Professional Documents
Culture Documents
Projects III
2021
1
Table of Contents Introduction......................................5
Objectives.......................................................................................................................................6
Expansion and modernization of the Cofema S.A class II cattle and pig animal
1. Integrate the concepts, methodologies, the steps to design and build an indicator, the
2 With what was developed in problem 2; build the content of key performance
2.2. Considering the Balanced Scorecard approach, build the indicators for a project. . .15
2.3. Calculate cost performance index and schedule performance index. Calculate the
project costs..............................................................................................................................21
Execution Report...................................................................................................................33
2
2.3.2.2.1 Calculation of program variation (SV):..............................................................35
¿According to the budget and initial programming to the fifth month the project
Taking into account the project execution report and the graph, the possible causes of
Taking into account the work execution report and the graph, determine possible causes
Performance indices.........................................................................................................38
¿Is the variation in the total program and its indicator, together with the variation in
3 Based on the development of problem 3 activity, Calculate the Critical Path and the
4. Determine methods for implementing indicators in project management, select one and
document it...................................................................................................................................57
5. Link to the deliverable document, the criteria of each member of the group, referring
3
to lessons learned, contributions to knowledge, applicability in projects in the
Conclusions...................................................................................................................................64
Bibliography.................................................................................................................................65
4
Introduction
The development of a system of indicators of a project allows to know in a fast, simple and
reliable way the status, as well as, the progress during its life cycle, from the design stage,
following through the execution, operation, delivery, guarantee and ending with closure or
customer satisfaction That is why to measure the progress of a project, data that are comparisons
with respect to a programmed value are required, therefore, the progress indicators will be
On the other hand, the way to assign a numerical value to an attribute is through counts or
proportions. In this case, the key indicators are used to describe the performance in each of the
stages of a project.
Therefore, it can be said that an indicator is defined as a measure used to quantify the
the definition, is to clearly establish the purpose of the measurement, it is say, how this indicator
will affect the behavior of the company. This work is focused on evaluating strategic decisions
through indicators associated with management as support in the follow-up and follow-up
processes of the project “Expansion and modernization of the Cofema SA class II cattle and pig
5
Objectives
General objective
Specific objectives
Build performance indicators to evaluate the progress of each process and Identify the
Identify key performance indicators, the balanced scorecard, the cost performance index
Build and calculate the Critical Path and the duration of the project.
6
PROJECT
Expansion and modernization of the Cofema S.A class II cattle and pig
animal processing plant located in the city of Florencia Caquetá.
1. Integrate the concepts, methodologies, the steps to design and build an indicator, the
Performance indicators are calculated based on objectives; therefore, it is important that the
proposed indicators have a direct relationship with the level of the objective (CONEVAL, 2013,
p. 20).
Indicators related to the scope of performance have been established (when measured) and
7
In the performance indicators (effectiveness and efficiency) focus on:
measuring the results of the program in solving a specific social problem: What is expected to be
measuring the production, delivery and characteristics of all goods and services that are provided
directly to the beneficiaries. This level includes the assets generated for the use of the program
is verified to create the products, both those that are delivered to the beneficiary population and
those that use the same program as an intermediate input. What activities does the program carry
Effectiveness Efficiency
8
It is the expression that measures the capacity of an economic
When the goals or objectives that had been
system or actor to achieve the fulfillment of a specific
previously established are achieved, the group is
objective, with a minimum of resources
effective (Méndez, 2018, p.15).
(Méndez, 2018, p.16).
𝑂𝑢𝑡𝑐𝑜𝑚𝑒 𝑆𝑝𝑒𝑛𝑑𝑖𝑛𝑔
𝐸𝑖𝑆𝑝𝑒𝑛𝑑𝑖𝑛𝑔
= ; 𝐸𝑖 = 𝑂𝑢𝑡𝑐𝑜𝑚𝑒
9
1.2 Comparative Matrix of the Methodologies
Performance Dimension
Dimension /
Indicator
Efficacy Quality Efficiency Economy Effectiveness Result Process Structure
It measures the
It measures
relationship
attributes,
between the
capacities or
products and
characteristics that It measures the
services generated
the capacity
with
goods or services of the program to
respect to the
must generate or
It Measures inputs or
have in order to adequately
the resources used.
adequately meet the mobilize
degree to project's Objectives. financial It is to measure the
which an • Production costs resources. effort, taking into
objective is (average costs, unit account what has They measure
Quality is a the different
met costs, been programmed They assess
dimension Of Economy is a activities or
Aspect that It's doing administrative and the adequate whether the Monitor
effectiveness, but dimension results at the
evaluates what's costs in use of resources proposed activities to
because Of efficiency. levels of the
scheduled relation to total "Quality of the activity generate a
of its importance it institution.
We have expenditure) goals was product or
is It is a measure of Strategic,
achieved achieved" achieved service.
distinguished by its management Tactical and
the own • Average
objectives. capacity in Operational
name. productivity Of ¿What use have we
the use of generated?
the various
financial
It is measuring the production
resources to
implementation and factors
meet the
progress of the objective
quality • It is to do what is .
management programmed with a
process. better use of
resources.
10
When measured
Indirect Influence
Direct Influence
Direct control
Scope of
performance Impact Results Products Processes Supplies
Component
End Purpose Activities
Efficacy
Indicators Efficacy Efficiency
Efficacy Efficacy Efficiency
Recommended Efficiency Economy
Quality
11
1.3 Comparison of indicators related to efficiency, effectiveness and Efficacy.
The efficiency indicators focus on the For the analysis of this type of When it comes to efficiency, it
control of resources or inputs of process; indicator, it is necessary to involve seeks to establish compliance
evaluate the relationship between resources efficiency and effectiveness, that is, with the entity's plans and
and their degree of use by part of them. "the achievement of programmed programs, previously
Differences results in time and with the most determined, so that the
The efficiency indicators measure the reasonable costs possible." opportunity (fulfillment of the
relationship between the achievement of the goal within the stipulated
program and the resources used for its It is related to the measurement of the period) can be evaluated, as
fulfillment. These indicators quantify what it level of satisfaction of the user who well as the quantity (volume of
costs to achieve the proposed objective, aspires to receive a product or service goods and services generated
without limiting it to economic resources; it under favorable conditions of cost and over
time).
12
also encompasses the human and material opportunity, and with the
resources that the program employs to meet establishment of the coverage of the The effectiveness indicators
the specific objective. service provided. inherently carry the prior
definition of objectives and the
These types of indicators measure how This type of indicator measures the monitoring of these through a
resources were used during the results achieved in relation to the minimum information system
product and / or service generation process. goods or services generated for that allows information on basic
customers and users. aspects of the program or
Efficiency analysis refers to the acquisition management to be evaluated,
and use of inputs (process inputs), which among that are mentioned:
must be acquired in a timely manner, at the
best cost • Products delivered by the
possible, in the right quantity and with a program or service.
good quality. For what means are included
human, material and financial. • Users to whom it is directed
(number, characteristics).
13
2 With what was developed in problem 2; build the content of key performance indicators,
balanced scorecard, calculation of cost performance index and performance index of the
Financial or 2022.
Investment Plan
Increase the company's sales of
industrial by-products by 25% in 5
years
Increase the organizational net
profit margin by 35% in the next 5
years.
Incorporate 12 new refrigeration
cellars in the animal processing
plant by 2020
Business or
Growth and
Expansion Plan. Slaughter a minimum of 480
cattle per day in 2018 and increase
by 10% annually in the next 5
years
14
2.2. Considering the Balanced Scorecard approach, build the indicators for a project
1. Inventory
turnover
5. Storage cost
with the number of
references in the
warehouse in a
specific period.
15
Increase by
35% the
income from 1. Income from
services of fair square
Fairgrounds services
in 2. Price per unit
5 years - kilo / head
3. Number of
hours of
Service
6% 7% 8% 9% 5%
4. Income from
services by fair
places
(Iplz's * n):
Increase the
organizational 1. Net profit
net profit margin
margin by 4% 8% 8% 8% 7%
35%
in the next 5
years.
