Professional Documents
Culture Documents
6.1. 501
A. 145 + 12.54
B. 147 + 05.23
C. 148 + 50.61
D. 151 + 03.32
6.2. 502
A parabolic crest curve is followed by a sag curve. The two curves are connected
by a tangent section, as shown. A bridge structure is located at station 45 +
55.00. The elevation of the low point on the bridge is 405.54 ft. The design speed
(mph) of a truck (assume driver's eye elevation = 7.6 ft), based on adequate sight
distance under the bridge overpass on curve number 2, is most nearly:
A. 65
B. 75
C. 80
D. 85
6.3. 503
A. 120
B. 140
C. 160
D. 180
6.4. 504
A 6-lane freeway through rolling terrain (rural) has12-ft lanes, interchanges every
1.25 mi and has 8-ft-wide shoulders. Traffic studies have resulted in the following
data:
K = 0.12
The LOS for the peak direction of the freeway is most nearly:
A. A
B. B
C. C
D. D
6.5. 505
A study area is divided into three socio-economic zones, whose trip production
and trip attractions are tabulated below:
Zone 1 2 3 Total
Zone 1 2 3
1 40 90 75
2 90 25 35
3 75 35 40
The number of trips produced by zone 3 and attracted to zone 2, according to the
first iteration of the gravity model, is most nearly:
A. 110
B. 130
C. 150
D. 170
6.6. 506
A 4-lane divided highway (2 lanes in each direction) currently has ADT of 23,000
vehicles (each way). Approximately 12% of the traffic consists of trucks. Traffic is
expected to grow by a 4% annual rate over the next 20 years. Table 1 shows data
collected from a weigh station during a typical day for 1,078 trucks.
Table 1. Traffic Data (Axle Counts)
10 2420
14 630
18 301
20 22
22 6 24
25 1 15
28 12
32 11
10 0.0877
14 0.360
18 1.0
20 1.51
22 2.18
25 3.53
22 0.180
25 0.308
28 0.495
32 0.857
Using the Asphalt Institute Load Equivalence Factors (LEF) shown in Table 2, the
design 20-year 18-k ESAL (W18) is most nearly
A. 9 × 106
B. 15 × 106
C. 20 × 106
D. 23 × 106
6.7. 507
Level terrain
The LOS for the peak direction of the highway is most nearly:
A. B
B. C
C. D
D. F
6.8. 508
A transition curve is to be used to implement a change in cross-section from a
normally crowned section to a fully superelevated section. The outer lane is to be
rotated from the normally crowned section to a straight level section at the
tangent-to-spiral (T.S.) station. The roadway section is rotated about the
centerline. The following information is given:
Grade = +1.50%
A. 86 + 50
B. 87 + 25
C. 88 + 00
D. 88 + 50
6.9. 509
What is the recommended length of cycle for a 4-phase signal with 3-sec lost time
per phase, with the following critical movements?
Saturation
Lane Group Volume for Green Time
Phase
Volume (vph) Lane Group Fraction
(vphg)
A. 105 sec
B. 125 sec
C. 140 sec
D. 160 sec
The following diagram and the associated data are to be used for problems 510–
512.
A right-angle intersection between two 4-lane highways (Main St. and South St.)
is shown above. The 80-sec signal cycle has four phases: (1) EBL and WBL, (2)
EBTH/R and WBTH/R, (3) NBL and SBL, and (4) NBTH/R and SBTH/R. Each yellow
time separating phase is 3 sec and each all-read interval between phases is 1
sec. The critical v/s ratios for each phase are listed below:
1 WBL 0.232
2 EBTH/R 0.156
3 NBL 0.150
4 SBTH/R 0.135
Heavy vehicles = 5%
PHF = 0.92
Vehicle length = 20 ft
6.10. 510
The saturation flow (vph) for the WBTH/R lane group is most nearly:
A. 2,650
B. 2,860
C. 3,030
D. 3,210
6.11. 511
The minimum clearance interval (sec) for the intersection is most nearly:
A. 4.0
B. 4.5
C. 5.3
D. 5.8
6.12. 512
The minimum green time for the north-south signal phase, based on pedestrian
volume, is most nearly:
A. 25 sec
B. 22 sec
C. 19 sec
D. 16 sec
6.13. 513
A. 3.7
B. 3.8
C. 3.9
D. 4.1
6.14. 514
Which warrant(s) from the 2009 MUTCD does this intersection meet?
