Normal normal crash

activity crash cost


time cost time
12 3 50 2 70
23 6 80 4 160
24 10 60 9 95
25 11 50 7 150
45 0 0 0 0
36 8 100 6 160
57 5 40 4 75
67 6 75 6 75

a). Jalur Kritis, total biaya dengan waktu normal 9 9 8


3
6

0 0 3 3 3 10 13 18
1 2 4
0

11 14 18
5
Jalur Kritis 1-2-3-6-7
Total Waktu 23 minggu
Total Biaya 455

b). Total biaya proyek bila diinginkan waktu penyelesaian 20 minggu

activity Normal normal crash crash cost Slope Rank


time cost time
12 3 50 2 70 20 1
23 6 80 4 160 40 5
24 10 60 9 95 35 4
25 11 50 7 150 25 2
45 0 0 0 0 -
36 8 100 6 160 30 3
57 5 40 4 75 35 4
67 6 75 6 75 -

crash kegiatan 1-2 8 8 8


3
6

0 0 2 2 2 10 12 17
1 2 4
0
11 13 17
5

crash kegiatan 3-6 8 8 6


3
6

0 0 2 2 2 10 12 15
1 2 4
0

11 13 15
5

c). Tabel aktivitas setelah crashing

Aktivitas Slope Crash Time Durasi Direct cost Inderect Total


1-2(1) 20 1 22 20 0
535
3-6(2) 30 2 20 60 0
17 17
6
6

23 23
7

16 16
6
6

22 22
7

5
14 14
6
6

20 20
7