You are on page 1of 10

International Journal of Construction Management

ISSN: 1562-3599 (Print) 2331-2327 (Online) Journal homepage: https://www.tandfonline.com/loi/tjcm20

Analysis of interaction among the factors affecting


delay in construction projects using interpretive
structural modelling approach

Abhishek Shrivas & Harish Kumar Singla

To cite this article: Abhishek Shrivas & Harish Kumar Singla (2020): Analysis of interaction among
the factors affecting delay in construction projects using interpretive structural modelling approach,
International Journal of Construction Management, DOI: 10.1080/15623599.2020.1728486

To link to this article: https://doi.org/10.1080/15623599.2020.1728486

Published online: 22 Feb 2020.

Submit your article to this journal

Article views: 5

View related articles

View Crossmark data

Full Terms & Conditions of access and use can be found at


https://www.tandfonline.com/action/journalInformation?journalCode=tjcm20
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT
https://doi.org/10.1080/15623599.2020.1728486

Analysis of interaction among the factors affecting delay in construction projects


using interpretive structural modelling approach
Abhishek Shrivas and Harish Kumar Singla
National Institute of Construction management and research, Pune, India

ABSTRACT KEYWORDS
This article identifies and analyse the critical factors affecting delay in construction projects in India and Interpretive structural
develops a model based on the mutual interaction of these factors using interpretive structural modelling modelling (ISM); cross-
approach. The article also identifies the ‘driving factors’ (i.e. the factors that influence the other factors) impact matrix multiplication
(MICMAC); delay;
and the ‘dependent factors’ (i.e. the factors that are influenced by others) using MICMAC analysis. Twelve construction; pro-
factors are identified as the most critical factors affecting delay through literature review and expert opin- ject management
ion. An ISM model is developed, with the help of five experts, (three from industry and two from aca-
demia). The findings of ISM suggest that lack of proper construction methodology and sequencing is the
root cause (i.e. driving factor) that is causing delay, hence at the bottom of the model. Lack of defined
project management plan, lack of proper contracting strategy, inter dependencies and evaluation of the
contractor not considered in advance and poor project monitoring, are intermediate causes positioned at
the middle of the model. Overlook of design review timelines, shortage of material, poor contract man-
agement, conflict between owners and other party, rework due to non-compliance in quality or poor
workmanship and poor site management and supervision are the dependent factors getting affecting by
level two factors as well have an interrelationship among themselves.

Introduction that if the delay problem in projects is controlled, it can lead to


improved productivity.
The construction industry has always remained a high risk and
Projects in any area of work are prone to delay, however, the
low margin industry (Jha and Devaya 2008). According to chances of delay is much higher in case of construction projects
KPMG’s 2015 global construction project owner’s survey, just as these projects are not executed in closed environment as in
25% of the projects came within ten percent of their original the case of manufacturing industry, rather the work is executed
deadlines in the past three years. According to Assaf and Al- in open site. Construction work involve creation of complex
Hejji (2006), ‘delay could be defined as the time overrun either structures such as dams, buildings, plants, bridges, roads, airports
beyond completion date specified in a contract, or beyond the to name a few. At the same time, delay should not be considered
date that the parties agreed upon for delivery of a project. It is a as usual or unavoidable. Delay as a problem must be addressed
project slipping over its planned schedule and is considered as by companies before it becomes huge and start affecting the cost,
common problem in construction projects’. Delay is also defined quality of work and relationships with stakeholders that may
as an ‘act or event which extends required time to perform or lead to disputes.
complete work of the contract manifests itself as additional days Knowing the importance of delay and how a delayed project
of work’ by Zack (2003). According to Mahamid et al. (2012), can lead to cost overruns and other issues, companies have
delay in construction projects is a universal phenomenon. Delays attempted to address this issue for long time now and this topic
happen to small and large projects in developing and developed has always been an area of active research for academicians.
nations, and are usually accompanied by cost overruns. Delay However, despite all efforts, the projects in India and across the
has a negative effect on all stakeholders of a project such as cli- globe are suffering from the issue of time overruns i.e. delay.
ent, contractor and consultant in terms of project progress, rela- The Indian construction industry contributes significantly to
tionships, communication among parties, and on financial the gross domestic product (appx. 6%), contributes 2.13% to
aspects, which sometimes may develop into serious disputes or exports and is one of the largest employment generators. The
legal battles in court (Semple et al. 1994; Yates and role of construction industry is ever increasing in India with
Epstein 2006). government of India setting huge targets for development of
Delay in any form leads to loss of revenue for client and infrastructure facilities like the development of smart cities, up-
excess cost of overheads for the contractor. In some cases, there gradation of existing railway stations, renovation of existing air-
is wastage and obsolesce of material due to delay. All in all, ports and development of green field airports, development of
delayed project delivery is not good for any stakeholder in the new cities, connecting major cities with metro rail for urban
construction projects. Kumaraswamy and Chan (1998) suggests transport etc. India has set an overwhelming goal of investing

CONTACT Harish Kumar Singla hsingla25@gmail.com


ß 2020 Informa UK Limited, trading as Taylor & Francis Group
2 A. SHRIVAS AND H. K. SINGLA