Increase 1. Increase in
participation participation in the
in the national national market
meat market
Customer by 15% by 2. Cross-selling 2% 3% 4% 4% 2%
2022. index
3. Number of
markets in which
it participates 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑚𝑎𝑟𝑘𝑒𝑡𝑠
3. 𝑴𝒑𝒂𝒓𝒕 = 𝑡𝑜𝑡𝑎𝑙 𝑚𝑎𝑟𝑘𝑒𝑡𝑠
4. cost of acquiring a
new customer
𝐴𝑚𝑜𝑢𝑛𝑡 𝑜𝑓 𝑚𝑜𝑛𝑒𝑦 𝑖𝑛𝑣𝑒𝑠𝑡𝑒𝑑
𝐶𝐴𝐶 =
16
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑐𝑙𝑖𝑒𝑛𝑡𝑠 𝑎𝑐ℎ𝑖𝑒𝑣𝑒𝑑
17
𝐶𝑎𝑠𝑒𝑠 𝑠𝑜𝑙𝑣𝑒𝑑
Achieve a 1. Monthly 1. PQRS = 𝑇𝑜𝑡𝑎𝑙 𝑐𝑎𝑠𝑒𝑠
customer PQRS Index 4% 8% 10% 12% 6%
retention rate
of 40% by 2. Customer 𝑁 ° 𝑐𝑙𝑎𝑖𝑚𝑠 𝑐𝑢𝑟𝑟𝑒𝑛𝑡 𝑝𝑒𝑟𝑖𝑜𝑑
2022. 1. IReclm= 𝑁°𝑐𝑙𝑎𝑖𝑚𝑠𝑝𝑟𝑒𝑣𝑖𝑜𝑢𝑠 𝑝𝑒𝑟𝑖𝑜𝑑
retention rate
𝑇𝑜𝑡𝑎𝑙 𝐶𝑙𝑖𝑒𝑛𝑡𝑠−𝐷𝑟𝑜𝑝𝑜𝑢𝑡𝑠
3. index of 2. IRC = 𝑇𝑜𝑡𝑎𝑙 𝐶𝑙𝑖𝑒𝑛𝑡𝑠
satisfied
customers 3.
4. Income from 4.
sales of
current
customers
5.
5. product return
rate
4. number of
macro business
rounds held per
year
18
Incorporate
12 new 1. Number of
refrigeration new
cellars in the refrigeration 2 2 3 3 2
animal cellars unidades unidades unidades unidades unidades
processing
plant by 2020
1. Weekly
Internal Slaughter a frequency -
Process minimum of 480 slaughter
cattle per day in service
2018 and
increase by 10% 2. Number of
annually in the 69120 76032 83664 92160 101376
cattle
following 5 slaughtered
years. daily
3. Number of
employees in
19
the benefit plant
4. Production
index
5. lead time
analysis -
production
cycle time
6. Mean Time
Between
Failures
7. List of new
sales of new
products
derived from
I+ D + i
19
Manufacturing
Practices
4. Verification of
the sanitary
profile by
processes
5. Sanitary
Certification for
Good
Training and Manufacturing
Growth. Practices
20
2.3. Calculate cost performance index and schedule performance index. Calculate the project costs
RESOURCE REQUIREMENT
21
1 lunch for each day of the Service contract to feed 40 people
2,1,7 Feeding Material resources Un 480 6 months $ 350.000
40 trained in the 12 days
2 snacks for each day of Service contract to feed 40 people
2,1,8 Refreshments Material resources Un 960 6 months $ 300.000
the 40 trained in 12 days x 2
Service contract to transport 40 to
2,1,9 Transport Material resources Trained transportation month 6 and from COFEMA and the 6 months $ 700.000
training site
Support stationery for the Deliver 2 brochures, 1 booklet, 2
2,1,10 Stationery Material resources Gl 1 6 months $ 350.000
professional and brochures CDs each day
Rental enclosure with A/C, double
2,1,11 Auditorium rental Material resources Venue rental month 6 6 months $ 400.000
emergency exit, with Audiovisuals
Phytosanitary regulatory
2,2 training
Contract for monthly report in the
Phytosanitary normative Hiring of professional staff
2,2,1 Human Resources mes 6 6 months, 12 campaigns of two 6 months $ 2.000.000
rapporteur in phytosanitary standards days
Per diem air transport Travel expenses to Air tickets Bogotá - Florence
2,2,2 Material resources Un 12 6 months $ 1.500.000
reporter mobilize professional staff round trip
Travel allowances to feed Food billing per day of two
2,2,3 Rapporteur feeding per diem Material resources Un 12 6 months $ 400.000
professional staff training days
Travel expenses to
Per diem accommodation Accommodation billing for
2,2,4 Material resources accommodate professional Un 12 6 months $ 450.000
rapporteur assistance
staff
Support material for the 40 Turnover prints of the 12 training
2,2,5 Prints Material resources Gl 1 6 months $ 80.000
trained sessions
Accreditation material for Service contract to accredit 40
2,2,6 Diplomas and accreditation Material resources Un 40 6 months $ 150.000
the 40 trained people
1 lunch for each day of the Service contract to feed 40 people
2,2,7 Feeding apprentices Material resources 40 trained Un 480 in the 12 days 6 months $ 350.000
2 snacks for each day of Service contract to feed 40 people $
2,2,8 Refreshments Material resources Un 960 6 months
the 40 trained in 12 days x 2 300.000
Service contract to transport 40 to
2,2,9 Transport Material resources Trained transportation month 6 and from COFEMA and the 6 months $ 700.000
training site
Support stationery for
Deliver 2 brochures, 1 booklet, 2
2,2,10 Stationery Material resources professional staff and Gl 1 6 months $ 350.000
brochures CDs each day
Rental enclosure with A/C, double
2,2,11 Auditorium rental Material resources Venue rental month 6 6 months $ 400.000
emergency exit, with Audiovisuals
Cavas cooling technology
2,3 and processing plant
Supply and installation of Operation manual, warranty 1
2,3,1 Firetube boiler Material resources Un 1 20 days $ 1.400.000
the good year, supervision 6 months
22
Gun weight max. 2.50 Kg, 9-
2,3,2 Stun gun Material resources Supply of the good Un 2 17mm ammunition 15 days $ 850.000
2,3,3 Compressor Material resources Supply of the good Un 1 1HP, 110V, 150Psi device 13 days $ 1.614.308
23
1 surveyor, 1 chain worker,
2,4,1,1 Location and stakeout Human Resources Topography hiring Gl 1 10 days $ 18.000.000
delivers monthly report
Excavations, demolitions and Human and Material Labor, machinery, Portfolio of volumes of land
2,4,1,2 Gl 1 15 days $ 48.000.000
fillings Resources transportation moved
Human and Material Labor, machinery, Portfolio of volumes of land
2,4,1,3 Surplus withdrawals m3 180 8 days $ 32.500
Resources transportation moved
2,4,2 Concrete structures
Human and Material Labor, equipment and Structural record plans, Quantity
2,4,2,1 Foundations m3 45 30 days $ 920.000
Resources construction materials reports, Specific quality tests
Human and Material Labor, equipment and Structural record plans, Quantity
2,4,2,2 Columns and beams m3 56 25 days $ 1.050.000
Resources construction materials reports, Specific quality tests
Human and Material Labor, equipment and Structural record plans, Quantity
2,4,2,3 Mezzanine plates Resources construction materials m2 200 reports, Specific quality tests 16 days $ 212.000
2,4,5 Finishes
Human and Material Labor and construction
2,4,5,1 Stucco and paints m2 720 Memories of work quantities 24 días $ 19.000
Resources materials
24
Ceramic floor and wall Human and Material Labor and construction
2,4,5,2 m2 410 Memories of work quantities 21 días $ 56.000
finishes Resources materials
Human and Material
2,4,5,3 Metal carpentry Supply and installation Gl 1 Memories of work quantities 7 días $ 68.000.000
Resources
2,4,6 Covers
2,4,6,1 Metal roof structure Human and Material Supply and installation m2 350 Structural record plans, quantity 23 days $ 256.000
Resources reports, welding and painting tests
Architectural sheet metal Human and Material
2,4,6,2 Supply and installation m2 350 Memories of work quantities 11 days $ 150.000
roof Resources
2,4,7 Electrical
Human and Material Labor and construction
2,4,7,1 Electric connection Un 1 Memories of work quantities 8 days $ 2.500.001
Resources materials
Human and Material Labor and construction
2,4,7,2 Light outputs Un 30 Memories of work quantities 6 days $ 195.000
Resources materials
Human and Material Labor and construction
2,4,7,3 Power outputs Un 35 Memories of work quantities 6 days $ 200.000
Resources materials
2,4,8 Furniture and solutions
Human and Material
2,4,8,1 Mesons Supply and installation ml 120 Memories of quantities 8 days $ 260.000
Resources
Human and Material
2,4,8,2 Sangria tunnels Resources Supply and installation ml 180 Memories of quantities 9 days $ 325.000
25
Human and Material Labor and construction
2,5,2,2 Plasters or plasters m2 300 Memories of work quantities 14 days $ 26.000
Resources materials
Human and Material Labor, equipment and
2,5,2,3 Concrete floors m2 240 Memories of work quantities 13 days $ 102.000
Resources construction materials
2,5,3 Hydraulic and sanitary