A. Warrants 1 & 2
B. Warrant 2 only
C. Warrants 1 & 3
D. Warrants 2 & 3
6.15. 515
A. 1.2
B. 2.5
C. 3.4
D. 4.8
6.16. 516
A. 2,800
B. 2,900
C. 2,950
D. 3,050
6.17. 517
A traffic network within a city planning zone is described by the following matrix.
Nodes are numbered 1 through 8.
Node 1 2 3 4 5 6 7 8
1 – 1 0 1 0 1 0 1
2 1 – 1 1 0 0 0 0
3 0 1 – 1 1 0 0 0
4 1 1 1 – 1 1 1 0
5 0 0 1 1 – 1 0 0
6 1 0 0 1 1 – 1 0
7 0 0 0 1 0 1 – 1
8 1 0 0 0 0 0 1 –
A. 14
B. 15
C. 16
D. 17
6.18. 518
A 2-lane rural freeway segment has 12-ft lanes and an 8-ft shoulder. A cut slope
of 1V:4H exists adjacent to the shoulder as shown. The ADT is 16,000 and the
design speed is 65 mph. The minimum width (ft) measured from the edge of the
shoulder, which should be free of any obstructions, is most nearly:
A. 18
B. 26
C. 38
D. 46
6.19. 519
For the design direction of the highway, the average travel speed has been
calculated as 42 mph and the percent-time spent following has been calculated
as 63%.
A. B
B. C
C. D
D. F
6.20. 520
A. 31°50′56″
B. 21°40′28″
C. 41°32′15″
D. 27°40′24″
6.21. 521
A parabolic vertical curve joins a grade of −5% to a grade of +3%. The PVC is at
station 53 + 12.50 and the PVI is at station 60 + 09.00. Elevation of the PVI is
365.57 ft. The curve passes under a bridge structure at station 55 + 05.20. The
bottom elevation of the bridge is 405.20 ft. The vertical clearance under the
bridge (ft) is most nearly:
A. 12.5
B. 13.4
C. 14.2
D. 14.9
6.22. 522
A 2-lane highway has a circular horizontal alignment with centerline radius of 750
ft. Lanes are 12 ft wide. An obstructing structure exists 10 ft from the inside edge
of the roadway as shown below. The safe design speed (mph), based on adequate
horizontal sightline offset, on the curve is most nearly:
A. 35
B. 40
C. 45
D. 50
6.23. 523
A 2-lane highway has a posted speed limit of 50 mph. The alignment consists of a
dangerous curve where the maximum posted speed is 20 mph. What is the
distance (ft) upstream of the low speed limit section where a warning sign must
be posted?
A. 125
B. 200
C. 150
D. 175
6.24. 524
A horizontal curve has a radius of 1,150 ft as shown below. A point P on the major
chord is located such that AP = 215 ft. The length of the chord offset PQ at point
P (ft) is most nearly:
A. 43
B. 48
C. 52
D. 21
6.25. 525
A vertical curve is being designed to connect two grades with G1 = +2.1% and G2
= −1.5%. If the design speed is 65 mph, the minimum length of vertical curve (ft)
to satisfy AASHTO safe stopping distance criteria is most nearly:
A. 600
B. 650
C. 800
D. 700
6.26. 526
A parking lot is open during the hours of 8 A.M. to 6 P.M. During this time, exactly
360 cars were parked on the lot; 10% for 1 hr, 15% for 2 hr, 20% for 3 hr, 30% for
4 hr, and the remaining for the entire day. On average, 15% of the spaces are
vacant and the operational efficiency factor is 80%.