USD one trillion in infrastructure during the 12th five year plan project. Assaf et al. (1995) studied causes of delay and catego-
period (Source: MOSPI annual report 14–15, 16–17). The gov- rized them into nine major groups: financing, materials, contrac-
ernment is giving a lot of importance to infrastructure sector like tual relationships, changes, government relations, manpower,
they had never done before in the past. scheduling and control, equipment and environment. Bordoli
However, despite all efforts of government, the projects in India and Baldwin (1998) examined the factors affecting delay in
still suffer from problem of delay. Therefore, knowing how import- building projects in the United States and found that weather
ant the construction sector is to India, the authors have attempted conditions, labour supply and sub-contractors were the major
to undertake the study on understanding the interrelation among causes of delays. Satyanarayana and Iyer (1996) and Iyer and Jha
factors affecting delay in construction projects in India. (2005) highlighted the conflict between owners and other party
and poor site management and supervision were the factors
causing delay. Pickavance (2000) identified poor site manage-
Need and objective of the study ment as a major reason for delay. Frimpong et al. (2003) identi-
The construction sector is of immense importance to India and fied factors affecting delay for groundwater construction projects
knowing how delayed projects can cause a major bottleneck in in Ghana. Based on the survey responses and relative importance
the economic development of a country; the authors have weight (RIW) method they found that monthly payment difficul-
attempted to undertake this study. ties from agencies; poor contractor management; material pro-
The objectives of the study are twofold. At first authors want curement; poor technical performances; and escalation of
to identify the factors affecting delay in construction industry in material prices were factors affecting delay. Assaf and Al-Hejji
India. This is being done by authors through literature review (2006) did a field survey in Saudi Arabia to determine the causes
and expert opinion. Most of the studies in the past, which have of delay and their importance according to each of the project
undertaken similar work, have identified and ranked factors participants, i.e. the owner, consultant and the contractor. The
affecting delay in construction projects using the conventional field survey conducted included 23 contractors, 19 consultants
approaches like mean score, median, frequency index or relative and 15 owners. Based on the importance index 73 causes of
importance index (RII). However, very limited work has been delay were ranked. They found that shortage and low productiv-
done by researchers to find the interrelationship among these ity of labour and site management and supervision were the
factors affecting delay. Kalidindi (2016), found the interrelation- most critical factors affecting delay from contractors perspective.
ships of factors causing delays in the relocation of utilities using While, Aibinu and Odeyinka (2006) and Lo et al. (2006) sug-
a cognitive mapping approach. This cognitive mapping approach gested that site related delay factors such as extreme weather
is useful in finding the interrelationship among factors, but it conditions, unforeseen ground conditions and delays in provid-
does not explain about the driving and dependent factors. ing design information and rework due to non-compliance in
Interpretive structural model (ISM) along with MICMAC is an quality or poor workmanship leads to delay. Sambasivan and
approach that identifies both the driving and dependent factors Soon (2007), based on the survey identified ten most critical fac-
as well as has the potential to facilitate strategies to overcome tors causing delay namely contractor’s improper planning, con-
delays. Therefore, the authors have attempted to identify the tractor’s poor site management, inadequate contractor
interrelationship among factors affecting delay using ISM and experience, inadequate client’s finance and payments for com-
further used MICMAC to find the driving and dependent fac- pleted work, problems with subcontractors, shortage in material,
tors. This can help all the stakeholders of construction projects labour supply, equipment availability and failure, lack of commu-
to understand the root cause of the problem. nication between parties, and mistakes during the construction
The rest of the study is divided into five sections. In section stage. The study was conducted for Malaysian construction
one; previous studies that have identified factors affecting delay industry. Ernawati et al. (2007) found that in Malaysian con-
are discussed so as to come up with a comprehensive list of fac- struction industry the critical factors causing delay from contrac-
tors affecting delay in construction projects. The section is fol- tor’s side were financial problems, poor site management, delay
lowed by methodology adopted in the study. In section three, in the delivery of materials to the site, and coordination prob-
authors discuss about interrelationship among variables and why lem. All this leads to construction mistakes. El-Razek et al.
ISM methodology is better over other methods. In section four, (2008) identified the causes of delay based on literature review
the ISM framework is developed based on a pre discussed meth- and finally delivered a list of delay causes which were appropri-
odology followed by section five which concludes the article and ate to building construction projects in Egypt. They used expert
discusses the implications of this for construction sector. opinion of five experts to arrive at this list. Kaliba et al. (2009)
found that the major causes of delays in construction projects in
road construction projects in Zambia were delayed payments,
Literature review financial deficiencies on the part of the client or the contractor,
The importance of delay in construction projects and the factors contract modifications, economic problems, material procure-
affecting delay are explored by many researchers in the past. The ment problems, changes in design drawings, staffing problems,
authors reviewed 25 recent articles and based on the review, unavailability of equipment, poor supervision, construction mis-
identified most important factors that are affecting delay in con- takes, poor coordination on site, changes in specifications, labour
struction projects. Few articles dates back to 1994, but the disputes and strikes. Fugar and Agyakwah-Baah (2010) named
authors have mostly relied on the recent work on delay in delay in honouring certificates, underestimation of cost of pro-
construction. ject, poor project management plan, shortage of material and 32
Mansfield et al. (1994) studied the causes of delay and cost other factors as contributors to delay. Haseeb et al. (2011) cited
overruns by taking client, consultant and contractors into con- 37 factors that cause delay and their effects on the success and
sideration and found that shortage of material, poor project completion of project. Haseeb et al. (2011) grouped these factors
monitoring and control and poor contract management were the into seven categories. The most common factors of delay were
most important items agreed by all three three stakeholders of a natural disaster, financial and payment problems, improper
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 3

