You are on page 1of 10

International Journal of Project Management 21 (2003) 537–546

www.elsevier.com/locate/ijproman

Design documents quality in the Japanese construction industry:


factors influencing and impacts on construction process
Andia,*, Takayuki Minatob
a
Department of Civil Engineering, Petra Christian University, Jalan Siwalankerto 121-131, Surabaya 60236, Indonesia
b
Institute of Environmental Studies, Graduate School of Frontier Sciences, The University of Tokyo, 7-3-1 Hongo, Bunkyo-ku, Tokyo 113-8656, Japan

Received 20 March 2002; received in revised form 19 June 2002; accepted 19 November 2002

Abstract
Despite its technological advance, the Japanese construction industry is currently paying attention to the quality of its design
documents. It acknowledges defective design as the most important risk for the success of a project. This paper aims to investigate
the quality of design documents in the industry by presenting factors that may influence design documents quality, and then dis-
cussing design document related problems and their impact on the construction process. The result is based on a number of inter-
views and questionnaire surveys involving 105 designers and 91 construction personnel. The results show that designers and
contractors have different perceptions of the quality of design documents. The study also finds that the problems of defective
designs are complex and deep rooted, influenced by many factors operating at individual designer, company, construction industry
and global or national levels. The paper discusses these problems and proposes possible solutions to improve the level of design
documents quality.
# 2003 Elsevier Ltd and IPMA. All rights reserved.
Keywords: Defective design; Design documents quality; Japan; Risk

1. Introduction Researchers and practitioners have acknowledged


defective design is a major cause of contract claims and
According to many independent analyses [1–3], design change orders during construction [4]. One study shows
fees are often less than one percent of the life-cycle cost that design error is the single most common cause for a
of a project (or less than 10% of the total construction contract claim [5]. It is also found that more than 50%
costs), yet the design is the single most important influ- of change orders are attributable to defective design
ence on those costs. Decisions and commitments made [6,7].
during the design phase have a tremendous impact on Let us see another view of this situation, that is, the
later expenditures. In a grass-roots petroleum refinery, importance of defective design in comparison to other
for example, ‘‘a rough guess would put the remaining risks in construction projects. A recent survey in Kuwait
level of influence at about 25% of the original by the [8] reports that defective design is one of the most sig-
time field construction commences on [1].’’ While this nificant risks to project delays. Similar results were also
concept of ‘ability to influence’ is well developed and obtained from studies in Japan [9], US [10] and Hong
well known in construction, it is believed that its imple- Kong [11]. Defective design is considered a critical risk
mentation is still under development in practice, leading in these countries, particularly in Japan. Here both
to low quality, inadequate and defective or deficient owners and contractors perceive defective design as the
design documents. most crucial for project success, as indicated in Table 1.
One survey conducted by Nikkei Construction invol-
ving 79 Japanese contractors [12] shows that 44% of
respondents often experienced significant number of
* Corresponding author. Tel.: +62-31-8494830; fax: +62-31-
8415274.
design documents problems, while 46 and 10% had
E-mail addresses: a_sunyoto@yahoo.com (Andi), fewer and no experiences, respectively. The common
minato@k.u-tokyo.ac.jp (T. Minato). problems experienced were constructability, conflicts in
0263-7863/03/$30.00 # 2003 Elsevier Ltd and IPMA. All rights reserved.
doi:10.1016/S0263-7863(02)00083-2
538 Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546

Table 1
Risks ranking in Japanese construction [9]

