Professional Documents
Culture Documents
Received 24.03.2016
Ground Investigation
Report
Branston Locks Development
Phase 1
CON-GE-BHAM-COSTCDX8620-GIR-001
Revision 0
February 2016
Project Name Branston Locks Development Phase 1
Document Title Ground Investigation Report
1 EXECUTIVE SUMMARY
The Branston Locks Housing Development is being undertaken by Nurton Development (Quintus)
Ltd, west of the A38, Burton upon Trent. Staffordshire County Council are overseeing the
expansion of the highways infrastructure associated with the development and have
commissioned Amey to develop the highways scheme; Phase 1 of the project is to develop new
access routes from Branston Road to the proposed Branston Locks Housing Development
including a new canal bridge across the Trent and Mersey Canal.
This Geotechnical Investigation Report briefly outlines existing information available for the Phase
1 site access area, and presents the findings of the Ground Investigation undertaken along the
proposed route of the Branston Locks Development Access Road. The ground investigation was
conducted in November 2015 and included two combined percussive/rotary boreholes with a
target depth of 20m, and six window sample holes with a target depth of 5m; the works were
evenly split on either side of the Trent and Mersey Canal. Due to difficult ground conditions the
bore hole on the eastern side of the canal was terminated before it reached a satisfactory depth;
however it was decided that sufficient information had been collected during the investigation to
not require further work. All other holes were advanced to depths sufficient to provide information
critical to geotechnical design.
In-situ testing was conducted and samples submitted for geotechnical and chemical laboratory
analysis. A ground water monitoring standpipe was installed in the borehole west of the canal.
Ground conditions were found to be River Terrace deposits composed of dense sands and
gravels to a depth of 4.70m below ground level (bgl), overlying Weathered Mercia Mudstone to a
depth of >16.20m bgl. The weathering grade of the mudstone is Grade IVa (matrix with
occasional claystone pellets) where first encountered, reducing to Grade II (angular blocks of
unweathered marl with virtually no matrix) by the terminal depth. The base of the Mercia
Mudstone was not determined.
Shallow thicknesses of made ground were encountered at three test locations, and was observed
to be reworked River Terrace Deposits. Where holes were advanced in the existing A38 Branston
Roundabout embankments Cohesive Fill was encountered to depths of 4.7m; this material
displays characteristics of reworked Mercia Mudstone. Inspection pits advanced in proximity to
the Trent and Mersey Canal showed Granular Fill material derived from River Terrace Deposits.
Contents
2 INTRODUCTION ................................................................................................. 5
2.1 Scope and Objectives of Report .......................................................................... 5
2.2 Description of Project......................................................................................... 5
2.3 Geotechnical Category of Project ........................................................................ 6
2.4 Other Relevant Information ................................................................................ 6
7 ENGINEERING ASSESSMENT............................................................................ 43
7.1 Ground Model ................................................................................................. 43
7.2 Site Access Road ............................................................................................. 44
7.3 Branston Locks Canal Bridge ............................................................................ 45
9 REFERENCES .................................................................................................... 57
10 GLOSSARY ........................................................................................................ 59
11 FIGURES ........................................................................................................... 61
12 DRAWINGS....................................................................................................... 62
Tables
Table 3-1: Summary of Superficial Geology .......................................................................................... 8
Table 3-2: Summary of Solid Geology .................................................................................................. 8
Table 3-3: BGS Borehole Data [6] ..................................................................................................... 10
Table 3-4: Summary of Geology from SGE 2009 [9] ........................................................................... 11
Table 3-5: Summary of SGE Atterberg Limit Testing [9] ...................................................................... 11
Table 3-6 Summary of SGE One Dimensional Consolidation Test ......................................................... 11
Table 3-7: Summary of SGE PSD Testing [9] ...................................................................................... 12
Table 3-8: Summary of SGE pH, sulphate and sulphur analysis [9] ...................................................... 12
Table 4-1:2015 GI Borehole Summary [16] ........................................................................................ 17
Table 5-1: Borehole Log Summary .................................................................................................... 21
Table 5-2: Generalised Interpreted Ground Conditions ........................................................................ 22
Table 6-1: Granular Fill PSD analysis results ....................................................................................... 23
Table 6-2: Average Atterberg Limit Results – Cohesive Fill .................................................................. 25
Table 6-3: Cohesive Fill PSD analysis results ...................................................................................... 25
Table 6-4: Cohesive Fill Cu, mv value vs Depth ................................................................................... 27
Table 6-5: Average Atterberg Limit Results – Made Ground................................................................. 28
Table 6-6: Made Ground PSD analysis results ..................................................................................... 29
Table 6-7: Average Atterberg Limit Results – River Terrace Deposits ................................................... 30
Table 6-8: River Terrace Deposit PSD analysis results ......................................................................... 31
Table 6-9: Average Atterberg Limit Results – Mercia Mudstone ........................................................... 34
Table 6-10: Mercia Mudstone PSD analysis results .............................................................................. 34
Table 6-11: Corrected SPT values: Mercia Mudstone ........................................................................... 36
Table 6-12: Mercia Mudstone cu values – SPT derived and published data ........................................... 37
Table 6-13: Undrained Unconfined Triaxial testing – Mercia Mudstone Grade IVa ................................ 37
Table 6-14: One-dimensional Consolidation testing – Mercia Mudstone Grade IVa ............................... 38
Table 6-15: Mercia Mudstone Eu, E’ and v values ............................................................................... 39
Table 6-16: Point Load testing – Mercia Mudstone Grade II ............................................................... 40
Table 6-17: ACEC classifications – Mercia Mudstone ........................................................................... 40
Table 6-18: Summary of Material Properties....................................................................................... 41
Table 6-19: Characteristic Geotechnical Parameters ............................................................................ 42
Table 7-1: Settlement Reduction Options For Embankment Construction ............................................. 47
Table 7-2: Embankment Fill Options .................................................................................................. 48
Table 7-3: Options for Branston Locks Canal Bridge............................................................................ 49
Table 8-1: Risk Evaluation Matrix ...................................................................................................... 54
Table 8-2: Geotechnical Risk Register ................................................................................................ 55
2 INTRODUCTION
The scope and objectives of this Ground Investigation Report (GIR) is to interpret the
information gathered during the ground investigation (GI), and to present a geotechnical
evaluation of the information stating the assumptions made in the interpretation of the
test results.
This report has been prepared in accordance with the Design Manual for Roads and
Bridges (DMRB) Volume 4 Section 1 Part 2 HD22/08 [1] specifically Appendix D. As the
project is not currently understood to impact Highways England (HE) assets this report
will not be subjected to the HE certification process; however if planned works are
altered to such an extent that they do affect HE property Key Stage 2 Preliminary
Certification will be sought.
Amey have been commissioned by SCC to undertake the following aspects of the
scheme, focused on providing information pertinent to Phase 1 of the scheme;
2. To assist in the design of the earthworks associated with the construction of the
access road for the Branston Locks development.
3. To assist in the design of the foundations of the new bridge structure associated
with the construction of the access road for the Branston Locks development.
The GI was commissioned in order to identify the ground conditions and material
properties along the proposed route of the Phase 1 access road. Amey invited four
ground investigation specialists to tender for the work, of which CC Ground
Investigations Ltd (CCG) was awarded the contract.
On the basis of the available information the scheme is considered to fall within
Geotechnical Category 2 as defined in HD22/08 [1]. As project area comes under the
jurisdiction of SCC rather than Highways England this document will not be submitted for
Geotechnical Certification.
3 EXISTING INFORMATION
The topography of the site has been determined using historic Ordnance Survey (OS)
maps, and Current OS Maps Ref [3].
The Branston Locks Development Site is predominantly flat arable farm land with a
number of isolated domestic and farm buildings scattered across the area. The site is
roughly ‘bottle-shaped’ and is bound on the east by the A38; the north by Shobnall
Road; the west by wooded hills; and the south by Branston Lane. The site is
approximately 1.36 hectares in area. The Trent and Mersey Canal bisects the site on a
southwest-northeast trend, with approximately two-thirds of the site to the west of
the canal and one-third to the east. The Phase 1 Site Access area is located in the
south-eastern corner of the Development Site (Figure 1)
OS Maps indicate the site topography to be generally flat and low lying at an elevation
of approximately 48m above Ordnance Datum (AOD).
Historical OS Maps available in the project Design Access Statement [4] have been
examined to determine historical land use and development. The earliest available
map from 1888 indicates that the site is predominantly defined farming fields, with a
small number residential and farm buildings scattered through the area. The Trent
and Mersey Canal is present on site, and the Branston Road overbridge is in place.
The Settlement of Branston is a short distance to the south-east of the site. The
historic layout and use of the site changes very little as successive OS maps are
viewed; field boundaries show minor changes and new farm buildings are erected,
but essentially the site remains the same. In the immediate vicinity to the site the A38
is constructed in between 1955 and 1991, during which time there is an increase in
the number of residential properties in the Branston Road areas.
An examination of the British Geological Survey (BGS) 1:50,000 Sheet 140 [5] and
information provided by the BGS Geoindex [6] have been undertaken.
Artificial ground has not been identified by the BGS in close proximity to the proposed
route of the access road and canal bridge; however the historic construction of the
A38 and the canal are likely to have resulted in engineered fill material being
encountered within the Phase 1 Access site location.
Recent aerial photography [3] reveals contemporary land use as predominantly arable
agriculture with a residential property (Bridgefield House) located immediately east of
the Trent and Mersey Canal. The Canal is seen to be active, with Narrow boats visible
in the channel and a tow path running parallel on the eastern bank. Overhead utility
cables are present within the fields on the western half of the site.
Branston is listed on the Coal Authority Coal Mining and Brine Gazetteer [7] as
potentially requiring a Coal mining and Brine subsidence report. Interrogation of the
BGS website [6], and the Coal Authority Gazetteer, indicates the location of mining
activities is outside the region of concern for the site.
Review of the historical OS maps [3] indicate a large opencast gravel pit to the south
west section of the site, as well as two old Marl Pits to the north west, no records of
mining activity within the site boundary have been ascertained.
A review of historic maps [4] identified that the area that the site is located on has
been predominately agricultural since 1888, with a small number of residential and
farm building being constructed in the area. Between the 1950’s and 1990’s the A38
was constructed to the east of the site.
Six boreholes have been identified in BGS [6] records that are located within the
Branston Locks Development Site details of the strata encountered are given in Table
3-3 (depths given in metres below ground level – m bgl). No boreholes are located
within the Phase 1 Access Area (Figure 3).
River Terrace
Hole Mercia Mudstone Ground Water
Deposits
†
No groundwater noted, however geology record is from a well
Peat was encountered in five window sample holes located in the southwest of the
development site; these holes are located approximately 350m west of the Phase 1
area.
Groundwater strikes were observed in the sand and gravel deposits from 2m bgl to
5m bgl, rising to a minimum depth of 0.8m bgl.
Two samples from clay deposits were subjected to Atterberg Limit testing. Results are
displayed in Table 3-5. Results of Atterberg limits test classify the clays as low to
intermediate plasticity.
Property Range
A single sample from the clay deposits was tested for coefficient of compressibility,
the results of which are displayed in Table 3-6. This result corresponds to clays of
medium compressibility.
Fifteen sand and gravel samples were subjected to particle size distribution (PSD)
analysis, the results of which are summarized in Table 3-7.
Cobbles 0% – 7%
Silt 0%
Selected samples were subject to pH, sulphate and sulphur analysis, a summary of
these is provided in Table 3-8.
Table 3-8: Summary of SGE pH, sulphate and sulphur analysis [9]
Parameter Result
Chemical analysis of soils and groundwater from across the development site was
conducted as part of the Shepherd Gilmore’s site investigation; conclusions made for
the entire development site that may be applicable to the Phase 1 Development are:
During the design of the GI works the Canal and Rivers Trust (CRT) were consulted;
works were not planned to take place within the CRT’s land, however given the
sampling methodology being used it was important to ensure the GI work did not
result in damage to the canal infrastructure. The CRT reviewed the Risk Assessments
and Method Statements (RAMS), as well as further detailed information relating to
sample locations and methodology. The CRT provided no objections to the planned GI
work as it was to be conducted at a sufficient distance from the canal infrastructure to
not pose a danger to the integrity of the canal.
The Multi-Agency Geographic Information for the Countryside (MAGIC) [10] was
interrogated to identify any points of concern to be considered. The following issues
were identified:
The Branston Water Park local Nature Reserve is present approximately 200m
to the south of the site.
Woodland on the hillside bordering the west of the site is listed in the
National Inventory of Woodland and Trees, and as a Priority Habitat
(Deciduous woodland).
The land within the A38 Branston Roundabout gyratory is classified on the
Priority Habitat Inventory as Deciduous Woodland.
Five species of birds are specified as being previously recorded within the
area. These include Curlew, Lapwing, Redshank, Tree Sparrow and Yellow
Wagtail.
Environment Agency (EA) flooding records [11] show the Site Access area to be
situated in an area generally of very low, to low risk from flooding from rivers and
surface water (Figure 4). It should be noted that the area to the west of the canal has
a higher risk of flooding than the area to the east.
A Flood Risk Assessment has been undertaken by SGE in October 2012 [12]. This
report considers the entire Branston Locks Development Site and the area local to the
site. The report concludes that there are relatively low risks of flooding from
numerous sources in the vicinity of the development area and recommends mitigation
measures to reduce flood risk.
The primary function of the site walkover was is to confirm potential issues arising
from preliminary sources of information and also to identify any geotechnical
constraints that may not be discernible from desk study information. The site consists
predominantly of open fields adjacent to Branston Road and the Trent and Mersey
Canal. A residential building (Bridgefield House) and grounds are located in the south
east of the site, with Branston road bordering the grounds to the south and the Trent
and Mersey Canal to the west. The development area is relatively flat however
embankments rise to a height of approximately 5m in border the eastern extent along
Branston Road and the A38. A number of observations made during the site walkover
have been summarised below:
Trent and Mersey Canal - observed to be active with Barges passing through
the area. Damage to the concrete on the western edge of the canal, which
suggests a canal survey may be required to assess the risk of any damage
during construction.
Farmed Fields– surface soils within the farmed areas were observed to be
relatively firm however could not be closely inspected due to access
restrictions. The fields were identified as being recently harvested. Track
imprints from machinery on the soil surface were shallow and indicate intense
rainfall may induce soft ground conditions. Access to fields on both sides of
the canal is good, with gated access and flat conditions. An above ground
storage tank was observed 280m north-west of the existing canal bridge;
labelling indicated this held Liquid Fertiliser (Omex Nitroflo 30% N).
