MOM

Joint patrolling of 220kv Dehri-Gaya(PG) transmission line was conducted on 11.30.22 and 12.03.2022 by LMD
Dehri and surveyor team for measuring the Ground clearance of B- Phase conductor (ckt-1 & ckt-2) by Total station
equipment at different suspicious locations.

Some important points about above mentioned line

1. Tie line as it connects 220kv Dos –Pusauli (PG) with 220 KV DOS –Gaya (PG)
2. Total length of this line is approx 95KM up to PG Gaya.
3. Total no of towers in this line is 287.
4. Line was constructed in year 1975.
During joint patrolling conducted following observations were made—
(a) Tripping of this line increasing comparatively every year particular in summer season.
(b) Span length of this line is bit abnormal due to presence of normal size of towers.
(c) Clearance of bottom conductor w.r.t. ground is very less in every span except at special towers.
(d) Many 11 KV & 33KV lines have been constructed in recent past as a result of which clearance
between bottom conductors and 11KV & 33KV lines has reduced resulting in tripping despite
lowering the 11KV & 33 KV conductors.
(e) Roads are being elevated at many places which is also reducing the ground clearance.
(f) New height raised towers are require for sufficient clearance at many road, canal , crossing ( list
enclosed with photographs).
Remarks :- Reconductoring and height raising of below mentioned towers of 220 KV Dehri-Gaya (PG) is urgently
required for reducing the trippings and to prevent any fatal accident.
Following are the details of towers were height raising of tower and tightening of conductors required.

Sl. Type of Location Place Crossing Ground Clearance Instant action may be
tower no. Ckt-1 ckt-2 take for overcome the
tripping problem.
1 Suspension- 128-129 Village- 11 KV & Rafiganj 6.75 mtr 7.779 Ground clearance may be
suspension Nima Kasma Road increased (approx 1
(Rafiganj) meter) by tightening of
R,Y & B phase conductor
of ckt 1 & ckt 2 from loc
nom 131 to 142(tension -
tension).
2 Suspension- 137-138 Rafiganj 33 KV and 8.98 mtr 8.75
suspension Rafiganj Shivganj mtr
Road
3 Suspension- 144-145 Village- 11 KV & Rafiganj 9.15 mtr 8.558
suspension nauakhap Aurangabad Road mtr
4 Tension- 152-153 Village- Rafiganj Obra 6.213 6.11 Ground clearance may be
suspension Pragbigha Road mtr mtr increased (approx 1
meter) by tightening of
R,Y & B phase conductor
of ckt 1 & ckt 2 from loc
nom 152 to 164(tension -
tension).
5 Suspension- 176-177 Village- Small Canal 4.508 5.049 Height raised required
suspension Jakhim mtr mtr
6 Suspension- 243-244 Village- Pond and road 4.77 mtr 6.809 Ground clearance may be
suspension Dudhaila mtr increased (approx 1
7 Suspension- 247-248 Village – Road and canal 6.05 mtr 7.06 meter) by tightening of
suspension ratnaur mtr R,Y & B phase conductor
of ckt 1 from loc nom 242
to 254(tension to
tension).
8 Suspension- 266-267 Village- Small Canal 7.391 6.404 Ground clearance may be
suspension Malkopa mtr mtr increased (approx 1
meter) by tightening of
R,Y & B phase conductor
of ckt 1 & ckt 2 from loc
nom 265 to 268(tension -
tension).

MOM

Joint patrolling of 220kv Dehri-Pusauli (PG) transmission line was conducted on 13.03.22 by LMD Dehri and
surveyor team for measuring the Ground clearance of B-Y- Phase of conductor by Total station equipment at
different suspicious locations.
Some important points about above mentioned line

1. Tie line as it connects 220kv Dos –Pusauli (PG) with 220 KV DOS –Gaya (PG)
2. Total length of this line is approx 54 KM up to LILO.
3. Total no of towers in this line is 169.
4. Tower under the jurisdiction under transmission circle Dehri. Location no. 1 to Location no 169 (LILO)
5. Line was constructed in year 1983.
During joint patrolling conducted following observations were made—
(a) Span length of this line is bit abnormal due to presence of normal size of towers.
(b) Clearance of bottom conductor w.r.t. ground is very less in every span except at special towers.
(c) Many 11 KV & 33KV lines have been constructed in recent past as a result of which clearance
between bottom conductors and 11KV & 33KV lines has reduced resulting in tripping despite
lowering the 11KV & 33 KV conductors.
(d) Roads are being elevated at many places which is also reducing the ground clearance.
(e) New height raising of towers are require for sufficient clearance at many road, canal , crossing ( list
enclosed with photographs).

Remarks :- Reconductoring and height raising of below mentioned towers of 220 KV Dehri-Pusauli (PG) are
urgently required for reducing the trippings and to prevent any fatal accident.
Following are the details of towers were height raising of towers & tightening of conductors required .

Sl. Type of tower Location Place Crossing Ground clearance Instant action may be
no. B-Phase Y-Phase take for overcome the
tripping problem.

1 Suspension- 14-15 Village- Akorhigola- 6.67 8.698 mtr Ground clearance may
suspension Bagen Amra tlav mtr be increased (approx 1
Road meter) by tightening of
R,Y & B phase
conductor from loc
nom 13-22(tension -
tension).
2 Suspension - 122-123 Village- 11 KV & 7.986 9.101 mtr
Tension sakhari Kudra- mtr Height raised required
chenari Road
3 Suspension- 137-138 chilbili road 6.99 8.5 mtr
suspension mtr Ground clearance may
be increased (approx 1
meter) by tightening of
R,Y & B phase
conductor from loc
nom 130-147(tension -
tension).

Tension- 158-159 Village- NH2- Sonhan 5.097 5.88 mtr Ground clearance may
suspension Khanerhi Road mtr be increased (approx 1
meter) by tightening of
R,Y & B phase
conductor from loc
nom 158-159(tension -
tension).