Ra Japanese owner Japanese contractor

1 Defective design Defective design


2 Acts of God Differing site conditions (lump sum contract)
3 Safety Changes in work
4 Contractor competence Change-order negotiation
5 Changes in work Safety
6 Quality of work Acts of God
7 Differing site conditions (lump sum contract) Financial failures
8 Contract-delay resolution Third-party delays
9 Third-party delays Contract-delay resolution
10 Defective material Quality of work
11 Site access/right of way Contractor competence
12 Financial failures Permits and ordinances
13 Labor, equipment, and material availability Site access/right of way
14 Permits and ordinances Defective material
15 Inflation (lump sum or unit price contract) Delayed payment on contract
16 Change-order negotiation Labor and equipment productivity
17 Changes in government regulations (lump sum) Labor, equipment, and material availability
18 Labor and equipment productivity Inflation (lump sum or unit price contract)
19 Labor disputes Changes in government regulations (lump sum)
20 Delayed payment on contract Labor disputes
a
Rank order from most to least important.

structural designs, inadequate temporary work designs, and one for contractors. After considering several ver-
improper construction methods, and differing site con- sions of questionnaires, the questionnaires used in a
ditions information. These design problems are ongoing similar study in an Australian context [13,14] were uti-
issues in the Japanese construction industry and of lized with some modifications. The questionnaires con-
major concern to many parties within the industry. tained both close and open types of questions.
Consultant companies, a key player at the design stage, A pilot study was conducted to test the developed
are attempting to reduce these problems. questionnaires. Several revisions were made to the origi-
This paper also aims to investigate further the quality nal questionnaires after that, including contents, wording
of design documents in Japanese construction by mea- and format, to make the questionnaires more applicable
suring the extents of design attributes (such as economy, and understandable in the Japanese context. The final
life cycle cost, and constructability) and its documenta- versions of the contractor’s and designer’s questionnaires
tion attributes (such as timeliness, completeness, accu- were six and eight pages long, respectively.
racy, coordination, and conformity). More importantly, To distribute the questionnaires, 20 contractor and 30
the paper identifies critical factors influencing design consultant companies, listed as members of Construc-
documents deficiencies and then presents design related tion Management Committee of JSCE (Japan Society of
problems, emphasizing their impact on the construction Civil Engineering) in 1998, were approached. Prior to
process and project performance. the distribution of the final versions, one representative
from each company was contacted first by phone to
assess their willingness to participate and distribute five
2. Research methodology and questionnaire survey sets of questionnaire to personnel who had experience
development and distribution either in construction or design works. It was thought
that by doing this would increase the response rate.
Results for this research were based on a ques- Finally, 150 designer’ and 100 contractor’ ques-
tionnaire survey and supplement interviews. The ques- tionnaires were distributed. It took about one and half
tionnaire survey is one of the most cost effective ways to months before the last set of questionnaires were
involve a large number of people in the process in order returned. The overall response rate for designers was
to achieve better results, whereas the face-to-face inter- 70%, i.e. 105 questionnaires, while for contractors a
views serve as crosscheck and, sometimes, unexpected return rate of 91% was achieved, i.e. 91 questionnaires.
information may be given during the interviews. These rates were considered high because in the Japa-
By focusing on traditional procurement projects, two nese environment, it is very difficult to obtain answer
types of questionnaires were developed, one for designers through questionnaires.
Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546 539

