTR-2 3.15
(JAGATSINGHPUR)
FDR-9
41 Cuttack CDD-2 CUTTACK KISHAN NAGAR PTR-3 5
(JAGATSINGHPUR)
FDR-9
42 Cuttack CDD-2 CUTTACK KISHAN NAGAR PTR-3 5
(JAGATSINGHPUR)
FDR-9
43 Cuttack CDD-2 CUTTACK SOMAPUR ODSSP PTR-1 5
(JAGATSINGHPUR)
FDR-9
44 Cuttack CDD-2 CUTTACK SOMAPUR ODSSP PTR-2 5
(JAGATSINGHPUR)
FDR-9
45 Cuttack CDD-2 CUTTACK SOMAPUR ODSSP PTR-2 5
(JAGATSINGHPUR)
MAHANADI VIHAR
46 Cuttack CDD-2 BIDANASI FDR- 2(TULSIPUR 2) PTR-1 8
ODSSP
MAHANADI VIHAR
47 Cuttack CDD-2 BIDANASI FDR- 2(TULSIPUR 2) PTR-1 8
ODSSP
MAHANADI VIHAR
48 Cuttack CDD-2 BIDANASI FDR- 2(TULSIPUR 2) PTR-2 8
ODSSP
MAHANADI VIHAR
49 Cuttack CDD-2 BIDANASI FDR- 2(TULSIPUR 2) PTR-2 8
ODSSP
BADAMBADI-1
BADAMBADI-2
Badambadi to Kalyaninagar
DOLMUNDAI-1/Badambadi to
OGP
DOLMUNDAI-2
JHINKIRIA
KALAPADA
CHANDULI
BENTAKAR
RING-1
MAHANADI
CHAULIAGANJ-2
CHAULIAGANJ-1
KALYANINAGAR
INDUSTRIAL-1
KATHAJODI
INDUSTRIAL-2
OGP&GHOSALA
NAYABAZAR
CRRI
MAHANADIBIHAR
AIR
MATAGAJPUR
JAICA
POPARDA
PHD
ODIE
NADIKULA
IDCO
BARRAGE
KHAIRA
MAHANADI
NEW INDUSTRIAL
AIR
KANDARPUR
PARAMAHANSA
AYETPUR
KISHAN NAGAR
SOMPUR-1
RAMCHANDRAPUR
MALIPUR
BISWALPUR
TELDIA
SOMPUR-2
RAMKUMARPUR
MAHANADIBIHAR-1
MAHANADIBIHAR-2
GANDARPUR
SIKHARPUR
Mahatab
Haripur
OSAP
Divine Nagar
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
CED - 11kV Feeder Loadi
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
CUTTACK
8 Cuttack CED FDR-1(BALIKUDA) GOPALPUR PTR-1 8
GRID
CUTTACK
9 Cuttack CED FDR-1(BALIKUDA) GOPALPUR PTR-2 8
GRID
CUTTACK
10 Cuttack CED FDR-1(BALIKUDA) GOPALPUR PTR-2 8
GRID
FDR-
CHOUDWAR
14 Cuttack CED 4(BAJARANGBALI/ CHOUDWAR PTR-1 12.5
GRID
CHOUDWAR)
FDR-
CHOUDWAR
15 Cuttack CED 4(BAJARANGBALI/ CHOUDWAR PTR-1 12.5
GRID
CHOUDWAR)
FDR-
CHOUDWAR
16 Cuttack CED 4(BAJARANGBALI/ CHOUDWAR PTR-1 12.5
GRID
CHOUDWAR)
FDR-
CHOUDWAR
17 Cuttack CED 4(BAJARANGBALI/ CHOUDWAR PTR-2 8
GRID
CHOUDWAR)
FDR-
CHOUDWAR
18 Cuttack CED 4(BAJARANGBALI/ CHOUDWAR PTR-2 8
GRID
CHOUDWAR)
FDR-
CHOUDWAR
19 Cuttack CED 4(BAJARANGBALI/ CHOUDWAR PTR-2 8
GRID
CHOUDWAR)
NADIAGURUDI FDR-
20 Cuttack CED DAMODARPUR PTR-1 3.15
GRID 2(DAMODARPUR)
NADIAGURUDI FDR-
21 Cuttack CED DAMODARPUR PTR-1 3.15
GRID 2(DAMODARPUR)
NADIAGURUDI FDR-
22 Cuttack CED DAMODARPUR PTR-2 8
GRID 2(DAMODARPUR)
BALICHANDRAPU
26 Cuttack CED BALIA GRID FDR-1 (MAHANGA) PTR-1 5
R
BALICHANDRAPU
27 Cuttack CED BALIA GRID FDR-1 (MAHANGA) PTR-1 5
R
BALICHANDRAPU
28 Cuttack CED BALIA GRID FDR-1 (MAHANGA) PTR-2 3.15
R
BALICHANDRAPU
29 Cuttack CED BALIA GRID FDR-1 (MAHANGA) PTR-3 3.15
R
BALICHANDRAPU
30 Cuttack CED BALIA GRID FDR-1 (MAHANGA) PTR-4 8
R
NADIAGURUDI
31 Cuttack CED FDR-1(NIALI) NIALI PTR-1 5
GRID
NADIAGURUDI
32 Cuttack CED FDR-1(NIALI) NIALI PTR-2 3.15
GRID
NADIAGURUDI
33 Cuttack CED FDR-1(NIALI) NIALI PTR-3 8
GRID
NADIAGURUDI
34 Cuttack CED FDR-1(NIALI) NIALI PTR-3 8
GRID
NADIAGURUDI
35 Cuttack CED FDR-1(NIALI) ADASPUR PTR-1 5
GRID
NADIAGURUDI
36 Cuttack CED FDR-1(NIALI) ADASPUR PTR-2 5
GRID
NADIAGURUDI
37 Cuttack CED FDR-1(NIALI) ADASPUR PTR-3 3.15
GRID
NADIAGURUDI
38 Cuttack CED FDR-1(NIALI) KASARDA PTR-1 3.15
GRID
NADIAGURUDI
39 Cuttack CED FDR-1(NIALI) KASARDA PTR-1 3.15
GRID
NADIAGURUDI
40 Cuttack CED FDR-1(NIALI) KASARDA PTR-2 3.15
GRID
CHOUDWAR
41 Cuttack CED FDR-1(ATHAGARH) SANKARPUR PTR-1 5
GRID
CHOUDWAR
42 Cuttack CED FDR-1(ATHAGARH) SANKARPUR PTR-2 5
GRID
CHOUDWAR
43 Cuttack CED FDR-1(ATHAGARH) SANKARPUR PTR-2 5
GRID
CHOUDWAR
44 Cuttack CED FDR-3(TANGI) TANGI PTR-1 5
GRID
CHOUDWAR
45 Cuttack CED FDR-3(TANGI) TANGI PTR-2 5
GRID
CHOUDWAR
46 Cuttack CED FDR-3(TANGI) TANGI PTR-3 3.15
GRID
CHOUDWAR
47 Cuttack CED FDR-3(TANGI) TANGI PTR-4 5
GRID
CHOUDWAR
48 Cuttack CED FDR-3(TANGI) TANGI PTR-4 5
GRID
PHULNAKHAR
53 Cuttack CED NIALI KULAKAPASI PTR-1 5
A GRID
PHULNAKHAR