Human and Material Labor and construction Structural record plans, Quantity
2,5,3,1 Concrete gutters ml 180 24 days $ 58.000
Resources materials reports, Specific quality tests
Human and Material Labor and construction
2,5,3,2 Sanitary networks ml 135 Memories of work quantities 6 days $ 38.500
Resources materials
Human and Material Labor and construction
2,5,3,3 Sanitary distribution boxes un 25 Memories of work quantities 8 days $ 220.000
Resources materials
2,5,4 Furniture and solutions
Human and Material Memories of quantities, welding
2,5,4,1 Corrals in metallic structure Supply and installation ml 180 15 days $ 240.000
Resources and painting tests
Human and Material
2,5,4,2 Scale room Supply and installation m2 10 Memories of quantities 4 days $ 1.214.460
Resources
3 PHASE III - MONITORING AND CONTROL
1 construction manager, 1
Project team service and
3,1 Organizational performance Human Resources administrative staff Month 1 accountant, 1 secretary, 1 orderly, 6 months $ 10.873.680
1 assistant
Monitoring of costs and Project team service and
3,2 Human Resources Month 1 1 Site manager, 1 site resident 6 months $ 2.505.490
schedule of the work administrative staff
1 Site manager, 1 site resident, 1
3,3 Inspection of construction Human Resources Project team service and Month 1 construction technologist, 1 6 months $ 8.348.057
processes administrative staff environmental, 1 siso
26
Staff Costs
COST OF SALARY + PARTIAL
POSITION QTY. SALARY BASE % BENEFITS DEDICATION
SERVICES BENEFITS COST
TECHNICAL WORK STAFF
Resident engineer 1 $ 3.500.000 41,56% $ 1.454.600 $ 4.954.600 100% $ 4.954.600
Construction Technologist 1 $ 2.500.000 42,98% $ 1.074.500 $ 3.574.500 100% $ 3.574.500
Environmental engineer 1 $ 3.500.000 41,56% $ 1.454.600 $ 4.954.600 50% $ 2.477.300
Sisoma Technician 1 $ 2.000.000 44,23% $ 884.600 $ 2.884.600 100% $ 2.884.600
Storer 1 $ 2.000.000 44,23% $ 884.600 $ 2.884.600 100% $ 2.884.600
Structural engineer 1 $ 4.500.000 40,76% $ 1.834.200 $ 6.334.200 25% $ 1.583.550
ADMINISTRATIVE STAFF
Construction manager 1 $ 4.500.000 40,76% $ 1.834.200 $ 6.334.200 100% $ 6.334.200
Counter 1 $ 2.500.000 42,98% $ 1.074.500 $ 3.574.500 100% $ 3.574.500
Administrative secretary 1 $ 1.500.000 46,32% $ 694.800 $ 2.194.800 100% $ 2.194.800
Watchman 1 $ 1.500.000 46,32% $ 694.800 $ 2.194.800 100% $ 2.194.800
Assistant 1 $ 1.100.000 49,34% $ 542.740 $ 1.642.740 100% $ 1.642.740
1 Month $ 34.300.190
Source: Self made
Benefit base for personnel costs
BASICS $ 1.202.854 $ 1.602.854 $ 2.102.854 $ 2.602.854 $ 3.602.854 $ 4.602.854
Salary $ 1.100.000 $ 1.500.000 $ 2.000.000 $ 2.500.000 $ 3.500.000 $ 4.500.000
Transport $ 102.854 $ 102.854 $ 102.854 $ 102.854 $ 102.854 $ 102.854
SOCIAL BENEFITS
Layoffs $ 100.238 $ 133.571 $ 175.238 $ 216.905 $ 300.238 $ 383.571
Interest on severance pay $ 12.029 $ 16.029 $ 21.029 $ 26.029 $ 36.029 $ 46.029
Premiums $ 100.238 $ 133.571 $ 175.238 $ 216.905 $ 300.238 $ 383.571
Vacations $ 45.686 $ 60.878 $ 79.869 $ 98.860 $ 136.841 $ 174.822
27
CONTRIBUTIONS TO SOCIAL
SECURITY
Pensions (AFP) $ 132.000 $ 180.000 $ 240.000 $ 300.000 $ 420.000 $ 540.000
Health (EPS) $ 93.500 $ 127.500 $ 170.000 $ 212.500 $ 297.500 $ 382.500
RI occupational risks (ARL) $ 5.742 $ 7.830 $ 10.440 $ 13.050 $ 18.270 $ 23.490
PARAFISCAL
Family Compensation Fund $ 44.000 $ 60.000 $ 80.000 $ 100.000 $ 140.000 $ 180.000
ICBF $ 33.000 $ 45.000 $ 60.000 $ 75.000 $ 105.000 $ 135.000
SENA $ 22.000 $ 30.000 $ 40.000 $ 50.000 $ 70.000 $ 90.000
EXONERATIONS Art. 65 Law
1819 of 2016
Health (EPS) -$ 93.500 -$ 127.500 -$ 170.000 -$ 212.500 -$ 297.500 -$ 382.500
ICBF -$ 33.000 -$ 45.000 -$ 60.000 -$ 75.000 -$ 105.000 -$ 135.000
SENA -$ 22.000 -$ 30.000 -$ 40.000 -$ 50.000 -$ 70.000 -$ 90.000
TOTAL MONTHLY PROVISION $ 1.642.786 $ 2.194.733 $ 2.884.667 $ 3.574.601 $ 4.954.469 $ 6.334.337
% BENEFITS 49,34% 46,32% 44,23% 42,98% 41,56% 40,76%
28
To build the effectiveness and efficiency indicators according to the objectives and goals of the project, - and in this way calculate
productivity based on the aforementioned indicators, the following simulations are used that allow the analysis of indicators supported
Actual
Planned
Activities Date PV Advance EV Real Cost AC
budget
(Close to 60%)
Studies, designs and permits 30/04/2020 $49.000.000 $49.000.000 $49.000.000 $49.000.000 $49.000.000 $49.000.000
Project formulation and evaluation 30/04/2020 $5.000.000 $54.000.000 $5.000.000 $54.000.000 $5.000.000 $54.000.000
Industrial safety and BPM's training 30/05/2020 $47.386.800 $101.386.800 $47.056.000 $101.056.000 $48.056.230 $102.056.230
Phytosanitary regulatory training 30/05/2020 $47.386.800 $148.773.600 $46.696.000 $147.752.000 $48.698.300 $150.754.530
Plant technology appliances 30/06/2020 $54.564.308 $203.337.908 $52.902.230 $200.654.230 $65.320.660 $216.075.190
Construction of Cavas for pigs and viscera 30/06/2020 $162.000.000 $365.337.908 $159.866.321 $360.520.551 $172.650.880 $388.726.070
Construction of bovine cellars 30/07/2020 $540.000.000 $905.337.908 $535.200.960 $895.721.511 $549.888.763 $938.614.833
Black and gray work adaptation of the
beneficiation plant 30/08/2020 $279.186.800 $1.184.524.708 $275.611.200 $1.171.332.711 $289.322.450 $1.227.937.283
Processing plant finishes 30/08/2020 $648.526.501 $1.833.051.209 $632.387.500 $1.803.720.211 $657.421.900 $1.885.359.183
Furniture and mill solutions 30/09/2020 $158.163.300 $1.991.214.509 $164.236.600 $1.967.956.811 $172.159.357 $2.057.518.540
Remodeling of corral floors and sleeves 30/09/2020 $142.412.100 $2.133.626.609 $140.236.000 $2.108.192.811 $149.322.978 $2.206.841.518
Organizational performance 30/10/2020 $91.883.272 $2.225.509.881 $90.665.300 $2.198.858.111 $105.226.643 $2.312.068.161
Monitoring of costs and schedule of the work 30/10/2020 $21.170.698 $2.246.680.579 $18.695.300 $2.217.553.411 $23.788.964 $2.335.857.125
Inspection of construction processes 30/10/2020 $70.540.600 $2.317.221.179 $68.752.300 $2.286.305.711 $77.458.990 $2.413.316.115
Control of acquisition of machinery and equipment
to be installed 30/11/2020 $64.710.776 $2.381.931.955 $60.412.996 $2.346.718.707 $67.560.500 $2.480.876.615
29
Compliance with design and construction technical
30/11/2020 $41.530.736 $2.423.462.691 $37.896.565 $2.384.615.272 $46.998.300 $2.527.874.915
specifications
Quality management plan 30/11/2020 $62.794.701 $2.486.257.392 $60.225.878 $2.444.841.150 $65.989.300 $2.593.864.215
Contingency reserve 30/12/2020 $124.312.883 $2.610.570.275 $120.569.092 $2.565.410.242 $132.000.600 $2.725.864.815
Reserve management 30/12/2020 $124.312.883 $2.734.883.158 $120.598.300 $2.686.008.542 $132.218.613 $2.858.083.428
TOTAL VALUE OF THE PROJECT $2.734.883.158 $2.686.008.542 $2.858.083.428
30
2.3.2.1.1 S Curve Comparison
From the S curve graph of both (PV), (EV) and (AC), and by making their respective
comparison, it was possible to determine in the first instance which project is on time and if a
significant cost overrun is occurring when observing that AC> PV> AC. That is, when running
and analyzing the simulation of the project completely in the 8 months and observing the
comparison of the Curve S, it can be said that the behavior of AC is higher than the PV and EV
obtained during the execution of the project. In this sense, the project is exposed to cost overruns
due to inadequate cost management since there is a cost that is higher than the budget and the
progress made, - which may be the product of a bias per action (estimation error), omission
(aspects not estimates that put the cost at risk) or corruption within the company or its partners
(cost aspects that were intentionally managed for the benefit of private interest).