3. General information of respondents Table 3


Attributes of ‘Design’ quality
In general, all companies who responded to the ques- Attributes of ‘design’ quality
tionnaires had ISO 9000 certification, except for one
designer company. Table 2 summarizes other general (a) Consideration of whole life-cycle cost issues
(b) Material efficiency—ensuring the efficient use of materials
information of the respondents for both contractors and (c) Economy—ensuring design solutions are cost effective
designers. For the purpose of analysis, the designers (d) Relevancy—ensuring project requirements are met
were grouped based on the number of employees in the (e) Constructability—considering constructability and safety
company. However, the groups did not indicate the real aspects
company size. They were just relative size, in which (f) Innovation—incorporating innovation in the design solution
(g) Expressiveness—provides symbolic expression and feeling
companies having 500 employees or more (totally 16 (h) Aesthetics—the finished product is visually pleasing
companies) were assumed bigger than those having less (i) Consideration of ecological sustainability
than 500 employees (totally 12 companies). (j) Site compatibility—effectively uses and makes due allowance
The respondents were experienced in their field since for site conditions
most of them have worked for more than 10 years in the (k) Material selection—ensuring the availability, suitability and
compatibility of materials
industry. The table also exhibits that most of the (l) Functionality—effectively serves the purpose for which it was
designer companies received work orders from public intended
clients, while the contractor companies received almost
equally from public and private clients. Considering the
types of projects, all respondents had experiences in civil designers and contractors have a similar trend, it is
engineering projects and only a few designers had obvious that designers rated all attributes higher than
experience in other types. It can be said therefore that contractors did, except for material selection. The dif-
the designers based their answers on civil engineering ferences in perceptions are higher for documentation
projects they worked on for public clients. attributes than design attributes. The big differences for
document attributes can be seen for site representation,
certainty, and completeness. While for design attributes
4. Design documents quality the big differences are found for economy and con-
structability. Statistical analysis, using the t-test, con-
Designers’ and contractors’ perceptions of the firmed the significant differences for these attributes (at
achievement of design document quality were assessed =1%).
using rating scales from Very Poor (1) to Excellent (5). Lack of feedback from contractors to designers about
The quality was evaluated from several attributes indi- the quality of design documents is one reason for the
cating the quality of design and its documentation (such differences. It is suggested that the original designers
as drawings and specifications). The addressed attri- should be also involved in the construction so that they
butes and their respective definition are listed in Tables 3 can make use of the learning opportunities to improve
and 4. design quality. To make it happen, the clients should
Fig. 1 shows the comparison of the perceptions by the consider the opportunities by which both contractors
respondents for the attributes. Several interesting findings and designers can learn from each other. Communi-
are pointed out there. While in general the perceptions of cation between designers and contractors during the
design process is also encouraged to improve the quality
Table 2 of design documents. Currently, such a link is very weak
General information of respondents in public projects.
No. Information Contractors Designers Averaging the designers’ and contractors’ answers,
design attributes having less-than-average rating are
1 Number of employees in the present 1707–15,400 40–1060
company
expressiveness, life cycle cost, and innovation, and for
2 Experience in industry (years) 10–39 3–40 documentation attributes are certainty, coordination,
3 Average proportion of clients or and accuracy.
projects (%): Both designers and contractors rated the design attri-
i. Public 43% 90% bute life cycle cost low. This was crosschecked from the
ii. Private 57% 10%
4 Type of projects usually involved with
direct interviews with some professionals. In Japan,
(% of respondents): there is low motivation or no incentive for value engi-
i. Building 80% 19% neering (VE) program under traditional design-then-
ii. Industrial (process plants) 22% 5% construction option. There are two possible reasons for
iii. Civil engineering 100% 100% this. First, the contractor gets nothing from the VE
iv. Manufacturing 57% 5%
v. Others 16% 5%
saving. In other words, it is a ‘free’ knowledge. There is
still no clause in the contract that requires VE program.
540 Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546

Table 4
Attributes of ‘Documentation’ quality

Attributes of ‘documentation’ quality

(a) Completeness—drawings and other documents provide all the information required
(b) Clarity—drawings and other documents are eligible and are easily read and interpreted
(c) Consistency—drawings and other documents are consistent
(d) Accuracy—drawings and other documents are free from errors and omissions
(e) Standardization—use of standard details and specifications in drawings and other documents
(f) Relevance—trade specifications and details are specific, relevant and appropriate to the project
(g) Timeliness—drawings and other documents are supplied when required, to avoid delays
(h) Coordination—drawings and other documents are thoroughly coordinated between design disciplines
(i) Certainty—drawings and other documents do not require changes or amendments
(j) Conformity—drawings and other documents indicate the requirements of performance standards and statutory regulations
(k) Representation—drawings and other documents correctly represent the geological (subsurface), topography (surface) conditions, including the
existing utilities and structures

Fig. 1. The extent of quality of design and documents attributes.

