You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/328969295

Longest HVAC Cable Systems: A Review

Conference Paper · June 2018


DOI: 10.1109/EEEIC.2018.8494213

CITATION READS

1 3,836

2 authors, including:

Giovanni Rinzo
University of Padova
9 PUBLICATIONS   53 CITATIONS   

SEE PROFILE

All content following this page was uploaded by Giovanni Rinzo on 07 February 2019.

The user has requested enhancement of the downloaded file.


Longest HVAC Cable Systems: A Review

G. Pedrazzoli and G. Rinzo


Department of Industrial Engineering
University of Padova
Padova, Italy

Abstract—This paper presents a state of the art of main high cable when considering factors such as converter costs, space
voltage alternate current (HVAC) cable installations. A requirements and overall system losses. When all these factors
particular focus is given to challenging choices to design the are taken into account, it is shown that there is an important
worldwide longest HVAC lines. A comparison between alternate advantage in adopting HVAC cables instead of other solutions
and high voltage direct current transmission systems (HVDC) [5].
brings then important considerations between the two
technologies. HVAC could be competitive with HVDC not only
for short distance installations, but also for some longer lines. In II. HVAC CABLE TRANSMISSION
the given examples, in fact, HVAC transmission systems have In the past, HV cables were insulated by means of paper
demonstrated to be the best budget solution for these specific impregnated with oil under pressure. There are several
cases. technical, installation and service limitations with these
designs, so that today other technologies are preferred. In these
Keywords—HVAC cable, HVDC cable, XLPE insulation years, a rapid improvement in material science made possible
to use Cross-linked polyethylene (XLPE) as insulating
I. INTRODUCTION material. XLPE ensures lower dielectric losses and a higher
The development of power transmission network during the operating temperature. Furthermore, an improved simplicity in
last decades has been based on overhead lines (OHLs), due to manufacturing process has led towards a dramatic increase in
their cheaper price. Underground cables systems have been the utilization of such material (see fig. 1). The insulation
available for a long time, but some issues (e.g. large thickness of XLPE cables is mainly determined by the
capacitance and a relatively low current rating compared to withstand voltage. In case of extra HV cables of long length,
OHLs) limited their development. The main problems for the insulation thickness also influences the reactive power
OHLs arise because of numerous fault sources. In fact, they are absorbed by the cable. The simple formula below shows that
susceptible to be damaged by wind-borne tree branches, debris, reactive power absorbed by the cable depends on squared
strong wind and ice-loading conditions from extreme weather. voltage, but also on capacitance and frequency:
Furthermore, OHLs undergo intermittent outages, in which the Qcable = 2πfCU 2 [var]
power is unavailable for few second fractions, a time interval
already critical for some industrial equipment, which shuts
down with very high damage for industrial customers and very where Qcable is the capacitive power absorbed by the cable,
high costs for the transmission system operators (TSOs). f [Hz] the frequency, C [F] the total capacitance and U [V] the
Nowadays, with the use of new materials and processing phase-to-phase voltage. As a consequence of the high value of
technology, the constraints on power transfer and maximum Qcable, reactive compensation may be needed by the
length have largely been overcome and HVAC cables are a installation of shunt reactors. Another procedure could consist
competitive solutions [1-4]. With the commissioning of new in decreasing the reactive power production by increasing the
transmission links, an important topic to be considered is the insulation thickness or decreasing the conductor size [6, 7].
bureaucratic process of getting environmental approvals. In the
case of OHLs, this may take several years because of
environmental issues, whereas for cables the process may be
much quicker. AC cable link may be installed in a shorter time
and often this reason alone could justify the cable link choice.
At the same time, the development of off-shore facilities raises
the market demand for long submarine cables. There are still
some technical challenges to be considered in cable installation
planning. The most subtle ones are those which concern
reliability, impact on the transmission grid and the installation
process. In the case of connections for offshore winds farms,
the use of AC cable may provide a lower cost solution than DC Fig. 1. Some examples of XLPE-insulated Milliken type cables

