Professional Documents
Culture Documents
net/publication/337881799
Best practices for geotechnical planning and design in open pit mining
operations -A sustainable engineering approach
CITATIONS READS
4 1,233
6 authors, including:
Some of the authors of this publication are also working on these related projects:
Development of tools for advanced calculations of surface deformations in the vicinity of linear water bodies (streams) View project
All content following this page was uploaded by Zach G. Agioutantis on 11 December 2019.
Best practices for geotechnical planning and design in open pit mining
operations - A sustainable engineering approach
C. Steiakakis
Geosysta ltd, Greece
Z. Agioutantis
Department of Mineral Recourses Engineering, Technical University of Crete, Greece
minimum additional cost. The cost of inclinom- ner assigning a suitable factor of safety (FS),
eter pipes can be in the order of couple of euro taking into account uncertainties in the geologi-
per meter. The cost of a drilling to install incli- cal model, geotechnical parameters, etc., as well
nometer pipes could be in the order of a 30-100 as the importance of the slope, i.e., hauling ac-
euro per meter. Geotechnical planning could cess, permanent slope, etc. In this way some-
produce a crude future monitoring program and times a false reassurance is provided to mine
the locations of such instruments (even in a planners and operators and at the same time the
speculative manner) could be installed and be allocated risk is not easily evaluated.
ready for use when needed at a significantly re- For example a slope designed using a FS>1.4
duced cost. can easily become unstable due to unfavorably
Although the majority of the drilling cam- dipping clay layers of centimeter thickness.
paigns for reserve estimation include sample Even in situations where geology predicts a fa-
collection, such samples may not be available vorable orientation for weak layers, significant
for overburden or floor rock formations which instability problems may occur. One such ex-
may be important for slope stability design. ample is the Thissavros hydroelectric dam pro-
When cores are available, it is easy to incorpo- ject in Northern Greece where the complex
rate geotechnical laboratory testing to the ore faulting and a favorable base trust fault (Fig. 1)
evaluation testing program which is performed. produced significantly unstable slopes during
Thus, tests of the physical properties and the construction (Anastassopoulos et al., 2006).
shear strength of encountered materials could be In recent years, slope stability tends to be
executed on selected core samples during the in- evaluated using a probabilistic approach (Ho
itial exploration stages. The cost of laboratory et al., 2000). Slope stability is seen as a risk
testing on selected samples during reserve esti- hazard analysis and appropriate risk manage-
mations is much lower than dedicated drilling(s) ment procedures are implemented. Thus, the
to obtain samples for the geotechnical investiga- risk of taking decisions can be better explained
tion. The engineering geologist or geotechnical to financial personnel and decision makers,
engineer responsible can select the appropriate while, at the same time, contingency planning
samples at the appropriate depths, so a database for risk mitigation is prepared.
of geotechnical testing properties can be slowly The geotechnical involvement at this stage it
developed and be available when the geotech- is much more important than before and it does
nical model is prepared sharing the expense not just include refinement of the geotechnical
with ore estimation process. model and running more limit equilibrium anal-
In summary it is good practice and a cost ef- yses. The identification of risk, the formulation
fective way to plan for a preliminary geotech- of a coherent risk assessment strategy and the
nical investigation during the initial phases of evaluation of alternatives for risk mitigation is a
developing an orebody in order to fully exploit complex and time consuming task that requires
drillings and other forms of investigation. significant knowledge and experience. Risk as-
sessment of slope stability and risk mitigation
2.3 Mine planning stage should be based on a coherent monitoring pro-
During the mine planning stage the geotechnical gram which incorporates many aspects from
calculations regarding slope design can make or
break the project. For example the steepening of
the slope angle about 1o in a 50o wall of a 500m
deep excavation can result in reduction of about
9000t per meter of face (Reat et al., 2009).
Experience has shown that even with access
to a vast amount of geotechnical information
(drillings, laboratory testing, etc.) the slope in-
clinations cannot be accurately determined. The
usual practice is to work in a deterministic man- Figure 1: Thissavros Area A geological section.
6th International Conference on Sustainable Development in the 641
Minerals Industry, 30 June – 3 July 2013, Milos island, Greece
visual observation, to slope face mapping, sur- erties, stratigraphy, dip - dip direction, presence
vey and inclinometer readings. This program of unmapped faults etc., should be recognized,
can have limited effect, if contingency measures logged and included in the geotechnical model.
and their implementation have not been planned If unexplored horizons are found (thin clay
in advance. seems, fault gouge etc.), additional laboratory
At this stage it is important to design the testing may be performed and the geotechnical
slopes either with deterministic or probabilistic model modified accordingly. A major contrib-
ways, but at the same time to implement the uting factor, which sometimes is overlooked, is
necessary monitoring program that will ensure the change of hydrogeological conditions of the
safe operation. Contingency plans should be mine and slopes, with time and as excavations
drafted and ready to be implemented as soon as progresses.
