Letter No: AA/EDB/DBL-SRBG (JV)/2296/2021-22/

Date: 09th September, 2021

To,
The Project Manager,
DBL-SRBG (JV) Base Camp,
Avinahalli (PO), Sagar Taluka,
Shimoga District,
Karnataka -577453.
Email Address:- dblsharavathi@dilipbuildcon.co.in

Sub: Consultancy Services for Authority’s Engineer for Supervision of construction of Major
Bridge across Sharavathi Backwaters and approaches between Ambargodu and Kalasavalli of NH-
369E in the state of Karnataka (Job No. NH-369E-KNT-2018-19-895) on EPC Basis. Reg:
Submission of Method statement and Drawings of Segment Erection Scheme for Balanced
Cantilever Bridge.

Ref: EPC Contractor Letter no. DBL-SO/D&TA/19067/AE/2021-22/413 dated 04.08.2021

Dear Sir,

1) Design of segment lifter not submitted along with Method statement and please note that
design and drawing should be proof checked by Proof Consultant and IIT.

2) Method statement should include details of segment transportation from camp to Loading
jetty and shifting to location of Erection.

3) New lifting equipment shall be proof load rested prior to its first use and should provide
certification from manufacture.

If lifter accessories are reassembled in site it should be tested as per IS 14470-1997.


Testing should be done by approved third party agency, Test certificates required for all
accessories like Stress bar, shackles, wire rope etc.

4) Details of pull down cylinder, rear tie down system, rear support and front barge need to be
explained in Method statement.

5) Detailed drawing to be submitted showing 36mm thread bar with embedded length in Pier
table. The Main rail upper beam and Lower beam drawing not Clear in Method statement.

6) strength requirement of stitch concrete should be confirmed from designer prior to starting
of Temporary and permanent stressing work.

7) Skilled and trained engineers to be deployed in lifting operations, it is better to submit


credentials of Persons involved in Erection work for our information.

8) The rear tie down system need to be detailed to allow for geometrical variations due to
camber and segment gradient. It has shown that their is two type of rear down system at 5
meter and 4.5 meter.

Detailed explanation required for these two types.


9) As you have mentioned that load of Lifting beam should be released after stressing of
Temporary and permanent tendon, this stressing load may effect the load on segment
which is given by segment lifter this need clarification.

10) Method Statement should include geometric survey, maintaining level and camber as per
drawing.

11) All materials / Accessories/ equipment like Thread bar, Epoxy glue, Jack's, etc using in
segment Erection need to be tested and report to be submitted.

12) Temporary PT bar destressing details not mentioned in Method statement. 

13) Safety check list, work permits to be made for Each activity in Segment Erection procedure.

14) Detailed dimensions drawing should me submitted for each component of segment lifter.

15) segment lifting frame should be equipped with fail safe brakes, suitable operating control,
emergency stops, machine guarding, Waring devices, etc and Safe working load to be
mentioned on Lifting frame.

16) As you mentioned in Method statement that segment lifter is operated with Remote control,
it has to ensure that whether remote control is built with safety features to revert back to
automatic safe mode, when remote control has signal problem or if remote is failed. Is
there any options to operate manually?

17) Please submit the Credentials of NRS (Lifter manufacture) previous experience, projects in
India etc. Whether competent person from NRS will be available during segment Erection
work.?

This is for your information.

With best regards


For Aarvee Associates Architects Engineers & Consultants Pvt. Ltd.,

Prasanta Bhattacharya
Team Leader

Copy to:

1. The Chief Engineer -NH, Karnataka PWD, Bengaluru for favor of information
2. The Chief Engineer -RO, MORT&H, Bengaluru for favor of information
3. The Superintending Engineer, NH Bengaluru Circle, PWD, Bengaluru for information
4. The Executing Engineer, NH Division, PWD, Shivamoga for information
5. The AEE, NH Sub-Division, Shivamoga for information