978-1-5386-5186-5/18/$31.00 ©2018 IEEE


Another important topic in cable transmission consists in
the conductor features. Typically, conductors are characterized Losses [MW]
by large cross-section but the ampacity of such cables is 5
reduced by skin and proximity effects. In order to reduce their
4
influences, so improving the quality of the transmission
system, it is possible to use conductors made up of a large 3
number of individually insulated wires. These are positioned
into segmental shaped bundles and singularly insulated 2
between each other. The conductors are stranded with
reference to the centre of each sector. Such conductors are 1
called "Milliken type conductors", shown in fig. 1 [8, 9]. It is
possible to determine the steady-state conductor behaviour by 0
132 kV AC 220 kV AC ± 150 kV DC
means of a powerful tool i.e. the Multiconductor Cell
Analysis, with acronym MCA [10-17]. Cable Compensation DC converter

III. TECHNOLOGY CHOICHES Fig. 3. Comparison of losses for 100 km long undergrounded transmission
lines with a 135 MVA load at 132 kV AC, 220 kV AC or ± 150 kV DC [20]
In these years, there is a growing interest in off-shore
power delivery for wind farms, oil platforms and connection Undoubtedly, it is too simplistic basing the choice of
between different countries. Furthermore, for land technology on a simple diagram cost vs distance. In fact, the
installations, even if OHLs are cheaper than cable systems, DC transmission scheme will not always result in lower power
more and more often cable systems are preferred because of a losses, in particular if the interconnection is characterized by
shorter bureaucratic process. In first instance, the choice is low power transfer. For high power flows and long distances,
between AC and DC transmission schemes. Usually for long lines with higher voltages are desirable. This is an advantage
distances, DC systems are preferred for its undoubted for AC systems, since converter technology is younger and
technical advantages, but this is not true in an absolute way more expensive than HV transformers [21].
(see fig. 2). In fact a complete cost-benefit analysis must be
carried out and there is a great amount of aspects to consider: IV. WORLDWIDE EXPERIENCE
• Design constraints such as temperature limits, The framework of the worldwide experience in cable
reliability indexes, electromagnetic interference, installation is full of examples in which technical and
voltage limits, etc…; economic issues suggest to adopt HVAC cables for long
• Frequency of the two interconnected systems; distances. In the following sub-sections, the most interesting
• Equipment and components; cases are presented in order to highlight challenging
• Overall losses of the system (see fig. 3). engineering choices.
Typically, the most important comparison factor is the cost
of the system, but there are many information difficult to A. Malta-Sicily interconnection
obtain: lifecycle, deployment, installation, maintenance and Part of the electrical power system in Malta is obsolete.
operation costs. An overall comparison may be found in [18- Pollutant power plants produce the most of the electrical power
20]. within the island. Moreover, the Maltese system is
characterized by poor robustness, limited reliability and high
P [MW] energy costs. The interconnection with the Italian grid allows
Malta to receive up to 225 MW and to decrease the production
1000 Sorgente-Rizziconi Legend:
Shin-Toyosu level of its plants [22-23]. The interconnector has been
Cook DC link
designed to minimize environmental impact on both sides. In
AC link
fact, the land route and the landing points of the interconnector
Vancouver *:Project
750 have been chosen to avoid protected areas and to minimize
Gemini
environmental impacts during construction and operation
phases.
Juan De Fuca*
TABLE I LONGEST IMPLEMENTATION OF HVAC CABLE SYSTEMS.
500 Anholt Year Length [km] V [kV] P [MVA] Name
2015 162 145 55 Martin Linge
Hokkaido-Honshu
2018 147 132 140 NASR full field
250 SACOI Murray 2014 126 230 225 Malta - Sicily
Malta-Sicily 2015 126 132 118 Mallorca - Ibiza
Martin-Linge
2013 107 123 75 Goliat
Length [km] 2000 104 90 40 Isle of man to England
50 100 150
2016 102 245 600 Gemini Windfarm
Fig. 2. Some AC and DC project around the world 2016 102 132 100 Ras Laffan – Halul island
Maghtab 1500/1800 mm
900
132 kV concrete jacking pipe
800 Current limit
700 land cable 880 mm between
Current limit
Ragusa centers
Current (A)

600 submarine cable


DTS duct
500
Maghtab strapped to
400 Marina di
Ragusa underneath side
230 kV
300
200
100 180 mm PE ducts
0 TR of encasement
0 10 20 30 40 50 60 70 80 90 100 110 120 grout to be 0.8 km/w
Distance from receiving end FO duct

Fig. 4. Current distribution for Malta-Sicily interconnection as a Fig. 5. Micro tunnel installation technique applied to the Victorian
consequence of non-homogeneous reactive compensation. desalination plant.

