Field visit report on drinking water treatment plant, MANPUR, GAYA
PROJECT REPORT
Submitted by
Rajeev kumar
Enrollment No.-CUSB2103212020
arene
MASTER OF SCIENCE
IN
ENVIRONMENTAL SCIENCE
CENTRAL UNIVERSITY OF SOUTH BIHAR
GAYA — 823001, INDIAReport on Ganga Water Lift Project, Manpur,GayaACKNOWLEDGEMENT
I would like to express my special thanks to our respected Head of
the Department Dr. Umesh Kumar Singh for not only providing us
the opportunity but also for making prior arrangements for the trip.
Talso want to thank our coordinator Dr. Prashant, Dr. Rajesh
Kumar Ranjan and Dr. NL Devi for taking out their time and effort
to accompany their students throughout the trip. I would like to
thank our kind professors Dr. Pradhan Parth Sarthi and Dr. Ram
Kumar for guiding us with their experiences.
I gratefully thank Abadesh Kumar Singh, wapcos India limited for
allowing us to visit the water treatment plant for public water
supply.
Special thanks is to my classmates for supporting each other to learn
new things from the upcoming water treatment plant visit, being
available to help in any ups and downs and making the trip
memorable for a lifetime.
Thank you to my parents for being my support system. Thank you!Contents Page No.
Acknowledgement
Table of Contents
Introduction
Ganga Water Lift Project Phase -1
List of FiguresINTRODUCTION
This report is about the field trip which was
organized on 12/04/2022 at 8:00 A.M from
Central University Of South Bihar Campus to the
Manpur, Patwatoli and Dubhal situated on the
outskirts of Gaya near the Falgu river. The
duration of the field visit was about 4 hours.
This project is about the ganga lift project the
water treatment plant is being constructed in gaya
to meet the water requirements in the whole city
bof gaya and Bodh Gaya. In Gaya,the water
treatment plant was started in July 2020.
Ganga water will be pumped in the Hathidah,one
pipeline will go to Rajgir, while another to
Nawada,then to Manpur where the water is stored
and treated.We first reach the under construction water
treatment plant around 9:30 A.M, here we receive
first hand information on design, construction and
functioning of the plant. It was nicely explained by
the Engineer Abadesh Kumar Singh who briefly
explained the scheme of the project and allowed us
to explore the constitution site. And he also
explained the process of who the water treatment
will work after the completion of the project.
The water treatment plant to supply ganga water is
built in the three cities of Bihar - Gaya, Rajgir,
Nawada where to of the constitution purpose have
been completed in Gaya. Collection of water will
be done from Tetar dam reservoir of raw water.
The water treatment plant started with the
pre-settling tank where all the suspended particles
settle down the it will be sent to cascadeaerator,here gaseous exchange will be done. The
water will be then passed to the clariflocculator
where the combination of flocculation and
clarifuction will be done in a double tank. The
water will then pass to the settling chamber where
chlorine will be added to the water and the process
of pre chlorination will be done. With the help of a
measuring channel the water will then pass to the
cascade aerator . After this process all the particles
will settle down with the help of measuring
channels, only water will move to the filter house
where the process of chlorination will be done.
Chlorination will be done on the pedestal and the
chlorine will be the liquid chlorine. In the filter
house the filtration of the water level is checked on
the utility building and further it will be passed to
the wash water tank for the washing purpose.Finally the water will be supplied to the pump
house and then it will be supplied to the entire
Gaya to Bodhgaya. It has a capacity of 186.6 MLD.
The state of the art plant is expected to supply
water by mid of next year.1 Ganga water uplift project upcoming model of treatment plant.
> This section is about the water treatment plant situated, in near manpur block. The air of
this project is to provided Ganga river water to the citizens of Gaya, Why Because the
water table of Gaya is decreasing at the rate of about 1 m per year. Bihar Government
took initative where the surpilus water that is present in Ganga during the rainy season
can be stred and transported to Gaya for Drinking Water Pourpose. Its aimme to provide
186.5 million liter per day
1.1-Sereening
Screening is the first unit operation used at wastewater treatment plants (WW TPs). Screening
removes objects such as rags, paper, plasties, and metals to prevent damage and clogging of
downstream equipment, piping, and appurtenances. Some modem wastewater treatment
plants use both coarse screens and fine screens.