needed in order to avoid slope instabilities that
can escalate to major incidents or even large 2.4.2 Routine monitoring of slopes
landslides. For example, before a slope starts Slopes should be routinely monitored for
“moving” over a weak surface, the initial shear movements; such measurements should be col-
strength of that surface is larger than after lected, interpreted and incorporated in a ge-
movement has been established. As movements otechnical database. This is usually performed
continue, the strength reduces (sometimes sig- in collaboration with the survey department of
nificantly) to the residual shear strength. A the mine and is of utmost importance for the
slope geometry, which could be stabilized with safe operation of slopes. The instrument loca-
minimum re-sloping (re-grading) at the initial tion, type and monitoring schedule is not a trivi-
movement stage, could become unstoppable af- al process. Careful planning is needed in order
ter the shear strength has dropped to residual to select the appropriate type of equipment that
especially in brittle soil or rock behavior. will satisfy the accuracy, compatibility and du-
If a contingency plan is not prepared taking rability needs. Different equipment such as vi-
into account numerous operational procedures, brating wire piezometers from different manu-
such situations cannot be easily amended in a factures may require different data loggers. In
timely fashion. For example if drilling horizon- such cases, ordering of cheaper types, ignoring
tal drainage holes is evaluated as a contingency the measuring device could actually produce
measure for improving the stability of a slope, higher costs when equipment incompatibilities
but equipment and trained personal are not occur and new units need to be obtained. Lon-
available at the mine site, this plan could fail gevity and raggedness is another important issue
from the start. that must be addressed when selecting equip-
ment. Selecting the most cost effective one is
2.4 Mine operation stage
not just finding the cheaper one. The cost of in-
During the mine operation stage geotechnical stallation often supersedes an order of magni-
involvement has a significant role in order to as- tude the cost of purchasing equipment, so mal-
sure safe operation and at the same time opti- functioning or easily damaged equipment can
mize the excavated slopes. Three main aspects significantly increase the cost, even though they
need to be incorporated in the mine operation. appear to cost less when ordered.
Accuracy and resolution is another important
2.4.1 Frequent re-evaluation of geo-models issue that should be seriously considered. Sec-
An evaluation of the available geological and tion 3.3 of this paper provides an example of
geotechnical model should be executed fre- how a high resolution surveying instrument can
quently, sometimes even on a daily or weekly help in developing solid geodetic information
basis, depending on the excavation progress. about slope movements.
Especially in high capacity continuous mine op- Emphasis should also be placed on the instal-
erations this task may require more than one lation location of the monitoring equipment for
shift per day. At this stage the soil or rock prop- many reasons. Location selection should con-
sider the geological model, the type of meas-
642 6th International Conference on Sustainable Development in the
Minerals Industry, 30 June – 3 July 2013, Milos island, Greece
urements (and the equipment) needed, the depth rium analysis is the most widely used technique
of measurements, etc. For example, pore pres- for evaluating the stability of the slopes, but in
sure measurements in different or compartment- complex situations, where high risks are not ac-
ed aquifers or the installation of inclinometers in ceptable, numerical modelling such as finite el-
locations of thin clay seam(s) that can produce a ement, finite difference or distinct element anal-
failure surface should be considered. Addition- ysis may be warranted (Hoek, 2009).
ally, the mine operation plan should be evaluat- It must be pointed out that limit equilibrium
ed in order to avoid installation of equipment in analysis is more easily executed and evaluated
areas where hauling roads will be formed or than numerical analysis. In any case the per-
very near excavation areas that may result in son(s) executing such analysis should be com-
monitoring equipment damage. This may be a petent and experienced in the geology and ge-
challenging task, since a compromise between otechnical conditions of the mine and can criti-
information and production must be accom- cally evaluate all outcomes in order to avoid se-
plished. In cases of geodetic monitoring (dis- rious mistakes. Among the most important as-
placements) the total station base should not be pect of modeling is the availability of “accurate”
established in moving or potentially creeping geological and geotechnical information.
areas; this will definitely produce erroneous re-
sults. A good practice is to install a continuous 2.5 Mine closing stage
operated reference GPS Station in such bases, Geotechnical input during the mine closing
so this effect can be addressed and corrected if stage should provide the stable slope inclination
needed. for permanent conditions and take into account
The monitoring schedule is something that long term phenomena. Possible future ground-
needs careful consideration in relation to mine water variations should be evaluated, and addi-
operation and safety issues. From a technical tional loads due to new developments adjacent
point of view the schedule should take into ac- to the slopes etc., should be examined.
count the parameter variation with time. For ex- Additionally, any mine tailings slopes or ex-
ample, if pore pressures change weakly due to ternal dumps should be evaluated for long term
rainfall, then monthly measurements will devel- stability and endurance due to erosion.
op inaccurate information that can lead to erro-
neous conclusions.
Furthermore, measurement of measurements 3. CASE STUDY
of interrelated parameters should be synchro-
In this section, a case study is presented, where
nized. For example, inclinometers that are lo-
an in-depth geotechnical investigation safe-
cated on the same slope should be measured on
guarded the sustainability of this surface mining
the same day, so that the potential presence of
operation as well as the stability of nearby loca-
one or more sliding surfaces can be established.
tions, and provided important data to the mine
Additionally, rainfall data should be synchro-
planning and mine operations personnel for con-
nized with pore pressure measurements in order
trolling movements.
to evaluate the effect at different elevations and
locations. Finally, measurements may obstruct
3.1 Mine location
mine operation and need to be taken into ac-
count in order not to result in significant delays The Mavropigi open pit lignite mine is located
or pose danger to monitoring personnel. in northern Greece in the Ptolemais area
(Kavvadas et al., 2013). Mining is predominant-
2.4.3 Slope stability calculations ly accomplished using bucket wheel excavators
on seven or eight benches, reaching to a depth
Information pertaining to the varying geologic
of about 150 m below the surface. Total excava-
and hydrogeologic conditions along with the
tions to-date (2002-2012) are in the order of 328
collected monitoring data should be evaluated
bank Mm3 (226 bank Mm3 using the continuous
for the safe operation of the slopes or for opti-
mization of the slope inclination. Limit equilib-
6th International Conference on Sustainable Development in the 643
Minerals Industry, 30 June – 3 July 2013, Milos island, Greece