Directional drilling usage allows to avoid problems on the reactors at line terminals allow to compensate 93.3% of the
coastline near the landing point in Ragusa (Sicilian side), total reactive power of the system [27, 28].
whereas the use of cast iron shells minimizes the impact on
Neptune grass colonies [24]. The cable is also designed to C. Victorian Desalination Plant
minimize the induced magnetic field: due to trefoil The Victorian desalination project in Wonthaggi is the
arrangement of land cables, the overall magnetic field is lower largest desalination plant in Australia. It is capable of
than 3 µT. The final design of the cable consists in 19.1 km providing more than one third of Melbourne’s annual water
long ungrounded single-core land cables and a 98.8 km long supply from a source that is independent of rainfall. When the
submarine section, which is made by a three-core armoured Victorian government started the project, it was clear that
cable. The intertie links Ragusa sub-station with the Maghtab Wonthaggi, 88 km far from Melbourne, had an insufficient
one. For voltage regulation issues, the HV connection can be power supply to support the plant. The original proposal was
energized only by the Ragusa substation, in order to avoid for an OHL but the opposition from the community persuaded
serious voltage violations on Maltese network, caused by the the government to build up an underground cable. Because of
reactive power absorption of the cable [25]. A main issue the distance, the first option was a DC cable but, thanks to
during the installation is the reactive power compensation of technology robustness and limited realization time, AC
two systems, characterized by different voltages levels, solution was eventually preferred. The entire project was an
stability and operational requirements. The optimal example of engineering efficiency because the works had to be
exploitation of the link can be achieved by means of two done under a very high humidity rate. Furthermore, there were
asymmetrical reactors: 220 Mvar in Ragusa and two units of five locations where power cables had to cross an existing
120 Mvar in Maghtab (one is redundant), where two 250 MVA service or a river; in such cases concrete pipes containing
autotransformers, equipped with OLTCs are also present. The cable ducts have been installed. These "micro tunnels", shown
adopted configuration allows operating at a near unity power in fig. 5, kept the ducts steady by filling void spaces with a
factor at both terminals (94% compensation), with the Maghtab thermal backfill material, specially designed to maintain cable
line reactor at rated power, but it causes an asymmetric current ratings [29]. In some sections AC, cable shared the same
distribution, as it is shown in fig. 4 [26]. easement with an existing 500 kV OHL. There, the evaluated
induced voltages could decrease below 120 V. For the sake of
B. 500 kV Shin - Toyosu security of the jointers, additional precautions have been
taken, e.g. isolating the far end of the cables, earthed during
The project was born in order to connect the Tokyo
jointing works and usage of insulating mats [30, 31].
electric power Shin-Keyo substation and the Shin-Toyosu
substation with two 40 km circuits (three in the future) with a
rated power of 900 MW (1200 MW in future) [27]. D. Sorgente Rizziconi
This installation is particularly interesting because, in The first link between Sicily and Italy mainland is dated
order to reduce the joint number (of the extruded mold type) 1955 and was a 220 kV double-circuit overhead line with a
and installation times, cables section are long up to 1800 m. In crossing span of 3.65 km. In 1981 this OHL was dismantled
order to install quickly and efficiently the long cables, a pull- and substituted by a submarine 400 kV single-circuit cable
driven system and magnetic-driven one were developed and installation. All this operation has been made in difficult
adopted. environmental conditions of the Messina Strait [32]. More
The cable has a cross section of 2500 mm2, with recently, this submarine oil-filled cable has been substituted by
corrugated aluminum sheath. With the aim of reducing a very long AC double-circuit single-core cable line, chiefly
insulation thickness, harmful contaminants in insulating constituted of a submarine armoured cable system (38 km
materials were eliminated by means of tighter controls. Two long) and of two land parts (wholly about 5 km long).
compensating
115