31
According to the results obtained by the S curve for (PV), (EV) and (AC) where the behavior
of the AC is above the planned value (PV), it could be argued that these results are due to
atypical factors for which it is As the project passes due to the health emergency, the low
demand for suppliers for the different assigned activities, influences the real cost, it is necessary
32
2.3.2.2 Work Performance Data and Earned Value Management
Execution Report
Industrial safety and BPM's training $47.386.800 99% $47.056.000 $47.056.000 $48.056.230 $0 -$1.000.230
Construction of cavas for pigs and viscera $162.000.000 99% $159.866.321 $159.866.321 $172.650.880 $0 -$12.784.559
Sv = Ev -Pv Cv = Ev - Ac
33
S CURVES (ACTIVITIES MONTH 5)
$700.000.000
$600.000.000
$500.000.000
$400.000.000
$300.000.000
$200.000.000
$100.000.000
Project formulation and Industrial safety and BPM's Phytosanitary regulatory Plant technology appliances Construction of cavas for Construction of
bovine evaluation training training pigs and viscera cellars
$0
Studies, designs and permits Black and gray work Processing plant finishes
adaptation of the
PLANNED VALUE (PV) EARNED VALUE (EV) REAL COST (AC) beneficiation plant
$0
-$5.000.000
-$10.000.000
-$15.000.000
-$20.000.000
-$25.000.000 Project formulation and Industrial safety and BPM's Phytosanitary regulatory Plant technology Construction of cavas for Construction of bovine
evaluation training training appliances pigs and viscera cellars
-$30.000.000
Studies, designs and Black and gray work Processing plant finishes
permits adaptation of the
PROGRAM AND / OR SCHEDULE VARIATION (SV) COST VARIATION (CV) beneficiation plant
34
2.3.2.2.1 Calculation of program variation (SV):
According to the activities that were academically chosen to carry out the analysis of the
Earned Value technique, in the fifth (05) month the project is neither behind schedule nor ahead
of schedule, since by subtracting the Value data Ev earned for the fifth month ($ 1,803,720,211)
of the data of the Real Cost spent in the fifth month ($ 1,803,720,211) gives 0. That is, the
activities resulting from the analysis of the variation of the schedule have generated expenses
¿According to the budget and initial programming to the fifth month the project should
According to the budget and initial programming for the fifth month, a physical advance of $
Taking into account the project execution report and the graph, the possible causes of
Regardless of the fact that the project has not presented variations in the schedule, some
causes that act on the project and show this difference could be highlighted:
1. Some of the activities on the critical path have been delayed in their execution and this
2. The returns developed in the execution of the activities are differing from the returns
3. Work shifts are being increased, which generates an early completion of some or all
activities.
35
4. There are delays in the delivery time of acquisitions.
5. During the execution of the project, it has been technically considered to carry out less
than what was planned, which generates less value earned by said activity or component.
6. Factors external to the project that impede the scheduled development of activities.
Taking into account the work execution report and the graph, determine possible causes of
1. In the execution of the procurement of type of services, a discount has been achieved by
products.
3. External factors of global influence that generate increases in the prices of products in
4. Suspensions of the project due to external factors that cause prices to be readjusted upon
5. Monopolization of the market of some products that generate an increase in the prices of
36
2.3.2.3 Execution and Performance Report
PHYSICAL
ACTIVITY BAC (PV) (EV) (AC) (SV) (CV) (SPI) (CPI)
ADVANCE (%)
Studies, designs and permits $49.000.000 100% $49.000.000 $49.000.000 $49.000.000 $0 $0 1 1
Project formulation and evaluation $5.000.000 100% $5.000.000 $5.000.000 $5.000.000 $0 $0 1 1
Industrial safety and BPM's training $47.386.800 99% $47.056.000 $47.056.000 $48.056.230 $0 -$1.000.230 1 0,979186257
Phytosanitary regulatory training $47.386.800 99% $46.696.000 $46.696.000 $48.698.300 $0 -$2.002.300 1 0,958883575
Plant technology appliances $54.564.308 97% $52.902.230 $52.902.230 $65.320.660 $0 -$12.418.430 1 0,809885111
Construction of cavas for pigs and viscera $162.000.000 99% $159.866.321 $159.866.321 $172.650.880 $0 -$12.784.559 1 0,925951382
Construction of bovine cellars $540.000.000 99% $535.200.960 $535.200.960 $549.888.763 $0 -$14.687.803 1 0,973289501
Black and gray work adaptation of the beneficiation
plant $279.186.800 99% $275.611.200 $275.611.200 $289.322.450 $0 -$13.711.250
1 0,952609104
Processing plant finishes $648.526.501 98% $632.387.500 $632.387.500 $657.421.900 $0 -$25.034.400 1 0,961920344
Sv = Ev -Pv Cv = Ev - Ac SPI = Ev / Pv CPI = Ev / Ac
TOTAL $1.833.051.209 $1.803.720.211 $1.803.720.211 $1.885.359.183 0 -$ 81.638.972
$1
$1
(CPI) (CPI)
$1
$1
$1 (SPI) (SPI)
$1
$0 (CV) (CV)
$0
$0
(SV) (SV)
$0
$0 Studies, designs and permits Project formulation and evaluation $0 $0 $0 $1 $1 $1 $0 $0 $0 $1 $1 $1
(SV) (CV) (SPI) (CPI)
37
2.3.2.3.1 Interpretation of the curve and the results obtained:Variation
According to the result, for the analysis of the variation index of the SV schedule in the month
(05) of the project, it gives us the value of zero (0), which indicates that the project is neither late
nor advanced according to the period study, that is, the programmed activities have generated
expenses according to the programmed, we can adjust actions that allow a greater performance in
Cost variation: CV = Ev - Ac
According to the graph for the cost variation calculated at month 5, this gives us negative
results, which indicates that the project is above the calculated budget, due to multiple factors
Performance indices
Using the graph as a tool, we find that the performance index for month 5 is equal to 1,
In view of the fact that there are incomplete activities, the project must carry out continuous
For the implementation of the Earned Value simulator, ten activities were taken for study, of
which only 2 of them show 100% progress, although the missing percentage in the rest of the
38
It should be noted that as the percentage of physical progress that is lacking is very minimal,
this would allow that in some cases it is not necessary to generate changes or rethinks in the
Although the schedule is being executed as planned, there is inefficiency in the management
of the resources of those incomplete activities because their CPI is less than 1, which shows that
But within the group of incomplete activities, there is “Plant Technology Devices”, which is
in a state of alert because it presents a CPI = 0.809, which indicates that the cost performance in
this activity has been lower than planned , a situation that must be monitored to evaluate the
possible actions that allow a recovery by optimizing the schedule, either with a reprogramming
or elimination of a process, changes that would make it very likely that the CPI will improve
In general, the results in the cost performance index for the analysis period indicate that we
are being efficient in managing the resources established for the project, and although there are
activities with an index lower than 1, it suggests that we must be cautious in this matter, which
may be due to the circumstances that are being presented to us, so it would be important to carry
out the exercise in a later period and evaluate the behavior of this activity for decision making.