The space-hr demand and number of parking spaces in the lot are most nearly:
6.27. 527
A 6-lane freeway through mountainous terrain has ADT of 52,500 veh/day. The
traffic stream includes 8% trucks, 3% buses, and 5% RVs. The FFS is estimated as
70 mph and the PHF = 0.9. Directional split is 60/40 and K = 0.12.
The LOS for the peak direction of the road is most nearly:
A. B
B. C
C. D
D. E
6.28. 528
The length of the reverse curve transition (ft), from PC to PT, is most nearly:
A. 1,250
B. 480
C. 960
D. 630
6.29. 529
The critical gap for the left turn movement from the minor street during the peak
hour is most nearly:
A. 7.1 sec
B. 7.5 sec
C. 7.8 sec
D. 8.5 sec
6.30. 530
A traffic stream has mean headways of 2.4 sec. If the jam density is 64 veh/mi,
the optimum speed is 50 mph, and the flow is 1,500 veh/hr, then the capacity of
the highway (veh/hr) is most nearly:
A. 1,530
B. 1,600
C. 1,640
D. 1,720
6.31. 531
No. 10 10
No. 20 12
No. 40 21
No. 100 15
No. 200 8
A. A-6
B. A-7
C. A-2-6
D. A-2-7
6.32. 532
Time (hr) 0 1 2 3 4 5 6
3
The peak stream discharge (ft3/sec) that would be recorded following a 2-hr
storm producing 1.7 in. of runoff is most nearly:
A. 90
B. 80
C. 180
D. 160
6.33. 533
The minimum vertical clearance (ft) between the roadway and the 100-year flood
elevation is most nearly:
A. 5.2
B. 2.2
C. 4.8
D. 7.8
6.34. 534
A trapezoidal open channel with bottom width of 10 ft and side slopes 2H:1V
conveys a flow rate of 150 ft3/sec. If the Manning's n is 0.016 and the bottom
slope is 0.4%, the depth of flow (in.) is most nearly:
A. 12
B. 16
C. 20
D. 24
6.35. 535
Results from a standard Proctor compaction test of six soil samples from a borrow
pit are tabulated. The natural moisture content of the excavated material is 12%.
The fill location requires 1.5 million yd3 of soil compacted to a minimum 90% of
the maximum Proctor dry density.
1 3.24 12
2 3.70 14
3 3.95 16
4 4.21 18
5 3.90 20
6 3.40 22
The total volume of borrow soil that must be excavated (yd3) is most nearly:
A. 1.72 million
B. 1.65 million
C. 1.53 million
D. 1.42 million
6.36. 536
A. 7.2
B. 72
C. 720
D. 7,200
6.37. 537
A. 4,800
B. 5,800
C. 6,800
D. 7,800
6.38. 538
A. 4
B. 5
C. 7
D. 8
6.39. 539
The table below shows areas of cut and fill sections at locations 50 ft apart.
Assume shrinkage = 12% and bulking = 25%. The cumulative earthwork volume
between stations 0 + 0.00 and 3 + 0.00 is most nearly:
A. 1,400
B. 1,800
C. 2,200
D. 2,600
6.40. 540
A. 0.85
B. 0.95
C. 1.04
D. 1.17
Citation
EXPORT
Dr. Indranil Goswami,: Civil Engineering PE Practice Exams: Breadth and Depth.
Transportation Depth Exam, Chapter (McGraw-Hill Professional, 2012),
AccessEngineering
Copyright © McGraw-Hill Global Education Holdings, LLC. All rights reserved.
Any use is subject to the Terms of Use. Privacy.
This product incorporates part of the open source Protégé system. Protégé is
available at http://protege.stanford.edu//