54 Cuttack CED NIALI KULAKAPASI PTR-1 5
A GRID
PHULNAKHAR
55 Cuttack CED NIALI KULAKAPASI PTR-2 5
A GRID
- 11kV Feeder Loading
Individual 11kV Feeder Peak 11kV Feeder Peak Load 13th
Date of Load 13th April-2022 April-2022, 23:00
Name of 11kV Feeder
Charging Peak Load Time Peak Load Time
(in A) (hh:mm) (in A) (hh:mm)
BANIPADA
CHOUDWAR IE
KUSPANGI
BADACHANA
SAKUNTALAPUR
BALICHANDRAPUR
CHANDIKHOLE
BARANGA
UTTAMPUR
42-MAUZA
CHHATIA(+ KADEI+BANDAL)
BAIRI(+MANDIR)
CHAMPAPUR
ARC
OTM
LOCAL
CHOUDWAR
CITY BARRAGE
NUNTIKRI
NIRTAR
GOBINDPUR-1
SUNDARGRAM
NAHALPUR
KHALARDA
GOBINDPUR-2
BANDANESWAR
MANITRI
BALICHANDRAPUR(+Kusupur)
Rukutipata
Charinangal
TOWN
KALIAGHAI
Krushnaparasad/Tola
PAHANGA
Adaspur
Eranch/Uttarana
Sithalo
KASARDA
ERANCH
KULASHRI(+SITHALO)
SANKARPUR
MANGARAJPUR
BEHRAMPUR
HARIPUR
MANGULI
BHATIMUNDA
LOCAL
NH-5
SALAPADA
SIHA
THEGUNDA
LOCAL
PANIMALA
PODANA
ARAKATA
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
AED - 11kV Feeder Loading
Name of PTR
Sl. Name of Name of Name of
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division 33/11kV PSS
PTR (in MVA)
Badamba Town
Ragadpada
Ratapata
Gopinathpur
Gopamathura
Nuapatna
Maniabandha
Narsinghpur
Nukhapada
Joypur
Kamaladiha(Old)
Kakudia
Balisahi
Odisingha
Kamaladhia(NEW)
Mahalaxmipur
Khuntuni
Gurudijhatia(OLD)
Town
Kantolo
Rasol
Karikolo
Ankulo
Dodora
Gurudihatia
Kumarpur
Megha
Mancheswar
Megha
Lift Irrigation
Tigira
Puruna Tigira
Panchagaan
Bindhanima
Khuntakanta
Godijharia
Kanpur
Balijharia
Baselihata
Godibandha
Ratapata-2
Bhatarika
Gopapur Local
Badakambilo
Banagerisingha
Badabarsingh
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
SED - 11kV Feeder Loadi
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
CHOUDWAR
1 Cuttack SED FDR- 5 ( BAHUGRAM) BAHUGRAM-1(old) PTR-1 5
GRID
CHOUDWAR
2 Cuttack SED FDR- 5 ( BAHUGRAM) BAHUGRAM-1(old) PTR-2 5
GRID
CHOUDWAR BAHUGRAM-
3 Cuttack SED FDR- 5 ( BAHUGRAM) PTR-1 5
GRID 2(new)
CHOUDWAR BAHUGRAM-
4 Cuttack SED FDR- 5 ( BAHUGRAM) PTR-2 5
GRID 2(new)
CHOUDWAR BAHUGRAM-
5 Cuttack SED FDR- 5 ( BAHUGRAM) PTR-2 5
GRID 2(new)
PADMAPUR
ICHHAPUR
PURANA
PATAPUR
GOPINATHPUR
Kurujanga
JAIPUR
MULABASANTA
BASUDEVPUR
KAUNPAL
CHAINPAL
MAHANGA
MANOHARPUR
RAISUNGUDA BAZAR
DHARMAGATPUR
RAMKRUSHNAPUR
BUHALO
UMAR
GOPINATHPUR
SOGAL
BILAHATA
RAISUGUNDA
NAIGUAN
BAZAR
KHANDASAHI
SOURI RAMESWAR
MALA
MOUDA
JAPAKUDA
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
DED - 11kV Feeder L
Name of
Sl. Name of Name of
Name of Grid Name of 33kV Feeder Name of 33/11kV PSS 33/11kV
No. Circle Division
PTR
PANCHUPADA/
39 Dhenkanal DED HINDOL HINDOL PTR-1
KHAJURIAKATA
PANCHUPADA/
40 Dhenkanal DED HINDOL HINDOL PTR-2
KHAJURIAKATA
PANCHUPADA/
57 Dhenkanal DED KHAJURIAKATA KHAJURIKATA PTR-1
KHAJURIAKATA
PANCHUPADA/
58 Dhenkanal DED KHAJURIAKATA KHAJURIKATA PTR-2
KHAJURIAKATA
PANCHUPADA/
59 Dhenkanal DED KHAJURIAKATA KHAJURIKATA PTR-3
KHAJURIAKATA
MAHULAPAL PTR-1
MAHULAPAL PTR-1
PANCHUPADA/
77 Dhenkanal DED HINDOL NUABAG PTR-1
KHAJURIAKATA
PANCHUPADA/
78 Dhenkanal DED HINDOL NUABAG PTR-1
KHAJURIAKATA
PANCHUPADA/
79 Dhenkanal DED HINDOL NUABAG PTR-2
KHAJURIAKATA
DED - 11kV Feeder Loading
Individual 11kV Feeder Peak 11kV Feeder Peak Load 13th
PTR Load 13th April-2022 April-2022, 23:00
Date of
Rating Name of 11kV Feeder
Charging Peak Load Time Peak Load
(in MVA)
(in A) (hh:mm) (in A)
5 Kamakhyanagar Town - I
Kamakhyanagar Town - II
5
OR Baunsapal
5 Baunsapal
5 Kadua
3.15 Mahulpal
3.15 Gundichanali
5 Banasingh
5 Chaulia
3.15 Ghatipiri
5 Bhapur
5 Lambodarpur
5 Town
5 Mahulpal Or Town -2
5 Bhusal
5 Antapur
5 Padan
8 Dhenkanal Town - I
8 Dhenkanal Town - II
8 Saptasajya
3.15 Govindapur
5 Joranda
8 Sasan
8 Deulasahi
8 Kantanali
8 koria
3.15 Goda
3.15 Baruan
5 Mandar
5 Pasupati
5 Pingua
5 Ankurda
5 Gondia
3.15 Kapilash