Coarse screens remove large solids, rags, and debris from wastewater, and ty]
openings of 6 mm (0.25 in) or larger. Types of coarse sereens include mechanically and
manually cleaned bar sereens, including trash racks
Fine sereens are typically used to remove material that may create operation and maintenance
problems in downstream processes, particularly in systems that lack primary treatment, Typical
‘opening sizes for fine screens are 1.5 to 6 mm (0.06 to 0.25 in). Very fine screens with openings of
0.2 to 1.5 mm (0.01 to 0.06 in) placed after coarse or fine screens can reduce suspended solids to
levels near those achieved by primary clarification
1.2-Grit Removal Chamber
Grit includes sand, gravel, cinder, or other heavy solid materials that are “heavier” (higher specific
gravity) than the organic biodegradable solids in the wastewater. Grit also includes eggshells, bone
chips, seeds, coffee grounds, and large organic particles, such as food waste. Removal of grit
prevents unnecessary abrasion and wear of mechanical equipment, grit deposition in pipelines and
channels, and accumulation of grit in anaerobic digesters and aeration basins. Grit removal
facilities typically precede primary clarification, and follow screening and comminution. This
6|Pageprevents large solids from interfering with grit handling equipment. In secondary treatment plants.
without primary clarification, grit removal should precede aeration (Metcalf & Eddy, 1991), Many
types of grit removal systems exist, including aerated grit chambers, vortex-type (paddle or
Jetinduced vortex) grit removal systems, detritus tanks (short-term sedimentation basins).
inlet i ‘ i outlet
fats, oll and grease
. compressed
air (optional)
ey”
Fig- Aerated Grit Chamber
1.3- Rake Clarifier
Clarifiers are settling tanks built with mechanical means for continuous removal of solids being
deposited by sedimentation, Clarification is the oldest and most widely used operation in the
effective treatment of wastewater. A rake clarifier is generally used to remove solid particulates or
suspended solids from liquid or clarification and thickening by gravitational settling. The main
purpose of the clarifier is to produce a cleaner effluents and to remove solids.
Clarifiers are slowly rotating rake arms, A liquid feed with suspended solids is fed to the
clarifier tank. Clear liquid overflows the top of the tank and is collected in a trough. The
clarifier slows the water down and removes the solids that settle on the bottom with a rotating
sludge raking system. It also removes solids that float to the surface of the tank with its
7|Pagerotating rake skimming system, Thereafter, the wastewater slowly removed from the tank and
delivered to oxidation ponds for the next step in the process,
Fig- Rack Clarifier and Primary Sedimentation Tank
1.4-. Activated Sludge Process
The activated sludge process is one of the most commonly used for secondary wastewater
treatment. As a suspended-growth biological treatment process, activated sludge utilizes a dense
microbial culture in suspension to biodegrade organic material under aerobie conditions and form
biological floc for solid separation in the settling units. Diffused or mechanical aeration
maintains the aerobic environment in the reactor ‘Typical retention times are 5-14 hours in
conventional units rising to 24-72 in low rate systems Performance of activated sludge systems in
removing parasites varies with parasite species, (BHASKARAN et al. (1956) reported greater
removal of Ascaris and Trichuris (96-97%) than for hookworm (88%). Similarly, higher rates of
removal have been reported for Giardia eysts (> 97%) than for cysts of Entamoeba histolytica (<
85%) or Cryptosporidium oocysts (around 80%) (Feachem et al, 1983) Efficacy of removal
reported may depend on whether effluents were sampled after aeration and sludge separation or
after secondary sedimentation following activated sludge treatment. Parasite removal during
activated sludge treatment occurs predominantly during secondary sedimentation with free and
assisted sedimentation likely to be occurring in a similar manner to that during primary
sedimentation. (Medema et al. (1998) reported that 70% of protozoan cysts attached to particles 0-
B[Page200 jum in secondary settled sewage after 24 h of activated sludge treatment suggesting enhanced
settling of protozoa during secondary sedimentation Higher removal efficiencies for protozoan
cysts have been reported after activated sludge treatment (including secondary sedimentation) than
during primary sedimentation. At two activated sludge plants, primary sedimentation removed 4-
42% protozoan cysts in comparison to 53-98% removal in activated sludge units (including
secondary sedimentation) (Robertson et al 2000b). Overall the activated sludge plants removed <
99% of protozoan cysts (primary and secondary sedimentation included). Similarly, Mayer and
Palmer (1996) found that most protozoan removal occurred after activated sludge treatment (84 5-
99.5%; lowest rates were that of Cryptosporidium); removal performance improved to 98 9-99.9%
for the activated sludge plant (complete works including primary sedimentation). In contrast, both
primary and secondary sedimentation may be important for helminth egg removal. In an activated
sludge plant not preceded by primary sedimentation, removal rates of 75% helminth eges and 93%,
protozoan cysts were reported. Where primary and secondary sedimentation was considered,
activated sludge plants (complete works) removed 97-100% Ascaris eges and 99.7% (mansoni
atel (Rowan, 1964), Effective removal of Ascaris is most likely due to sedimentation. The high
removal rates for Schistosoma may have been facilitated by egg hatching since Schistosoma eggs
have been found to hatch readily in experimental wastewater tanks
9|PageThe photo of the up-coming water treatment is given
below:-
Fig:- under constructed water treatment plant
10| Page