110

Cable Voltage [kV]


105

100

Tunnel 95
Voltage [kV] 240 mm2 145 kV
90 Voltage [kV] 300 mm2 145 kV
Voltage [kV] 400 mm2 145 kV
85
Fig. 6. Sicilia-Villafranca double circuit single core cable installation 0 20 40 60 80 100 120 140 160
Cable position [km]
Because of the difficult environmental conditions (see fig.
6 [33]), the cable route is much longer than the minimum
distance of the Messina strait. The Sicilian land cable is a Fig. 7. Optimization study on cable cross-section for Martin Linge
XLPE 2500 mm2 with Cu conductors. The Calabrian one, interconnection
instead, is very similar, but it has an aluminium-based
Milliken structure, to lighten it and render it more suitable for F. Martin Linge
vertical tunnel installation (fig. 6). In the submarine part, the With a length of 161 km, Martin Linge offshore gas field
solid-bonding technique has been chosen (screens and armours connection is the longest ac submarine cable of the world. In
earthed at each ends). This un-avoidable choice has some order to reduce the environmental impact of the platform, it
drawbacks: additional losses in screens and armours, voltage was preferred an on-shore power plant instead of a dedicated
rise along the cable and (chiefly in lead screens, since the gas turbine. This aspect allows to reduce CO2 and NOx
armours are in full contact with the seawater). In order to emissions of about two million tons per year [35]. During
avoid the latter, additional bondings between screens and development phase both ac and dc solution were analysed.
armours have been realized along the cables every 4 km [33]. The ac solution was preferred because allows not to modify
These bondings are performed directly in the manufacturer the existing layout. For this purpose, the system has been
site, since the entire submarine part has no joints. Along the designed without an offshore compensation reactor, even if
two land stretches, instead, usual cross-bonding has been this would have improved the current distribution. This
performed in order to zero the induced currents in screens. solution has the advantage of having a better offshore voltage
stability, because in case of full offshore load rejection, the
E. Anholt wind farm interconnection offshore reactive power variation is small. For the onshore
The Anholt wind farm has an output of 400 MW and it is power factor regulation, two redundant static VAR
located in the Kattegat Strait. The 136/235 (245) kV line that compensators are installed to support two other banks installed
links the collector substation with the grid consists of: on load tap changer transformers site [36]. Regarding the
operating transmission voltage, 100 kV has been chosen as the
• A submarine part, from the offshore collector substation
best tradeoff between several criteria (losses, induced
located in a sea platform and to the shore close to Grenaa,
voltages, transient studies, etc…). A 145 kV insulation class
with a length of 24 km;
has been preferred instead of a smaller one, so to have lower
• A land part, composed of a 500 m long cable, from the line capacitance and reducing the amount of generated
transition joint on-shore close to Grenaa, to the shunt reactive power. Another interesting aspect of this choice is the
reactor station and from the Grenaa shunt reactor station to decrease of electric stress on the cable, with a long-term
Trige substation, with a length of 60 km. positive effect on its aging. Cable cross-section was chosen in
The final proposal has been based on the prices of consequence of an optimization study on the cable voltage in
materials, of commissioning, of installation and of the function of the chosen insulation class, as it is shown in fig. 7.
capitalized power losses. As a consequence of this economic
study, the AC configuration was preferred instead of the DC G. Gemini wind farm connection
solution, for the high cost of the conversion substations.