8 caltax
8 PHD
8 Bhapur
8 Industrial
8 Siminai
5 Hindol
5 Dudurkote
5 4 Pole
3.15 Bazar
8 Badalo
8 Nimidha
5 Kanapura
5 Baisinga
5 Jiridamali
5 Natima
5 Kaluria
5 Karamula
3.15 Bazar
3.15 Kansa
3.15 Chingudipal
3.15 Urbengi
3.15 Rupabeda
3.15 Dandadhara
3.15 Bedapada
5 Rasol
3.15 Kalinga
3.15 Jiral
3.15 Marthapur
3.15 Balisahi
3.15 Beleisahi
5 Guneibili
5 Birasal
5 Surapratappur
5 Kanheipal
3.15 Nihalprasad
3.15 Kasipur
5 Analabereni
5 Baruan
5 Kotagara
5 Sogar
5 Similia
5 Tarava
5 Chaulia
5 Nuabag
5 Rasol
5 Naukiari
V Feeder Peak Load 13th Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak
April-2022, 23:00 Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022
Time Peak Load Time Peak Load Time Peak Load
(hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
ividual 11kV Feeder Peak 11kV Feeder Peak Load
Load 23rd April-2022 23rd April-2022, 23:00
Time Peak Load Time
(hh:mm) (in A) (hh:mm)
TED - 11kV Feeder Loadi
Name of
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV
No. Circle Division PSS
PTR
3.15 Jagannathapur
3.15 Gurudwar
5 Gobara
8 Kulad
8 Chainpal
8 Hindol
8 Meramandali
1.6 Dangarbeda/TUMUGULA
1.6 Baruan/KULEI
5 Bhogabereni
5 Ballahar
Gotamara
8 Danara
8 Kalamchhuin
8 Gopalprasad
8 BadaJorada
5 Bajrakote
5 Gunduri
8 Talcher Town-II
8 LIC
8 Godibandha
8 Hatotota RE-I
8 Hatotota RE-II
5 Talcher Town-I
8 Kaniha-II
8 Karadei
8 Dereng
8 Kaniha RE-I
8 Kaniha RE-II
1.6 Kaniha-I
1.6 Kiajhar
5 Sankhamur
5 Barakotia
3.15 Odasha
5 Injidi
5 Nuagaon
5 Rajadang
5 Pallahara Town
5 Seegarh
5 Kantala
3.15 Batisuan/ Farm
3.15 Phopond
1.6 PARABIL
3.15 Arkil
3.15 Gaham
5 Mahabiroad
5 Kualo
5 New Parjang
5 Old Parjang
5 Kandarsingha
5 RN Pur
5 Sarang
5 Rengali
3.15 Rengali
3.15 PGCIL
5 SAANDA
5 PANIGENGUTIA
1.6 Bijigol
1.6 Samal Barage
1.6 Samal Colony
1.6 Samal village
1.6 IGIT SARANG
5 Jatia
5 Sarang-II
5 Basulei
5 Jharanabahal
5 Dadraghati
5 VEJIA
8 Bantol
8 Handidhua
8 ITI Feeder
V Feeder Peak Load 13th Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak
April-2022, 23:00 Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022
Time Peak Load Time Peak Load Time Peak Load
(hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
ividual 11kV Feeder Peak 11kV Feeder Peak Load
Load 23rd April-2022 23rd April-2022, 23:00
Time Peak Load Time
(hh:mm) (in A) (hh:mm)
ANED - 11kV Feeder Loading
Name of PTR
Sl. Name of Name of Name of Name of 33kV Name of 33/11kV
33/11kV Rating
No. Circle Division Grid Feeder PSS
PTR (in MVA)
RAIRAKH
12 Dhenkanal ANED BAMUR BAMUR PTR-1 5
OL
RAIRAKH
13 Dhenkanal ANED BAMUR BAMUR PTR-1 5
OL
RAIRAKH
14 Dhenkanal ANED BAMUR BAMUR PTR-1 5
OL
RAIRAKH
15 Dhenkanal ANED BAMUR BAMUR PTR-1 5
OL
RAIRAKH
32 Dhenkanal ANED BAMUR DAURAPALLI PTR-1 3.15
OL
RAIRAKH
33 Dhenkanal ANED BAMUR DAURAPALLI PTR-1 3.15
OL
RAIRAKH
34 Dhenkanal ANED BAMUR DAURAPALLI PTR-2 3.15
OL
RAIRAKH
35 Dhenkanal ANED BAMUR DAURAPALLI PTR-2 3.15
OL
INDUSTRIAL
41 Dhenkanal ANED ANGUL ANGUL 2 PTR-1 5
ESTATE
INDUSTRIAL
42 Dhenkanal ANED ANGUL ANGUL 2 PTR-2 7.5
ESTATE
INDUSTRIAL
43 Dhenkanal ANED ANGUL ANGUL 2 PTR-2 7.5
ESTATE
RAIRAKH
54 Dhenkanal ANED BAMUR NAKCHI PTR-1 5
OL
RAIRAKH
55 Dhenkanal ANED BAMUR NAKCHI PTR-1 5
OL
RAIRAKH
56 Dhenkanal ANED BAMUR NAKCHI PTR-2 5
OL
Kutulisinga
Thakurgarh
Krutibash Pur
Ghodabandhuni
Binkei
Puruna manitri
Jadupur
Baghuakata
Athamallik Town
Badakera
Dudhiabeda
Fasipal
Ambapal
Brahmanidei
Nakchi/Khairamunda
Khinda
Sarangapur/tumugal
Bantala
Sabal bhanga
Luhamunda
Boinda local
Handapa
Paika sahi
Sanahulla
Jamunali
Bagedia
Pipalabahal
Bahalasahi
Chhendipada
Brahmanbil
Dubanali
Kadalimunda
Kishorenagar
Talapadar
Raniakata
Hemasarapda
Sikhyakapada
Jarasingha
MCL
Medical
Industrial
Estate(Tamrit Colony)
Kurudul/NALCO
To Zeith Carbon