Overheard power cables were identified crossing the development site from
southwest to north east. A spur of this line terminates close to the Trent and
Mersey Canal, where it is diverted underground.
The GI fieldwork was undertaken between 12th and 18th October 2015 by CCG in
general accordance with the Eurocode 7 (EC7) Part 2, Ground Investigation and
testing (1997) [13], BS5930:2015 [14] and BS10175:2001 [15].
The GI scope was specified by Amey to provide geotechnical information required for
the preliminary and detailed design of the Branston Locks Development Site Access
(Phase 1). Specialist GI contractors CCG supplied the following:
A single Terrier 2002 track mounted rig to advance the six window sample
holes up to 5.00m bgl.
During the GI works adverse ground conditions resulted in hole P1-BH02 failing to
reach target depth; The Amey Engineer on site elected not to continue or re-drill the
hole as sufficient ground information was deemed to have been obtained. Two
additional inspection pits were advanced to identify the make-up of artificial ground
associated with the Trent and Mersey Canal (P1-BH01A) and the A38 embankments
(P1HP-01). Table 4-1 summarizes the locations, extent and installation of the ten
boreholes.
Physical and digital copies of the report generated for the GI work have been supplied
by CCG. This factual report [16] presents the locations of all exploratory holes,
borehole logs, and laboratory results; a copy of the report is presented in Appendix B.
In-situ Standard Penetration Tests (SPTs) utilising split spoon sampler or solid cone
methods were carried out at regular intervals in boreholes in accordance with BS
1377 Part 9 [17] and BS EN ISO 22476-3:2005 [18]. Results are given in the CCG
Factual Report [16] (Appendix B) and displayed in Figure 8 of this report.
BS EN ISO 22476 [18] provides the following equation for adjusting Standard
Penetration Resistance (N) values to account for the energy delivered to the drive
rods (N60 = N value adjusted to a reference energy ratio of 60%):
The CCG factual report (Appendix B) gives the Er value for the test equipment as
60.76%, therefore the adjusted N60 value is only fractionally higher than the
uncorrected ‘N’ value; when decimal rounding is applied N60 = N, therefore
uncorrected N values are used for the derivations in Section 6.
On 13th November two inspection pits were excavated to determine the location of
the BskyB fibre optic cables installed in the tow path on the eastern canal bank. This
work was conducted by LG Construction and falls outside the scope of work of the
Ground Investigation being reported in the document. A visual inspection was made
of each hole by the Amey Geotechnical Engineer on site during the GI works. The tow
path appears to have been constructed form re-worked river terrace materials. The
cables were identified in a green four-inch duct at 0.51m depth in the north pit
(321383E, 421731N), and 0.575m depth in the south pit (321366E, 421722N). As the
pits did not form part of the GI work, and at the time of inspection no LG
Construction personnel were not present on site; the Engineer did not interfere with
the pits or services, and no samples were taken.
The following laboratory testing was undertaken on soil samples recovered from the
site:
• Liquid limit (LL), plastic limit (PL) and plasticity index (PI);
Asbestos Screen.
Copies of laboratory testing results are contained within the CCG Factual Report 2015
[16] and are presented in Appendix B.
5 GROUND SUMMARY
The following geological units were anticipated within the study area following the
review of information sources.
Made Ground
This GIR will utilize the in-situ and laboratory observations and results of the CCG
2015 GI work (Appendix B). Preliminary Geotechnical Design Parameters have been
derived from these ground investigations are outlined in Section 6.
Table 5-1 provides a summary of the general ground conditions present collected
from the borehole data. The determination of Mercia Mudstone Weathering Grades
is outlined in Section 6.5 of this document.
5.1.1 Geology
All exploratory hole information available to Amey has been reviewed for identifying
the geology across the site. A plan showing the locations of all exploratory holes and
cross-sections across the site are presented in Drawings No. COSTCDX8620-GEO-002
and COSTCDX8620-GEO-003.
The Code of Practice for Site Investigations [14] subdivides anthropogenic soils so as
to differentiate between disturbed natural ground and engineered fill. This report
therefore adopts the following terminology:
Made ground was observed on site, usually as the result of farming. Fill material was
observed in two forms:
1. Granular Fill material associated with the construction of the Trent and Mersey
Canal.
Stratum
BH01 BH01A BH02 WS01 WS02 WS03 WS04 WS05 WS06 HP01
(depth m bgl)
0.00 to
Granular Fill - - - - - - - - -
0.751
0.00 to 0.00 to
Cohesive Fill - - - - - - - -
4.701 1.051
0.00 to 0.00 to 0.00 to
Made Ground - - - - - - -
0.30 0.85 0.40
0.31 to 0.85 to 0.00 to 0.00 to 0.00 to 0.40 to 0.00 to
River Terrace Deposits - - -
4.70 3.201 3.001 3.001 3.001 2.001 2.001
4.70 to
Weathered Mercia Mudstone (Grade IVa)2 - - - - - - - - -
6.20
6.20 to
Weathered Mercia Mudstone (Grade III)2 - - - - - - - - -
12.05
12.05 to
Weathered Mercia Mudstone (Grade II)2 - - - - - - - - -
16.201
Ground water 0.90 - - 2.00 2.50 2.20 - 2.35 - -
1
Note: Indicates base of strata not observed
2
Weathering grades determined in Section 6.5
The generalised ground conditions expected to be found across the site are
displayed in Table 5-2 and are noted as metres Above Ordnance Datum (m AOD).
Note that this generalisation does not identify thicknesses of fill material in proximity
to the A38 or Trent and Mersey Canal as these are anticipated to change with the
varying alignment of these earthworks.
Groundwater 45.39m
1
Note: Weathering grade determined in Section 6.5.1
2
Indicates base of strata not observed
The strata encountered during the 2015 GI programme, together with depths and
thicknesses are summarised in Section 5. In-situ and laboratory testing results can be
found in the GI Factual Reports attached in Appendices B. A summary of the material
properties for each stratum is provided in Table 6-18. A summary of the derived
geotechnical parameters of each stratum is presented in Table 6-19.
Granular Fill is observed in hole P1-BH01A only; this was an inspection pit advanced to
0.75m bgl in the ramp to the Branston Road Bridge from the track to the east of the
Trent and Mersey Canal. The Granular Fill is described as brown slightly clayey sandy
gravel, which changes to a slightly sandy clayey gravel at depth. The gravel in both
cases is sub-angular to rounded fine to coarse siliceous material, siltstone, brick concrete
and porcelain.
Classification
One natural moisture content (NMC) tests was conducted on the Granular Fill returning a
NMC value of 13% (Figure 5). One Particle Size Distribution (PSD) tests with pipette
sedimentation was undertaken in the Granular fill, results are provided in Table 6-1 and
Figure 6. The average material is described as a clayey silty sandy gravel.
Using guidance given in BS8002:2015 ( [19] Figure 1 p15), and assuming the Granular
Fill to be a medium density gravel / coarse engineered fill above the water table a bulk
density of 17kN/m³ has been assigned to this material.
Shearing Resistance
Due to the Granular Fill being observed only in a single inspection pit no SPT testing was
conducted in the material; therefore no correlations between SPT N values and strength
or stiffness have been possible.
BS8002:2015 allows for the estimation of the critical state effective angle of shearing
resistance (Φ’) based on soil angularity and grading ( [19]Equation 3 and Table 1 p16
and 18); using this equation the Granular Fill is determined to have Φ’=34°.
Chemistry
Classification of the Aggressive Chemical Environment for Concrete (ACEC) has been
undertaken on one sample from Granular Fill material. This has returned a Design
Sulfate class of DS-1, and ACEC class of AC-1.
One sample of Granular Fill was submitted for Midi-s analysis (As, Cd, Cr, Cu, Ni, Zn, Pb,
Hg, Se, W, S, B, hexavalent chromium, total cyanide, free cyanide, total sulphate,
sulphide, total sulphur, pH, total PAH, phenols, thiocyanate). No results of concern were
received.
Two samples of Granular Fill were submitted for Total Petroleum Hydrocarbon – Criteria
Working Group (TPH-CWG) analysis. No results of concern were received.
One sample of Granular Fill was submitted for Asbestos Screening; no asbestos was
detected.
Cohesive Fill material was observed within P1-WS06 and P1-HP01; both of which were
advanced in the existing A38 embankment. Neither investigation points proved the base
of the stratum, and therefore total thickness of the Cohesive Fill. The material is
described as firm locally friable reddish brown and brown slightly sandy slightly gravelly
to locally gravelly clay. Gravel is angular to sub-rounded fine to coarse siliceous material,
concrete, mudstone, limestone, wood, sandstone and brick. At depth the material is
observed to become soft and the gravel to be made up of angular to sub-rounded fine to
coarse siliceous material and mudstone. The make-up of the Cohesive Fill indicates that
weathered Mercia Mudstone Formation provides a proportion of the source material.
Classification
Testing undertaken within the Cohesive Fill included four NMC tests and three Atterberg
Limits tests. Plasticity classification has been determined as per BS5930 (2015) [14];
results are displayed in Figures 5 and 7 and average values in Table 6-2.
Three samples were submitted for PSD testing with pipette sedimentation; Figure 6 and
Table 6-3 displays results. The average material is described as a clayey silty gravelly
sand.
Using guidance given in BS8002:2015 [19] and assuming the Cohesive Fill to be have
characteristics of both coarse and fine engineering fill above the water table a bulk
density of 19kN/m³ has been assigned to this material.
Shearing Resistance
BS8002:2015 allows for the estimation of the critical state effective angle of shearing
resistance (Φ’) based on the soils Plasticity Index ( [19]Equation 7 p19);
( )
Using this equation with the average Plasticity Index the Cohesive Fill is determined to
have Φ’=26.6°.
Cohesive Fill was encountered in one window sample hole (P1-WS06) resulting in five
SPT test being conducted within the material. A review of the results described in Figure
8 shows that the uncorrected SPT ’N’ value steadily decreases with depth, with the
exception of the deepest point in the hole returned an uncorrected ‘N’ value of 50 over
30mm, indicating refusal. Removing this result from the cohort gives an average ‘N’
value of 7. The correlation between uncorrected ‘N’ value, Plasticity Index (PI) and
undrained shear strength (cu) outlined by Stroud (1974) [20] has been utilised to
calculate an average cu value:
1 72 0.14
2 48 0.21
3 36 0.28
4 18 0.56
Deformability
Stroud & Butler (1975) [21] provide the following equation for determining the
coefficient of volume compressibility (mv):
Plasticity Index is used to determine f2. Using this equation an average mv value of
0.3m2/MN can be assigned the Cohesive Fill material; alternatively the fill can be given
the mv value associated to its depth, as is indicated in Table 6-4 and Figure 10.
Chemistry
Classification of ACEC has been undertaken on one sample from Cohesive Fill material.
This has returned a Design Sulfate class of DS-3, and ACEC class of AC-3.
Two samples of Cohesive Fill were submitted for Midi-s analysis. No results of concern
were received.
Four samples of Cohesive Fill were submitted for TPH-CWG analysis. No results of
concern were received.
Two samples of Cohesive Fill were submitted for Asbestos Screening. No asbestos was
detected.
One sample of Cohesive Fill was submitted for Waste Acceptance Criteria (WAC) testing.
The results of elute analysis are below that of limit values for inert waste; however the
sulphate value of 1600mg/kg exceeds the 1000 mg/kg upper limit for Inert Waste. This
indicates that excavated Cohesive Fill will be required to be disposed of in a licensed
hazardous waste landfill site; however testing will be required of excavated material to
determine the nature of the waste material.
Made Ground was seen within three of the exploratory holes (P1-BH01, P1-BH02 and P1-
WS04), up to a maximum depth of 0.85m bgl. Made Ground has been identified both
within arable agriculture fields, and within the grounds of Bridgefield House. The Made
Ground is described brown slightly sandy clayey gravel to slightly sandy gravelly clay. In
all instances the stratum was observed to have occasional rootlets (<2mm) and the
gravels were angular to rounded fine to coarse siliceous material and siltstone with a
varying content of metal fragments, clinker, slag, wood fragments and twine.
Classification
Testing undertaken within the Made Ground included one NMC test and one Atterberg
Limits test. Plasticity classification has been determined as per BS5930 (2015) [14];
results are displayed in Figures 5 and 7; average values are displayed in Table 6-5.
One sample was submitted for PSD testing with pipette sedimentation; Figure 6 and
Table 6-6 displays results. The average material is described as a clayey silty gravelly
sand.
Using guidance given in BS8002:2015 [19], and assuming the Made Ground to be a
medium density gravel / sand above the water table a bulk density of 17kN/m³ has been
assigned to this material.
Shearing Resistance
Due to the Made Ground being observed only in inspection pits no SPT testing was
conducted in the material; therefore no correlations between SPT ‘N’ values and strength
or stiffness have been possible.
BS8002:2015 [19] allows for the estimation of Φ’ based on soil angularity and grading;
the Made ground is determined to have Φ’=34°.
Chemistry
ACEC classification has been undertaken on two samples from Made Ground material.
Both samples returned a Design Sulfate class of DS-2, and ACEC class of AC-2.
One sample of Made Ground was submitted for Midi-s analysis. No results of concern
were received.
Two samples of Made Ground were submitted for TPH-CWG analysis. No results of
concern were received.
One sample of Made Ground was submitted for Asbestos Screening. No asbestos was
detected.
The River Terrace material was identified within seven of the exploratory holes. Only P1-
BH01 encountered the base of the unit at 4.7m bgl, with a total thickness of 4.4m. The
unit is generally described as being grey to brown slightly clayey sandy gravel; however
areas tend to sandy gravelly clay and clay gravelly sand. The River terrace deposits are
observed to be interbedded, with significant variations of particle size and density
present over very small thicknesses.
Classification
Testing undertaken within the River Terrace deposits included twelve NMC test and two
Atterberg Limits test. Plasticity classification has been determined as per BS5930 (2015)
[14]; results are displayed in Figures 5 and 7; average values in Table 6-7.
Ten samples was submitted for PSD testing with three of those scheduled for additional
pipette sedimentation; Figure 6 and Table 6-8 displays results. River terrace deposit
material shows a wide variation of particle size distributions; however a general trend is
discernible showing low cohesive content, and significant sand and gravel components.
Material grading alternates between gap graded and uniform graded. The average
material is described as a slightly clayey silty very sandy gravel.
2
Min, Max and Average calculated for the sum of Clay and Silt fractions
Using guidance given in BS8002:2015 [19], and assuming the River Terrace Deposits to
be dense sands and gravels with a silty component and above the water table a bulk
density of 19kN/m³ has been assigned to this material. Where the material is below the
water table a unit weight of 21kN/m³ has been assigned.