¿Is the variation in the total program and its indicator, together with the variation in the
Taking into account the figures found in the performance table and when comparing the
results, it is evident that there is coherence between the indices and their variation. For example,
in the activities "Studies, designs and permits" and "Formulation and evaluation of the project",
the variation of the program is 0, therefore the SPI must be equal to 1, as it is observed.
39
Now, in the case of activities that show a negative variation, this situation is clearly reflected
in the Performance Index (CPI), since the values are less than 1, which refers to the fact that
40
2.3.3 Performance information work
PROJECTIONS
FORECAST
VARIATIONS
PHYSICAL
ACTIVITY BAC ADVANCE (EV) (CPI) (AC) ESTIMATED BAC-AC BAC-EV TCPI
ESTIMATED UP TO
% AT
CONCLUSION WITH
CONCLUSION
TYPICAL
EAC = (AC +
VARIATION ETC)
Studies, designs and permits $49.000.000 100% $49.000.000 1 $49.000.000 $0 $49.000.000 $0 $0 -$1
Project formulation and evaluation $5.000.000 100% $5.000.000 1 $5.000.000 $0 $5.000.000 $0 $0 -$1
Industrial safety and BPM's training $47.386.800 99% $47.056.000 0,979186257 $48.056.230 $337.832 $48.394.062 -$669.430 $330.800 -0,494151741
Phytosanitary regulatory training $47.386.800 99% $46.696.000 0,958883575 $48.698.300 $720.421 $49.418.721 -$1.311.500 $690.800 -0,526725124
Plant technology appliances $54.564.308 97% $52.902.230 0,809885111 $65.320.660 $2.052.239 $67.372.899 -$10.756.352 $1.662.078 -0,154520603
Construction of Cavas for pigs and viscera $162.000.000 99% $159.866.321 0,925951382 $172.650.880 $2.304.310 $174.955.190 -$10.650.880 $2.133.679 -0,200328893
Construction of bovine cellars $540.000.000 99% $535.200.960 0,973289501 $549.888.763 $4.930.743 $554.819.506 -$9.888.763 $4.799.040 -0,485302358
Black and gray work adaptation of the
beneficiation plant $279.186.800 99% $275.611.200 0,952609104 $289.322.450 $3.753.481 $293.075.931 -$10.135.650 $3.575.600 -0,352774612
Processing plant finishes $648.526.501 98% $632.387.500 0,961920344 $657.421.900 $16.777.898 $674.199.798 -$8.895.399 $16.139.001 -1,814308835
TCPI = BAC - EV / BAC -
ETC=(BAC-EV) /CPI) EAC=(AC+ETC) AC
TOTAL $1.833.051.209
According to the performance index or performance until the conclusion of TCPI, which presents (- negative) values, it is observed that the project until month 5 is in a comfortable position, is easy to complete and does
not require increased efforts to achieve results. Taking into account the results of the projections within the framework of a typical variation, we can say that the projections point in conditions of typical variation the project
will NOT have a saving. When analyzing the behavior of the EAC indicator, it is projected to have an extra cost until the conclusion of the project by having a variation in the budget where the projected costs are exceeded as
a trend in each activity that by the 5th month are not 100% completed. An overcharge on the scenario of an original WBS that presents faulty estimates and that after month 5 are no longer relevant due to a change in
conditions.
On the other hand, it should be noted that the activities of studies and designs and formulation - evaluation of the project yield indeterminate TCPI values because the subtraction generated in the dividend is given by the
equal costs of BAC and AC, in other words, how activities are 100% completed, it is not necessary to take them to projection analysis.
41
Therefore, if what the director wants is for the project to end on budget, that is, to spend
exactly what was budgeted, the project must be adjusted in such a way that the total cost index at
conclusion (TCPI) is 0.94 as shown in the table at the end of the calculations you did. This value
is obtained by dividing (BAC –EV) by (BAC-AC) whose operation seeks a balance between the
progress of the work (EV) and its real cost (AC); Ideally, the TCPI would be 1 for the project to
be on budget, but since there is already a saving, work costs should be readjusted with a total
In that order of ideas and to achieve this end, you as a member of the project what
modifications do you propose to the EDT to achieve this new scope (modification, elimination or
For the CPI index = 0.94, the following activities must be included within the EDT to achieve
this new scope: * Training control process, * Procurement Control and Inspection * Control of
The national planning department (DNP) in Colombia has established a group of metrics to
evaluate project management in three categories: product, management and impact, within these
there are established indicators that verify project management. These indicators have been
selected from the Bank of Sectorial Indicators (BIS), which contains approximately 2,400
indicators classified in the three categories already mentioned, the selection has been made on
those indicators that evaluate the performance of the projects. From the BIS, 607 indicators have
been found that make up the management category, of which the BIS has established 17
performance indicators related to project management, which are located in the categories of
time and costs, referring to the triangle of iron (time, cost and scope), these indicators are:
42
Indicador name
Compliance with budget execution Activity compliance rate
Royalties are an economic consideration in favor of the State, a product of the exploitation of
In accordance with the provisions of subsection 2 of article 360 of the Political Constitution of
Colombia, Law 1530 of 2012, in which it determines the distribution, objectives, purposes,
administration, execution, control, efficient use and destination of the income from the
beneficiaries. This set of income, allocations, organs, procedures and regulations constitute the
general system of royalties -SGR (NPD, 2019, p. 5) The National Planning department is the one
who distributes the resources of the SGR but it is the SGR who through the system of
monitoring, follow-up, control and evaluation (SMSCE) is the one who ensures the efficient and
effective use of the resources assigned to the SGR (NPD, 2019, p. 9).
Based on the information registered by the executing entities of the projects approved with
SGR resources and the actions of the monitoring, follow-up, control and evaluation system
(SMSCE), the Royalty Projects Management Index -IGPR was created, which is a preventive
43
control and management tool (Indicators technical sheets, 2017, p.3). The IGPR includes the
evaluation of two dimensions in four categories with fifteen management indicators based on
those described by Diez et al. (2011) of the Bank of Sectorial Indicators (BIS). The structure of
the Royalty Project Management Index - IGPR is as follows, where it is evidenced that the
performance indicators for project management are located in the dimension of "Project
Management of Performance:
Measures performance in execution of Projects.
Efficiency 40%:Evaluate the opportunity in hiring, the compliance with the execution on time and in
scheduled budget.
Effectiveness (20%): Verifies the fulfillment of the programmed goals, the completion and
closure of the projects.
44
Management indicators projects in the SGR. Taken from: IGPR IV-2019. (2019).
management in the SGR, in the event that the “Expansion and modernization of the Cofema SA
class II cattle and pig animal processing plant located in the city of Florencia Caquetá”, project
Purpose: Evaluate the opportunity of the executing entities to carry out the procedures
related to the contracting for the execution of investment projects financed with resources from
the
SGR from of the applicable regulations.
Calculation formula:
45
∑𝒏 𝟏 𝑵𝒖𝒎𝒆𝒓𝒊𝒄𝒂𝒍
𝒊= 𝒓𝒆𝒔𝒖𝒍𝒕 (𝒊)
=
𝑵𝒖𝒎𝒃𝒆𝒓 𝒐𝒇 𝒑𝒓𝒐𝒋𝒆𝒄𝒕𝒔𝒘𝒊𝒕𝒉𝒏𝒖𝒎𝒆𝒓𝒊𝒄𝒂𝒍 𝒓𝒆𝒔𝒖𝒍𝒕𝒔
46
Indicator Sheet: Compliance in the completion of projects
Purpose: Measure the entity's compliance with the completion of activities regarding the number
of projects it had scheduled to finish by the cutoff date.