Katada
Railway
Kanjara
Jagannathpur
Kosala
Kosala Local
Madhapur
Nilakanthapada
Kiakata
Lunahandi
Urukula
Budulimunda
Nakchi
Turanga
Gopinathpur( Benthap
ur)
Angul Town - I
Angul Town - II
College
Angul Town - IV
Angul R.E-I
Angul R.E-II
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
KED-1 - 11kV Feeder Loadin
Name of
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV
No. Circle Division PSS
PTR
ADHAJORI/
1 Paradeep KED-01 PATTAMUNDAI RAJANAGAR PTR-1
PATTAMUNDAI-II
ADHAJORI/
2 Paradeep KED-01 PATTAMUNDAI RAJANAGAR PTR-2
PATTAMUNDAI-II
ADHAJORI/
3 Paradeep KED-01 PATTAMUNDAI RAJANAGAR PTR-2
PATTAMUNDAI-II
BALARAMPUR/ BALARAMPUR/
9 Paradeep KED-01 OLAVER PTR-1
OLAVER OLAVER
BALARAMPUR/ BALARAMPUR/
10 Paradeep KED-01 OLAVER PTR-1
OLAVER OLAVER
BALARAMPUR/ BALARAMPUR/
11 Paradeep KED-01 OLAVER PTR-1
OLAVER OLAVER
DUHURIA/
14 Paradeep KED-01 LUNA CHHAGHARIA PTR-1
KENDRAPARA
DUHURIA/
15 Paradeep KED-01 LUNA CHHAGHARIA PTR-1
KENDRAPARA
DUHURIA/
16 Paradeep KED-01 LUNA CHHAGHARIA PTR-2
KENDRAPARA
DUHURIA/
17 Paradeep KED-01 INDUPUR CHHATA PTR-1
KENDRAPARA
DUHURIA/
18 Paradeep KED-01 INDUPUR CHHATA PTR-1
KENDRAPARA
DUHURIA/
19 Paradeep KED-01 LUNA CHOKODA PTR-1
KENDRAPARA
DUHURIA/
20 Paradeep KED-01 LUNA CHOKODA PTR-1
KENDRAPARA
DUHURIA/
21 Paradeep KED-01 LUNA CHOKODA PTR-2
KENDRAPARA
DUHURIA/
24 Paradeep KED-01 DANPUR DANPUR PTR-1
KENDRAPARA
DUHURIA/
25 Paradeep KED-01 DANPUR DANPUR PTR-1
KENDRAPARA
DUHURIA/
26 Paradeep KED-01 DANPUR DANPUR PTR-2
KENDRAPARA
DUHURIA/
27 Paradeep KED-01 DANPUR DKBHOLA PTR-1
KENDRAPARA
DUHURIA/
28 Paradeep KED-01 DANPUR DKBHOLA PTR-2
KENDRAPARA
DUHURIA/ DUHURIA/AUL-
29 Paradeep KED-01 DUHURIA PTR-1
KENDRAPARA PATTAMUNDAI
DUHURIA/ DUHURIA/AUL-
30 Paradeep KED-01 DUHURIA PTR-1
KENDRAPARA PATTAMUNDAI
DUHURIA/ DUHURIA/AUL-
31 Paradeep KED-01 DUHURIA PTR-1
KENDRAPARA PATTAMUNDAI
DUHURIA/
34 Paradeep KED-01 INDUPUR INDUPUR PTR-1
KENDRAPARA
DUHURIA/
35 Paradeep KED-01 INDUPUR INDUPUR PTR-1
KENDRAPARA
DUHURIA/
36 Paradeep KED-01 INDUPUR INDUPUR PTR-2
KENDRAPARA
DUHURIA/
37 Paradeep KED-01 INDUPUR INDUPUR PTR-2
KENDRAPARA
DUHURIA/
40 Paradeep KED-01 KENDRAPADA KENDRAPADA PTR-1
KENDRAPARA
DUHURIA/
41 Paradeep KED-01 KENDRAPADA KENDRAPADA PTR-2
KENDRAPARA
DUHURIA/
42 Paradeep KED-01 KENDRAPADA KENDRAPADA PTR-3
KENDRAPARA
DUHURIA/
43 Paradeep KED-01 KENDRAPADA KENDRAPADA PTR-4
KENDRAPARA
DUHURIA/
44 Paradeep KED-01 KENDRAPADA KENDRAPADA PTR-5
KENDRAPARA
PATTAMUNDAI KHAMAR
68 Paradeep KED-01 GOGUA PTR-1
GRID KESHPUR
PATTAMUNDAI KHAMAR
69 Paradeep KED-01 GOGUA PTR-2
GRID KESHPUR
PATTAMUNDAI KHAMAR
70 Paradeep KED-01 GOGUA PTR-2
GRID KESHPUR
3.15 DAMARPUR
5 Koriapala
5 CHANDAN NAGAR
5 AUL
3.15 MENDHAPUR
3.15 CHOTOKANIKA
3.15 BHUINPUR
3.15 SASAN
5 OLAVER
5 HATASAHI
5 DASIPUR
5 GHAGARA
5 CHAUDAKULAT
5 KANSAR
5 Baladevjew
AJODHYANAGAR/
5
BLOCK
3.15 DANDISAHI
3.15 BERHAMPUR
11KV Janara
5 75A 22:00 75A 23:00
Barimula
LAW
5
COLLEGE(NO.2)
CHHAGORIA(SPAR
5
E)
5 DUHURIA(NO.1)
5 NAPANGA
5 DOBANDA
1.6 INDUPUR
1.6 DHUMAT
3.15 NIKIRAI
3.15 BAIRI
5 JARIMULA
BALARAM
5
PUR/ISWARPUR
3.15 TINIMUHANI
5 BATIPADA
5 DASIPUR
5 JHARIA
5 BALIPATNA
5 BELTAL
5 BALADEV NAGAR
5 BAZAR
3.15 OSTIA
5 GIRIA
BAZAR(KANTAPAD
5
A)
3.15 VARIGUDA
3.15 OLAVER
5 KERADAGARA
5 KOILIPUR
5 MADANPUR
5 RAJNAGAR
5 Barpara
5 Gangarangpur
5 GOVINDAPUR
5 MAHARAKULA
5 SPARE
8 ISWARPUR
8 TALCHUA
5 AYATAN
5 NAHULIA
5 JAYNAGAR
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
23:00
KED-2 - 11kV Feeder Load
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
MARSHAGHAI
1 Paradeep KED-02 MAHAKALPADA BADHI/BABAR PTR-1 3.15
GRID
MARSHAGHAI
2 Paradeep KED-02 MAHAKALPADA BADHI/BABAR PTR-2 3.15
GRID
MARSHAGHAI
3 Paradeep KED-02 MAHAKALPADA BADHI/BABAR PTR-2 3.15
GRID
MARSHAGHAI