Another reason is that even if they successfully reduce systems. Despite the limited number of responses, they
the cost, the saving is not shared between contractors still could supply valuable information as denoted in
and clients. According to the Japanese accounting law, Fig. 2. The figure indicates the average value of the
it is to be returned to the Ministry of Treasury. There- quality in public and private projects.
fore, it is argued that a reasonable incentive plan should Apparently there are differences between contractors’
be implemented to motivate not only contractors but and designers’ perceptions with the use of traditional
more importantly the designers too, so as to encourage and D&B procurement systems. While the contractors
VE, and finally to minimize the life cycle cost. perceived the quality of design documents were better in
While the focus of this study is on traditional pro- D&B systems than in traditional systems, the designers
curement projects, part of this quality section also took the opposite view. Statistical t-test analysis sig-
requests contractors and designers’ perception for the nificantly confirmed the differences (at =5%).
overall quality of design documents produced in three The differences in perceptions above might be under-
different procurement systems—traditional, design and stood from the controversy about the D&B procure-
build (D&B), and construction management (CM) ment system in Japanese public works that has taken
methods—using the same rating scales as discussed ear- place since about 80 years ago [15]. The designers favor
lier. Note that not all respondents gave their opinion for traditional procurement systems in order to maintain
this part, especially for the two modern systems. This their independent status. With regards to D&B systems
may be because they did not have experience with the one design firm argues, ‘‘if contractors can do design and
Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546 541

Fig. 2. Perceived quality level in design documents produced in three different procurement systems.

build, we can design the project and also build the project’’ difference (at =5%) between smaller and bigger compa-
(Interviews). This paper, however, will not discuss fur- nies, where the former perceive more frequent problems.
ther about the controversy. Readers may refer to other
sources for more details [15].
6. Aspects of people, organization and management

5. Factors affecting design documents quality In addition to the earlier factors, designers were also
asked to rate aspects related to people, organization and
To examine factors affecting quality of design docu- management, which were believed to have impact on the
ments, designers were given a list of influential factors quality of design document. Using the same scale and
and then asked to indicate frequency (F) and impact (I) method of analysis as earlier, Fig. 4 shows the results of
of each factor using a five-point rating scale. The ana- the analysis.
lysis depended on the weighted average of the frequency If we examine the first three most important aspects
and impact of each factor. Then these two values were (time pressures, work overload and high stress situation),
multiplied to obtain importance level (IL) of each fac- it can be understood that they are interrelated to one
tor. Finally, these importance levels were sorted from another. Time pressures may cause work overload and
highest to lowest in order to rank the factors. Fig. 3 high stress situation, where designers will easily make
presents the rank and the frequency and impact levels mistakes during designing. It is also known that in
for each factor. Japan, there is usually no overtime payment in designer
It can be learned that there are two key factors companies.
affecting design documents quality. They are time and The designers also acknowledged that ‘lack of con-
fee for design works. The designers regarded insufficient struction knowledge’ had been a major problem for
design time as the most important issue influencing them, bringing impractical design. It is suggested that
design document quality. According to the open dis- they should have more chance to observe and get
cussion, it was pointed out that the Japanese fiscal year themselves involved during the construction phase,
system (April–March) was a major cause of this. Most especially those young and inexperienced designers.
design works are usually subcontracted to designers at Currently, the role of designers during construction is
the end of each fiscal year (January–March). That small and almost none for the management of con-
means design firms have to complete the jobs within a struction works in public projects (Interviews). This is
short period of time with limited number of qualified quite different from practices in US or UK, where the
personnel. original designers are often employed as client repre-
Designers also regarded client’s tendency to shop sentatives to supervise the construction works.
around for design fee and a low design fee as most
important factors affecting the quality of design docu-
ments. As will be detailed later in the paper, the design- 7. Level of design fees
ers thought the design fee was mostly unreasonable in
both public and private projects. These findings were in Another part of the designer questionnaire was
line with those in the Australian context [16] too. designed specifically to look at the reasonableness of the
Statistical analysis (t-test) shows that the frequency of current fee level for design service in public and private
the issue ‘difficulty in finding good staff’ has a significant projects. The question required the respondents to
542 Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546

Fig. 3. Factors influencing design documents quality.

