Câu 4: T1=7, T2=5

Day Mon. Tue. Wed. Thur. Fri. Sat. Sun.


Min. 6 8 9 7 7 5 5
Number

Mon. Tue. Wed. Thur. Fri. Sat. Sun.


1 6 8 9 7 7 5 5
2 5 7 8 6 6 5 5
3 4 6 7 5 5 5 5
4 3 5 6 5 5 4 4
5 3 5 5 4 4 3 3
6 2 4 4 3 3 3 3
7 2 4 3 2 2 2 2
8 1 3 2 2 2 1 1
9 0 2 1 1 1 1 1
10 0 1 1 1 0 0 0
Total 8 8 9 7 7 5 6
Requiremen 6 8 9 7 7 5 5
t

=> 10 full-time nurse

Câu 5:

A B C E F G
Processing 6 5 7 7 8 5
time
Due date 24 13 9 15 16 14

SPT

M Flow time(Fi) Due date Lateness Tardiness


B 5 13 -8 0
G 5+5=10 14 -4 0
A 10+6=16 24 -8 0
C 16+7=23 9 14 14
E 23+7=30 15 15 15
F 30+8=38 16 22 22
Average 20,333 5,167 8,5

EDD

M Flow time(Fi) Due date Lateness Tardiness


C 7 9 -2 0
B 7+5 = 12 13 -1 0
G 12+5=17 14 2 3
E 17+7=24 15 8 9
F 24+8=32 16 15 16
A 32+6=38 24 13 14
Average 21.667 6.5 7
Conclude: I recommend SPT rule. Because Flow time average(20,333) and lateness
average(5,167) of SPT rule is lower than Flow time average(21.667) and lateness
average(6.5) of EDD rule.