Transmission Division, Dehri on sone

Work Period-01.01.2021 to 31.03.2022


Name of work under Transmission Division,
sl no. Work to be done Completed Remarks
Dehri on sone
foundation-40 100%
Erection-40 100%
Construction of 132 KV Bikramganj- Bikramganj Stringing-10.8 Km 98%
1 TSS Transmission line and one no. 132 KV bay
at GSS Bikramganj Charged on
132 KV Bay TSS Bikramganj 98% dated.
06.09.2021

(OPGW WORK)
220 KV- Dehri GSS 100%
Regarding permission from PGCIL to work in
132 KV Dehri-Bikramganj
various lines for supply, erection, testing and 100%
2 commissioning of reliabe communication and 132 KV Dehri-Kerpa 100%
data acquisition for implementation of 132 Kv Kerpa-Banjari 100%
integrated communication system upto 132 kv
in bihar with amc for 6 years under state plan132 KV Banjari- Sasaram 100%
against NIT no. 79/PR/BSPtCL/2018. 132KV Kochas-Kudra 100%
132 KV Kochas-Pusauli 10%
foundation- 04/51km 7.80%
Construction of D/C 220 KV Dehri- Pusauli Tr. Erection- 04/73km
3 5.47%
Line (Re-tender)
Stringing- 5.8/33km 17.57%