Fig. 4. Aspects of people, organization, and management influencing design documents quality.

express their perceptions of the fee in terms of one of current design fee is ‘mostly unreasonable’ from both
four levels (Reasonable, Mostly Reasonable, Mostly public and private client. It can be concluded that there
Unreasonable, and Unreasonable). The result was then is a decrease in the design fee level in the current sit-
compared to a similar study conducted by Nikkei uation compared to 10 years ago. Many believed that
Architect in 1992 [15] as summarized in Table 5. this situation is also influenced by the overall economic
It is interesting to see that there is no single response condition in Japan, whereby the unit rate (Yen/man
for ‘reasonable’ level in the current survey. About two- day) for design service is decreasing year by year
third of the current respondents perceived that the (Interviews).
Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546 543

Table 5 design firm had to pay 3 Millions Yen for construction


Reasonableness of design fee level rework because of an error in the produced design [17].
Reasonableness of Nikkei survey Current survey (2000/2001) In addition to the immediate consequences, defective
design fee (1992)a (%) designs place other costs on companies. The total costs
Public (%) Private (%) may be higher than the actual figure they spent, because
Unreasonable 9.4 11 12
they could include other such indirect costs as decrease
Mostly unreasonable 40.4 65 70 in the designers’ productivity and lost of contracts (lost
Mostly reasonable 40.4 24 18 of reputation).
Reasonable 8.8 0 0
a
Source: Nikkei Architecture, September 1992, pp. 110–142, cited
from Ref. 15. 9. Areas of design documents problems

8. Design practices With regard to design document problems, con-


tractors were requested to give their opinion on the fre-
In this section, designers were asked to consider 20 quency of the occurrence of this problem and their
different aspects of design practices and to rate the relative impact on construction processes, using a five
extent to which each aspect had been fulfilled using a point rating scale. Fig. 6 graphs the contractors’ per-
five-point scale: never (1), rarely (2), sometimes (3), ceptions. Using the aforementioned important levels
often (4) and always (5). A bar graph in Fig. 5 presents (IL), the contractors perceive insufficient clearances prior
the result. to commencement on site to be the most important. The
In average there is no single design practice with the process of clearances is often in progress when con-
rating ‘always’ or even ‘often.’ That is to say that they just struction activities start. The contractors sometimes had
‘sometimes’ performed some design practices although to wait for approval to start the project although the
some of them, such as design reviews, are a must do in completion date was unchanged. There are occasions
order to produce a quality design document. Further when contractors need to get clearance with no money.
statistical analysis found no significant differences (at In the worst cases, the clearance may involve disputable
=5%) between the smaller and bigger companies. elements from the viewpoint of the statutory body. It
While there are many factors constraining their prac- may result in changes to design and hence time will be
tice, it is suggested that design firms should improve spent on redesign. Consequently the contractor might
their own design practice as far as possible, when they exceed the time allocated to complete the project if no
can exercise control over a project. They should con- additional time is allowed.
sider liquidated damages resulting from defective One contractor narrated one example of the clear-
design. Since 1999 design firms have to be fully respon- ances problem in a subway construction project in
sible for liquidated damages (including the costs of Tokyo area (Interviews). When the construction work
construction rework) if damages result from any defec- had been awarded, the process of clearances for prop-
tive design. For example in one bridge construction, a erty right had not yet finished. Because the project area

Fig. 5. Extents of fulfillment of some aspects of design practices.