planning, poor site management, insufficient experience and site were the prime factors followed by price increases in materi-
shortage of materials. als and late design and design documents to name a few.
Doloi et al. (2012) identified 45 critical factors affecting delay Most of the articles reviewed by authors have used survey
in construction projects in India. Based on the factor analysis, based approach to collect data from respondents and used RII as
they reduced these to seven factors namely lack of commitment, a major tool to rank the critical factors for delay. In some cases
inefficient site management, poor site coordination, improper frequency index and risk weighted analysis were also used to
planning, lack of clarity in project scope, lack of communication rank the critical factors. Several researches have extended the
and Sub-standard contract. They used RII to rank these factors. work beyond finding the critical factors for delay and have dis-
Aziz (2013) did a study on Egyptian construction projects cussed about the effects of those factors on the success or failure
and used RII approach for ranking the causes of delay. He iden- of the project. The articles in the past have also categorized the
tified that delay in approving major changes in scope of work by factors affecting delay on the basis of stakeholders, nature of
consultant was very critical factor that cause delay. Ineffective work and stage of work. However, except for work done by
project planning and scheduling was identified as a major con- Kalidindi (2016), authors did not come across any study that dis-
tractor related factor and design changes by owner or his agent cussed the interrelationship among critical factors affecting delay.
during construction was identified as a design related factor. Researchers in the past, have mostly worked on the assumption
Marzouk and El-Rasas (2014) in Egyptian construction projects that factors causing delay are mutually exclusive, hence there is
found that projects are suffering delay due to ineffective planning no need to examine the interrelationship amongst them.
and scheduling of project, difficulties in financing project by However, this assumption may not be valid in all cases, hence,
contractor, variation orders/changes of scope by owner during authors in the present study attempted to examine and explore
construction, poor site management and supervision, type of the interrelationship amongst factors causing delay.
project bidding and award (negotiation, lowest bidder), low
productivity level of labours, effects of subsurface conditions (e.g.
soil, high water table, etc.), unqualified workforce, shortage of Research methodology
construction materials in market, and delays in sub-contractors Authors identified 56 critical factors based on the literature
work. These factors were identified from owner’s point of view. review and than a panel of experts critically examined each of
The article also talks about the factors from the consultants and these (56) factors causing delay. They reduced these factors caus-
contractors view and used ANOVA to find the difference in the ing delay to 12, identified as the most critical factors. The meth-
three views. odology followed is similar to the one followed by El-Razek et al.
Enshassi et al. (2010) did a questionnaire survey in Palestine (2008). The panel of experts were interviewed with semi struc-
and found that strikes, border closures, lack of materials in mar- ture questions. The questions framed for experts were like ‘Do
kets, shortage of construction materials at site, delay of material you think, from your expert opinion, this factor affects delay in
delivery to site, cash-flow problems during construction, and construction projects in India’, ‘is there any other factor which
poor site management were the most significant factors affecting you would like to add based on your expert opinion’ and ‘are
delay. These factors were ranked based on the importance index. there any factors that have similar meaning and you would like
Khoshgoftar et al. (2010) in a similar study ranked 28 critical to group them as one based on your expert opinion’.
factors affecting delay using RII. The factors that were the most The panel of experts which facilitated the process included
critical as per RII were financial problems, poor site manage- two experts from academia having a teaching and research
ment, improper planning, contract problems, lack of communi- experience of more than 20 years in the field of construction
cation between parties and inadequate experience. Santoso and management. Three experts were from construction industry
Soeng (2016) analysed the delay factors in road construction working with construction companies and handling complex
projects in Cambodia and found that poor site arrangement, projects and had a work experience of more than 25 years in
management and supervision; and poor qualifications of the con- India and abroad. The final list of 12 factors affecting delay is
tractor technical staff and project team and frequent equipment given below.
breakdown were some of the key factors. Aziz and Abdel-Hakam 1. Lack of defined project management plan
(2016) studied factors causing delay for road construction proj- 2. Lack of proper contracting strategy
ects in Egypt using a questionnaire survey and RII approach and 3. Lack of proper construction methodology and sequencing
found that financial problems, shortages in equipment, construc- 4. Interdependencies and evaluation of the contractor not
tion materials, skilled operators, inadequate experiences, reworks, considered in advance
changes or errors in design, delays in design submittal, soil and 5. Overlook of design review timelines
underground problems in investigation or management or 6. Shortage of material
expropriation, physical obstructions were some of the reasons for 7. Poor project monitoring and control
delay. Kalidindi (2016) identified the factors that cause delay in 8. Poor contract management
the relocation of utilities on 11 road and bridge projects in 9. Extreme weather conditions
India. Slow response from utility agencies, difficulty in identifica- 10. Conflict between owners and other party
tion of underground utilities, lack of information on under- 11. Rework due to non-compliance in quality or poor
ground utilities and conflict between agencies were some of the workmanship
critical factors affecting delay. Initial level factors were identified 12. Poor site management and supervision
through literature review. Later, Kalidindi (2016) used cognitive In order to accomplish the second objective of the study i.e.
mapping approach to find the interrelationships among these to find the interrelationship among the critical factors, the
factors. In a recent research, Gebrehiwet and Luo (2017) ranked authors used ISM approach. ISM is an expert opinion based
52 factors affecting delay using RII and found that in Ethiopian approach, and the same experts who came up with a final list of
construction projects, corruption and unavailability of utilities at 12 factors affecting delay helped in creation of ISM framework.
4 A. SHRIVAS AND H. K. SINGLA

Figure 1. Flow diagram for preparing the ISM model.


Source: Self generated.