Eighteen SPT tests were conducted within the River Terrace Deposits. A review of the
results described in Figure 8 shows that the uncorrected SPT ’N’ value shows no specific
trend with depth down-hole; the average uncorrected ‘N’ value of the material is 35.
Utilizing the correlation between uncorrected ‘N’ value and undrained shear strength (cu)
outlined by Stroud (1974) [20] an average cu value of 246kN/m2 can be assigned the
River Terrace Deposit material.
Shearing Resistance
BS8002:2015 [19] allows for the estimation of Φ’ based on soil angularity and grading;
using this equation the River Terrace Deposit is determined to have Φ’=32°.
Thomlinson ( [22] Figure 2.13) allows for derivation of Ф’ using SPT results. Using the
average uncorrected ‘N’ value Ф’=37°.
The average Φ’ of 37° derived from the Tomlinson method is recommended for the
material parameter for the River Terrace Material
Stiffness
Bowles (1996) provides equations for the calculation of Undrained Young’s Modulus
(Table 5-6 in [23]) for soils. Using the average material classification described as slightly
clayey silty very sandy gravel the following equation has been used to determine the
Young’s Modulus (Eu):
( )
Thomlinson [22] defines the relationship between undrained and drained Young’s
Modulus (E’) as:
Poisson’s Ratio (v) for sands is defined by Thomlinson [22] as 0.1 to 0.3; it is
recommended that a conservative value of v = 0.3 be used for River Terrace Deposits.
Chemistry
Three samples of River Terrace Deposits were submitted for Midi-s analysis. The
following results of note were returned. No results of concern were received.
Five samples of River Terrace Deposits were submitted for TPH-CWG analysis. No results
of concern were received.
One sample of Made Ground was submitted for WAC testing. Analysis results indicate
that excavated River Terrace Deposit can be classified as Inert Waste; however any
excavated material will require further WAC testing prior to disposal.
The Mercia Mudstone was identified within P1-BH01 from 4.70m bgl to 16.2m bgl; the
base of the unit was not encountered. The unit was described as reddish brown with
rare blue grey mottling (<10mm) firm slightly sandy clay, developing to a very stiff
slightly sandy gravelly clay with increased depth. The gravels were observed to be sub-
angular fine to coarse extremely weak lithorelics of mudstone. From 12.05m bgl the unit
was described as extremely weak thinly laminated reddish brown mudstone with
occasional veins of light grey gypsum up to 25mm in thickness. Gypsum veins were
observed to predominantly be orientated normal to the mudstone laminations; however
gypsum veins were observed perpendicular to the mudstone laminations linking
horizontal veins 25cm apart.
Weathering grade of the Mercia Mudstone has been determined using weathering
scheme and ranges of index and other properties outlined in CIRIA C570: Engineering in
Mercia Mudstone ( [24] Section 3.2 including Tables 3.2 and 3.3 p28-29). The
weathering profile of the Mercia Mudstone encountered during the 20115 GI is outlined
below:
Classification
Testing undertaken within the Mercia Mudstone included six NMC test and four Atterberg
Limits test. Plasticity classification has been determined as per BS5930 (2015) [14];
results are displayed in Figures 5 and 7; average values in Table 6-9.
Four samples were submitted for PSD testing with pipette sedimentation; Figure 6 and
Table 6-10 displays results. The Mercia Mudstone shows varying grain size distribution
which does not appear to be obviously linked with weathering grade, however the
sample cohort size does not allow for accurate interpretation. An average material
composed of all tested weathering grades is described as a slightly gravelly clayey sandy
silt.
Min 15 22 9 1
Max 35 55 52 36
Average 25 37 26 13
1
Note 10% fraction not recorded thus true grading undetermined.
Bulk density values determined for Grade IVa material in consolidation and compression
testing indicate a bulk density of 2.08 Mg/m3, which provides an average bulk unit
weight of 20.4kN/m3.
Using guidance given in BS8002:2015 [19], and assuming the Mercia Mudstone
encountered to be below the water table and a slightly gravelly clayey sandy SILT a bulk
density of 21kN/m³ has been assigned to this material.
Shearing Resistance
BS8002:2015 [19] allows for the estimation Φ’ based on the soils Plasticity. Given the
average PI the Mercia Mudstone weathering grades Φ’ values are determined as follows:
Grade II Φ’=28.1°
Overall Φ’=28.5°
It is recommended that the average overall effective angle of shearing resistance (Φ’) of
28.5° be used for all weathering grades of Mercia Mudstone
Eight SPT test were conducted within the Mercia Mudstone; one in Grade IVa, four in
Grade III, and three in Grade II material. A review of the results described in Figure 8
shows that the uncorrected SPT ’N’ value increases with depth downhole. It should be
noted that seven of the eight SPT tests were halted at 50 blows as the tests were unable
to penetrate the required 300mm; these tests were all those carried out in Grade III and
II weathering categories. Table 6-11 provides raw (N) and corrected (N300) SPT values.
7.9 50 240 63
8.7 50 210 71
65 III
10.2 50 210 71
11.7 50 270 54
13.2 50 20 750
16.2 50 90 158
The very low penetration rates observed in the Grade II weathered material indicate
refusal due to the material becoming increasingly competent; therefore derivation of
material properties from SPT values obtained from the Grade II material are not reported
in this document.
The correlation between uncorrected ‘N’ value, PI and cu outlined by Stroud (1974) [20]
has been utilised to calculate an average cu value. The CIRIA guide to Engineering in
Mercia Mudstone [24] gives the average f1 value for the formation as 5. Measured PI
values of the various grades of weathered Mercia Mudstone fall outside the given range
of f1 values; the conservative f1 value of 5 has been used. cu values derived from SPT
results are plotted in Figure 8 with average values for weathering grades are given in
Table 6-12.
Table 2.4 in the CIRIA guide to Piled foundations in weak rock [25] provides engineering
properties of the Mercia Mudstone weathering grades; cu values are displayed in Table 6-
12.
II - 1450 kPa
A single undrained unconfined triaxial shear strength test was conducted on Weathering
Grade IVa material obtained from a depth of 5.2 to 5.65m bgl. Table 6-13 displays shear
undrained shear strength versus cell pressure.
It is recommended that where derived parameters for cu and E’ are available they be
used in geotechnical design, where they are not figures from CIRIA 181 should be used.
The following values for cu are recommended:
Deformability
Using Stroud & Butler (1975) [21] to determine the coefficient of volume compressibility
from SPT ‘N’ Value and PI the following values for the weathering grades encountered
have been calculated. The PI values of the Mercia Mudstone range from 10% to 13%;
this results in correlations to f2 falling below the lowest part of the trend line provided by
Stroud and Butler. As a result the f2 value adopted for this calculation is the value
recommended in CIRIA C570 [24] of 0.5. Average values are given below and displayed
in Figure 10.
An mv value for Grade II weathering has not been provided as the uncorrected SPT ‘N’
values indicate refusal; thus providing unrealistic values.
A single one dimensional consolidation test was conducted on Weathering Grade IVa
material obtained from a depth of 5.2 to 5.65m bgl. Table 6-14 displays coefficient of
volume compressibility versus pressure range.
Stiffness
Table 2.4 in the CIRIA guide to Piled foundations in weak rock [25] provides engineering
properties of the Mercia Mudstone weathering grades; Eu values are displayed in Table
6-15.
Thomlinson [22] defines the relationship between undrained and drain Young’s modulus
(E’) as:
Using the methods described above average Eu and E’ for the varying grades of
weathered Mercia Mudstone have been calculated and are displayed in Table 6-15
Poisson’s Ratio (v) is defined by Thomlinson [22] for various material types, values
recommended for use in geotechnical design are listed in Table 6-15.
Grade Eu E’ v
Point Loading
Point load testing was conducted on three samples of Grade II material; two samples
were of mudstone, one of gypsum. Valid fractures were achieved in each test, and Point
Load Strength Index (Is50) values obtained. The International Society for Rock Mechanics
[26] provides the following equation to determine Uniaxial Compressive Strength (C0)
from Is50
Table 6-16 provides Is50 and C0 values. Due to the low number of tests conducted Is50
values and information derived from these results should be considered to be indicative
rather than definitive.
Depth
Is50 C0
Material Downhole m
MPa MPa
bgl
Chemistry
Classification of the ACEC has been undertaken on two samples from Mercia Mudstone
material; one from weathering Grade III, the other from Grade II. Table 6-17 provides
Design Sulfate and ACEC classes
Design
Weathering ACEC Class
Sulfate Class
Water Soluble
NMC LL PL PI N300 pH
Sulphate
(%) (%) (%) (%) (mg/l)
River Terrace 35
9 38 24 14 - -
Deposit
Mercia
Mudstone 20 29 19 10 34 - -
Grade IVa
Mercia
Mudstone 21 36 23 13 65 8.4 570
Grade III
Mercia
Mudstone 16 32 19 13 353 8.2 1800
Grade II
ACEC
γb Ф’ cu mv Eu E’ v DS Class
Strata Class
(kN/m3) (°) (kN/m2) (MN/m2) MPa MPa
Mercia Mudstone
21 30 170 0.06 230 138 0.5 - -
Grade IVa Weathering
Mercia Mudstone
21 28 324 0.03 350 210 0.2 DS-2 AC-2
Grade III Weathering
Mercia Mudstone
21 28 1450 0.03 2830 1698 0.2 DS-3 AC-3
Grade II Weathering
7 ENGINEERING ASSESSMENT
The PSSR document [2] outlined a preliminary engineering assessment based upon the
ground conditions as they were understood given the historic information available and the
planned alignment given in Drawing No. COSTCDX8620-GEO-001. The primary engineering
considerations were:
Potential ground improvement techniques to allow shallow foundations for the new
Trent and Mersey Canal road overbridge.
Piling systems for the new Trent and Mersey Canal road overbridge.
Extensive consideration was given to numerous solutions for these issues, the options
considered the most appropriate for the ground conditions and proposed construction as
were understood from the available information were:
The 2015 GI work has greatly increased the understanding of the subsurface conditions at
the Phase 1 development site; as a result the preliminary engineering assessment has been
reviewed below.
The generalised ground model is presented in Section 5 of this report; this can be
summarised as:
Engineered fill is present on site associated with the A38 embankments and the Trent
and Mersey Canal; the type and thickness of material is dependent on the location.
The proposed Phase 1 Site Access Road is aligned with the existing A38 Branston
Roundabout exit currently used by Branston road. The new road will bear north-west
from the present alignment and cross the Mersey and Trent Canal approximately 15m
north of the existing overbridge. The new road will be constructed on material added to
the northern side of the existing embankment; as the road alignment diverges from the
current road alignment the new embankment will become independent of the existing
earthworks. The embankment leaves the A38 roundabout and loses elevation to meet
the new Mersey and Trent overbridge which requires a minimum clearance of 2.7m
between the level of the tow path and the underside of the bridge. Once the road has
crossed the canal it grades down to the planned ground level, as do planned spurs
leaving the access road.
Settlement of the underlying materials has the potential to cause delays in construction
and damage the completed works; differential settlement an issue of particular concern
due to the following circumstances:
Transition between loaded material types (i.e. where the embankment passes
from current embankment to River Terrace Deposits)
Table 7-1 summarises the advantages and disadvantages of the options proposed to
reduce differential settlement and consolidation of the embankments.
Table 7-2 summarises the advantages and disadvantages of the proposed embankment
fill options.
Branston Locks Canal Bridge will connect the proposed access road on either side of the
Trent and Mersey Canal. The design must conform to design standards set by the Canal
and River Trust and recommendations from the flood risk assessment undertaken by
SGE. These include an aesthetically pleasing appearance, 2.7m clearance from ground
level adjacent to the underside of the bridge and the design must not compromise or
influence inflows from external water sources. The bridge will require significant
foundations to allow it to perform as required. Shallow foundation techniques, such as
pad or raft foundations or a geogrid reinforced earth bridge abutments may be
considered for the development if the bridge loads can be supported by the River
Terrace Deposits. Alternatively, piling systems that may be considered for the
development are:
Sheet piles
CFA piles
Table 7-3 summarises the advantages and disadvantages of the proposed foundation
options.
Option Recommendation
For
Can be easily designed and controlled to suit the ground conditions
Many different systems available
Rapid application, provides rapid results where there are granular soils
Against
Dynamic Compaction Not Recommended Settlement will be accelerated, however consolidation will not be addressed, therefore not suitable for all soil types and ground
conditions
Cost of mobilising, running and demobilising equipment
Dynamic solutions will result in noise/vibration issues which will potentially have harmful effects on the existing infrastructure
(services, existing roads, canal)
Effectiveness of treatment is highly dependable on the ground conditions; therefore a risk that the correct depth of treatment
may not be met.
For
Once placed the system will only require monitoring until it is removed
Settlement and consolidation of underlying material will be addressed
The additional use of wick drains will increase the efficiency of the process
Recommended Effective option if construction programme allows for the construction of embankments followed by a delay in construction of
Preloading
where the bridge.
and / or
programme Against
surcharging allows Requires the importation and exportation of large quantities of load material
Consolidation to required residual values will take a significant period of time (months)
Use of wick drains will increase the cost of the process
Placement of material will stop any other work being conducted if the preloading is not planned to take place within the
construction programme.
Option Recommendation
For
Wide range of materials can be considered for use depending on slope requirements
Unit weight of cohesive material is likely to be lower than that of granular; therefore a lower load will be imposed on the
underlying material
Use of cohesive fill Not Recommended
Against
Material will be subject to long-term consolidation
Material placement will need to take place in specific weather conditions
Shallower slope angles compared to other options, therefore a larger landtake will be required. Typical slope angles 1 in 3
For
Wide range of materials can be considered for use depending on slope requirements
Free draining
Use of granular fill Recommended
Steeper slope angles than with the use of cohesive fill, therefore steeper slope angles of up to 1 in 2 can be used.
Against
Material placement will need to take place in specific weather conditions
For
Light-weight nature will significantly reduce load on underlying strata
Potential cost savings if source of material is local and abundant
Use of light-weight fill
Not Recommended Against
options (PFA)
Material placement will need to take place in specific weather conditions
Some light-weight fills are classified as waste products, so require permits, specific handling techniques and base layers which
will increase complexity and cost.