Calculation formula:
𝑵𝒖𝒎𝒃𝒆𝒓 𝒐𝒇 𝒄𝒐𝒎𝒑𝒍𝒆𝒕𝒆𝒅 𝒑𝒓𝒐𝒋𝒆𝒄𝒕𝒔
𝑽𝒂𝒓𝒊𝒂𝒕𝒊𝒐𝒏 ($) =
𝑵𝒖𝒎𝒃𝒆𝒓 𝒐𝒇 𝒑𝒓𝒐𝒋𝒆𝒄𝒕𝒔 𝒔𝒄𝒉𝒆𝒅𝒖𝒍𝒆 𝒕𝒐 𝒇𝒊𝒏𝒊𝒔𝒉 𝒃𝒆𝒇𝒐𝒓𝒆 𝒕𝒉𝒆 𝒅𝒂𝒕𝒆 𝒐𝒇 𝒎𝒆𝒂𝒔𝒖𝒓𝒆𝒎𝒆𝒏𝒕
Calculation formula:
𝑵𝒖𝒎𝒃𝒆𝒓 𝒐𝒇 𝒑𝒓𝒐𝒋𝒆𝒄𝒕𝒔 𝒄𝒍𝒐𝒔𝒆𝒅
=
𝑵𝒖𝒎𝒃𝒆𝒓 𝒐𝒇 𝒄𝒐𝒎𝒑𝒍𝒆𝒕𝒆𝒅 𝒑𝒓𝒐𝒋𝒆𝒄𝒕𝒔 𝒕𝒉𝒂𝒕 𝒔𝒉𝒐𝒖𝒍𝒅 𝒃𝒆 𝒄𝒍𝒐𝒔𝒆𝒅
47
3 Based on the development of problem 3 activity, Calculate the Critical Path and the duration of the project.
48
:• EXoansion and modernization of the Cofema S.A class II cattle and oig animal orocessing plant located in the city of *lorencia Caqueta. - C:\Users\Usuario JP\Des klo a\Semestre 1 Maestrfa\ 5 PROY ECTOS III - 202...
44 Cava poi k cai cass meat II days 'f.? . Cava poi k cai cass meat;I...
37 Ld Remodeling and adaptation of I I 1.7 ". ‹I.aye ñ I it "›8J i. i.II I .iifl
@- Concrete structures •. h I.›y i J;i•i Hii Hiii.iiii
69
70 MeLaI i oof sti uctuie "3 days 't. ”' " ” ” Weldei l;WeIdei E;Sti ucL,..
7t Ai chitectui al sheet metal i oof It days t.\ t I . .. . . Covei ed Woi kei Team; l•1...
76 0— FurniLure and soluLions 1 i-i ‹I.aye s 1 ".fJ I i› 1 7i”ii”i.i”ii”i
79 Foi feitui e Pi ocessing Ai ea 10 days '.':'. I'. .'.'.. . . Pi ocessing team;Seizui e ...
10? PI-IASE IY - CLOSURE 0 days I
49
50
Expansion and modernization of the Cofema S.A class II and pig animal processing plant located in city of Florencia Caqueté. - C:\Users\Usuario JRDesktop\ Semestre 1 Maestria\5 PROYECTOS III - 202...
Projec ”t ff›re.
f Rad
tves RBS @] Proyactos Histograma @] Uso da Faraas Critical
recurso Uso da racurso Informa ShuWatdaKo
qyq¿¿ Umodeta&aa Racur#os
Graficos No subvantana I\ +pz+a
Uso da taraa
Task views Resource views Other views sub-viens
Duraclon Eosto Nombres del 3 jul 20 |27 Jul |3 ago ZD |t0 ago 20 |17 ago 20 |21 ago 20 |31 ago
Recurso 20
IM IM I3 I\/ IS ID IL IM IM I3 I\/ IS ID IL IM IM I3 I\/ IS ID IL IM IM I3 IV IS ID IL IM IM I3 IV IS ID IL IN IM I3 IV IS ID IL IM IN
{ |EXTENSION MD I"1ODERNiZATION i t69,7s days $2423462961,00
g EjPMASK II - E¥EEUTION 134,75 days $20796Z6609,0O
31 E|Cavas coollng technology and 21 days 47ssss43o8,oo
Cavaporkcaicass meat *I days $9d000000.00 Cava poi k carcass meat,I...
E|RemodeIlng and adaptation of 113,7d days
$1OB5B76601,0O E]Concrete structures 55 days
$14Z60O000,0O
5n Columns and beams 25 days $58800000.00 Columns workei's team;C...
69 E]Covers 3s days 314Z11O500,0O
70 I letal roof structui'e 23 days $89600000.00 t¥elder 1;WeIdei' 2;Struct...
Architectural sheet metal roof It days $5*510500.00 Covered Worker Team;l"l...
76 EjFurnlLure and soluLlons la days isaisa3oo,oo
I°orfeiture Processing Area l0 daye $6d'I63300.00 Processing team;5eizure ...
PHASE IV- CLO5uRE 0 days $0.00
a2ft nue a
51
Expansion and modernization of the Cofema S.A class II and pig animal plant located in the city of Florencia Caqueté. - c:\ users\ Usuari o JR Desktop\Semestre 1 PROYECTOS III - 202...
52
" Expansion and modernization of the Cofema S.A class II cattle and pig animal processing plant located in the city a f *lorencia Caquetâ. - C:\Users\Usuario JP\Desktop\Semestre 1 Maestria\5 °ROYECTOS III - 202...
Project£ibre.
@| Red
ROS P!^Y^ctos HisLo9! af0a Uso d^ !^cu+so .^..!:.e.^. . .!::!':!‹..^......................v
W%
Usode iecurso Infoime Graficos No subventana Sin oidenamienLo v
Gantt Uso de tai“ea Recui sos
f@ Usode Laiea Ninguno v
Task views || Pesoui ce views || Othei views Sub-views Filters
@ /'Iombre Duracion ftombres del Recurso |2t sep 20 |28 sep 20 |5 oct 20 |l2 oct 20 |t9 oct 20 |26 oct 20
IY I5 ID IL IN IN IN IY 15 ID IL IN III I3 IY I5 ID IL IN IN IN IY I5 ID IL IN IN I3 IY I5 ID IL III IN IN IV I5 ID IL IN IM |$ IV I?
E]EXTENS1ON AND MQDERN1ZAT1ON I I G?.7 5 $2-I2JJ G2?G I .00
dnys
6 @-PHASE II - EXECUTION 1 JI.7 s $zu 7'i+z+6o' .uo
days
31 D- Casas cooling technology and 21 leys 7 VG SG-I 308.00
99 Cava poi k cai'c ass meat 2I days '{.?‘... . . '. .'. '.'. ' Cava pork car cass me atj I. ..
54 Columns and beams US davs f. ' ' Columns woi kei s team;C...
69 E3lowers s› duys i‹z i taboo.oo
70 Metal i oof sti ucfui e 23 days 't. ” '? ”'-'” -” -'. '” -' Weldei l;WeIdei 2;Sti ucf...
7t Architectural sheet metal roof I I days t.* L 1'.'* '. '.'. :'. Covered Worker Team;I'4...
76 @-Furniture and solutions 10 leys \t 158 1C 1300,00
79 Foi feitui'e Processing Ai'ea t0 days 'f .1 .'. '. .'. . . Pi ocessing team;Seizure ...
53
" \*' Expansion and modernization of the Cofema S.A class II cattle and pig animal processing plant located in the city of Florencia
Caquetâ-. C:\Users\Usuario J ^\Desktop\Semestre 1 Maestrfa\5 PROYECTOS II- 202... — 6
I
r jec ibre. E an n and de
-b R - e
Red
WBS
cantt Uso de taiea eecuis os
Task views pesoui ce Othei 5ub- Filtei'
views views views s
Duracion nombres del Recurso 26 oct 20 2 nov 20 9 nov 20 16 nov 20 23 nov 20 30 nov 20
6
3.1 f2 Casas cooling technology and z I days $7 SG SGD 308.00
49 Cava pork carcass meat 21 days |':' '.' '.' '.' . ' ' “ Cava pork car cass meatjl ...
’ ‘ G ’
5? ’
Columns woi kei s team C
” s andf:I: • • *"5 da s
*
69
70 * Metal i oof sti ucLui e *23 days ! | '-'!'”: - : - : '-: Weldei l;WeIdei 2;Sti uct...
71 Architectural sheer metal
1.1 days | '. '1'.'L '.'. ' ' . Covered Woi ker Team;M... M ce*'erDfi 1
roof
10 dnys $ 1 ‘iR I r 1300.00
76 @- Furniture and solutions
79 Foi feitui e Processing Ai l0 days |'- - I - -.- '. - ' - Pi ocessing team;5eizure ...
54
?•*“ Exoansion and modernization of the Cofema S.A class I I cattle and pig animal orocessing plant located in the city of Florencia Caquetâ. - C:\Users\Usuario JP\Des ktop\Semestre 1 Maestria\5 ROYECMOS I II - 202...
Project£ibre.