544 Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546

Fig. 6. Levels of impact and frequency of deficiencies in design documents.

belonged to two different government agencies, it took design attributes. Based on several interviews, several
about one year for the client to settle the land acquisi- problems inhibiting innovation in public projects were
tion. Consequently the contractor had to delay their identified. Among many factors is conflict of interest
work. among client divisions. The use of innovative design
Another important problem faced by contractors in sometimes will necessitate higher initial construction
the survey was design not being achievable within the cost, leading in the end to a more economical total life
project budget (which means that the cost of designed cycle cost (e.g. due to low maintenance and operational
construction exceeds the budget). If the budget for a costs). However, the construction division’s personnel
project has no allowance for unforeseen costs, the pub- may disagree with this because they will be responsible
lic clients will not be able to pay even if the project costs for the high cost. Another problem expressed was reg-
exceed its limit. In such a case, contractors sometimes ular changes of client personnel every two years, which
have to cover the overrun even though it is not their may introduce motivational problem. Even though the
responsibility (Interviews). innovation is successfully done in a project, the efforts
The next three important problems are related to of former officer(s) may be left out of evaluation at the
constructability, in which lack of construction knowl- end of construction period because they may not be in
edge on the designer side and inadequate site investiga- charge anymore with the project. Hence, his/her succes-
tion were believed by many contractors to be sor will get the advantage/reward from the evaluation.
responsible for many of the problems. The problems (The rewards maybe promotion or praise.)
can also be explained from Fig. 1, in which site repre-
sentation attribute has the biggest difference in percep-
tion between designers and contractors. There are many 10. Impact of deficient design documents on
cases told during interviews, where contractors suffer construction process efficiency
from designs that are difficult or even impossible to be
built on site. The contractor’s questionnaire also asked the propor-
Considering only the frequency of occurrence, lack of tion (%) of poor performances from the total amount/
innovation was found to be the most critical issue. This value generally achieved on a project, which were con-
answer may perhaps confirm previous finding in Fig. 1 sidered as a direct result of design documents defi-
about the low ratings of life cycle cost and innovation ciencies. The poor performances taken into account
Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546 545

Fig. 7. Proportion of poor performance caused by defective design.

were rework, delays, cost overruns, changes, accidents, role of quality in design phase. In one designer’s words,
disputes and loss of profit. It should be noted that the ‘‘Recently, the condition of the consultant company is
loss of profit might be of interest because if defective really difficult to get over. Although we know that the
design occurred in a project it could lead to changes, quality of the design document is very important, we
and such changes may cause a ripple effect, in which a cannot afford to take control of it.’’ It would appear
contractor could lose money [18]. Fig. 7 summarizes the therefore, that the tenet ‘what you pay is what you get’ is
results. very appropriate when it comes to procuring design
Concurrent with the results discussed in other papers services.
[6,7], respondents believed that a significant proportion Despite the time and financial constraints, there are
of changes, i.e. almost 40%, originated from defective still many aspects within individual consultant compa-
design. However, the client does not always reimburse nies that need improvement. As observed in Fig. 5, all
all the costs of the changes. As seen in the answer for design practices were yet completely done. In fact, few
loss of profit, contractors said that about 29% of the of the suggestions expressed in the paper are novel. This
total loss was caused by defective design. This result should not be surprising since many of the designers’
also confirms the findings of two previous researches in problems stem not from a dearth of technical or man-
Japan about the compensation for defective design agement approaches, but rather from the failure to
[9,12]. Meanwhile defective design occupied about 30% integrate them into a coherent and consistent manage-
of total rework and cost overruns. ment strategy of design practice.
In long run, there will be slow changes to the current
situation due to, among other things, the procurement
11. Conclusions system in the public work construction in Japan, i.e.
separation between design and construction. Close
The defective design problems in Japanese construc- coordination between designers and contractors during
tion industry are both complex and deep rooted, influ- the design stage thus needs to be increased. This will
enced by many factors operating at individual designers, enhance the constructability, innovation and value
company, construction industry and global or national engineering aspects in design. Currently, all the aspects
levels. This paper has shown that significant and become consideration only at the end of the construc-
enduring improvements will occur when both designers tion contract. This is too late and more expensive! They
and clients realize these problems. should get more attention early during the design stage,
Based on the responses of the surveys it is believed i.e. conceptual design. In short, all of these are directed
that the reduction in the level of design fees together to implement the concept of ‘ability to influence’ in
with the limited time made available to carry out the practice by increasing awareness and ensuring an active
work have caused problems in the quality of design role for all players in the construction industry.
documents. Further, these problems have affected the While this paper has highlighted important causes for
efficiency of the construction process. deficiencies, it is found that the process of occurrence is
By reducing design fees to minimize costs, clients are not just that easy to understand. There are many com-
by their own actions contributing to the problems. Sav- plex relationships among the factors to be considered.
ing money at the expense of design can have a 100 to 1 The authors have looked further at this topic toward
negative impact on the ultimate life-cycle cost of the development of a mechanism for defective design cau-
project. The clients need to understand these realities sation. By developing such mechanism, understanding
and then cooperate with the designers to agree upon the of inherent influencing factors and, more importantly,
546 Andi, T. Minato / International Journal of Project Management 21 (2003) 537–546