Option Recommendation
For
Recommended if Reinforcement can be added to carry tensile stresses and required loads
Option Recommendation
For
Traditional Construction Methods
Quick and easy to implement
Piles can be driven to formation height
The relatively thin pile cross-section should allow the pile to be driven to depth more easily when compared to other piling
systems
Recommended Against
subject to Vibration during installation may exceed limits required for working in the vicinity of the canal
Sheet Piling
successful pile The flat cross-section of the sheet pile will impact on the stiffness of the pile
testing A facia will be required to cover the sheet piles to aid aesthetics (e.g. concrete panels/block work, brickwork)
Any movement of the pile due to bending will damage the proposed facia
The drivability of the pile will depend on the ground conditions (large cobbles or boulders may deflect or stop piles being driven)
The nature of the River Terrace Deposits may cause significant damage to the piles during installation – damage would be
undetected
Large sheet pile sections may be required leading to the need for a crane on site
Potential delivery issues if long pile lengths are required
Option Recommendation
For
Piles can be manufactured to specification off-site; improved Health Safety Environment and Quality control.
Low materials movement on and around site when compared to other methods
Piles can be driven to current ground level for the bridge superstructure (wingwalls and abutment) to be constructed off the
piles
Against
Pre-cast driven piles Not Recommended
Vibration during installation may exceed limits required for working in the vicinity of the canal
Smooth shaft surface reduces skin friction, so reliance on end bearing pressure critical
Potential for damage to pile during installation going undetected
Pile tops will need to be broken down to the required height – vibration and HS issues
Driving piles through the River Terrace Deposits may prove difficult to reach target depth
River Terrace Deposits are likely to cause significant damage to the pile
Option Recommendation
For
Piles are constructed on site to required specifications
Simple, rapid process
Is not a dynamic, impact intensive process
No hole casing required
Irregular shaft surface increases skin friction
Low noise and vibration generation
Against
CFA piles Not Recommended
Potential for hole collapse or voiding depending on ground conditions
Multi-phase process
Implemented at ground level and a traditional abutment and wingwall bridge structure is used.
Pile tops will need to be broken down to the required height – vibration and HS issues
Integrity of piles dependent on timely concrete supply
Pre-fabricated steel pile cages will be required
River Terrace Deposits are likely to cause significant damage to equipment
River Terrace Deposits are prone to collapse in open-hole situations
Option Recommendation
For
Piles are constructed on site to required specifications
Simple, rapid process
Is not a dynamic, impact intensive process
Against
The options considered the most appropriate for the ground conditions and proposed
construction are summarised below:
OR
A review of the geotechnical and environmental risks associated with the proposed
works has been undertaken. The risks have been evaluated using a risk evaluation
matrix as presented below in Table 8.1. Reference has been made to Part 3 of HD 41/03
‘Maintenance of Highway Geotechnical Assets’ [28] as part of the risk assessment
process.
The risk register is detailed in Table 8.2. The risk register lists the anticipated
geotechnical and environmental hazards associated with the works and the potential
consequences of those hazards. The risk before control of the hazard has been assessed
quantitatively as has the anticipated risk following the proposed response to each
hazard.
Likelihood
Client/business relationships SHE risks and
Negligible 1 Threat to contract credibility 5 reputation 1 1 2 3 4 5
Risk Ratings
1 to 5 Green Risk is negligible or of otherwise low severity and shall be set aside for further consideration.
5 to 12 Amber Risk is of concern and shall be subject to further analysis and evaluation.
12 to 25 Red Risk is unacceptable and shall be subject to immediate analysis and evaluation.
Encountering
Historical land use indicates extensive farming. Any evidence of contaminants being
unaccounted
Health and Safety implications to personnel encountered to be recorded and appropriate
contaminants from 3 2 6 2 1 2
with regards to contaminants associated with personnel notified. Suitable PPE must be worn at
historical land use
agriculture. all times.
(Agriculture).
Trent and Mersey Damage to canal during construction of road Follow protocols set by the Canals and Rivers
2 5 10 1 2 2
Canal structures. Mass flooding Trust
Inability of piling
technique to reach
appropriate depth
(boulders in the Inappropriate geotechnical design leading to Undertake test piling to confirm the best piling
2 5 10 1 2 4
River terrace potential failure. method for the scheme
deposits, skerries in
the Mercia
Mudstone)
9 REFERENCES
[1] Highways Agency, “Design Manual for Roads and Bridges (DMRB) Volume 4 Section 1 Part
2 HD22/08,” Highways Agency, 2008.
[2] Amey, “Branston Locks Development Phase 1: Preliminary Sources Study Report. CON-GE-
BHAM-COSTCDX8620-PSSR,” Amey, Birmingham, 2015.
[5] British Geological Survey, 1:50,000 Geological Sheet 140 (Burton Upon Trent) Solid and
Drift Edition.
[6] BGS, “Geoindex,” NERC, [Online]. Available: http://www.bgs.ac.uk/GeoIndex/. [Accessed
02 November 2015].
[7] Coal Authority, “Coal Mining and Brine Gazetteer,” [Online]. Available:
https://www.gov.uk/government/publications/coal-mining-and-brine-subsidence-claim-
search-directory-of-places. [Accessed 09 Novemeber 2015].
[8] BGS, “Gypsum Mineral Planning Fact Sheet.,” Office of the Deputy Prime Minister., 2006.
[9] Shepherd Gilmore, “ Geo-environmental site investigation and generic quantitative risk
assessment, Report no. R0017 DH ME1072.,” Shepherd Gilmour Environment Ltd. , 2009.
[11] Environment Agency, “What's in your Backyard?,” Environmental Agency, October 2015.
[Online]. Available: http://maps.environment-
agency.gov.uk/wiyby/wiybyController?ep=maptopics&lang=_e. [Accessed 02 Novemeber
2015].
[12] Shepherd Gilmore, “ Flood Risk Assessment; Branston Locks, Burton upon Trent,”
Shepherd Gilmour Environment Ltd. , 2012.
[14] Bristish Standards Institution, “BS5930:2015. Code of Practice for Site Investigations,”
Bristish Standards Institution, 2015.
[17] British Standards Institute, “BS1377-9:1990 Methods ofor Testing For Soils For Civil
Engineering Purposes Part 9. In-Situ Tests,” British Standards Institute, British Standards
Institute, 1990.
[19] British Standards Institution, “Code of Practice for Earth Retaining Structures,” British
Standards Institution, 2015.
[20] M. Stroud, “The Standard Penetration Test - its application and interpretation,” in
Proceedings of the European Symposium on Penetration Testing (ESOPT I), 1974.
[21] M. Stroud and B. F. Butler, “The standard penetration test and the engineering properties
of glacial materials,” in Proceedings of the Syposium on Engineering Properties of Glacial
Materials, Midlands Geotechnical Society, Birmingham, 1975.
[22] M. Tomlinson, “Foundation Design and Construction,” Pearson Education Ltd, 2001.
[24] Construction Industry Research and Information Association, “CIRIA C570: Engineering in
Mercia Mudstone,” Construction Industry Research and Information Association, London,
2001.
[26] International Society for Rock Mechanics, “RTH 325-89: Suggested methods for
determining point load strength,” International Society for Rock Mechanics, 1984.
[27] Environment Agency, The Regulation of the Use of Unbound Pulverised Fuel Ash and
Furnace Bottom Ash, Environment Agency, 2014.
[28] The Highways Agency, “HD 41/03 Design Manual for Roads and Bridges: Maintenanve of
Highway Geotechnical Assets,” The Highways Agency, 2003.
10 GLOSSARY
Abbreviation Meaning
BS British Standard
EA Environment Agency
EC7 Eurocode 7
Er Energy Ratio
Eu Young’s Modulus
GI Ground Investigation
HE Highways England
kN Kilonewton
l Litre
LL Liquid Limit
Abbreviation Meaning
m Metre
mm Millimetre
mg Milligrams
MN Meganewton
OS Ordnance Survey
PI Plasticity Index
PL Plastic Limit
v Poisson’s Ratio
11 FIGURES
5 Moisture Content, Plastic Limit and Liquid Limit vs. Depth – All Strata
Phase 1 Site
Branston Locks
Development
Site Boundary
Branston Locks Development Site
Phase 1 Site
Report
Project: Brantson Locks Development: Phase 1 CON-GE-BHAM-COSTCDX8620-GIR-001
Reference:
Figure
Report: Ground Investigation Report Figure 01
Reference:
Reproduced from Ordnance Survey map with the permission of the controller of H.M.
Title: Site Location Maps Stationery Office © Crown copyright reserved. Licence no. 100033905
N
Phase 1 Access
1 in 100 to 1 in 30 1 in 100 to 1 in 30
Report
Project: Brantson Locks Development: Phase 1 CON-GE-BHAM-COSTCDX8620-GIR-001
Reference:
Figure
Report: Ground Investigation Report Figure 4
Reference:
Title: Flood Risk Zones
MC, PL and LL vs. Depth - All Strata
53
52
51
50
49
48
47
46
45
Depth (m AOD)
44
43
42
41
40
39
38
37
36
35
34
33
0 10 20 30 40 50
Moisture Content (%)
Made Ground MC Made Ground LL Made Ground PL
Granular Fill MC Cohesive Fill MC Cohesive Fill LL
Cohesive Fill PL River Terrace Deposits MC River Terrace Deposits LL
River Terrace Deposits PL Weathered Mercia Mudstone Formation MC Weathered Mercia Mudstone Formation LL
Weathered Mercia Mudstone Formation PL
Title: Moisture Content, Plastic Limit and Liquid Limit vs. Depth - All Strata
Report
CON-GE-BHAM-COSTCDX8620-001 Figure 5
Reference:
Particle Size Distribution - All Strata
100
90
80
70
Percentage Passing (%)
60
50
40
30
20
10
0
0.002 0.006 0.02 0.06 0.2 0.6 2 6 20 60 200
Mercia Mudstone Weathering Grade IVa Mercia Mudstone Weathering Grade III
Report Figure
CON-GE-BHAM-COSTCDX8620-001 Figure 6
Reference: Reference:
60
CL CI CH CV
50
40
Plasticity Index(%)
30
20
10
ML MI MH MV
0
0 10 20 30 40 50 60 70 80 90 100
53
52
51
50
Cohesive Fill
49
47.84m SPT N = 500
48
47
46
45
44
43
42
41
Depth (m AOD)
40
39
38
37
36
Mercia Mudston G II
35 34.4m SPT N = 750
34
33
32
31
30
0 20 40 60 80 100 120 140 160
SPT N values
NOTES: - SPT derived Mass Shear Strength from Stroud c = f1*N (f1 = 5.5 - 5.8)
Cohesive Fill RTD
- HV Mass Shear Strength values limited to 120 kPa
Mercia Mudstone Weathering Grade IVa Mercia Mudstone Weathering Grade III
Mercia Mudstone Weathering Grade II
Report Figure
CON-GE-BHAM-COSTCDX8620-001 Figure 8
Reference: Reference:
cu value vs. Depth- All Strata
53
52
51
50
49
48
47
46
45
44
Depth (m AOD)
43
42
41
40
39
38
37
36
35
0 100 200 300 400 500 600
Cu (kPa)
Cohesive Fill
NOTES: - SPT derived Mass Shear Strength from Stroud c = f1*N (f1 = 5.5 - 5.8)
RTD- HV Mass Shear Strength values limited to 120 kPa
Mercia Mudstone Weathering Grade IVa
Mercia Mudstone Weathering Grade III
Report Figure
CON-GE-BHAM-COSTCDX8620-001 Figure 9
Reference: Reference:
mv value vs. Depth- All Strata
53
52
51
50
49
48
47
46
45
44
Depth (m AOD)
43
42
41
40
39
38
37
36
35
0.00 0.10 0.20 0.30 0.40 0.50 0.60
Mv values
NOTES: - SPT derived Mass Shear Strength from Stroud c = f1*N (f1 = 5.5 - 5.8)
- HV Mass Shear Strength values limited to 120 kPa
Report Figure
CON-GE-BHAM-COSTCDX8620-001 Figure 10
Reference: Reference:
Project Name Branston Locks Development Phase 1
Document Title Ground Investigation Report
12 DRAWINGS
59 43
0.0 0.0
00 00
58
2.4
38
580 42
0.0
.00 00
0
41
0.0
00
570.000
50
560.
000
40
0.0
00
Site Location
40
39
0.0
00
4
0. 0500
0.0
55
30
38
0.0
00
00
0.0
54
LEGEND
20
37
0.0
00
00
0.0
53
18
3.9
10
52 36
0.0
00
0
.00
520
Site Location
35
0.0
00
0
510.000
34
0.0
00 Approximate Extents of
A1
49
500
.000
Phase One Works
6.3
02
33
0.0
00
49
0.0
00
32
0.0
00 Approximate Extents of
48
0.0
00 Phase Three Works
31
0.0
00
47
0.0
00
30
0.0
00
46
0.0
00
45
7.9
08
29
0.0
00
450
.00
0
28
0.0
00
440.000
27
0.0
00
430.0
00
26
0.0
00
420.000
25
0.0
00
24
410.000 0.0
00
23
0.0
00
400.000
22
0.0
00
0
390.00
21
0.0
00
00
380.0
20
1.2
20 08
0.0
00
000
370.
19
0.0
00
360.000
18
0.00
0
.000 17
350
0.
00
0
Trim to this line for A1
16
0 0.
.00 00
340 0
5
00
.90
335
0.0
15
0.
000
00
0
10.
0
.00
330
000
20.
14
0.
000
00
0
30.
671
00
0.0
40.000
36.
32
0
13
50.00
0.
00
60.000
0
80.000
70.000
0.000
00
0.0
12
31
1.
76
12
4
0.
00
0
\\idhrs001\Consdata\RailData\Projects\IDH - Geotechnical Projects\Staffordshire Infrastructure+\Branston Locks Development\CAD\WIP\1 Live Drgs\COSTCDX8620-GEO-001.dwg
10.000
11
00 0.
0.0 00
30 0
17.854
10
0.
20.000 00 00
0.0 0
29
90
.0
0 00
30.00 0.00
28
0
80
0 .00
00 0
By
0.
0 70
.00
50
00
50
0. 0
.0.100
Revisions
26
21
60
.000
0
00
0. 60
25 .00
0
70
.000
0
00
0.
24
50
.00
80
0
.000
0
00
0.
23
89
.478
40
.00
0
0
00
0.
22
0
00
30.00
0.
0
21
13
9.
07
7
0
0.00
20
13
20.00
1.40 0
13
0
0.00
The Built County - Highways
6
00
0.0
19
98
6.8
12
18
0.0
1 Staffordshire Place
117
00
00
.40
0.0
10.00
6
18
0
11
0.0
10
Tipping Street
0.
00
00
72
0.0
0
0.0
00
9.6
16
15
91
.00
90 .2
20
150
.0
00
0
86
.00
.0
140
15
.000
80
.000
130
.000
120
Phase One
70
000
.00
67
0
110.