4 Paradeep KED-02 LUNA GARADPUR PTR-1 3.15
GRID
MARSHAGHAI
5 Paradeep KED-02 LUNA GARADPUR PTR-2 3.15
GRID
DUHURIA
6 Paradeep KED-02 GRID/KENDRA DANPUR KORUA/kudanagari PTR-1 5
PARA GRID
DUHURIA
7 Paradeep KED-02 GRID/KENDRA DANPUR KORUA/kudanagari PTR-1 5
PARA GRID
DUHURIA
8 Paradeep KED-02 GRID/KENDRA DANPUR KORUA/kudanagari PTR-2 3.15
PARA GRID
DUHURIA
9 Paradeep KED-02 GRID/KENDRA DANPUR KORUA/kudanagari PTR-3 3.15
PARA GRID
MARSHAGHAI
10 Paradeep KED-02 LUNA LUNA PTR-1 5
GRID
MARSHAGHAI
11 Paradeep KED-02 LUNA LUNA PTR-1 5
GRID
MARSHAGHAI
12 Paradeep KED-02 LUNA LUNA PTR-2 5
GRID
MARSHAGHAI
13 Paradeep KED-02 LUNA LUNA PTR-2 5
GRID
MARSHAGHAI
14 Paradeep KED-02 LUNA LUNA PTR-3 1.6
GRID
MARSHAGHAI
15 Paradeep KED-02 LUNA LUNA PTR-4 5
GRID
MARSHAGHAI
16 Paradeep KED-02 MAHAKALPADA MAHAKALPADA PTR-1 5
GRID
MARSHAGHAI
17 Paradeep KED-02 MAHAKALPADA MAHAKALPADA PTR-2 3.15
GRID
MARSHAGHAI
18 Paradeep KED-02 MAHAKALPADA MAHAKALPADA PTR-3 3.15
GRID
MARSHAGHAI
19 Paradeep KED-02 MAHAKALPADA MARSHAGHAI PTR-1 5
GRID
MARSHAGHAI
20 Paradeep KED-02 MAHAKALPADA MARSHAGHAI PTR-1 5
GRID
MARSHAGHAI
21 Paradeep KED-02 MAHAKALPADA MARSHAGHAI PTR-2 5
GRID
MARSHAGHAI
22 Paradeep KED-02 MAHAKALPADA THAURI PTR-1 8
GRID
MARSHAGHAI
23 Paradeep KED-02 MAHAKALPADA THAURI PTR-2 8
GRID
MARSHAGHAI
24 Paradeep KED-02 LUNA BEDARI PTR-1 8
GRID
MARSHAGHAI
25 Paradeep KED-02 LUNA BEDARI PTR-1 8
GRID
BIJAYANAGAR
BABAR
JAMBOO
GARADPUR-1
GARADPUR-2
BANAKHUDA
NARENDRA PUR
NAGAN PUR
KORUA
NALADIA
ANKO
OSTAR
KARANJA
PATKURA
CHAPALI
MAHAKALPADA
DASAMOUZI
MARSHAGHAI
SILIPUR
ANGULAI
ORTHAGHAT
KURUTUNGA
ANTEI
PATKURA NEW
-
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
23rd April-2022, 23:00 Load 25rd April-2022 25rd April-2022, 14:00
Time Peak Load Time Peak Load Time
(hh:mm) (in A) (hh:mm) (in A) (hh:mm)
PDP - 11kV Feeder Loa
Name of
Sl. Name of Name of
Name of Grid Name of 33kV Feeder Name of 33/11kV PSS 33/11kV
No. Circle Division
PTR
PARADEEP
1 Paradeep PDP BIJAYACHANDRAPUR BIJAYACHANDRAPUR PTR-1
GRID
PARADEEP
2 Paradeep PDP BIJAYACHANDRAPUR BIJAYACHANDRAPUR PTR-2
GRID
KRISHNANDAPUR
15 Paradeep PDP TIRTOL GRID TIRTOL/BODHEI PTR-1
(SIBAPUR)/ KOLAR
KRISHNANDAPUR
16 Paradeep PDP TIRTOL GRID TIRTOL/BODHEI PTR-1
(SIBAPUR)/ KOLAR
KRISHNANDAPUR
17 Paradeep PDP TIRTOL GRID TIRTOL/BODHEI PTR-2
(SIBAPUR)/ KOLAR
KRISHNANDAPUR
18 Paradeep PDP TIRTOL GRID TIRTOL/BODHEI PTR-2
(SIBAPUR)/ KOLAR
PARADEEP
19 Paradeep PDP TIRTOL KUJANG PTR-1
GRID
PARADEEP
20 Paradeep PDP TIRTOL KUJANG PTR-2
GRID
PARADEEP
21 Paradeep PDP TIRTOL KUJANG PTR-3
GRID
PARADEEP
22 Paradeep PDP TIRTOL KUJANG PTR-3
GRID
PARADEEP
23 Paradeep PDP PARADEEP PARADEEPGARH PTR-1
GRID
PARADEEP
24 Paradeep PDP PARADEEP PARADEEPGARH PTR-2
GRID
PARADEEP
25 Paradeep PDP PARADEEP PARADEEPGARH PTR-2
GRID
PARADEEP
26 Paradeep PDP PARADEEP PARADEEPGARH PTR-3
GRID
PARADEEP
27 Paradeep PDP PARADEEP PARADEEPGARH PTR-3
GRID
PARADEEP
30 Paradeep PDP TIRTOL RAHAMA PTR-1
GRID
PARADEEP
31 Paradeep PDP TIRTOL RAHAMA PTR-1
GRID
PARADEEP
32 Paradeep PDP TIRTOL RAHAMA PTR-2
GRID
PARADEEP
33 Paradeep PDP TIRTOL RAHAMA PTR-2
GRID
JAGATSINGH
34 Paradeep PDP TIRTOL TIRTOL PTR-1
PUR GRID
JAGATSINGH
35 Paradeep PDP TIRTOL TIRTOL PTR-2
PUR GRID
JAGATSINGH
36 Paradeep PDP TIRTOL TIRTOL PTR-2
PUR GRID
JAGATSINGH
37 Paradeep PDP TIRTOL TIRTOL PTR-3
PUR GRID
PARADEEP
38 Paradeep PDP JHIMANI JHIMANI PTR-1
GRID
PARADEEP
39 Paradeep PDP JHIMANI JHIMANI PTR-1
GRID
PARADEEP
40 Paradeep PDP JHIMANI JHIMANI PTR-2
GRID
PARADEEP
41 Paradeep PDP JHIMANI TRILOCHANPUR PTR-1
GRID
PARADEEP
42 Paradeep PDP JHIMANI TRILOCHANPUR PTR-2
GRID
PARADEEP
43 Paradeep PDP JHIMANI TRILOCHANPUR PTR-2
GRID
PDP - 11kV Feeder Loading
Individual 11kV Feeder Peak 11kV Feeder Peak Load 13th
PTR Load 13th April-2022 April-2022, 23:00