The reason for choosing ISM approach over others is discussed supply chain. Fuzzy cognitive maps is a modelling technique,
in section three. arising from the combination of fuzzy logic and neural networks
In ISM approach experts were asked to brainstorm and come (Groumpos 2015). Fuzzy cognitive maps model is a general
up with a structural self-interaction matrix (SSIM), which was model for the cause-effect phenomenon, which is taken from
prepared based on a set of rules. While there is no criteria as to cognitive maps model (Kosko 1986). On the other hand, ISM
how many experts should be used for development of SSIM shows the relationship between the variables of a complex system
matrix, studies in the past, have used three to five experts to (Huang et al. 2005), which can be used to analyze the effect of
come up with SSIM matrix. While developing SSIM, the context- one variable over the others. Interpretive structural modelling is
ual relationship of each variable, the existence of a relation defined as a process that transforms unclear and poorly articu-
between any two enablers (i and j) and the associated direction lated mental models of systems into visible, well-defined models
of the relation is questioned. In this article, four symbols are useful for various purposes (Sushil 2012). Agarwal et al. (2007)
used to denote the direction of the relationship between the ena- states that ISM model combines three modelling languages i.e.
blers (i and j). If i affects j but does not get affected by j, the discrete words, diagrams and mathematics and therefore is better
relationship is symbolized as V, if i does not affect j, but get in terms of providing graphical representation of complex prob-
affected by j, the relationship is symbolized as A, if both i and j lems. The approach is easy to understand for different users in
affect each other, the relationship is symbolized as X and if both interdisciplinary groups. It’s a tool to integrate different percep-
i and j are independent and do not affect each other, the rela- tions and provide a system. ISM is seen as a useful tool that
tionship is symbolized as O. The experts came up with an SSIM deals with complex issues with logical thinking and then com-
matrix after a brainstorming session. The whole flow chart of municates the results. It is much more flexible than many con-
ISM approach is shown in Figure 1. ventional quantitative modelling approaches that require
variables to be measured on ratio scales. It offers a qualitative
model by structuring complexity on an issue through building
Use of interpretive structural model (ISM) approach to
an agreed structural model (Panackal and Singh 2015). ISM is an
study the interrelationships among factors
interactive learning process in which a set of dissimilar and dir-
As noted in the objectives of the study, the article aims to find ectly related elements are structured into a comprehensive sys-
the interrelationship among factors affecting delay in construc- tematic model. The model so formed, portrays the structure of a
tion projects in India. There are quantitative methods such as complex issue or problem, a system or a field of study, in a care-
structural equation modelling that can be used to find the inter- fully designed pattern implying graphics as well as words. The
relationship among variables based on the secondary data or basic idea of ISM is to use experts’ practical experience and
data generated through survey. knowledge to construct a multilevel structural model (Warfield
Cognitive mapping approach and word frequency analysis can 1973; Sage 1977). Considering the advantages of ISM, authors
also be used for the same, which are software based approaches. decided to use ISM approach in the study. ISM has been used
Kalantari and Khoshalhan (2017) used hybrid/mixed model along with Matriced’ Impacts Croise’s Multiplication Appliquee
approach by using both fuzzy cognitive maps and interpretive a UN Classement (MICMAC) analysis as a prevailing tool in
structural modelling to study the readiness assessment of leagility most of the complex situations involving modelling of critical
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 5

Table 1. SSIM matrix. Table 2. Initial reachability matrix.


I J! 12 11 10 9 8 7 6 5 4 3 2 1 I J! 1 2 3 4 5 6 7 8 9 10 11 12
# #
1 V V O O V V O X A A X V 1 1 1 0 0 1 0 1 1 0 0 1 1
2 O O V O X O O O V O V 2 1 1 0 1 0 0 0 1 0 1 0 0
3 V V V O O V V O O V 3 1 0 1 0 0 1 1 0 0 1 1 1
4 V O V O X O O O V 4 1 0 0 1 0 0 0 1 0 1 0 1
5 O O X O V A V V 5 1 0 0 0 1 1 0 1 0 1 0 0
6 O O V O O O V 6 0 0 0 0 0 1 0 0 0 1 0 0
7 A V V O O V 7 0 0 0 0 1 0 1 0 0 1 1 0
8 O O V O V 8 0 1 0 1 0 0 0 1 0 1 0 0
9 O V O V 9 0 0 0 0 0 0 0 0 1 0 1 0
10 X O V 10 0 0 0 0 1 0 0 0 0 1 0 1
11 X V 11 0 0 0 0 0 0 0 0 0 0 1 1
12 V 12 0 0 0 0 0 0 1 0 0 1 1 1
Source: Self generated with the help of expert opinion. Source: Self generated.

success factors (CSFs), key variables, enablers, inhibitors or bar- Table 3. Final reachability matrix after transitivity.
riers in different areas (Jena et al. 2017). The ISM has been used
I J! 1 2 3 4 5 6 7 8 9 10 11 12 Driving
to find the mutual relationship among the critical variables for # variables
the implementation of knowledge management in engineering
1 1 1 0 1a 1 1a 1 1 0 1a 1 1 10
industries (Singh et al. 2003); modelling for main barriers of 2 1 1 0 1 1a 1a 1a 1 0 1 1a 1a 10
reverse logistics in automobile industries (Ravi and Shankar 3 1 1a 1 1a 1a 1 1 0 0 1 1 1 10
2005); product design (Lin et al. 2006); supply chain manage- 4 1 1a 0 1 1a 0 1a 1 0 1 1a 1 9
ment (Agarwal et al. 2007; Charan et al. 2008); value chain man- 5 1 1a 0 1a 1 1 0 1 0 1 0 1a 8
6 0 0 0 0 1a 1 0 0 0 1 0 1a 4
agement (Mohammed et al. 2008); modelling for key enablers of 7 1a 1a 0 1a 1 1a 1 1a 0 1 1 1a 10
six sigma (Soti et al. 2010); modelling for improvement in service 8 0 1 0 1 1a 0 0 1 0 1 0 1a 6
quality of technical education (Debnath and Shankar 2012); 9 0 0 0 0 0 0 0 0 1 0 1 1a 3
information security management for Indian organizations’ rela- 10 1a 1a 0 1a 1 1a 1a 1a 0 1 1a 1 10
11 0 0 0 0 0 0 1a 0 0 1a 1 1 4
tionship model (Chander et al. 2013) and hierarchical inter-rela-
12 1a 1a 0 1a 1a 1a 1 1a 0 1 1 1 10
tionships among the critical success factors for a smart phone Dependent variable 8 9 1 9 10 8 8 8 1 11 9 12
manufacturing system (Jena et al. 2016). a
Indicate transitivity.
Source: Self generated.