Branston Lock
0.000
.29
00
10.000
9
100.0
20.000
60.0
23.066
30.000
90.000
40.000
00
47.631
50.000
80.664
80.000
45
.37
70.000
42
3
.21
40
60.000
6
.00
50.000
0
0.000
Development
40.000
30.000
10.000
13.620
20.000
30.000
20.000
10.000
0.000
IT NM TB 1:1000
Grid Reference
SK2221
Date Size
21.09.15 A1
Drawing No. Revision
Phase Three
A1
COSTCDX8620-GEO-001 P1
Status
. Preliminary
P1
COSTCDX8620-GEO-002
100
N
50
LEGEND
40
Inspection Pits
10
A
003
A
003
Section Marker
0
A1
00
A
3
Borehole Location Table
Ground
Easting Northing
Hole ID Level
(x) (y)
(mAOD)
P1-BH01 421714 321402 47.54
P1-BH01A 421719 321397 48.16
P1-BH02 421733 321371 47.76
P1-WS01 421614 321430 47.41
P1-WS02 421649 321514 47.77
P1-WS03 421677 321445 47.54
P1-WS04 421787 321350 48.08
P1-WS05 421826 321413 47.87
P1-WS06 421841 321335 52.58
P1-HP01 421903 321329 48.08
Trim to this line for A1
\\IDHRS001\ConsData\RailData\Projects\IDH - Geotechnical Projects\Staffordshire Infrastructure+\Branston Locks Development\CAD\WIP\1 Live Drgs\COSTCDX8620-GEO-002 & 003.dwg
Revisions
Branston Lock
Development
Exploratory Hole
Location Plan
Prepared Produced Checked Scale
00
A
3
IT NM TB 1:500
Grid Reference
SK2221
Date Size
27.11.15 A1
Drawing No. Revision
002
COSTCDX8620-GEO-002
P1
Status
. SHARED
P1
COSTCDX8620-GEO-003
100
LEGEND
40
Inspection Pits
10
0
A1
LEGEND
Made Ground
Granular Fill
Cohesive Fill
\\IDHRS001\ConsData\RailData\Projects\IDH - Geotechnical Projects\Staffordshire Infrastructure+\Branston Locks Development\CAD\WIP\1 Live Drgs\COSTCDX8620-GEO-002 & 003.dwg
Revisions
Branston Lock
Development
IT NM TB 1:500
Grid Reference
SK2221
Date Size
27.11.15 A1
Drawing No. Revision
003
COSTCDX8620-GEO-003
P1
Status
. SHARED
Project Name Branston Locks Development Phase 1
Document Title Ground Investigation Report
CONTENTS
REPORT
1. INTRODUCTION 1
2. SITE DESCRIPTION AND GEOLOGY 3
2.1 Site Description 3
2.2 Geology 3
3. GROUND INVESTIGATION 4
3.1 Fieldwork 4
3.2 In Situ Testing 6
3.3 Logging 6
3.4 Laboratory Testing 7
4. REFERENCES 9
APPENDICES
Appendix A – Site Plan
Appendix B – Exploratory Hole Data
Appendix C – Laboratory Test Results
Appendix D – SPT Calibration Data
CC Ground Investigations Ltd Report C4877
1. INTRODUCTION
This investigation was carried out by CC Ground Investigations Ltd (CCGI) on the
instruction and on behalf of Staffordshire County Council / Nurton Development
(Quintus) LTD (The Client) under the technical direction of Amey OWR Limited.
The purpose of the ground investigation was to provide information to assist in the
design of Branston Locks Development Phase 1; a new access route from the A38
roundabout, canal bridge and roads in to the Branston Locks Development.
The scope of the ground investigation was defined in the Engineer’s specification,
reference: Ground Investigation Specification Staffordshire County council‐
Branston Locks Development (CON‐GE‐BHAM‐COSTCDX8620‐GI‐001‐Revision 0).
This report describes the work carried out by CC Ground Investigations Ltd and
presents the findings.
All information, comments and opinions given in this report are based on the
ground conditions encountered during the site work, and on the results of
laboratory and field tests performed during the investigation. There may however
be conditions at or adjacent to the site which have not been taken into account,
such as unpredictable soil strata and water conditions between or below
exploratory holes. A careful watch should be maintained during any future
groundworks and the comments of this report reviewed as necessary.
This report has been prepared for Staffordshire County Council / Nurton
Development (Quintus) LTD and Amey OWR Limited. This report shall not be
Page 1
CC Ground Investigations Ltd Report C4877
relied upon or transferred to other parties without the written consent of CC
Ground Investigations Ltd. Should any information contained within this report
be used by any unauthorised third party it is done so at their own risk and shall
not be the responsibility of CC Ground Investigations Ltd.
Page 2
CC Ground Investigations Ltd Report C4877
2. SITE DESCRIPTION AND GEOLOGY
2.1 Site Description
The area of investigation comprises a small residential area and local nature
reserve, North of Branston Road with the land currently used for agricultural
purposes, which consists of predominantly open fields at, nearest postcode DE14
3EZ. The site is centred on the approximate National Grid Reference SK 21705
21302.
2.2 Geology
Geological Records (British Geological Survey (BGS), England and Wales sheet 140
Burton upon Trent 1:50,000 scale) indicate the site is underlain by superficial
deposits of Holme Pierrepont Sand and Gravel Member, part of the Trent Valley
Formation. Underlying solid geology comprising mudstones of the Mercia
Mudstone Group is recorded.
Page 3
CC Ground Investigations Ltd Report C4877
3. GROUND INVESTIGATION
3.1 Fieldwork
Ten exploratory holes were carried out between 12th and 17th of November 2015.
All exploratory hole locations are shown on the site plan (Appendix A). The
exploratory hole locations were set out by CCGI as directed by the Client on site.
The fieldwork was carried out in general accordance with BS5930, Amendment 2
(2010).
The boreholes, referenced P1‐BH01, P1‐BH01A and P1‐BH02 (Exploratory Hole Data
– Appendix B) were formed using a track mounted Comacchio MC300 multi
purpose rig. Following CAT scanning hand tools were used to excavate an
inspection pit to a maximum depth of 1.20m to check for buried services. Bulk and
environmental soil samples were taken and retained from the inspection pits. The
boreholes were then advanced using percussive sampling techniques to produce
continuous disturbed samples ranging between 112mm and 98mm diameter.
On refusal of percussive sampling the boreholes were continued by rotary core
drilling techniques utilising a water/polymer flush. A double‐tube swivel core barrel
with a semi‐rigid plastic liner was utilised to recover continuous cores of 91mm
diameter.
Undisturbed samples of 100mm nominal diameter were taken in suitable cohesive
material using an open drive sampler U(T)100. The samples were wax sealed on site
to prevent moisture loss.
Page 4
CC Ground Investigations Ltd Report C4877
The boreholes, referenced P1‐WS01 to P1‐WS06 (Exploratory Hole Data – Appendix
B) were formed using a track mounted Terrier drilling rig. Following CAT scanning
hand tools were used to excavate an inspection pit to a maximum depth of 1.20m
to check for buried services. Bulk and environmental soil samples were taken and
retained from the inspection pits. The boreholes were then advanced using
percussive sampling techniques to produce continuous disturbed samples ranging
between 83mm and 71mm diameter.
Soil samples were retained in semi‐rigid plastic liners, which were capped on site to
prevent moisture loss.
Boreholes were monitored for groundwater ingress as they were advanced. Upon
encountering water, sampling was temporarily stopped to allow the level to
stabilise. Water levels were also recorded at the start and finish of each shift, on
completion of the borehole and are presented on the relevant log.
On completion, a gas/water monitoring standpipes was installed in P1‐BH01. Each
installation consisted of a 50mm ID HDPE slotted tube set in a filter response zone
of limestone free gravel. The installation was sealed above and below with a
bentonite pellet seal and accessed via a valve assembly. The installation was
protected at the surface by a lockable stopcock cover set in concrete. Installation
details are given on the relevant borehole log.
The inspection pits, referenced P1‐BH01A and P1‐HP01 (Exploratory Hole Data –
Appendix B) were undertaken to provide further information in close proximity to
the existing embankment and canal towpath. Representative bulk disturbed and
environmental soil samples were taken at a range of depths.
Page 5
CC Ground Investigations Ltd Report C4877
On completion, all remaining positions were backfilled with bentonite pellets and
arisings with the surface reinstated.
Subsequent to fieldwork, all exploratory hole positions were surveyed and National
Grid co‐ordinates and levels are presented on the relevant log.
On completion of fieldwork all samples were brought to CCGI’s office for storage.
3.2 In Situ Testing
Standard penetration tests (SPT) were carried out in general accordance with BS EN
ISO 22476‐3:2005. A split barrel or a solid cone was used depending upon the
materials encountered and the split barrel samples retained as small disturbed
samples. The SPT N value was taken as the number of blows to penetrate the
300mm test drive following a 150mm seating drive. Where low penetration was
recorded the seating drive was terminated at 25 blows and the test drive
completed after a further 50 blows. SPT results are summarised as uncorrected N
values on the borehole logs and . SPT hammer calibration data is presented in
Appendix D.
3.3 Logging
Soil and rock samples from the exploratory holes were logged by an Engineering
Geologist in general accordance with BS5930, Amendment 2 (2010). Bulk, small
disturbed, core and environmental soil samples were taken retained at a range of
depths. Environmental soil samples were stored on site in temperature controlled
conditions. Soil and rock descriptions are presented in the borehole logs together
Page 6
CC Ground Investigations Ltd Report C4877
with details of sampling, in situ testing and relevant comments on drilling
techniques.
Prior to logging photographs of the samples were taken and are presented
following the relevant log.
3.4 Laboratory Testing
The following laboratory tests were carried out by Professional Soils Laboratory
(UKAS No. 4043) in accordance with BS1377:1990, Parts 1 to 8, unless otherwise
stated. The results are presented in Appendix C.
The results are shown on the
Natural Moisture Content 24
summary of soil classification tests.
The results are shown on the
Liquid and Plastic Limits 11 plasticity chart and summary of soil
classification tests.
The fine fractions of 12 of these tests
Particle Size Distribution (wet sieving
19 were further analysed using the
method)
pipette method.
One Dimensional Consolidation 1
Multi‐stage Quick Undrained Triaxial Carried out on a full diameter UT100
1
Test sample.
Point Load Strength 3 ISRM RTH 325‐89 SR12
Testing carried out by Chemical
BRE SD1 chemical testing suite for soil
6 Testing Laboratories in accordance
and water
with BRE Special Digest 1.
Page 7
CC Ground Investigations Ltd Report C4877
A range of chemical tests were carried out on soil and water samples by i2
Analytical (UKAS No. 4041). Testing was carried out in accordance with ISO 17025.
The results are tabulated and presented in Appendix C.
CC GROUND INVESTIGATIONS LIMITED
Mike Atherton BSc (Hons) FGS Rob Clarke. BSc (Hons) MSc (Eng) FGS
Senior Engineering Geologist Director
Page 8
CC Ground Investigations Ltd Report C4877
4. REFERENCES
British Geological Society, Solid and Drift Sheet 140, Burton Upon Trent, 1:50,000 scale
BRE Special Digest 1:2003: Concrete in aggressive ground. Part 1.
BS 5930+A2:1999 (2010), Code of Practice for Site Investigations
BS 1377: Parts 1 to 9 (1990), Methods of Tests of Soils for Civil Engineering Purposes
BS EN ISO 14688: Part 1: (2002), Identification and description of soil.
BS EN ISO 14688: Part 2: (2004), Principles for a classification of soil.
BS EN ISO 14689: Part 1: (2003), Identification and description.
BS EN ISO 22475: Part 1: (2006), Technical principles for execution.
BS EN ISO 22476: Part 3: (2005), Standard penetration test.
ISRM RTH 325‐89 SR12, Suggested Method for Determining Point Load Strength.
Page 9
CC Ground Investigations Ltd Report C4877
APPENDIX A
Appendix A – Site Plan
Notes:
Reproduced from base plan
provided by Engineer
Site Layout Plan
Branston Lock Development
Staffordshire County Council
Appendix A
Contract No: C4877
Drawn by: Scale:
MA NTS
CC Ground Investigations Ltd Report C4877
APPENDIX B
Appendix B – Exploratory Hole Data
CC Ground Investigations Ltd
KEY TO EXPLORATORY HOLE LOGS
Logging
The logging of soils and rocks has been carried out in general accordance with BS 5930:1999 (Amendment No.2, 2010).
Sample no/type
Water levels
Insitu Tests
Sample range
6 6
B 6.20 - 6.70 6.20 41.34
Very stiff indistinctly thinly laminated brown and reddish
brown slightly sandy silty CLAY with rare bluish grey
mottling (<10mm).
6.20-6.80m: Locally gravelly. Gravel is sub-angular fine
SPT 6.70 - 7.15 S 34
to coarse of extremely weak mudstone lithorelicts.
7 B 7.00 - 7.90 7
(3.00)
8 8
CC ROTARY LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
REMARKS:
EQUIPMENT: Hand digging tools. Comacchio MC300 multi purpose track mounted rig.
METHOD: Hand dug inspection pit: 0.00-1.20m. Continuous dynamic sampled (128mm and 113mm diam) 1.20-7.90m. Waterflush rotary coring using T6-116 core
barrel 7.90-16.20m.
CASING: SW diam to 1.50m, PW diam to 5.30m.
GROUNDWATER: Seepage at 0.90m. No rise recorded.
INSTALLATION: 50mm ID HDPE slotted pipe with washed gravel response zone: 1.00-16.00m, plain pipe with bentonite pellet seal: 0.20-1.00m, flush 150mm steel
cover set in concrete 0.00-0.20m. Gas valve fitted.
20 20
21 21
22 22
23 23
24 24
25 25
CC ROTARY LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
26 26
27 27
0.30m
Client: Staffordshire County Council / Nurton Development 0.75m Logged By
(Quintus) LTD DP
Water Samples & In Situ Testing Depth Level
(m) Description Legend
Levels No/Type Depth (m) Result (m) (mAD)
FILL: Grass over soft grey and brown slightly gravelly sandy CLAY with frequent
roots and rootlets (<2mm). Gravel is sub-angular to rounded fine to coarse of
concrete, sandstone and siliceous material. (0.15)
0.15 48.01
FILL: Brown slightly clayey sandy GRAVEL. Gravel is sub-angular to rounded fine
B 0.20 to coarse of siliceous material, siltstone, brick, concrete and porcelain.
ES
(0.30)
0.45 47.71
FILL: Brown and dark brown silty very sandy GRAVEL. Gravel is sub-angular to
B 0.50 rounded fine to coarse of siliceous material, brick and siltstone.