Date of
Rating Name of 11kV Feeder
Charging Peak Load Time Peak Load
(in MVA)
(in A) (hh:mm) (in A)
5 HANDIA
5 BIJAYACHANDRAPUR
5 ERASAMA
5 KOTHI
3.15 PANCHAPALLI
3.15 AMBIKI
5 BAILO
5 PANDUA
5 NUAPOKHARI
8 DIHASAHI
8 JAGANNATH PUR
8 KANAKPUR-2
8 GOVINDPUR
8 Spare
5 PAIKAKULA
5 KRISHNANDAPUR
5 DIGABARINI
5 MANAPUR
5 SANTARA
8 CHATUA
5 BAZAR
5 TALANDANDA
8 ATHARBANKI
7.5 RANGIAGARH
5 BHUTMUNDAI
5 CHOUMUHANI
5 POSHAL
5 RAHAMA
5 PANKAPALA
5 MEDICAL
5 BEHERADA
5 KANAKPUR-1
5 KOTKANA
5 TIRTOL BAZAR
5 TARTOL
5 JHIMANI
5 KOTHI
5 BOGADIA
5 DHINKIA
5 TRILOCHANPUR
5 SANDHAKUDA
V Feeder Peak Load 13th Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak
April-2022, 23:00 Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022
Time Peak Load Time Peak Load Time Peak Load
(hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
ividual 11kV Feeder Peak 11kV Feeder Peak Load
Load 23rd April-2022 23rd April-2022, 23:00
Time Peak Load Time
(hh:mm) (in A) (hh:mm)
JED - 11kV Feeder
PTR-1 5 ADHANGA
PTR-1 5 SIBAPUR
PTR-2 5 BALIA
PTR-2 5 JAYASALA/Anakhia
PTR-1 5 NAUGAON/DENGAPOLA
PTR-2 8 BORIKINA-1
PTR-2 8 PHD/RWSS
PTR-2 8 BALIKUDA
PTR-2 8 NAGAPUR
PTR-1 5 Debidola
PTR-2 5 KHAIRA
PTR-2 5 Mundalo
PTR-1 8 ALPINGAL
PTR-3 5 MEDICAL
PTR-4 5 PUNANGA
PTR-1 5 DHIASAHI
PTR-2 5 ODISSO
PTR-1 5 TARIKUNDA
PTR-2 5 MANDASAHI
PTR-1 5 ROHIA
PTR-1 5 SIKHARA
PTR-2 5 CHANDAPURA
PTR-1 5 PITEIPUR
PTR-1 5 NALIBAR
PTR-2 5 ICHHAPUR
PTR-2 5 OSKANA
PTR-2 5 SOBHA
PTR-1 5 Tarapur
PTR-1 5 Railway
PTR-2 5 Raghunathpur
PTR-2 5 Kantuar
PTR-3 5 Ranipada
PTR-1 5 BORIKINA-2
PTR-1 5 TITIRA
PTR-1 5 NAHARANA
PTR-1 5 CHIKINIA
PTR-1 5 DERIKI
PTR-1 5 SALIJANGA
PTR-2 5 MUTUNIA
11kV Feeder Peak Load 13th Individual 11kV Feeder Peak 11kV Feeder Peak Load
April-2022, 23:00 Load 18th April-2022 18th April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm)
Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time
(in A) (hh:mm) (in A) (hh:mm)
KHD - 11kV Feeder Loadi
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
BINODPADA/
6 BBSR-2 KHD RAJPATANA BINODPADA PTR-1 5
Rajsunakhala
BINODPADA/
7 BBSR-2 KHD RAJPATANA BINODPADA PTR-2 5
Rajsunakhala
BINODPADA/
8 BBSR-2 KHD RAJPATANA BINODPADA PTR-3 5
Rajsunakhala
BINODPADA/
9 BBSR-2 KHD RAJPATANA BINODPADA PTR-3 5
Rajsunakhala
BINODPADA/
10 BBSR-2 KHD RAJPATANA BINODPADA PTR-4 5
Rajsunakhala
CHHANAGIRI
11 BBSR-2 KHD KHURDA TANGI / JANKIA PTR-1 5
ODSSP
CHHANAGIRI
12 BBSR-2 KHD KHURDA TANGI / JANKIA PTR-1 5
ODSSP
CHHANAGIRI
13 BBSR-2 KHD KHURDA TANGI / JANKIA PTR-2 5
ODSSP
CHHANAGIRI
14 BBSR-2 KHD KHURDA TANGI / JANKIA PTR-2 5
ODSSP
INFOCITY -II
15 BBSR-2 KHD CHHATABAR CHHATABAR PTR-1 5
GIS
INFOCITY -II
16 BBSR-2 KHD CHHATABAR CHHATABAR PTR-2 5
GIS
DADHIMACHAGAD
17 BBSR-2 KHD KHURDA TANGI / JANKIA PTR-1 5
I
DADHIMACHAGAD
18 BBSR-2 KHD KHURDA TANGI / JANKIA PTR-1 5
I
DADHIMACHAGAD
19 BBSR-2 KHD KHURDA TANGI / JANKIA PTR-2 5
I
DADHIMACHAGAD
20 BBSR-2 KHD KHURDA TANGI / JANKIA PTR-2 5
I
INFOCITY -II
23 BBSR-2 KHD INFOSYS- JATANI HARIRAJPUR PTR-1 3.15
GIS
INFOCITY -II
24 BBSR-2 KHD INFOSYS- JATANI HARIRAJPUR PTR-2 5
GIS
INFOCITY -II
25 BBSR-2 KHD INFOSYS- JATANI HARIRAJPUR PTR-2 5
GIS
INFOCITY -II
26 BBSR-2 KHD INFOSYS- JATANI HARIRAJPUR PTR-3 5
GIS
INFOCITY -II
27 BBSR-2 KHD INFOSYS- JATANI HARIRAJPUR PTR-3 5
GIS
RAGADI/
39 BBSR-2 KHD SUNADEIMUNDIA JATAMUNDIA PTR-1 5
BANKI
RAGADI/
40 BBSR-2 KHD SUNADEIMUNDIA JATAMUNDIA PTR-1 5
BANKI
RAGADI/
41 BBSR-2 KHD SUNADEIMUNDIA JATAMUNDIA PTR-2 1.6
BANKI
RAGADI/
42 BBSR-2 KHD SUNADEIMUNDIA JATAMUNDIA PTR-3 3.15
BANKI
INFOCITY -II
81 BBSR-2 KHD SEA FOOD SEA FOOD PTR-1 8
GIS
INFOCITY -II
82 BBSR-2 KHD SEA FOOD SEA FOOD PTR-2 8
GIS
RAGADI/
83 BBSR-2 KHD SUNADEIMUNDIA SUNADEIMUNDIA PTR-1 5
BANKI
RAGADI/
84 BBSR-2 KHD SUNADEIMUNDIA SUNADEIMUNDIA PTR-2 5