Data analysis using ISM factor itself and other factors, which may help achieving it. The
intersection of these two sets named as intersection set (Digalwar
The experts, based on the set of rules provided to them (dis-
and Giridhar 2015), as shown in Table 4–6. If intersection set is
cussed in the research methodology section) to prepare SSIM,
same as the reachability set, factors are placed at the top level.
came up to the consensus and gave a SSIM, which is presented
in Table 1. The top level factors satisfying the above condition are removed
The interpretations of the identified relationships have been from the element set for further calculation and the exercise is
used as the basis to form the initial reachability matrix. This is repeated iteratively till all the levels are determined. These levels
done by replacing V, A, X and O by 1 and 0 in accordance with help in building the diagraph and the ISM model (Sushil 2012).
the VAXO rules. Tables 4–6, show three iterations that took place in the article,
 If the entry of (i,j) in the SSIM is ‘V’, then enter the value which means that there are three levels in the model.
of the element (i,j) as ‘1’ and subsequently (j,i) as ‘0’ in the From the above Tables 4–6, we can observe that overlook of
initial reachability matrix design review timelines (5), shortage of material (6), poor con-
 If the entry of (i,j) in the SSIM is ‘A’, then enter the value tract management (8), conflict between owners and other party
of the element (i,j) as ‘0’ and subsequently (j,i) as ‘1’ in the (10), rework due to non-compliance in quality or poor work-
initial reachability matrix manship (11) and poor site management and supervision (12)
 If the entry of (i,j) in the SSIM is ‘X’, then enter the value are top level factors; hence these will be placed at the top in the
of the element (i,j) as ‘1’ and subsequently (j,i) as ‘1’ in the diagraph. At level two, there are five factors namely lack of
initial reachability matrix defined project management plan (1), lack of proper contracting
 Finally, if the entry of (i,j) in SSIM is ‘O’, then enter the strategy (2), interdependencies and evaluation of the contractor
value of the element (i,j) as ‘0’ and subsequently (j,i) as ‘0’ not considered in advance (4), poor project monitoring and con-
in the initial reachability matrix. (Panackal and Singh 2015) trol (7) and extreme weather conditions (9). At level three, only
(Table 2). one factor i.e. lack of proper construction methodology and
Based on the initial reachability matrix, a final reachability sequencing (3) is placed. The level indicates the importance of
matrix is prepared following the principal of transitivity. factors. The bottom level factors are most important and root
Transitive relationship is one where, if an element ‘a’ is related cause to the real problem.
to an element ‘b’ and ‘b’ is related to an element ‘c’ then ‘a’ is On the basis of the level positioning obtained and final reach-
also related to ‘c’ (Table 3). ability matrix, a conical matrix (lower triangular matrix) is con-
From the final reachability matrix, the reachability and ante- structed (Table 7). A conical matrix is simply arrangement of the
cedent set for each enabler is obtained (Warfield 1973). The factors of final reachability matrix in a sequential manner based
reachability set consists of the factor itself and other factors, which on the levels identified. The conical matrix is used to define the
it may help achieve, whereas the antecedent set consists of the relationship among factors.
6 A. SHRIVAS AND H. K. SINGLA

