BATCH SHEET FOR CONCRETE PER CUM

M-25 (RCC)
Grade of Conc Batching Plant Location __________________________ Date:- __________________________

WA of 20MM 0.39 Moisture Content 20mm __________________________ Moisture Correction for 20mm __________________________

WA of 10MM 0.65 Moisture Content 10mm __________________________ Moisture Correction for 10mm __________________________

WA of Sand 1.18 Moisture Content Sand __________________________ Moisture Correction for Sand __________________________

Brand of Cement __________________________

TYPE OF
CEMENT (kg) WATER (kg) AGGRIGATE 20MM (kg) AGGRIGATE 10MM (kg) COARSE SAND (kg) ADMIXTURE Lt/kg
MATERIAL

AS PIER MIX
DESIGN
366 164.7 685 448.6 751 2.562

MOISTURE
CORRECTION

ACTUAL MIX
QUANTITY

For 0.5 cum.

REMARKS