The project was initially based on a HVDC transmission
Several cable routes were considered since there are some system, but in consequence of a consistent cost-benefit
protected natural areas and it was necessary to take city analysis, it was clear that the AC solution was more
expansion into account. As a consequence of such convenient even in view of an increasing generation capacity.
considerations, final route is longer than the initial proposal. Along the line, it is possible to find four different cross-
Directional drilling technique is used to pass under all sections, chosen to minimize project costs and respecting
protected natural areas. The submarine cable system is thermal constraints (800 mm2, 1000 mm2, 1200 mm2, 1600
designed in order to minimize losses and weight. Individual mm2). For the sake of environmental issue and technical
cables are lead screened with an outer semi-conductive PE problems, i.e. anchoring or seabed movements, various
techniques for installation and burial have been used along the
sheath. The three cables phase are laid up and two fibre optical 110 km of cable length, as the jetting technique or the use of a
cables are included in the design before going to the pre-dredged trench [22]. Because of the complex cable
armouring line, where a layer consisting of partly steel wire configuration, in order to guarantee the optimal cable lifetime,
and partly plastic wires is applied. The armouring is covered it is necessary to regularly inspect the burial depth and the
by bitumen [34]. temperature of the different parts.
H. Isle of man – UK For the sake of overcome thermal limitations above the
The electricity demand on the Isle of Man were provided low tide level, a cooling system has been made by installing a
by pollutant diesel and gas turbines, with very high electricity 110 mm polyethylene pipes alongside each cable and the
costs as well as the Malta situation. With the aim of costs and system is in closed loop with a cooling station. The cooling
emissions reduction, in order to improve network stability, the liquid is a mixture of water and glycol, which circulates
AC submarine cable was commissioned. With an undersea through a chiller [42]. It was decided to bury the cables from
length of 104 km and a land length of approximatively 4 km, it the potheads seaward to where the water is 20 m deep at low
would have been the longest AC cable until 2013 [37]. It is tide. In most of shoreline locations, cables and cooling pipes
composed of a three cores XLPE insulation, lead sheathed, are protected above the low tide mark by rectangular
with a cross copper section of 300 mm2 laid up within a reinforced ducts backfilled with sand or sand/cement thermal
protective armour layer of galvanized steel wires. Two material, as it is shown in fig. 8 [43].
different companies manufactured the subsea section and the
different portions were jointed using a fully flexible joint, V. CONCLUSIONS
buried at 2 m in the seabed [38]. Special attention for such
long cable has been given in fault location technique. A time In this paper some of the longest HVAC links have been
domain based reflectometry technique was chosen as the presented in order to highlight the interesting installation
optimal solution, even if the pulse front is strongly damped choices. The choice between a HVAC and HVDC line is not
from the interconnection joint. A 100 V pulse signal generator trivial, even if the link length is long. In fact, AC link can be
is used and by studying the time interval between the pulse designed and put into operation in relatively shorter periods
injection and the reflected one arrival time, it is possible to and with less space requirements. In the paper it is also shown
determine the fault section with good accuracy [39]. The how cable links can overcome acceptance problems and
seabed through the cable route is very mobile and movements satisfy environmental requirements, differently from OHLs