BANKI
RAGADI/
85 BBSR-2 KHD SUNADEIMUNDIA SUNADEIMUNDIA PTR-2 5
BANKI
RAGADI/
86 BBSR-2 KHD SUNADEIMUNDIA SUNADEIMUNDIA PTR-3 5
BANKI
RAGADI/
87 BBSR-2 KHD SUNADEIMUNDIA SUNADEIMUNDIA PTR-3 5
BANKI
RAGADI/
93 BBSR-2 KHD CHARCHIKA TULASIPUR PTR-1 1.6
BANKI
EMC PARK
96 BBSR-2 KHD PTR-1 8
Infovalley
EMC PARK
97 BBSR-2 KHD PTR-2 8
Infovalley
ATRI
SARUA
PODADHIA
DINGER FEEDER
BEGUNIA FEEDER
BANKOI
BSNL
BAYAPALLI
KADAB
SANAPADAR
CHHANAGIRI
SIKO
HAJA
SARPARI
JAMUJHARI
PANIORA
KAIPADAR
DALEIPUT
BAJPUR
DADHIMACHAGADIA
HALADIA
IDEAL
KANTIA
GOLAPADA
KUDIARY
KAKUDIA
BAILIPADA
HATABASTA 1
HATABASTA 2
BADAPOKHARIA
OLOSING
NIRAKARPUR
GOLABAI
MADANPUR
OIL MILL-1
OIL MILL-2
MENDHASAL
IDEAL
TARPUR
RAMCHANDI
JATAMUNDIA
TALABASTA
MEDICAL
RURAL
GAJAPATI NAGAR
RAJABAZAR
TOWN
KUSUMATI
BACHHORA
INDUSTRIAL
MUKUNDAPRASAD
TAPANGA
BPCL
TOWN-II
PANABARAJA
TOWN-I
GURUJANGA
TARTUA
MEDICAL
NARANGARH
BHAGABATI
TAPANGA
CHATRAM
NIRAKARPUR
MANAPUR
MANDARBASTA
KAIMATIA
ROUTPADA
PATNAHATA
GADAMANITRI
PARICHHALA
GUDUNGI
DERAS
GIRINGPUT
MENDHASAL
IDEAL
KATHAKHUNTIA
SARUA
INDUSTRIAL
PUBUSAHI
FEEDER-1
PROPOSED
BANKI TOWN
CHAKAPADA
RAGADI RWSS
VEDA
RAJIB
TARABOI
PHD
TIRUMALA
RENGALA
IDCO
TULASIPUR
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
BAED - 11kV Feeder Load
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
RAJPATANA/
18 BBSR-2 BAED RANAPUR DARPANARANPUR PTR-1 5
NAYAGARH
RAJPATANA/
19 BBSR-2 BAED RANAPUR DARPANARANPUR PTR-2 5
NAYAGARH
HARIPUR/
20 BBSR-2 BAED BALUGAON TANGI PTR-1 5
Gangaharpur
HARIPUR/
21 BBSR-2 BAED BALUGAON TANGI PTR-1 5
Gangaharpur
HARIPUR/
22 BBSR-2 BAED BALUGAON TANGI PTR-2 5
Gangaharpur
TOWN
PRATAP
NILADRI
PANCHU GAON
BALUGAON
SINGHESWARA
BANPUR-I
BANPUR-II
HARIPUR
BHUSANDPUR
IDEAL
CHANDPUR
RAIPADA
VIVA CITY
KAMAGURU
CHILIKA DEDICATED
IDEAL
DARPANARAYANPUR
GAURANGPUR
BAULABANDHA
HATABADHI
IDEAL
NATIM
MAYUR JHALIA
MAHAT PALLA
CHANDESWAR
KUHUDI
GAMBHARIMUNDA
NAIRI
KAITHAPOLA
RURAL
RANPUR
GOPALPUR
KALUPADA
CHANDPUR
BADAPARI
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
NYED - 11kV Feeder Load
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
CHAMUNDIA
7 BBSR-2 NYD RAJPATANA KHANDAPADA PTR-1 5
ODSSP
CHAMUNDIA
8 BBSR-2 NYD RAJPATANA KHANDAPADA PTR-1 5
ODSSP
CHAMUNDIA
9 BBSR-2 NYD RAJPATANA KHANDAPADA PTR-2 5
ODSSP
DHALABANDHA
15 BBSR-2 NYD RAJPATANA KHANDAPADA PTR-1 5
ODSSP
DHALABANDHA
16 BBSR-2 NYD RAJPATANA KHANDAPADA PTR-2 5
ODSSP
DHALABANDHA
17 BBSR-2 NYD RAJPATANA KHANDAPADA PTR-2 5
ODSSP
RAJPATANA/
24 BBSR-2 NYD GODIPADA GODIPADA ODSSP PTR-1 5
NAYAGARH
RAJPATANA/
25 BBSR-2 NYD GODIPADA GODIPADA ODSSP PTR-1 5
NAYAGARH
RAJPATANA/
26 BBSR-2 NYD GODIPADA GODIPADA ODSSP PTR-2 5
NAYAGARH
RAJPATANA/
27 BBSR-2 NYD GODIPADA GODIPADA ODSSP PTR-2 5
NAYAGARH
RAJPATANA/
28 BBSR-2 NYD GODIPADA GODIPADA ODSSP PTR-3 5
NAYAGARH
HARIPUR
29 BBSR-2 NYD RAJPATANA ODOGAON (BAHADAJHOLA) PTR-1 5
ODSSP
HARIPUR
30 BBSR-2 NYD RAJPATANA ODOGAON (BAHADAJHOLA) PTR-1 5
ODSSP
HARIPUR
31 BBSR-2 NYD RAJPATANA ODOGAON (BAHADAJHOLA) PTR-2 5
ODSSP
RAJPATANA/
32 BBSR-2 NYD BINODPADA ITAMATI PTR-1 8
NAYAGARH
RAJPATANA/
33 BBSR-2 NYD BINODPADA ITAMATI PTR-1 8
NAYAGARH
RAJPATANA/
34 BBSR-2 NYD BINODPADA ITAMATI PTR-2 8
NAYAGARH
RAJPATANA/
35 BBSR-2 NYD BINODPADA ITAMATI PTR-2 8
NAYAGARH
RAJPATANA/
36 BBSR-2 NYD BINODPADA ITAMATI PTR-2 8
NAYAGARH
RAJPATANA/
41 BBSR-2 NYD KHANDAPADA KHANDAPADA PTR-1 8
NAYAGARH
RAJPATANA/
42 BBSR-2 NYD KHANDAPADA KHANDAPADA PTR-1 8
NAYAGARH
RAJPATANA/
43 BBSR-2 NYD KHANDAPADA KHANDAPADA PTR-2 5
NAYAGARH
RAJPATANA/
44 BBSR-2 NYD KHANDAPADA KHANDAPADA PTR-2 5
NAYAGARH
RAJPATANA/ LATHIPADA
48 BBSR-2 NYD LATHIPADA PTR-1 5
NAYAGARH ODSSP
RAJPATANA/ LATHIPADA
49 BBSR-2 NYD LATHIPADA PTR-2 5
NAYAGARH ODSSP
RAJPATANA/ MACHHIPADA
50 BBSR-2 NYD MACHHIPADA PTR-1 5