Table 4. Level identification (Iteration I). The final graphical model is constructed based on the level
Ij Reachability set Antecedent set RS\AS Level identified in Table 4–6 and the relationship among factors is
1 1,2,4,5,6,7,8,10,11,12 1,2,3,4,5,7,10,12 1,2,4,5,7,10,12 defined based on the conical matrix (Talib et al. 2011) as shown
2 1,2,4,5,6,7,8,10,11,12 1,2,3,4,5,7,8,10,12 1,2,4,5,7,8,10,12 in Figure 2.
3 1,2,3,4,5,6,7,10,11,12 3 3 Three levels have been identified and the Figure 2 is showing
4 1,2,4,5,7,8,10,11,12 1,2,3,4,5,7,8,10,12 1,2,4,5,7,8,10,12
5 1,2,4,5,6,8,10,12 1,2,3,4,5,6,7,8,10,11,12 1,2,4,5,6,8,10,12 I
all the three levels where lack of proper construction methodology
6 5,6,10,12 1,3,5,6,7,10,12 5,6,10,12 I and sequencing (3) is placed at the bottom and is affecting lack of
7 1,2,4,5,6,7,8,10,11,12 1,2,3,4,7,10,11,12 1,2,4,7,10,11,12 defined project management plan (1), lack of proper contracting
8 2,4,5,8,10,12 1,2,4,5,7,8,10,12 2,4,5,8,10,12 I strategy (2), interdependencies and evaluation of the contractor
9 9,11,12 9 9
10 1,2,4,5,6,7,8,10,11,12 1,2,3,4,5,6,7,8,10,11,12 1,2,4,5,6,7,8,10,11,12 I
not considered in advance (4) and poor project monitoring and
11 7,10,11,12 1,2,3,4,7,9,10,11,12 7,10,11,12 I control. In middle, five factors, lack of defined project manage-
12 1,2,4,5,6,7,8,10,11,12 1,2,3,4,5,6,7,8,9, 10,11,12 1,2,4,5,6,7,8,10,11,12 I ment plan (1), lack of proper contracting strategy (2); interdepen-
Source: Self generated. dencies and evaluation of the contractor not considered in
advance (4), poor project monitoring and control (7) and extreme
weather conditions (9) are placed. The factors in the middle are
Table 5. Level identification (Iteration II). intermediate as they are affecting others as well as getting affected
Ij Reachability set Antecedent set RS\AS Level by others. Overlook of design review timelines (5), shortage of
1 1,2,4,5,6,7,8,10,11,12 1,2,3,4,5,7,10,12 1,2,4,5,7,10,12 II material (6), poor contract management (8), conflict between
2 1,2,4,5,6,7,8,10,11,12 1,2,3,4,5,7,8,10,12 1,2,4,5,7,8,10,12 II owners and other party (10), rework due to non-compliance in
3 1,2,3,4,5,6,7,10,11,12 3 3
quality or poor workmanship (11) and poor site management and
4 1,2,4,5,7,8,10,11,12 1,2,3,4,5,7,8,10,12 1,2,4,5,7,8,10,12 II
7 1,2,4,5,6,7,8,10,11,12 1,2,3,4,7,10,11,12 1,2,4,7,10,11,12 II supervision (12) are the factors placed at the top, as these factors
9 9,11,12 9 9 II are affected by others but do not influence others.
Source: Self generated. ISM fuzzy MICMAC analysis is performed to confirm the
findings of proposed ISM model. The MICMAC analysis stands
for Cross-Impact Matrix Multiplication Applied to the
Table 6. Level identification (Iteration III).
Classification analysis. The MICMAC analysis works on the
principle of multiplication properties of matrices (Kannan et al.
Ij Reachability set Antecedent set RS\AS Level
2009). The purpose of performing MICMAC analysis is to ana-
3 1,2,3,4,5,6,7,10,11,12 3 3 III
lyze the dependence and driving power of inhibitors (Mandal
Source: Self generated. and Deshmukh 1994; Wakchaure and Jha 2011). It is basically
performed for identifying inhibitors, which are responsible to
Table 7. Conical matrix.
drive the whole system. It is a technique to represent inhibitors
graphically into four clusters (Jena et al. 2017) namely autono-
Factors 5 6 8 10 11 12 1 2 4 7 9 3
mous, dependent, linkage and driving cluster.
5 1 1 1 1 0 1 0 0 0 0 0 0
Table 8 highlights each variable with its driving and depend-
6 1 1 0 1 0 1 0 0 0 0 0 0
8 1 0 1 1 0 1 0 0 0 0 0 0 ent power.
10 1 1 1 1 1 1 0 0 0 0 0 0 Based on Table 8, a MICMAC matrix is prepared. The matrix
11 0 0 0 1 1 1 0 0 0 0 0 0 is divided into four clusters. The factors placed in cluster one are
12 1 1 1 1 1 1 0 0 0 0 0 0 called autonomous variables. They indicate a weak driving power
1 1 1 1 1 1 1 1 1 1 1 0 0
2 1 1 1 1 1 1 1 1 1 1 0 0 and subsequently a weak dependence power. These variables are
4 1 0 1 1 1 1 1 1 1 1 0 0 disconnected from the system. They are not linked to other fac-
7 1 1 1 1 1 1 1 1 1 1 0 0 tors and are independent in the system (Jena et al. 2017). An
9 0 0 0 0 1 1 0 0 0 0 1 0 extreme weather condition (9) is the only factor that is placed in
3 1 1 0 1 1 1 1 1 1 1 0 1
this cluster. In cluster two, those factors are placed that have
Source: Self generated. strong dependence power. These factors are influenced by other
factors but do not influence others (Jena et al. 2017). Shortage of

Figure 2. Model depicting relation among variables based on ISM.


Source: Self generated.
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 7

Table 8. Driving and dependent variables for MICMAC analysis.


Factors Dependent Variables Driving Variables
Lack of defined project management plan (1) 8 10
Lack of proper contracting strategy (2) 9 10
Lack of proper construction methodology and sequencing (3) 1 10
Inter dependencies and evaluation of the contractor not considered in advance (4) 9 9
Overlook of Design review timelines (5) 10 8
Shortage of material (6) 8 4
Poor project monitoring and control (7) 8 10
Poor contract management (8) 8 6
Extreme weather conditions (9) 1 3
Conflict between owners and other party (10) 11 10
Rework due to non-compliance in quality or poor workmanship (11) 9 4
Poor site management and supervision (12) 12 10
Source: Self generated.

Figure 3. Graph of MICMAC Analysis.


Source: Self generated.

material (6), poor contract management (8) and rework due to Conclusion and discussion
non-compliance in quality or poor workmanship (11), are the fac-
tors that are placed in this cluster, meaning they have strong The article initially identified 12 most critical factors affecting
dependent power. The factors that are placed in cluster three are delay of construction projects in India based on literature review
known to have a strong driving and strong dependence power. and expert opinion. Later based on the expert opinion, an ISM
The factors are unstable; any action on these variables will have model is developed along with MICMAC matrix. Looking at
an effect on others and a feedback effect on themselves. They are MICMAC matrix and ISM model (Figure 2 and 3) collectively,
the connecting link among factors (Jena et al. 2017). Lack of authors found mixed results. According to ISM model, lack of
defined project management plan (1), lack of proper contracting proper construction methodology and sequencing (3) is placed at
strategy (2), interdependencies and evaluation of the contractor the bottom level, which implies that this factor has influence
not considered in advance (4), overlook of design review timelines over others but does not get affecting by others. The same is
(5), poor project monitoring and control (7), conflict between confirmed through MICMAC analysis as this factor is placed in
owners and other party (10) and poor site management and cluster four, which indicate the same. This factor can be identi-
supervision (12) are the factors placed in this cluster. Finally the fied as the root cause of many problems and any change in this
factors that have a strong driving power are placed in forth quad- can lead to a cascading effect. Lack of proper construction meth-
rant. They drive other factors but are not influenced by others. odology and sequencing is influencing the lack of defined project
Lack of proper construction methodology and sequencing (3) is management plan (1), lack of proper contracting strategy (2),
the only factor placed in this quadrant. interdependencies and evaluation of the contractor not
8 A. SHRIVAS AND H. K. SINGLA