of the sand may occasionally expose parts of the cable lying. technology. Overall, each technology entails different benefits
To protect the surface laid, ensuring that the fishing can and issues and accurate cost/benefit analyses have to be
continue safely along the route, protective mattresses have achieved in order to determine the best solution for the
been installed in most critical locations [40]. particular case study. Even if a wide reference section has
been provided, for other not presented issues (reliability, other
HVAC installations etc…) the reader may refer to [44-50].
I. Vancouver to Mainland
The connection was built during 1980s and consists of two ACKNOWLEDGMENT
525 kV parallel circuits of OHLs and submarine cables, which
can supply 1200 MW. The submarine cables start on the We want to dedicate this work to our colleague and friend,
Mainland at Cape Cockburn and cross the ocean for 9 km to Luca Russo, tragically died in Barcelona Rambla, on August
reach a terminal station on the east side of Texada Island. 17, 2017. His passion and motivation have often inspired us.
OHLs cross the island and connect from a terminal on the We will always remember you with unchanged affection.
island’s west side a second set of cables long 30 km reach the
Nile Creek terminal on Vancouver island. The cables are
insulated with fluid impregnated paper tapes. Since the cables REFERENCES
are laid under 400 m of water, cables and potheads were [1] R. Benato, D. Napolitano: "Overall Cost Comparison Between Cable
designated to operate with an internal fluid pressure of 1.3 and Overhead Lines Including the Costs for Repair After Random
MPa to prevent from water leakage. Three compensation Failures", IEEE Trans. on Power Del., Vol. 27, Issue 3, doi:
reactor are installed: two 135 Mvar reactors at the line 10.1109/TPWRD.2012.2191803, pp. 1213 - 1222, 2012.
terminals and a 45 Mvar in the mid-point, on Texada Island [2] R. Benato, S. Dambone Sessa: "A new multiconductor cell three-
[41]. Two different manufacturer have produced the dimension matrix based analysis applied to a three-core armoured cable"
submarine cable and two different bonding connection are IEEE trans. On Power Del., vol.: PP, issue 99, doi:
used. In the first cable, since it has an extruded polyethylene 10.1109/TPWRD.2017.2757084, 2017.
jacket between reinforced lead sheath and armour, bonding [3] R. Benato, S. Dambone Sessa, M. Forzan: "Experimental Validation of
connections were placed every 4 km. The second cable uses a 3-Dimension Multiconductor Cell Analysis by a 30 km Long Submarine
semi-conducting lapped layer and a continuous bonding Three-Core Armoured Cable", IEEE Trans. on Power Delivery, 2018.
connection is formed. [4] R. Benato, S. Dambone Sessa, M. Forzan, M. Marelli, D. Pietribiasi:
"Core laying pitch-long 3D finite element model of an AC three-core
Sea bottom level armoured submarine cable with a length of 3 metres", Electric Power
Systems Research, Vol. 150, Pages 137-143, 2017.
Sand & cement [5] F. Rudolfsen, G.E. Balog, G. Evenset: "Energy transmission on long
(1:14) three core / three foil XLPE power cables". Int. Conf. on Insulated
1.5 m in rock Power Cables, JICABLE 2003.
2.0 m in sand
[6] Y. Liu, X. Cao: "A novel method for the insulation thickness design of
HV XLPE cable based on electrical treeing tests", IEEE Trans. Dielectr.
Electr. Insul., vol. 21, no. 4, pp. 1540-1546, 2014.
110 mm
cooling pipes [7] D. S. Shin, H. D. Cho, W. S. Park, S. Yi, J. Sun: "Extraction of
propagation constant of XLPE cable using time-domain transmission"
Submarine cables IEEE trans. On instr. and meas., vol. 63, issue 12, pp. 2855-2862, 2014.
[8] R. Benato, A. Paolucci: "Multiconductor cell analysis of skin effect in
Milliken type cables" Electr. Power Syst. Res., vol. 90, pp.90-106, 2012
Fig. 8. Conductors and cooling pipes burial in the Vancouver to Mainland [9] H. M. Ryan: High voltage engineering and testing, 3rd edition, pp. 230-