their interactions becomes clearer and consequently [6] Kirby JG, et al. Improvements in design review management.
effort to reduce design defects turn to be more effective Journal of Construction Engineering and Management 1988;
114(1):69–82.
and efficient. This will be elucidated in forthcoming
[7] Lutz JD, et al. Framework for design-quality-review data-base
papers. system. Journal of Management in Engineering 1989;6(3):296–
312.
[8] Kartam NA, Kartam SA. Risk and its management in the
Acknowledgements Kuwaiti construction industry: a contractors’ perspective. Inter-
national Journal of Project Management 2001;19:325–35.
[9] Sawada M. A fundamental study of risk management in con-
The authors would like to express their sincere grati- struction projects—risk allocation between owners and con-
tude to Asian Development Bank—Japan for providing tractors for public works. Unpublished Master thesis, University
the financial support for the research and also Ministry of Tokyo, Japan; 2000 [In Japanese].
of Education of Japan through Grant-in-Aid No: [10] Kangari R. Risk management perceptions and trends of US
10305038. Many thanks to consultants and contractors construction. Journal of Construction Engineering and Manage-
ment 1995;121(4):422–9.
who kindly participated the survey and interviews. The [11] Ahmed SM. Risk management trends in Hong Kong construc-
authors are also very grateful to anonymous reviewers tion industry: a comparison of contractors and owners percep-
for their valuable comments to this paper. tions. Engineering, Construction and Architectural Management
1999;6(3):225–34.
[12] Anon. Impossible to be built design drawing. Nikkei Construc-
tion 2000;253:60–85 [in Japanese].
References [13] Tilley PA, McFallan SL. Design and documentation quality sur-
vey: designer’s perspective. Australia: CSRIO; 2000.
[1] Paulson BC. Designing to reduce construction costs. Journal of [14] Tilley PA, McFallan SL. Design and documentation quality sur-
the Construction Division 1976;102(CO4):587–92. vey: contractor’s perspective. Australia: CSRIO; 2000.
[2] McGeorge JF. Design productivity: a quality problem. Journal of [15] Matsushita F. Design and construction practice in Japan: a
Management in Engineering 1988;4(4):350–62. practical guide. Tokyo: Kaibunsha Ltd; 1994.
[3] Eldin NN. Management of engineering/design Phase. Journal of [16] Tilley PA et al. Design and documentation quality and its impact
Construction Engineering and Management 1991;117(1):163–75. on the construction process. CIB W55 & W65 Joint Triennial
[4] Vlatas DA. Owner and contractor review to reduce claims. Journal Symposium, Cape Town; 1999.
of Construction Engineering and Management 1986;112(1):104–11. [17] Anon. How to protect from recurrence errors. Nikkei Construc-
[5] Diekmann JE, Nelson MC. Construction claims: frequency and tion 2001;275:46–85 [in Japanese].
severity. Journal of Construction Engineering and Management [18] Gerwick and Woolery. Construction and engineering marketing
1985;111(1):74–80. for major project services. New York: John Wiley & Sons; 1983.

You might also like