NAYAGARH ODSSP
RAJPATANA/ MACHHIPADA
51 BBSR-2 NYD MACHHIPADA PTR-1 5
NAYAGARH ODSSP
RAJPATANA/ MACHHIPADA
52 BBSR-2 NYD MACHHIPADA PTR-2 5
NAYAGARH ODSSP
RAJPATANA/ MACHHIPADA
53 BBSR-2 NYD MACHHIPADA PTR-2 5
NAYAGARH ODSSP
RAJPATANA/
54 BBSR-2 NYD DASPALLA MAHIPUR PTR-1 1.6
NAYAGARH
RAJPATANA/
55 BBSR-2 NYD DASPALLA MAHIPUR PTR-1 1.6
NAYAGARH
RAJPATANA/
56 BBSR-2 NYD DASPALLA MAHIPUR PTR-2 1.6
NAYAGARH
RAJPATANA/
57 BBSR-2 NYD DASPALLA MAHIPUR PTR-3 5
NAYAGARH
RAJPATANA/
58 BBSR-2 NYD NAYAGARH NAYAGARH PTR-1 8
NAYAGARH
RAJPATANA/
59 BBSR-2 NYD NAYAGARH NAYAGARH PTR-1 8
NAYAGARH
RAJPATANA/
60 BBSR-2 NYD NAYAGARH NAYAGARH PTR-2 8
NAYAGARH
RAJPATANA/
61 BBSR-2 NYD NAYAGARH NAYAGARH PTR-2 8
NAYAGARH
RAJPATANA/
62 BBSR-2 NYD NAYAGARH NAYAGARH PTR-2 8
NAYAGARH
RAJPATANA/
66 BBSR-2 NYD ODOGAON ODOGAON PTR-1 5
NAYAGARH
RAJPATANA/
67 BBSR-2 NYD ODOGAON ODOGAON PTR-1 5
NAYAGARH
RAJPATANA/
68 BBSR-2 NYD ODOGAON ODOGAON PTR-2 8
NAYAGARH
RAJPATANA/
69 BBSR-2 NYD ODOGAON ODOGAON PTR-2 8
NAYAGARH
RAJPATANA/
70 BBSR-2 NYD ODOGAON ODOGAON PTR-2 8
NAYAGARH
RAJPATANA/
71 BBSR-2 NYD ODOGAON ODOGAON PTR-2 8
NAYAGARH
RAJPATANA/
72 BBSR-2 NYD ODOGAON SARANKUL PTR-1 8
NAYAGARH
RAJPATANA/
73 BBSR-2 NYD ODOGAON SARANKUL PTR-1 8
NAYAGARH
RAJPATANA/
74 BBSR-2 NYD ODOGAON SARANKUL PTR-1 8
NAYAGARH
RAJPATANA/
75 BBSR-2 NYD ODOGAON SARANKUL PTR-1 8
NAYAGARH
RAJPATANA/
76 BBSR-2 NYD ODOGAON SARANKUL PTR-2 5
NAYAGARH
RAJPATANA/
77 BBSR-2 NYD ODOGAON SARANKUL PTR-2 5
NAYAGARH
BIJIPUR
MARADA
BOLOGARH
KAPASIA
KHANGURIA
SHYAMSUNDARPUR
CHHAMUNDIA
ISWARPUR
IDEAL
DASPALLA TOWN
KUANIRIA
POIBARI
MADHYA KHANDA
KHAMARASAHI
RANICHELLI
SALAPADA
BADASAHARA
GOLAPOKHARI
BHAPUR
FATEGARH
GANIA
KUSKA
BALARAMPRASAD
GODIPADA
DAMASAHI
KESHPANIA
NAGAMUNDULI
NOT CHARGED
BAHADJHOLA
BERUANBARI
SINGHARPALLI
BADA PANDUSARA
CHAMPATIPUR
ITAMATI
LATHIPADA-I
LATHIPADA-II
BENGADIA
BANAPUR
KANTILO
PHD
KHANDAPADA
PHD
BAIGUNIA
PANIPOILLA
KURALA
KOMANDA
SUNAMUHIN
NA
NA
KALYANPUR
MACHHIPADA
LENKUDIPADA
PALLISASANA
SINGARPALLY-I
SINGARPALLY-II
MAHIPUR
BIRUDA
NAYAGARH
SIMILISAHI
BARABATI
SINDURIA
MEDICAL
SANAPADA
MAHITAMA
NUAGAON
BAHADAJHOLA
KOMANDA
ODOGAON-I
ODOGAON-II
NANDIGHOR
AMBERAPUR
PANCHIDA
SARANKUL
GODIPADA
SHIKARPUR
MACHHIPADA
DARAPADA
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)
PED - 11kV Feeder Loadi
Name of PTR
Sl. Name of Name of Name of 33/11kV
Name of Grid Name of 33kV Feeder 33/11kV Rating
No. Circle Division PSS
PTR (in MVA)
GABAKUNDA
24 BBSR-2 PURI SAMAGARA GABAKUNDA PTR-1 3.15
(SUANLO) ODSSP
GABAKUNDA
25 BBSR-2 PURI SAMAGARA GABAKUNDA PTR-2 3.15
(SUANLO) ODSSP
PANASPADA
36 BBSR-2 PURI SAMUKA ALARNATH PTR-1 5
ODSSP
PANASPADA
37 BBSR-2 PURI SAMUKA ALARNATH PTR-2 5
ODSSP
MADHUBAN
MUKUBAN
KHANDIABANDHA
LOKANATH
PHD
KACHERI
PRACHI OH
PRACHI UG
BASUDEIPUR
HANTUKA
KAPILESWARPUR
PALANKA
BASUDEVPUR
BRAHMAGIRI
ALARNATH
BALABHADRAPUR
CHANDANPUR
SIROLI(BIRANARSINGH PUR)
HAREKRUSHNAPUR
KHANDIABANDHA
BIJAY MARINE
MM NAGAR
KETAKIPATANA
IDEAL
SEA BEACH UG
SWARGADWAR-I
SWARGADWAR-II
DOLAMANDAP
DUTTOTOTA
SRIMANDIRA UG
KHAJURIA
SIRULI
RAIBIDHAR
TALAMALA
PROPOSED
PROPOSED
SARANGJODI
SATASANKHA
SAKHIGOPAL(BAJAR)
EXPRESS
BALANGA
SPARE
KUMARESWAR
SPARE
TOSHALI
WOTER WORKS
BALIGUALI
PKRIT
SPARE
SATAPARA
BRAHMAGIRI
MODIRATH
GUNDICHA
MEDICAL UG
KACHERI
MAUSIMA UG
RAJBHAWAN OH
SRIMANDIRA OH
RAJBHAWAN UG
SRIMANDIRA UG
GHORODIHA
DELANGA
GELABAI
KANASA
KARAMALA
JAGANNATH PUR
Individual 11kV Feeder Peak 11kV Feeder Peak Load Individual 11kV Feeder Peak 11kV Feeder Peak Load
Load 18th April-2022 18th April-2022, 23:00 Load 23rd April-2022 23rd April-2022, 23:00
Peak Load Time Peak Load Time Peak Load Time Peak Load
(in A) (hh:mm) (in A) (hh:mm) (in A) (hh:mm) (in A)
1kV Feeder Peak Load
23rd April-2022, 23:00
Time
(hh:mm)