interconnection 235, 2013.
[10] R. Benato: "Multiconductor analysis of underground power transmission [30] Nexans Olex: "Design report for 220 kV underground T/L cranbourne
systems: EHVAC cables", Elec. Power syst. Research 79, pp. 27-38, terminal station to victorian desalination plant", 2010.
2009. [31] "Technical specification for 220 kV underground T/L Cranbourne
[11] R. Benato, S. Dambone Sessa, F. Guglielmi, E. Partal, N. Tleis: "Ground terminal station to Victorian desalination plant", 2009.
Return Current Behaviour in High Voltage Alternating Current Insulated [32] L. Rebuffat, G.M. Lanfranconi, F. Magnani, U. Arnaud: "Installation of
Cables", Energies 2014, 7, 8116-8131; doi:10.3390/en7128116. submarine power cables in difficult environmental conditions. The
[12] R. Benato, S. Dambone Sessa, F. Guglielmi, E. Partal, N. Tleis: "Zero experience with 400kV Messina cables", Proc. of Cigré, 1984.
sequence behaviour of a double-circuit overhead line", Electric Power [33] R. Benato, S. Dambone Sessa, R. De Zan, M. Guarniere, G. Lavecchia,
Systems Research 116, pp. 419-426, doi:10.1016/j.epsr.2014.07.011, P. Sylos Labini: "Different Bonding Types of Scilla-Villafranca (Sicily-
2014. Calabria) 43 km Double-Circuit AC 380 kV Submarine-Land Cable",
[13] R. Benato, S. Dambone Sessa, M. Forzan, F. Gentilin, M. Marelli, D. IEEE Transactions on Industry Applications, Volume: 51, No. 6, Pages:
Pietribiasi: "Finite Element model of a 3 m long three-core armoured 5050 - 5057, 2015, DOI: 10.1109/TIA.2015.2448676.
submarine cable", Proc. Of AEIT 2016 – International Annual [34] T. Kvarts, M. Bailleul, J. M. Doming, Y. Douima, F. Peitot, A. Jensen,
Conference, 2017. S. T. Salwin. "400 MW grid connection to the Anholt offshore wind
[14] R. Benato: "Steady State Assessment of Shunt Compensated EHV farm in a single 220 kV cable system" 10th international workshop on
Insulated Cables by Means of Multiconductor Cell Analysis (MCA)", large scale integration of wind power into power system as well as on
Energies. 2012; 5(1):168-180. transmission networks for offshore wind power plants, 2001.
[15] R. Benato, M. Forzan, M. Marelli, A. Orini, E. Zaccone: "Harmonic [35] E. Thibaut, B. Leforgeais. "Martin Linge electric power from shore",
behaviour of HVDC cables", Electric Power Systems Research 89 Proc. Adipec, 2012.
(2012), pp. 215– 222, doi: 10.1016/j.epsr.2012.03.012. [36] E. Thibaut, B. Leforgeais. "Selection of power from shor for an offshore
[16] R. Benato, L. Colla, S. Dambone Sessa, M. Marelli: "Review of high oil and gas development". IEEE trans. On Ind. Applications, vol. 51,
current rating insulated cable solutions", Elec. Power Syst. Research issue: 2, pp. 1333-1340, 2014.
133, pp. 36-41, 2016. [37] "The Longest AC Subsea Cable in the World". Major Assets. Manx
[17] P. Bettini, R. Benato, S. Dambone Sessa, R. Specogna: "T-Ω Electricity Authority. Retrieved 2008-10-22.
formulation for eddy current problems with periodic boundary [38] Pickin, M. "Power to Pulrose". Power Engineer. IEEE. 18 (1): 14–16,
conditions", IEEE Trans. On Magnetics, Vol. 53, Issue 6, Article 2014
Sequence Number 7201604, doi: 10.1109/TMAG.2017.2654498, 2017.
[39] Howarth, B.; Coates, M.; Renforth: "Fault location techniques for one of
[18] S. Wright, A. Rogers, J. Manwell, and A. Ellis: "Transmission options the World's longest AC interconnector cables". 8th IEE International
for offshore wind farms in the United States," Proceed. AWEA Annual Conference on AC and DC Power Transmission. pp. 14–18, March
Conference, pp. 1-12, Portland, OR, June, 2002. 2016.
[19] Roozbeh Asad, Ahad Kazemi: "A Quantitative Analysis of Effects of [40] M. Bawart, M. Marzinotto, G. Mazzanti: "A deeper insight into fault
Transition from AC to DC System on Storage and Distribution location on long submarine power cables". CIGRE, paper B1-201, 2014.
Systems", Power and Energy Engineering Conference (APPEEC) 2012