considered in advance (4) and poor project monitoring and con- Aziz R. 2013. Ranking of delay factors in construction projects after Egyptian
trol (7) but it does not have a relationship with extreme weather revolution. Alex Eng J. 52(3):387–406.
Aziz RF, Abdel-Hakam AA. 2016. Exploring delay causes of road construc-
conditions (9) as shown in Figure 2. There are also interrelation- tion projects in Egypt. Alex Eng J. 55(2):1515–1539.
ship among the level two factors as shown in Figure 2. These Bordoli DW, Baldwin AN. 1998. A methodology for assessing construction
findings also confirm to MICMAC analysis as lack of defined project delays. J Constr Manage Eng. 16(3):327–337.
project management plan (1), lack of proper contracting strategy Chander M, Jain SK, Shankar R. 2013. Modeling of information security
(2), interdependencies and evaluation of the contractor not con- management parameters in Indian organizations using ISM and
MICMAC approach. J Model Manage. 8(2):171–189.
sidered in advance (4) and poor project monitoring and control Charan P, Shankar R, Baisya RK. 2008. Analysis of interactions among the
(7) are placed in cluster three indicating they are linkage varia- variables of supply chain performance measurement system implementa-
bles. Lack of proper construction methodology and sequencing tion. Bus Process Manage J. 14(4):512–529.
does not affect extreme weather conditions as extreme weather Debnath RM, Shankar R. 2012. Improving service quality in technical educa-
tion: use of interpretive structural modeling. Q Assur Edu. 20(4):387–407.
conditions (9) is an autonomous factor and almost disconnected Dewangan DD, Agrawal R, Sharma V. 2015. Enablers for competitiveness of
to the entire system. Overlook of design review timelines (5), Indian manufacturing sector: an ISM-fuzzy MICMAC analysis. Proc
shortage of material (6), poor contract management (8), conflict Social Behav Sci. 189:416–432..
between owners and other party (10), rework due to non-compli- Digalwar AK, Giridhar G. 2015. Interpretive structural modeling approach
ance in quality or poor workmanship (11) and poor site manage- for development of electric vehicle market in India. Proc CIRP. 26:40–45..
Doloi H, Sawhney A, Iyer KC, Rentala S. 2012. Analysing factors affecting
ment and supervision (12) are placed at the top of ISM model delays in Indian construction projects. Int J Project Manage. 30(4):479–489.
indicating that these factors get influenced level two and level El-Razek AME, Bassioni HA, Mobarak AM. 2008. Causes of delay in building
three factors but does not influence over others. These findings construction projects in Egypt. J Constr Eng Manage. 134:831–841.
are in little contradiction to MICMAC findings as according to Enshassi A, Kumaraswamy M, Al-Najjar J. 2010. Significant Factors Causing
MICMAC only shortage of material (6), poor contract manage- Time and Cost Overruns in Construction Projects in the Gaza Strip: con-
tractors’ perspective. Int J Constr Manage. 10(1):35–60.
ment (8) and rework due to non-compliance in quality or poor Ernawati S, Mohd A, Razali A, Azizah K. 2007. The significant factors caus-
workmanship (11) are the factors that are dependent whereas ing delay of building construction projects in Malaysia. Eng Constr
overlook of design review timelines (5), conflict between owners Architect Manage. 14(2):192–206.
and other party (10) and poor site management and supervision Frimpong Y, Oluwoye J, Crawford L. 2003. Causes of delay and cost over-
runs in construction of groundwater projects in a developing countries:
(12) are linkage variables. Ghana as a case study. Int J Project Manage. 21(5):321–326.
The article is an attempt to provide an insight to academia Fugar FD, Agyakwah-Baah AB. 2010. Delays in building construction proj-
and practitioners about the interrelationship among the critical ects in Ghana. AJCEB. 10(1/2):103–116.
factors affecting delay in construction projects. A conceptual Gebrehiwet T, Luo H. 2017. Analysis of delay impact on construction project
framework is developed that helps understand the inter-relation- based on rii and correlation coefficient: empirical study. Proc Eng. 196:
366–374.
ships among the critical factors affecting delay in construction Groumpos PP. 2015. Modelling business and management systems using
projects. This article can serve as a base to the project managers fuzzy cognitive maps: a critical overview. IFAC-Papers on Line. 48(24):
working on construction projects, to understand the inter- 207–212.
relationships and interdependencies among the critical factors Haseeb M, Lu X, Bibi A, Dyian M, Rabbani W. 2011. Problems of projects
for delay. The proposed ISM can be useful in understanding the and effects of delays in the construction industry of Pakistan. Aust J Bus
Manage Res. 1(5):41–50.
critical factors as well as the push pull effect of the factors on Huang J, Tzeng G, Ong C. 2005. Multidimensional data in multidimensional
each other. This article can serve as a base to researchers for fur- scaling using the analytic network process. Pattern Recog Lett. 26(6):
ther research in the field to empirically test the proposed model. 755–767.
The ISM method has many advantages, but it also has a few Iyer KC, Jha KN. 2005. Factors affecting cost performance: evidence from
Indian construction projects. Int J Project Manage. 23(4):283–295.
limitations. The major limitation of ISM is that the relationship Jena J, Fulzele V, Gupta R, Sherwani F, Shankar R, Sidharth S. 2016. A TISM
among the variables totally depends upon the expert’s knowledge modeling of critical success factors of smartphone manufacturing ecosys-
and their experience within their industries. Therefore, prejudice tem in India. J Adv Manage Res. 13(2):203–224..
of the one who is judging the variables might manipulate the Jena J, Sidharth S, Thakur LS, Pathak DK, Pandey VC. 2017. Total
final result. (Dewangan et al. 2015). Interpretive Structural Modeling (TISM): approach and application. J Adv
Manage Res. 14(2):162–224. http://dx.doi.org/10.1108/JAMR-10-2016-
Despite the inherent limitation of ISM, the study contributes 0087.
significantly to the body of knowledge by suggesting a model Jha NK, Devaya MN. 2008. Modelling the risks faced by Indian construction
that highlights the interrelationship among those factors affecting companies assessing international projects. Constr Man Econ. 26(4):
delay. The proposed model can be put to test and modified in 337–348. http://dx.doi.org/10.1080/01446190801953281.
the future studies. Kalantari T, Khoshalhan F. 2017. Readiness assessment of leagility supply
chain based on fuzzy cognitive maps & interpretive structural modeling: a
case study. J Bus Indus Market. 33(4):442–456..
Kaliba C, Muya M, Mumba K. 2009. Cost escalation and schedule delays in
Disclosure statement road construction projects in Zambia. Int J Project Manage. 27(5):
522–531.
No potential conflict of interest was reported by the author(s). Kalidindi AVSN. 2016. Interrelationships of factors causing delays in the
relocation of utilities. Eng Constr Architect Manage. 23(3):349–368.
http://dx.doi.org/10.1108/ECAM-10-2014-0127.
References Kannan G, Pokharel S, Kumar SP. 2009. A hybrid approach using ISM and
fuzzy TOPSIS for the selection of reverse logistics provider. Resour
Agarwal A, Shankar R, Tiwari MK. 2007. Modeling agility of supply chain. Conserv Recycl. 54(1):28–36.
Indus Market Manage. 36(4):443–457. Khoshgoftar M, Bakar AHA, Osman O. 2010. Causes of delays in Iranian
Aibinu AA, Odeyinka HA. 2006. Construction delays and their causative fac- construction projects. Int J Constr Manage. 10(2):53–69.
tors in Nigeria. J Constr Eng Manage. 132(7):667–677. Kosko B. 1986. Fuzzy cognitive maps. Int J Man-Mach Stud. 24(1):65–74.
Assaf SA, Al-Hejji S. 2006. Causes of delay in large construction projects. Int Kumaraswamy M, Chan D. 1998. Contributors to construction delay. Constr
J Project Manage. 24(4):349–357. Manage Econ. 16(1):17–29.
Assaf SA, Al-Khalil M, Al-Hazmi M. 1995. Causes of delays in large building Lin MC, Wang CC, Chen TC. 2006. A strategy for managing customer-ori-
construction projects. ASCE J Manage Eng. 11(2):45–50. ented product design. Concurrent Eng. 14(3):231–244.
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT 9