ES
(0.30)
1 1
2 2
CC INS PIT LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
REMARKS:
EQUIPMENT: Hand digging tools.
METHOD: Hand dug inspection pit: 0.00-0.75m.
GROUNDWATER: Not encountered.
BACKFILL: Upon completion hole backfilled with bentonite pellets 0.00-0.75m and the ground surface reinstated.
REMARKS: Terminated on engineer's instruction.
CC GROUND INVESTIGATIONS LTD
Borehole No.
5 5
6 6
7 7
8 8
CC ROTARY LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
REMARKS:
EQUIPMENT: Hand digging tools. Comacchio MC300 multi purpose track mounted rig.
METHOD: Hand dug inspection pit: 0.00-1.20m. Continuous dynamic sampled (128mm diam) 1.20-2.20m, (113mm diam) 2.20-3.20m.
CASING: SW diam to 1.30m, PW diam to 2.20m.
GROUNDWATER: None encountered prior to the use of a water flush.
BACKFILL: Upon completion hole backfilled with bentonite pellets 0.00-3.20m and the ground surface reinstated.
3 3.00 44.41 3
Borehole completed at 3.00m
4 4
5 5
REMARKS:
CC WS LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
B 0.50
ES
B 0.70 0.70 47.07
Medium dense brown and orangish brown locally light grey and
ES orange slightly clayey sandy locally very sandy GRAVEL. Gravel
is sub-angular to rounded fine to coarse of siliceous material,
1 B 1.00 siltstone and sandstone. 1
ES 1.00-1.20m: Locally clayey.
B 1.20 - 2.00 S 27 1.20m: 1 no. rounded cobble of siliceous material.
SPT 1.20 - 1.65
(1.50)
4 4
5 5
REMARKS:
CC WS LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
1 B 1.00 1
1.00-1.20m: Locally very sandy.
ES
SPT 1.20 - 1.65 S 25 1.25 46.29
B 1.25 - 1.60 Medium dense light brown locally dark brown slightly clayey
SAND with occasional black partially decomposed organic
(0.35)
matter (<2mm).
4 4
5 5
REMARKS:
CC WS LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
B 1.35 - 1.65 1.35-1.65m: Light grey locally off white and purplish brown.
Sandy.
3 3
4 4
5 5
REMARKS:
CC WS LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
3 3
4 4
5 5
REMARKS:
CC WS LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
1 B 1.00 1
ES
SPT 1.20 - 1.65 S 12
B 1.30 - 2.00
B 2.25 - 3.00
2.30-2.40m: Dark brown.
3 ES 3.00 S6 3
SPT 3.00 - 3.45
B 3.40 - 3.90
3.90 48.68
FILL: Soft reddish brown sandy slightly gravelly CLAY. Gravel is
4 B 4.00 - 4.70 S3 sub-angular to rounded fine to coarse of siliceous material and 4
SPT 4.00 - 4.45 mudstone. (POSSIBLE NATURAL).
(0.80)
5 5
REMARKS:
CC WS LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
0.30m
Client: Staffordshire County Council / Nurton Development 1.05m Logged By
(Quintus) LTD DP
Water Samples & In Situ Testing Depth Level
(m) Description Legend
Levels No/Type Depth (m) Result (m) (mAD)
FILL: Soft brown slightly sandy gravelly CLAY with frequent roots and rootlets
(<10mm). Gravel is sub-angular to rounded fine to coarse of siliceous material
and mudstone.
B 0.20 (0.40)
ES
0.40 47.68
FILL: Soft friable light brown slightly sandy slightly gravelly locally gravelly CLAY
locally tending to a very clayey sand with occasional roots and rootlets (<2mm).
Gravel is angular to sub-rounded fine to coarse of siliceous material, porcelain,
B 0.50 mudstone, gypsum and sandstone.
ES
(0.65)
B 0.90
ES
1 1
Dry 1.05 47.03
Inspection pit completed at 1.05m
2 2
CC INS PIT LOG C4877.GPJ GINT STD AGS 3_1.GDT 7/1/16
REMARKS:
EQUIPMENT: Hand digging tools.
METHOD: Hand dug inspection pit: 0.00-1.05m.
GROUNDWATER: Not encountered.
BACKFILL: Upon completion hole backfilled with bentonite pellets 0.00-1.05m and the ground surface reinstated.
REMARKS: Terminated on engineer's instruction.
CC Ground Investigation Limited
STANDARD PENETRATION TEST
Telephone: 01452 739165, Fax: 01452 739220, Email: info@ccground.co.uk
CLIENT Staffordshire County Council
SITE Branston Lock Development
Borehole Borehole Bottom Casing Water Seating Drive Test Drive Test
No. Depth Depth Depth Level Blows Pen (mm) Blows Pen (mm) Type N
(m) (m) (m) (m)
BH01 1.20
1.65
Nil
0.90 4
6
75 75 6 7 7 6 75 75
75
75 S 26
BH01 2.20
2.65
2.20
GL
2
4
75 75 6 6 8 10 75 75
75
75 S 30
BH01
3.20
3.64
3.20
GL
2
9
75
75
13
15
12
10
75
75
75
65
S
*52
BH01
4.20
4.65
4.20
1.87 2
2
75 75 3 4 4 7 75 75
75
75 C 18
BH01
6.70
7.15
5.20
2.71 6
6
75 75 9 9 8 8 75 75
75
75 S 34
BH01
7.90
8.29
5.30
0.78 5
5
75 75 13 13 15 9 75 75
75
15 S *63
BH01
8.70
9.06
5.30
2.40 6
13
75 75 14 20 16 ‐ 75 75
60
‐ S *71
BH01
10.20
10.56
5.30
2.62 8
12
75 75 14 19 17 ‐ 75 75
60
‐ C *71
BH01
11.70
12.02
5.30
2.51 8
7
75 75 10 14 11 15 75 75
75
45 C *54
BH01
13.20
13.35
5.30
2.35 7
18
75
55
50
‐
‐
‐
20
‐
‐
‐
C
*750
BH01
14.70
14.89
5.30
2.58 18
7
75 15 30 20 ‐ ‐ 75 25
‐
‐ C *150
BH01
16.20
16.34
5.30
2.47 25
‐
45 ‐ 36 14 ‐ ‐ 75 20
‐
‐ C *158
BH02
1.20
1.65
Nil
Dry 3
6
75
75
8
9
10
11
75
75
75
75
S
38
BH02 2.20 2.65 1.50 Dry 3 7 75 75 10 11 12 14 75 75 75 75 C 47
WS01
1.20
1.65
Nil
Dry 4 4
75 75 5 4 4 4 75 75
75
75 S 17
WS01
2.00
2.45
2.00
Dry 4 6
75 75 8 8 6 5 75 75
75
75 S 27
WS02
1.20
1.65
Nil
Dry 2 4
75 75 5 6 8 8 75 75
75
75 S 29
WS02
2.00
2.45
2.00
Dry 5 9
75 75 11 12 12 12 75 75
75
75 S 47
WS02
3.00
3.45
2.00
2.50 2 4
75
75
5
4
5
5
75
75
75
75
S
19
WS03
1.20
1.65
Nil
Dry 3 3
75 75 5 5 7 8 75 75
75
75 S 25
WS03
2.00
2.45
2.00
2.20 5 5
75 75 5 5 5 5 75 75
75
75 S 20
WS03
3.00
3.45
2.00
2.20 2 3
75 75 3 5 5 8 75 75
75
75 S 21
WS04
1.20
1.65
Nil
Dry 7 7
75 75 9 10 11 13 75 75
75
75 S 43
WS04
2.00
2.29
Nil
Dry 20 5
75 20 16 22 12 ‐ 75 75
40
‐ C *79
WS05
1.20
1.65
Nil
Dry 4 6
75 75 8 9 9 10 75 75
75
75 S 46
WS05
2.00
2.38
Nil
2.35 12 13
75
60
13
17
16
4
75
75
75
20
S
61
WS06
1.20
1.65
Nil
Dry 3 4
y
75 75 3 3 3 3 75 75
75
75 S 12
WS06
2.00
2.45
Nil
Dry 2 1
75 75 2 2 2 2 75 75
75
75 S 8
WS06
3.00
3.45
Nil
Dry 0 1
75 75 1 1 2 2 75 75
75
75 S 6
WS06
4.00
4.45
Nil
Dry 0 0
75 75 0 0 2 1 75 75
75
75 S 3
WS06
4.70
4.77
Nil
Dry 25 ‐
40 ‐ 50 ‐ ‐ ‐ 30 ‐
‐
‐ S *500
Notes:
1. Test carried out in general accordance with BS. 1377: Part 9: 3.3.
2. N values have not been subjected to any correction.
3. Test carried out using split spoon S, solid cone C.
4. Where full test drive not completed, linearly extrapolated N value reported.
5. <1 Denotes hammer self weight penetration (sank under own weight).
6. ** Denotes no effective penetration. CONTRACT CHECKED
C4877 MA
CC Ground Investigations Ltd Report C4877
APPENDIX C
Appendix C – Laboratory Test Results
LABORATORY
REPORT
4043
A copy of the Laboratory Schedule of accredited tests as issued by UKAS is attached to this report. This certificate is
issued in accordance with the accreditation requirements of the United Kingdom Accreditation Service. The results
reported herein relate only to the material supplied to the laboratory. This certificate shall not be reproduced in full,
without the prior written approval of the laboratory.
D Lambe S Royle
(Senior Technician) (Senior Technician)
Page 1 of
5 – 7 Hexthorpe Road, Hexthorpe,
Doncaster DN4 0AR
tel: +44 (0)844 815 6641
fax: +44 (0)844 815 6642
e-mail: rgunson@prosoils.co.uk
awatkins@prosoils.co.uk
SUMMARY OF LABORATORY SOIL DESCRIPTIONS
SYMBOLS : NP : Non Plastic * : Liquid Limit and Plastic Limit Wet Sieved.
90
CL CI CH CV CE
80
70
60
Plasticity Index (PI%).
50
40
30
20
10
ML MI MH MV ME
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Liquid Limit (LL%).
4043 C4877
SYMBOLS : NP : Non Plastic * : Liquid Limit and Plastic Limit Wet Sieved.
90
CL CI CH CV CE
80
70
60
Plasticity Index (PI%).
50
40
30
20
10
ML MI MH MV ME
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Liquid Limit (LL%).
4043 C4877
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: D
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: D
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: B
0.020
0.300
0.002
0.006
0.063
0.150
0.600
0.212
2.00
20.0
3.35
10.0
37.5
1.18
125
6.3
63
75
100.00
90.00
80.00
70.00
Percentage Passing.
60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.0001 0.001 0.01 0.1 1 10 100 1000
Particle Size (mm).
Sample Type: UT
16.0
14.0
12.0
Cv - m2/yr
10.0
8.0
6.0
4.0
2.0
0.0
10 100 1000
Pressure -kPa
10 100 1000
0.440
0.430
0.420
Voids Ratio
0.410
0.400
0.390
0.380
0.370
Sample Type UT
700
600
500
Deviator Stress kPa
400
300
200
100
0
0 2 4 6 8 10 12 14
Axial Strain %
Dimensions 2
Borehole Sample Test Orientation Area De De Failure Load (P) Is Corr Fac Is50 Failure
Depth (m) (mm) Remarks
Number Ref Type Type
Par / Perp W D (mm2) (mm) (Mpa) (kN) (MPa) F (MPa)
P1-BH01 12.03-12.10 I N/A 45 21 441 1203.21 34.69 0.410 0.55 0.455 0.848 0.39 Valid
P1-BH01 14.64-14.70 I N/A 49 31 961 1934.05 43.98 0.340 0.45 0.235 0.944 0.22 Valid
P1-BH01 16.10-16.20 I N/A 64 32 1024 2607.59 51.06 0.590 0.79 0.302 1.010 0.30 Valid
*Note All testing carried out on samples at as received water content Par = parallel, Perp = perpendicular, N/A = Not Applicable
Approved By
Rob Brown
Business Manager
Key: * -not accredited. # -MCERTS (accreditation only implied if report carries the MCERTS logo). n/s -not supplied. Page 2 of 3
Information in Support of the Analytical Results
Our Ref 15-53754
Client Ref PSL15/5865
Contract PSL15/5865
Disposal
From the issue date of this test certificate, samples will be held for the following times prior to disposal :-
Soils - 1 month, Liquids - 2 weeks, Asbestos (test portion) - 6 months
Page 3 of 3
Certificate of Analysis
Certificate Number 15-53055
18-Dec-15
Approved By
Rob Brown
Business Manager
Key: * -not accredited. # -MCERTS (accreditation only implied if report carries the MCERTS logo). n/s -not supplied. Page 2 of 3
Information in Support of the Analytical Results
Our Ref 15-53055
Client Ref PSL15/5865
Contract Branston Lock
Disposal
From the issue date of this test certificate, samples will be held for the following times prior to disposal :-
Soils - 1 month, Liquids - 2 weeks, Asbestos (test portion) - 6 months
Page 3 of 3
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 1 of 5
i2 Analytical Telephone: 01923 225404
7 Woodshots Meadow Fax: 01923 237404
Croxley Green Business Park email:reception@i2analytical.com
Watford, WD18 8YS
Client: CCGROUND
Results are expressed on a dry weight basis, after correction for moisture content where applicable
Stated limits are for guidance only and I2 cannot be held responsible for any discrepencies with current legislation
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 2 of 5
i2 Analytical Telephone: 01923 225404
7 Woodshots Meadow Fax: 01923 237404
Croxley Green Business Park email:reception@i2analytical.com
Watford, WD18 8YS
Client: CCGROUND
Results are expressed on a dry weight basis, after correction for moisture content where applicable
Stated limits are for guidance only and I2 cannot be held responsible for any discrepencies with current legislation
*= UKAS accredited (liquid eluate analysis only)
** = MCERTS accrediited
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 3 of 5
Analytical Report Number : 15-83305
Project / Site name: Branston Lock Development
* These descriptions are only intended to act as a cross check if sample identities are questioned. The major constituent of the sample is intended to act with respect to MCERTS
validation. The laboratory is accredited for sand, clay and loam (MCERTS) soil types. Data for unaccredited types of solid should be interpreted with care.
Stone content of a sample is calculated as the % weight of the stones not passing a 10 mm sieve. Results are not corrected for stone content.
511096 P1-BH02 None Supplied 0.90 Brown sandy loam with gravel.
511097 P1-WS06 None Supplied 0.50 Brown loam and clay with gravel.
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 4 of 5
Analytical Report Number : 15-83305
Project / Site name: Branston Lock Development
Water matrix abbreviations: Surface Water (SW) Potable Water (PW) Ground Water (GW)
Acid neutralisation capacity of soil Determination of acid neutralisation capacity by In-house method based on Guidance an L046-PL W NONE
addition of acid or alkali followed by electronic Sampling and Testing of Wastes to Meet
probe. Landfill Waste Acceptance
Chloride in WAC leachate (BS EN Determination of Chloride colorimetrically by In house based on MEWAM Method ISBN L082-PL W ISO 17025
12457-3 Prep) discrete analyser. 0117516260.