Asia-Pacific, pp. 1-5, 2012, ISSN 2157-4839. [41] R. G: Foxall, et al. "Design, manufacture and installation of a 525 kV
Alternating carrent submarine cable link from mainland canada to
[20] D. L. Gerber, V. Vossos, W. Feng, A. Khandekar, C. Marnay, B. vancouver island" CIGRE, paper 21-04, 1984.
Nordman: "A simulation based comparison of AC and DC power
distribution networks in buildings". 2nd IEEE international conference [42] S. Cherukupalli et al.:"Application of distributed fibre optic temperature
on DC microgrids, 2017. sensing on BC hydro’s 525 kV submarine cable system" CIGRE, paper
B1-203, 2006.
[21] F. Wang, Y. Pei, D. Boroyevich, R. Burgos, K. Ngo: "Ac vs. dc
distribution for off-shore power delivery", Ind. Elec. IECON 2008. 34th [43] R.G. Foxall: " The design, installation and operation of 500 kV AC
Annual Conference of IEEE, 2008. power supply to Vancouver island". EHV Cable conf., Lausanne,
Switzerland, 1987.
[22] Cigré Technical Brochure # 680: "Implementation of long AC HV and
EHV cable systems", 2017. [44] R. Benato, ˙I. Balanuye, F. Köksal, N. Ozan and E. Özdemirci:
"Installation of XLPE-Insulated 400 kV Submarine AC Power Cables
[23] G. M. Giannuzzi, F. Palone, M. Rebolini, J. Vassallo, R. Zaottini: "The under the Dardanelles Strait: A 4 GW Turkish Grid Reinforcement",
Malta-Sicily EHV-AC interconnector", Proc. of 8th mediterranean Energies, 11, 164; doi:10.3390/en11010164, pp. 1-15, 2018.
conference on power gen., transm., distribution and energy conversion,
2012. [45] R. Benato, S. Dambone Sessa: "Analysis of real kilometric three-core
armoured cables by means of an integral multiconductor three-
[24] S. Lauria, F. Palone: "Operating envelopes of the Malta-Sicily 245 kv- dimensional model", Proc. of 2017 AEIT International Annual
50 Hz cable", Proc. of IEEE internation energy conference and Conference, 2018.
exhibition, 2012.
[46] R. Benato, I. Balanuye, F. Köksal, N. Ozan, E. Özdemirci: "A 4 GW AC
[25] G. Paternò, A. Madonia, M. G. Ippolito, F. Massaro, S. Favuzza, C. submarine Turkish power grid reinforcement under the Dardanelles
Cassaro: "Analysis of the new submarine interconnection system Strait", Proc. of 2017 AEIT International Annual Conference, 2018.
between Italy and Malta: simulation of transmission network operation"
[47] R. Benato, L. Caciolli: "Sequence Impedances of Insulated Cables:
Proc. of IEEE 16th international conf. on environment and electrical
engineering, 2016. Measurements versus Computations", Proc. of IEEE PES Transmission
and Distribution Conference and Exposition (T&D), Orlando, 2012.
[26] S. Lauria, F. Palone: "Optimal operation of long inhomogeneous AC DOI: H10.1109/TDC.2012.6281574.
cable lines: the Malta-Sicily interconnector" IEEE Trans. on Power Del.,
vol. 29, issue 3, pp. 1036-1044 2014 [48] R. Benato, D. Napolitano: "State-space model for availability
assessment of EHV OHL–UGC mixed power transmission link",
[27] H. Yamanouchi, S. Seo, Y. Kumada, M. Itoh, S. Kunimus, S. Electric Power Systems Research 99 (2013), pp. 45– 52.
Nakamura, Y. Fujii, T. Ishii: "Construction of the world’s first long-
distance 500 kV XLPE cable line" Fujikura technical review, 2003. [49] R. Benato, S. Dambone Sessa, L. Guizzo, M. Rebolini: "The synergy of
the future: high voltage insulated power cables and railway-highway
[28] Y. Ohki, S. Yasufuku: "The world’s first long distance 500 kV-XLPE infrastructures", IET Generation, Transmission & Distribution, Vol. 11,
cable line. 3. Underground apparatus" IEEE Electrical Insulation Issue 10, pp. 2712 – 2720, DOI: 10.1049/iet-gtd.2016.2082.
Magazine, vol. 18, issue 4, pp. 44-45, 2002."
[50] R. Benato, A. Paolucci: EHV AC Undergrounding Electrical Power.
[29] .N. Rahman: " 220 kV long distance undergroun HVAC cable circuit" Performance and Planning, SPRINGER, Series: Power Systems
AORC technical meeting, cigré, 2014. Volume 47, ISBN: 978-1-84882-866-7.

View publication stats

You might also like