"*¿ Ped
55
3.2 Duration of the Project.
O PE N P RO J
Abur “ Cei"i ai lmpi imii Inf or macion Guai dai Line a de
Nuevo Vista pi eliminai 8ase
cuai dai @ Guai dai como PDF " ' Calendai io L impiai Line a de
Base Pi o\ ectos . Dialogo de pi ojecIas
Actuali*ai
Sombre
@ Covers
.' I AI cllitectui .aI sheet metal i oof
56
4. Determine methods for implementing indicators in project management, select one and
document it.
activity or result; provides a signal related to a single information, which does not imply that it
cannot be reinterpreted in another context The indicators fulfill the function of showing
information concerning a single objective; They must provide clear and precise information on
the performance and fulfillment of the objectives established in the MIR (Matrix of Indicators for
a. Efficacy indicators: Efficacy indicators measure the degree of compliance with the
established objective, that is, they provide evidence of the degree to which the described
objectives are being achieved. These types of indicators are the most common within the
MIRs.
b. Efficiency indicators: The efficiency indicators measure the relationship between the
achievement of the program and the resources used for its fulfillment. These indicators
quantify what it costs to achieve the proposed objective, without limiting it to economic
resources; it also encompasses the human and material resources that the program employs
c. Economic indicators: The economic indicators measure the capacity of the program to
adequately manage, generate or mobilize financial resources. These indicators quantify the
proper use of these resources, understood as the ability of the program to attract monetary
resources outside of it that allow it to enhance its financial capacity and recover borrowed
financial resources.
57
d. Quality indicators: These measure the attributes, capacities or characteristics that the
goods and services produced have or should have. Steps To Build An Indicator In order to
The literature related to the PDCA control cycle as a method for the implementation of
indicators in project management. It is a simple but powerful method where you Plan, Make,
Check and Act. In Rincón's reflections (1998), PHVA is a managerial conception that dynamizes
the relationship between man and processes, this relationship is controlled by establishing,
maintaining and improving standards based on the technical specifications of the process and
Planning: materializes with the definition of goals and the methods to achieve them.
To do: consists of the execution of the activities that will lead to the fulfillment of the goals,
Verify: The results of the executed task are evaluated, the problems that cause the non-
Act: corrective measures are taken to achieve the fulfillment of the goals.
In the works presented by Rincón (1998), he establishes the following procedure for the
implementation of indicators:
58
1. A working group must be formed that are involved in the project and in the processes to be
2. Identify the activities to measure. In this part the author recommends starting from
3. Execution of activities that feed the perspectives and objectives of the balanced scorecard
(Do).
5. Execute the activities that feed the corrective actions and / or the revision, adjustment of
indicators.
Whatever methodology the organization adopts for the implementation of indicators in project
management, Rincón (1998) recommends keeping in mind the following elements associated
Definition: it must be simple and clear and also include only one characteristic.
Responsibility: indicates the area that owns the indicator and therefore is responsible for
59
Reading points: it must be clear at which points the measurement will be carried out; at
Decision-making: it must allow adequate feedback and also present clear information and
be complemented with other management tools that help analyze causes and establish
points for improvement to support the decision to be made. If possible, the relationship it
60
5. Link to the deliverable document, the criteria of each member of the group, referring to lessons learned, contributions to knowledge, applicability in projects in the construction of indicators and methods in project management
Name Learned lessons Contributions to knowledge Applicability in projects in the construction of indicators and methods in project
management.
Unit 1 - Problem 2
En la Unidad 1 - Problema 1 - Metodologías y herramientas
Claudia apropiadas para indicadores en proyectos, comprendí la
Gisella importancia de constrir los indicadores de desempeño In general, it was evidenced that the cost performance index for the analysis
Rengifo period indicates that it is efficient in managing the resources established for the
Unidad 1 - Problema 1 con el ejercio mediante 3 ejercicios o project, and although there are activities with an index lower than 1, it suggests
ejemplos para cada tipo de indicadores a medir, tales como that we must be We are cautious in this matter, which may be due to the
Impacto, Resultados, Productos, Procesos e Insumos. circumstances that arise, so it would be important to carry out the exercise at a
later period and evaluate the behavior of this activity for decision-making.
Unit 1 - Problem 1 Indicator is understood as the way of comparing the behavior of two variables which yields a
In Unit 1 - Problem 1 - Appropriate methodologies and tools for value, a magnitude, a criterion. The result can then be a measure (quantitative) or an observation
indicators in projects, it allowed me to define what an indicator is, The indicators fulfill two basic functions: one of a quantitative nature and the (qualitative) that indicates or expresses the current situation of a system, process, project, etc.
its structure, steps to build an indicator - when designing a flow other of a qualitative nature. against the fulfillment of the proposed objectives.
chart-, what the indicators are for and differentiate between: Data,
KPIs are used to monitor and find out if the set objectives are being met, and to
metrics, KPIs, objectives. The project called Expansion and modernization of the Cofema SA class II cattle and pig animal
be able to quickly make corrective decisions in the event of deviations from the
set objectives. processing plant located in the city of Florencia Caquetá was part of an exercise developed in the
Likewise, I was able to make a comparison with the types of Projects III course where, based on a project with previous information, indicators of efficiency,
Diagnostic KPI´s allow the comparison of the actual situation with the planned
indicators specifically with the predictive and diagnostic indicators efficiencies, and effectiveness have been designed and calculated following the methodology of
one in order to detect deviations. They are essential for all types of projects.
linking the characteristics of each one. CONVEL (2013) and DPN (2009). The calculation of management indicators was also
A KPI or predictive indicator allow us to estimate the final situation of a
Jefferson project, starting from its current situation and taking data from its historical developed through an earned value management simulator that found to analyze and evaluate the
Velez Castro Thus, in Unit 1 - Problem 1 the exercise was completed with 3
situation. In other words, anticipating possible problems and thinking about performance and financial health (costs) panorama of the project and change its course through
examples for each type of indicators to measure, such as Impact,
potential risks. • If we are not able to explain how and to what extent an corrective decisions.
Results, Products, Processes and Inputs.
indicator directly reflects the achievement of the objectives and goals set, then
it is not a good KPI. The objectives were identified in each phase of the project, they were elaborated taking into
In Unit 1 - Problem 2 _ Efficiency and effectiveness indicators,
account the type of objective, the level of the objective and the dimension of the indicator for
it was possible to build indicators of efficiency and effectiveness
each level of the objective.
for the project named - Expansion and modernization of the
Cofema S.A., class II cattle and pig animal processing plant located Unit 1 - Problem 2
Finally, the elaboration of the project was developed with the calculation of the costs and the
in the city of Florencia Caquetá. planning of the activities using the Free Project which allowed to identify the number of
• Managing the cost of a project is an important task to achieve success and face
the obstacles that arise along the way. In this sense, an efficient and effective activities, the sequencing of the critical path and the allocation of resources.
In addition, in Part A, the Methodologies for the formulation of
performance, efficiency and effectiveness indicators were cost management can avoid the generation of significant cost overruns or
savings in the project, since in the first case it can trigger problems with the Also, I can conclude the following
reviewed, with the above, a comparative matrix of the
methodologies could be made. In this sense, the indicators leverage of resources and recurrent delays in complying with the activities
proposed in the EDT regarding the schedule and budget. While a significant An indicator is a quantitative representation (variable or relationship between variables),
related to efficiency and objectively verifiable, from which the necessary information is recorded, processed and
effectiveness were compared. saving in the project can be derived in a positive scenario of the efficient
61
management of the project presented to measure the advance or setback in the achievement of a certain objective. So
62
costs, - or of the limitation of activities and / or resources that on the fly are the indicators should represent the relationship of two or more variables in order to make it
While Unit 2- Problem 3 _ Performance indicators, was worked considered unnecessary or dispensable in the execution of the project. easier to analyze the results achieved by a program
in 2 parts. In Part A, the project was designed and planned using A KPI (Key performance indicator) is a unit of measurement that provides data on the
free project, the Budgeting, cash flow was designed and later, performance of a specific aspect of a strategy. In this sense, it is important to highlight that
economic or cost information analysis, project requirements, and Unit 2- Problem 3 KPIs directly influence the decisions made in the company or project.
then it was design key project management indicators were made. KPIs are based on metrics, associated with the performance of the company to achieve
Through the indicators the quantified evaluation of the performance of the specific objectives. However, metrics are measurable values of some of the different
In Part B, twelve key performance indicators were designed and processes, services, products are obtained. In general terms, two types of processes carried out in the company, but their analysis will not provide information on the
built for the Cofema's project - post project closure). Likewise, and indicators are identified: Process indicators which measure the progress of the efficiency of business strategies. Therefore, although all KPIs are business metrics, not all
considering the Balanced Scorecard (BSC) approach, it was project and the result indicators, which measure the final effectiveness of the metrics are KPIs.