DOC in WAC leachate (BS EN 12457- Determination of dissolved organic carbon in In-house method based on Standard L037-PL W NONE
3 Prep) leachate by TOC/DOC NDIR analyser. Methods for the Examination of Water and
Waste Water, 21st Ed.
Fluoride in WAC leachate (BS EN Determination of fluoride in leachate by 1:1ratio In-house method based on Standard L033-PL W NONE
12457-3 Prep) with a buffer solution followed by Ion Selective Methods for the Examination of Water and
Electrode. Waste Water, 21st Ed.
Metals in WAC leachate (BS EN 12457- Determination of metals in leachate by acidification In-house method based on Standard L039-PL W ISO 17025
3 Prep) followed by ICP-OES. Methods for the Examination of Water and
Waste Water, 21st Ed.
Moisture Content Moisture content, determined gravimetrically. In-house method based on BS1377 Part 3, L019-UK/PL W NONE
1990, Chemical and Electrochemical Tests
pH in soil Determination of pH in soil by addition of water In-house method based on BS1377 Part 3, L005-PL W MCERTS
followed by electrometric measurement. 1990, Chemical and Electrochemical Tests
Phenol Index in WAC leachate (BS EN Determination of monohydric phenols in leachate In-house method based on Examination of L080-PL W ISO 17025
12457-3 Prep) by continuous flow analyser. Water and Wastewater 20th Edition:
Clesceri, Greenberg & Eaton (skalar)
Stones content of soil Standard preparation for all samples unless In-house method based on British Standard L019-UK/PL D NONE
otherwise detailed. Gravimetric determination of Methods and MCERTS requirements.
stone > 10 mm as % dry weight.
Sulphate in WAC leachate (BS EN Determination of sulphate in leachate by In-house method based on Standard L039-PL W ISO 17025
12457-3 Prep) acidification followed by ICP-OES. Methods for the Examination of Water and
Waste Water, 21st Ed.
TDS in WAC leachate (BS EN 12457-3 Determination of total dissolved solids in leachate In-house method based on Standard L004-PL W NONE
Prep) by electrometric measurement. Methods for the Examination of Water and
Waste Water, 21st Ed.
Total organic carbon in soil Determination of organic matter in soil by oxidising In-house method based on BS1377 Part 3, L023-PL D MCERTS
with potassium dichromate followed by titration 1990, Chemical and Electrochemical Tests
with iron (II) sulphate.
For method numbers ending in 'UK' analysis have been carried out in our laboratory in the United Kingdom.
For method numbers ending in 'PL' analysis have been carried out in our laboratory in Poland.
Soil analytical results are expressed on a dry weight basis. Where analysis is carried out on as-received the results obtained are multiplied by a moisture
correction factor that is determined gravimetrically using the moisture content which is carried out at a maximum of 30oC.
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 5 of 5
Dan Page
CC Ground Investigation Ltd i2 Analytical Ltd.
Unit A2 7 Woodshots Meadow,
Innsworth Tech Park Croxley Green
Innsworth Lane Business Park,
Gloucester Watford,
GL3 1DL Herts,
WD18 8YS
t: 01452 739 165 t: 01923 225404
f: 01452 739 220 f: 01923 237404
e: dan@ccground.co.uk e: reception@i2analytical.com
Project / Site name: Branston Lock Development Samples received on: 19/11/2015
Signed: Signed:
Other office located at: ul. Pionierów 39, 41 -711 Ruda Śląska, Poland
Standard sample disposal times, unless otherwise agreed with the laboratory, are : soils - 4 weeks from reporting
leachates - 2 weeks from reporting
waters - 2 weeks from reporting
asbestos - 6 months from reporting
Excel copies of reports are only valid when accompanied by this PDF certificate.
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 1 of 10
Analytical Report Number: 15-83303
Project / Site name: Branston Lock Development
Accreditation
detection
Analytical Parameter Limit of
Status
Units
(Soil Analysis)
Stone Content % 0.1 NONE < 0.1 < 0.1 - < 0.1 < 0.1
Moisture Content % N/A NONE 15 14 - 13 8.2
Total mass of sample received kg 0.001 NONE 1.6 2.0 - 2.0 2.0
General Inorganics
pH pH Units N/A MCERTS 6.8 - - - 7.7
Total Cyanide mg/kg 1 MCERTS <1 - - - <1
Free Cyanide mg/kg 1 NONE <1 - - - <1
Thiocyanate as SCN mg/kg 5 NONE < 5.0 - - - < 5.0
Total Sulphate as SO4 mg/kg 50 MCERTS 1900 - - - 1100
Sulphide mg/kg 1 MCERTS < 1.0 - - - 12
Total Sulphur mg/kg 50 NONE 1600 - - - 1200
Total Phenols
Total Phenols (monohydric) mg/kg 1 MCERTS < 1.0 - - - < 1.0
Speciated PAHs
Naphthalene mg/kg 0.05 MCERTS < 0.05 - - - < 0.05
Acenaphthylene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Acenaphthene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Fluorene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Phenanthrene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Anthracene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Fluoranthene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Pyrene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Benzo(a)anthracene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Chrysene mg/kg 0.05 MCERTS < 0.05 - - - < 0.05
Benzo(b)fluoranthene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Benzo(k)fluoranthene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Benzo(a)pyrene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Indeno(1,2,3-cd)pyrene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Dibenz(a,h)anthracene mg/kg 0.1 MCERTS < 0.10 - - - < 0.10
Benzo(ghi)perylene mg/kg 0.05 MCERTS < 0.05 - - - < 0.05
Total PAH
Speciated Total EPA-16 PAHs mg/kg 1.6 MCERTS < 1.60 - - - < 1.60
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 2 of 10
Analytical Report Number: 15-83303
Project / Site name: Branston Lock Development
Accreditation
detection
Analytical Parameter Limit of
Status
Units
(Soil Analysis)
Monoaromatics
Benzene µg/kg 1 MCERTS < 1.0 < 1.0 - < 1.0 < 1.0
Toluene µg/kg 1 MCERTS < 1.0 < 1.0 - < 1.0 < 1.0
Ethylbenzene µg/kg 1 MCERTS < 1.0 < 1.0 - < 1.0 < 1.0
p & m-xylene µg/kg 1 MCERTS < 1.0 < 1.0 - < 1.0 < 1.0
o-xylene µg/kg 1 MCERTS < 1.0 < 1.0 - < 1.0 < 1.0
MTBE (Methyl Tertiary Butyl Ether) µg/kg 1 MCERTS < 1.0 < 1.0 - < 1.0 < 1.0
Petroleum Hydrocarbons
TPH-CWG - Aliphatic >EC5 - EC6 mg/kg 0.1 MCERTS < 0.1 < 0.1 - < 0.1 < 0.1
TPH-CWG - Aliphatic >EC6 - EC8 mg/kg 0.1 MCERTS < 0.1 < 0.1 - < 0.1 < 0.1
TPH-CWG - Aliphatic >EC8 - EC10 mg/kg 0.1 MCERTS < 0.1 < 0.1 - < 0.1 < 0.1
TPH-CWG - Aliphatic >EC10 - EC12 mg/kg 1 MCERTS < 1.0 < 1.0 - < 1.0 < 1.0
TPH-CWG - Aliphatic >EC12 - EC16 mg/kg 2 MCERTS < 2.0 < 2.0 - < 2.0 < 2.0
TPH-CWG - Aliphatic >EC16 - EC21 mg/kg 8 MCERTS < 8.0 < 8.0 - < 8.0 < 8.0
TPH-CWG - Aliphatic >EC21 - EC35 mg/kg 8 MCERTS < 8.0 < 8.0 - < 8.0 < 8.0
TPH-CWG - Aliphatic (EC5 - EC35) mg/kg 10 MCERTS < 10 < 10 - < 10 < 10
TPH-CWG - Aromatic >EC5 - EC7 mg/kg 0.1 MCERTS < 0.1 < 0.1 - < 0.1 < 0.1
TPH-CWG - Aromatic >EC7 - EC8 mg/kg 0.1 MCERTS < 0.1 < 0.1 - < 0.1 < 0.1
TPH-CWG - Aromatic >EC8 - EC10 mg/kg 0.1 MCERTS < 0.1 < 0.1 - < 0.1 < 0.1
TPH-CWG - Aromatic >EC10 - EC12 mg/kg 1 MCERTS < 1.0 < 1.0 - < 1.0 < 1.0
TPH-CWG - Aromatic >EC12 - EC16 mg/kg 2 MCERTS < 2.0 < 2.0 - < 2.0 < 2.0
TPH-CWG - Aromatic >EC16 - EC21 mg/kg 10 MCERTS < 10 < 10 - < 10 < 10
TPH-CWG - Aromatic >EC21 - EC35 mg/kg 10 MCERTS < 10 < 10 - < 10 < 10
TPH-CWG - Aromatic (EC5 - EC35) mg/kg 10 MCERTS < 10 < 10 - < 10 < 10
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 3 of 10
Analytical Report Number: 15-83303
Project / Site name: Branston Lock Development
Accreditation
detection
Analytical Parameter Limit of
Status
Units
(Soil Analysis)
Stone Content % 0.1 NONE < 0.1 < 0.1 < 0.1 < 0.1 < 0.1
Moisture Content % N/A NONE 16 13 17 16 8.5
Total mass of sample received kg 0.001 NONE 1.7 1.7 1.5 1.6 1.7
General Inorganics
pH pH Units N/A MCERTS - 7.2 - 6.6 7.3
Total Cyanide mg/kg 1 MCERTS - <1 - 1 <1
Free Cyanide mg/kg 1 NONE - <1 - 1 <1
Thiocyanate as SCN mg/kg 5 NONE - < 5.0 - < 5.0 < 5.0
Total Sulphate as SO4 mg/kg 50 MCERTS - 950 - 870 350
Sulphide mg/kg 1 MCERTS - < 1.0 - < 1.0 < 1.0
Total Sulphur mg/kg 50 NONE - 530 - 700 200
Total Phenols
Total Phenols (monohydric) mg/kg 1 MCERTS - < 1.0 - < 1.0 < 1.0
Speciated PAHs
Naphthalene mg/kg 0.05 MCERTS - < 0.05 - < 0.05 < 0.05
Acenaphthylene mg/kg 0.1 MCERTS - < 0.10 - < 0.10 < 0.10
Acenaphthene mg/kg 0.1 MCERTS - < 0.10 - < 0.10 < 0.10
Fluorene mg/kg 0.1 MCERTS - < 0.10 - < 0.10 < 0.10
Phenanthrene mg/kg 0.1 MCERTS - 0.69 - < 0.10 < 0.10
Anthracene mg/kg 0.1 MCERTS - 0.14 - < 0.10 < 0.10
Fluoranthene mg/kg 0.1 MCERTS - 2.4 - < 0.10 < 0.10
Pyrene mg/kg 0.1 MCERTS - 2.1 - < 0.10 < 0.10
Benzo(a)anthracene mg/kg 0.1 MCERTS - 1.2 - < 0.10 < 0.10
Chrysene mg/kg 0.05 MCERTS - 1.4 - < 0.05 < 0.05
Benzo(b)fluoranthene mg/kg 0.1 MCERTS - 1.2 - < 0.10 < 0.10
Benzo(k)fluoranthene mg/kg 0.1 MCERTS - 1.1 - < 0.10 < 0.10
Benzo(a)pyrene mg/kg 0.1 MCERTS - 1.2 - < 0.10 < 0.10
Indeno(1,2,3-cd)pyrene mg/kg 0.1 MCERTS - 0.47 - < 0.10 < 0.10
Dibenz(a,h)anthracene mg/kg 0.1 MCERTS - < 0.10 - < 0.10 < 0.10
Benzo(ghi)perylene mg/kg 0.05 MCERTS - 0.51 - < 0.05 < 0.05
Total PAH
Speciated Total EPA-16 PAHs mg/kg 1.6 MCERTS - 12.3 - < 1.60 < 1.60
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 4 of 10
Analytical Report Number: 15-83303
Project / Site name: Branston Lock Development
Accreditation
detection
Analytical Parameter Limit of
Status
Units
(Soil Analysis)
Stone Content
Monoaromatics % 0.1 NONE
Benzene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 < 1.0
Toluene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 < 1.0
Ethylbenzene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 < 1.0
p & m-xylene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 < 1.0
o-xylene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 < 1.0
MTBE (Methyl Tertiary Butyl Ether) µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 < 1.0
Petroleum Hydrocarbons
TPH-CWG - Aliphatic >EC5 - EC6 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 < 0.1
TPH-CWG - Aliphatic >EC6 - EC8 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 < 0.1
TPH-CWG - Aliphatic >EC8 - EC10 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 < 0.1
TPH-CWG - Aliphatic >EC10 - EC12 mg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 < 1.0
TPH-CWG - Aliphatic >EC12 - EC16 mg/kg 2 MCERTS < 2.0 < 2.0 < 2.0 < 2.0 < 2.0
TPH-CWG - Aliphatic >EC16 - EC21 mg/kg 8 MCERTS < 8.0 < 8.0 < 8.0 < 8.0 < 8.0
TPH-CWG - Aliphatic >EC21 - EC35 mg/kg 8 MCERTS 27 11 < 8.0 < 8.0 < 8.0
TPH-CWG - Aliphatic (EC5 - EC35) mg/kg 10 MCERTS 30 11 < 10 < 10 < 10
TPH-CWG - Aromatic >EC5 - EC7 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 < 0.1
TPH-CWG - Aromatic >EC7 - EC8 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 < 0.1
TPH-CWG - Aromatic >EC8 - EC10 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 < 0.1
TPH-CWG - Aromatic >EC10 - EC12 mg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 < 1.0
TPH-CWG - Aromatic >EC12 - EC16 mg/kg 2 MCERTS 4.6 2.8 < 2.0 < 2.0 < 2.0
TPH-CWG - Aromatic >EC16 - EC21 mg/kg 10 MCERTS 26 19 < 10 < 10 < 10
TPH-CWG - Aromatic >EC21 - EC35 mg/kg 10 MCERTS 87 41 < 10 < 10 < 10
TPH-CWG - Aromatic (EC5 - EC35) mg/kg 10 MCERTS 120 63 < 10 < 10 < 10
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 5 of 10
Analytical Report Number: 15-83303
Project / Site name: Branston Lock Development
Accreditation
detection
Analytical Parameter Limit of
Status
Units
(Soil Analysis)
Stone Content % 0.1 NONE < 0.1 < 0.1 < 0.1 < 0.1 -
Moisture Content % N/A NONE 7.4 11 9.9 12 -
Total mass of sample received kg 0.001 NONE 1.2 1.7 1.8 1.6 -
General Inorganics
pH pH Units N/A MCERTS - 7.6 7.7 - -
Total Cyanide mg/kg 1 MCERTS - <1 <1 - -
Free Cyanide mg/kg 1 NONE - <1 <1 - -
Thiocyanate as SCN mg/kg 5 NONE - < 5.0 < 5.0 - -
Total Sulphate as SO4 mg/kg 50 MCERTS - 10000 5000 - -
Sulphide mg/kg 1 MCERTS - < 1.0 < 1.0 - -
Total Sulphur mg/kg 50 NONE - 3400 1700 - -
Total Phenols
Total Phenols (monohydric) mg/kg 1 MCERTS - < 1.0 < 1.0 - -
Speciated PAHs
Naphthalene mg/kg 0.05 MCERTS - < 0.05 < 0.05 - -
Acenaphthylene mg/kg 0.1 MCERTS - < 0.10 < 0.10 - -
Acenaphthene mg/kg 0.1 MCERTS - 0.46 < 0.10 - -
Fluorene mg/kg 0.1 MCERTS - 0.45 < 0.10 - -
Phenanthrene mg/kg 0.1 MCERTS - 3.7 < 0.10 - -
Anthracene mg/kg 0.1 MCERTS - 1.3 < 0.10 - -
Fluoranthene mg/kg 0.1 MCERTS - 4.8 0.24 - -
Pyrene mg/kg 0.1 MCERTS - 3.7 0.26 - -
Benzo(a)anthracene mg/kg 0.1 MCERTS - 1.7 < 0.10 - -
Chrysene mg/kg 0.05 MCERTS - 1.4 < 0.05 - -
Benzo(b)fluoranthene mg/kg 0.1 MCERTS - 1.5 < 0.10 - -
Benzo(k)fluoranthene mg/kg 0.1 MCERTS - 0.87 < 0.10 - -