Lo TY, Fung IWH, Tung KCF. 2006. Construction delays in Hong Kong civil Satyanarayana KN, Iyer KC. 1996. Evaluation of delays in Indian construc-
engineering projects. J Constr Eng Manage. 132(6):636–649. tion contracts. J Inst Eng (India). 77:14–22.
Mahamid I, Bruland A, Dmaidi N. 2012. Causes of delay in road construc- Semple C, Hartman FT, Jergeas G. 1994. Construction claims and disputes:
tion projects. J Manage Eng. 28(3):300–310. causes and cost/time overruns. J Constr Eng Manage. 120(4):785–795.
Mandal A, Deshmukh SG. 1994. Vendor selection using interpretive struc- Singh MD, Shankar R, Narain R, Agarwal A. 2003. An interpretive structural
tural modeling (ISM). Int J Op Prod Manage. 14(6):52–59. modeling of knowledge management in engineering industries. J Adv
Mansfield N, Ugwu O, Doran T. 1994. Causes of delay and cost overruns in Manage Res. 1(1):28–40.
Nigerian construction projects. Int J Project Manage. 12(4):254–260. Soti A, Shankar R, Kaushal OP. 2010. Modeling the enablers of Six Sigma
Marzouk MM, El-Rasas TI. 2014. Analyzing delay causes in Egyptian con- using interpreting structural modeling. J Model Manage. 5(2):124–141.
struction Projects. J Adv Res. 5(1):49–55. Sushil. 2012. Interpreting the interpretive structural model. Global J Flexi
Mohammed IR, Shankar R, Banwet DK. 2008. Creating Flex-lean-agile value Syst Manage. 13(2):87–106.
chain by outsourcing: an ISM based interventional roadmap. Bus Process Talib F, Rahman Z, Qureshi MN. 2011. Analysis of interaction among the
Manage J. 14(3):338–389. barriers to total quality management implementation using interpretive
Panackal N, Singh A. 2015. Using interpretive structural modeling to deter- structural modeling approach. Benchmarking. 18(4):563–587..
mine the relation between youth and sustainable rural development. Wakchaure SS, Jha KN. 2011. Modeling of post-construction failure factors
IBMRD’s J Manage Res. 4:58–74. of bridges. J Adv Manage Res. 8(2):246–262.
Pickavance K. 2000. Delay and disruption in construction contracts. 2nd ed. Warfield JN. 1973. An assault on complexity. Battelle monograph no 3.
London (UK): Sweet & Maxwell. Columbus (OH): Battelle Memorial Institute.
Ravi V, Shankar R. 2005. Analysis of interactions among the barriers of Yates J, Epstein A. 2006. Avoiding and minimizing construction delay claim
reverse logistics. Technol Forecast Social Change. 72(8):1011–1029. disputes in relational contracting. J Prof Issues Eng Educ Pract. 132(2):
Sage A. 1977. Interpretive structural modelling: methodology for large scale 168–179.
systems. New York: McGraw-Hill. Zack JG. 2003. Schedule delay analysis; is there agreement? In: Proceedings,
Sambasivan M, Soon YW. 2007. Causes and effects of delays in Malaysian PMI-CPM College of Performance Spring Conference, Project
construction industry. Int J Project Manage. 25(5):517–526. Management Institute—College of Performance Management, New
Santoso DS, Soeng S. 2016. Analyzing delays of road construction projects in Orleans, May 7–9. Available from: http://www.pmicpm.org/public/news_
Cambodia: causes and effects. J Manage Eng. 32(6):05016020. events/2003_spring_conf/index.html_.

You might also like