building the indicators (KPIs) for the project. Then the cost project and the fulfillment of the results. In this last sense, the performance
The performance indicators are closely related to the evaluation, the follow-up, the
performance indicators after the project closure is part of the Ex - Post evaluation where the
implementation time, the timing of the monitoring, the observation method and the
index and schedule performance index were calculated. pre-investment, investment and operation stages are complemented, these project
progress of the different strategies proposed.
closure indicators allow measuring the degree to which the company has
Evaluation, can focus on the results of the intervention and its effects; It can also focus on
Regarding Unit 2 _ Problem 4 - Integration of indicators of a achieved the objectives of the project. For the project "Expansion and
the costs of what is being evaluated, on the way in which the intervention is applied and
project for decision making, - the concepts, methodologies, the modernization of the Cofema S.A class II bovine and pig animal processing plant
managed, and even on the course and relevance of said intervention.
steps to design and build an indicator, the classification or typology located in the city of Florencia Caquetá", the closure indicators must be related
to: Monitoring, for its part, is defined as a process, continuous and systematic, after the
of indicators were integrated. Now, with what was developed in
evaluation, for the analysis of the information collected, in order to determine the progress
problem 2; The content of key performance indicators, balanced
• Analysis of the investment stage of the project: indicators in relation to the of the intervention carried out in terms of the achievement of objectives and goals.
scorecard, calculation of cost performance index and performance
index of the project schedule were constructed. project schedule, sources of financing, investment costs, executed works
Then with what was developed in problem 3 activity, the Critical • Analysis of the Project Operation Stage: indicators related to: associated
Path and the duration of the project were calculated. resources, costs, user satisfaction analysis, re-estimation of project indicators
derived from Earned Value Management (EVM) and balanced scorecard.
Finally, one of the methods for implementing indicators in project
management was determined and documented.
Unit 2 _ Problem 4
• From the S curve graph of both (PV), (EV) and (AC), and by making their
respective comparison, it was possible to determine in the first instance which
project is on time and if a significant cost overrun is occurring when observing
that AC> PV> AC. That is, when running and analyzing the simulation of the
project completely in the 8 months and observing the comparison of the Curve
S, it can be said that the behavior of AC is higher than the PV and EV obtained
during the execution of the project. In this sense, the project is exposed to cost
overruns due to inadequate cost management since there is a cost that is higher
than the budget and the progress made, - which may be the product of a bias per
action (estimation error), omission (aspects not estimates that put the cost at
risk) or corruption within the company or its partners (cost aspects that were
intentionally managed for the benefit of private interest). 51
• According to the results obtained by the S curve for (PV), (EV) and (AC)
where the behavior of the AC is above the planned value (PV), it could be
argued that these results are due to atypical factors for which it is as the project
passes due to the health emergency, the low demand for suppliers for the
different assigned activities, influences the real cost, it is necessary to establish
a financial buffer destined to mitigate these cost overruns.
• According to the activities that were academically chosen to carry out the
analysis of the Earned Value technique, in the fifth (05) month the project is
neither behind schedule nor ahead of schedule, since by subtracting the Value
data Ev earned for the fifth month ($ 1,803,720,211) of the data of the Real
Cost spent in the fifth month ($ 1,803,720,211) gives 0. That is, the activities
resulting from the analysis of the variation of the schedule have generated
expenses according to the programmed.
• According to the result, for the analysis of the variation index of the SV
schedule in the month (05) of the project, it gives us the value of zero (0),
which indicates that the project is neither late nor advanced according to the
period study, that is, the programmed activities have generated expenses
according to the programmed, we can adjust actions that allow a greater
performance in the development of the project.
63
• In view of the fact that there are incomplete activities, the project must carry
out continuous monitoring of these activities for their completion.
• For the implementation of the Earned Value simulator, ten activities were taken
for study, of which only 2 of them show 100% progress, although the missing
percentage in the rest of the activities ranges between 1 and 3 percentage
points.
• In general, the results in the cost performance index for the analysis period
indicate that we are being efficient in managing the resources established for
the project, and although there are activities with an index lower than 1, it
suggests that we must be cautious in this matter, which may be due to the
circumstances that are being presented to us, so it would be important to carry
out the exercise in a later period and evaluate the behavior of this activity for
decision making.
• On the other hand, it should be noted that the activities of studies and designs
and formulation - evaluation of the project yield indeterminate TCPI values
because the subtraction generated in the dividend is given by the equal costs of
BAC and AC, in other words, how activities are 100% completed, it is not
necessary to take them to projection analysis.
64
Conclusions
Through the development of this course, the importance of the Implementation of the
proposed balanced scorecard was established, to strategically direct the company, manage
organizational performance and control the results obtained in each of the business lines.
competitiveness of the livestock sector in Colombia: on the one hand, there is to generate a
vision of Entrepreneurship for the management of farms, and on the other, there is
implementation and massification of the use of science and technology tools available for
livestock.
Regarding the first mentioned, the ranchers must manage the farms as if they were companies
and therefore do serious planning in different areas (strategy, finances, operations with plans at
least in the medium term, as well as designing processes that facilitate their management) and
design control tools to monitor the results. Regarding the use of science and technology, farmers
must make use of modern tools for soil management as well as implement genetic improvement
64
Bibliography
Ambriz Avelar, R. (2008). La gestión del valor ganado y su aplicación: Managing earned value
and its application. Paper presented at PMI® Global Congress 2008—Latin America, São
Cofema S.A. (2020). Cofema Caquetá. Página Web Corporativa . Florencia, Colombia, Caquetá.
CONEVAL. (2013). Manual for the Design and Construction of Indicators. Main instruments for
897f03-9b26-4e10-85a7-789c9e54f5a3
DNP. (2016). Proyectos Tipo: Construcción de planta de beneficio animal categoria auto
attachment.googleusercontent.com/attachment/u/0/?ui=2&ik=165f09c210&attid=0.2&perm
msgid=msg-a:r7720408201692057170&th=16d179d993148fe4&view=att&disp=inline
&realattid=f_k0ctydl21&saddbat=ANGjdJ_AJSOP4jLmE8XfWAFYElURKY3ZoZY261hl
hkbyDwQTmjmu4wk5
efficiency indicators in villa don lino Heredia, J.A. (2001). System of Indicators for the
improvement and integrated control of the quality of the processes [University of Holguín
Oscar%20M%C3%A9ndez%20Oliva.pdf
65
Duitama Mayor's Office (2019). Health situation analysis with the model of social determinants
https://duitamaboyaca.micolombiadigital.gov.co/sites/duitamaboyaca/content/files/000864/4
3188_asis_duitama_2019.pdf
guidelines, standards and minimum conditions of the School Feeding Program (PAE).
https://huila.gov.co/pae/descargas/category/5-resoluciones?download=358:resolucion-
29452-de-2017
Municipality of Duitama (2017). Investment projects registered in the BPIM Validity 2017
https://duitamaboyaca.micolombiadigital.gov.co/sites/duitamaboyaca/content/files/000147/7
325_proyectos-vigencia-2017.pdf
Municipality of Duitama (2018). Investment projects registered in the BPIM Validity 2018
https://duitamaboyaca.micolombiadigital.gov.co/sites/duitamaboyaca/content/files/000644/3
2172_proyectos-registrados-vigencia-2018-1.pdf
National Planning Department -DPN. (December, 2019). School meals. Version 3.0.
https://proyectostipo.dnp.gov.co/images/pdf/alimentacionescolar/GuiaMetodologicaPAE.pdf
National Council for the evaluation of social development policy-CONEVAL. (2013). Manual
66
Office of the Comptroller General of Boyacá (2018). Final audit report express school feeding
program. http://cgb.gov.co/inicio/Archivos/controlfiscal/2018/INFORME%20DEFINITIVO
%20DUITAMA%20PAE.pdf
http://semduitama.gov.co/sem2020/archivosem/PLAN%20DESARROLLO%20EDUCACI
ON%202016%20%202019.pdf
Sierra, M. (2020). First Webconference Project III - Construction of indicators and methods of
Rincon, RD. (1998). Organizational management indicators: A guide for their definition. Eafit
University Magazine.
https://repository.eafit.edu.co/bitstream/handle/10784/16386/document%20-%202020-08-
17T103302.529.pdf?sequence=2&isAllowed=y
67