Benzo(a)pyrene mg/kg 0.1 MCERTS - 1.2 < 0.10 - -
Indeno(1,2,3-cd)pyrene mg/kg 0.1 MCERTS - 0.56 < 0.10 - -
Dibenz(a,h)anthracene mg/kg 0.1 MCERTS - < 0.10 < 0.10 - -
Benzo(ghi)perylene mg/kg 0.05 MCERTS - 0.61 < 0.05 - -
Total PAH
Speciated Total EPA-16 PAHs mg/kg 1.6 MCERTS - 22.2 < 1.60 - -
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 6 of 10
Analytical Report Number: 15-83303
Project / Site name: Branston Lock Development
Accreditation
detection
Analytical Parameter Limit of
Status
Units
(Soil Analysis)
Stone Content
Monoaromatics % 0.1 NONE
Benzene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 -
Toluene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 -
Ethylbenzene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 -
p & m-xylene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 -
o-xylene µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 -
MTBE (Methyl Tertiary Butyl Ether) µg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 -
Petroleum Hydrocarbons
TPH-CWG - Aliphatic >EC5 - EC6 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 -
TPH-CWG - Aliphatic >EC6 - EC8 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 -
TPH-CWG - Aliphatic >EC8 - EC10 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 -
TPH-CWG - Aliphatic >EC10 - EC12 mg/kg 1 MCERTS < 1.0 < 1.0 < 1.0 < 1.0 -
TPH-CWG - Aliphatic >EC12 - EC16 mg/kg 2 MCERTS < 2.0 < 2.0 < 2.0 < 2.0 -
TPH-CWG - Aliphatic >EC16 - EC21 mg/kg 8 MCERTS < 8.0 < 8.0 < 8.0 < 8.0 -
TPH-CWG - Aliphatic >EC21 - EC35 mg/kg 8 MCERTS 470 43 < 8.0 10 -
TPH-CWG - Aliphatic (EC5 - EC35) mg/kg 10 MCERTS 480 46 < 10 13 -
TPH-CWG - Aromatic >EC5 - EC7 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 -
TPH-CWG - Aromatic >EC7 - EC8 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 -
TPH-CWG - Aromatic >EC8 - EC10 mg/kg 0.1 MCERTS < 0.1 < 0.1 < 0.1 < 0.1 -
TPH-CWG - Aromatic >EC10 - EC12 mg/kg 1 MCERTS < 1.0 1.2 < 1.0 < 1.0 -
TPH-CWG - Aromatic >EC12 - EC16 mg/kg 2 MCERTS < 2.0 7.4 < 2.0 < 2.0 -
TPH-CWG - Aromatic >EC16 - EC21 mg/kg 10 MCERTS < 10 21 < 10 < 10 -
TPH-CWG - Aromatic >EC21 - EC35 mg/kg 10 MCERTS 830 49 < 10 25 -
TPH-CWG - Aromatic (EC5 - EC35) mg/kg 10 MCERTS 830 79 < 10 35 -
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 7 of 10
Analytical Report Number : 15-83303
Project / Site name: Branston Lock Development
* These descriptions are only intended to act as a cross check if sample identities are questioned. The major constituent of the sample is intended to act with respect to MCERTS
validation. The laboratory is accredited for sand, clay and loam (MCERTS) soil types. Data for unaccredited types of solid should be interpreted with care.
Stone content of a sample is calculated as the % weight of the stones not passing a 10 mm sieve. Results are not corrected for stone content.
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 8 of 10
Analytical Report Number : 15-83303
Project / Site name: Branston Lock Development
Water matrix abbreviations: Surface Water (SW) Potable Water (PW) Ground Water (GW)
Asbestos identification in soil Asbestos Identification with the use of polarised In house method based on HSG 248 A001-PL D ISO 17025
light microscopy in conjunction with disperion
staining techniques.
Boron, water soluble, in soil Determination of water soluble boron in soil by hot In-house method based on Second Site L038-PL D MCERTS
water extract followed by ICP-OES. Properties version 3
BTEX and MTBE in soil Determination of BTEX in soil by headspace GC-MS. In-house method based on USEPA8260 L073B-PL W MCERTS
Free cyanide in soil Determination of free cyanide by distillation In-house method based on Examination of L080-PL W NONE
followed by colorimetry. Water and Wastewater 20th Edition:
Clesceri, Greenberg & Eaton (Skalar)
Hexavalent chromium in soil Determination of hexavalent chromium in soil by In-house method L080-PL W MCERTS
extraction in water then by acidification, addition of
1,5 diphenylcarbazide followed by colorimetry.
Metals in soil by ICP-OES Determination of metals in soil by aqua-regia In-house method based on MEWAM 2006 L038-PL D MCERTS
digestion followed by ICP-OES. Methods for the Determination of Metals in
Soil.
Moisture Content Moisture content, determined gravimetrically. In-house method based on BS1377 Part 3, L019-UK/PL W NONE
1990, Chemical and Electrochemical Tests
Monohydric phenols in soil Determination of phenols in soil by extraction with In-house method based on Examination of L080-PL W MCERTS
sodium hydroxide followed by distillation followed Water and Wastewater 20th Edition:
by colorimetry. Clesceri, Greenberg & Eaton (skalar)
pH in soil (automated) Determination of pH in soil by addition of water In-house method based on BS1377 Part 3, L099-PL D MCERTS
followed by electrometric measurement. 1990, Chemical and Electrochemical Tests
Speciated EPA-16 PAHs in soil Determination of PAH compounds in soil by In-house method based on USEPA 8270 L064-PL D MCERTS
extraction in dichloromethane and hexane followed
by GC-MS with the use of surrogate and internal
standards.
Stones content of soil Standard preparation for all samples unless In-house method based on British Standard L019-UK/PL D NONE
otherwise detailed. Gravimetric determination of Methods and MCERTS requirements.
stone > 10 mm as % dry weight.
Sulphide in soil Determination of sulphide in soil by acidification In-house method L010-PL D MCERTS
and heating to liberate hydrogen sulphide, trapped
in an alkaline solution then assayed by ion selective
electrode.
Thiocyanate in soil Determination of thiocyanate in soil by extraction In-house method L049-PL D NONE
in caustic soda followed by acidification followed by
addition of ferric nitrate followed by
spectrophotometer.
Total cyanide in soil Determination of total cyanide by distillation In-house method based on Examination of L080-PL W MCERTS
followed by colorimetry. Water and Wastewater 20th Edition:
Clesceri, Greenberg & Eaton (Skalar)
Total sulphate (as SO4 in soil) Determination of total sulphate in soil by extraction In-house method based on BS1377 Part 3, L038-PL D MCERTS
with 10% HCl followed by ICP-OES. 1990, Chemical and Electrochemical Tests
Total Sulphur in soil Determination of total sulphur in soil by extraction In-house method based on BS1377 Part 3, L038-PL D NONE
with aqua-regia, potassium bromide/bromate 1990, and MEWAM 2006 Methods for the
followed by ICP-OES. Determination of Metals in Soil
TPHCWG (Soil) Determination of hexane extractable hydrocarbons In-house method L076-PL W MCERTS
in soil by GC-MS/GC-FID.
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 9 of 10
Analytical Report Number : 15-83303
Project / Site name: Branston Lock Development
Water matrix abbreviations: Surface Water (SW) Potable Water (PW) Ground Water (GW)
For method numbers ending in 'UK' analysis have been carried out in our laboratory in the United Kingdom.
For method numbers ending in 'PL' analysis have been carried out in our laboratory in Poland.
Soil analytical results are expressed on a dry weight basis. Where analysis is carried out on as-received the results obtained are multiplied by a moisture
correction factor that is determined gravimetrically using the moisture content which is carried out at a maximum of 30oC.
Iss No 15-83303-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 10 of 10
i2 Analytical Telephone: 01923 225404
7 Woodshots Meadow Fax: 01923 237404
Croxley Green Business Park email:reception@i2analytical.com
Watford, WD18 8YS
Client: CCGROUND
Results are expressed on a dry weight basis, after correction for moisture content where applicable
Stated limits are for guidance only and I2 cannot be held responsible for any discrepencies with current legislation
*= UKAS accredited (liquid eluate analysis only)
** = MCERTS accrediited
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 3 of 5
Analytical Report Number : 15-83305
Project / Site name: Branston Lock Development
* These descriptions are only intended to act as a cross check if sample identities are questioned. The major constituent of the sample is intended to act with respect to MCERTS
validation. The laboratory is accredited for sand, clay and loam (MCERTS) soil types. Data for unaccredited types of solid should be interpreted with care.
Stone content of a sample is calculated as the % weight of the stones not passing a 10 mm sieve. Results are not corrected for stone content.
511096 P1-BH02 None Supplied 0.90 Brown sandy loam with gravel.
511097 P1-WS06 None Supplied 0.50 Brown loam and clay with gravel.
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 4 of 5
Analytical Report Number : 15-83305
Project / Site name: Branston Lock Development
Water matrix abbreviations: Surface Water (SW) Potable Water (PW) Ground Water (GW)
Acid neutralisation capacity of soil Determination of acid neutralisation capacity by In-house method based on Guidance an L046-PL W NONE
addition of acid or alkali followed by electronic Sampling and Testing of Wastes to Meet
probe. Landfill Waste Acceptance
Chloride in WAC leachate (BS EN Determination of Chloride colorimetrically by In house based on MEWAM Method ISBN L082-PL W ISO 17025
12457-3 Prep) discrete analyser. 0117516260.
DOC in WAC leachate (BS EN 12457- Determination of dissolved organic carbon in In-house method based on Standard L037-PL W NONE
3 Prep) leachate by TOC/DOC NDIR analyser. Methods for the Examination of Water and
Waste Water, 21st Ed.
Fluoride in WAC leachate (BS EN Determination of fluoride in leachate by 1:1ratio In-house method based on Standard L033-PL W NONE
12457-3 Prep) with a buffer solution followed by Ion Selective Methods for the Examination of Water and
Electrode. Waste Water, 21st Ed.
Metals in WAC leachate (BS EN 12457- Determination of metals in leachate by acidification In-house method based on Standard L039-PL W ISO 17025
3 Prep) followed by ICP-OES. Methods for the Examination of Water and
Waste Water, 21st Ed.
Moisture Content Moisture content, determined gravimetrically. In-house method based on BS1377 Part 3, L019-UK/PL W NONE
1990, Chemical and Electrochemical Tests
pH in soil Determination of pH in soil by addition of water In-house method based on BS1377 Part 3, L005-PL W MCERTS
followed by electrometric measurement. 1990, Chemical and Electrochemical Tests
Phenol Index in WAC leachate (BS EN Determination of monohydric phenols in leachate In-house method based on Examination of L080-PL W ISO 17025
12457-3 Prep) by continuous flow analyser. Water and Wastewater 20th Edition:
Clesceri, Greenberg & Eaton (skalar)
Stones content of soil Standard preparation for all samples unless In-house method based on British Standard L019-UK/PL D NONE
otherwise detailed. Gravimetric determination of Methods and MCERTS requirements.
stone > 10 mm as % dry weight.
Sulphate in WAC leachate (BS EN Determination of sulphate in leachate by In-house method based on Standard L039-PL W ISO 17025
12457-3 Prep) acidification followed by ICP-OES. Methods for the Examination of Water and
Waste Water, 21st Ed.
TDS in WAC leachate (BS EN 12457-3 Determination of total dissolved solids in leachate In-house method based on Standard L004-PL W NONE
Prep) by electrometric measurement. Methods for the Examination of Water and
Waste Water, 21st Ed.
Total organic carbon in soil Determination of organic matter in soil by oxidising In-house method based on BS1377 Part 3, L023-PL D MCERTS
with potassium dichromate followed by titration 1990, Chemical and Electrochemical Tests
with iron (II) sulphate.
For method numbers ending in 'UK' analysis have been carried out in our laboratory in the United Kingdom.
For method numbers ending in 'PL' analysis have been carried out in our laboratory in Poland.
Soil analytical results are expressed on a dry weight basis. Where analysis is carried out on as-received the results obtained are multiplied by a moisture
correction factor that is determined gravimetrically using the moisture content which is carried out at a maximum of 30oC.
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 5 of 5
Iss No 15-83305-1
This certificate should not be reproduced, except in full, without the express permission of the laboratory.
The results included within the report are representative of the samples submitted for analysis. Page 1 of 5
CC Ground Investigations Ltd Report C4877
APPENDIX D
Appendix D – SPT Calibration Data