You are on page 1of 5

ENGINEERING REPORT

Budi Artanto - Technical Expert

1. Overhaull

Overhaulling Prosess . figure 2.

Fig 2. Overhaull Prosses

Dismantle All Component, Cleaning, Cheking Electrical, Mechanical Fungtion figure 3.


Take Out For Composit Water Carbon Inside Boiler Group
Fig 3. Takeout Composit And Cleaning Inside Boiler System

Using Chemical Cleaner And Air Pressure For Takeout Composit

2. Recallibration and gasket change all grup head system


Installation Prosess figure 4

.
Figure 4

Fig 4. Recallibration and gasket change all grup head system


Replace sensor heat Grouphead for PID delivery system PN.9985-1

Change All gasket component boiler, gruphead, linier gruphead and vacuum valve system

Re callibration and restarting programable system PID Controller to back standart


performance
Berikut adalah price dari proses overhoull per tanggal 11//6/2022 yaitu mesin SLAYER
ESPRESSO
2Gp 180 Coffee

NO PART DESCRIPTION PRICE


1 General Overhoull Technical Maintenance 8.000.000
. Takeout sediment boiler
. Change all gasket boiler system
. Change gasket gruphead callibration
. Change gasket steamwand and callibration
. Restarting PID controller and programable system
. Change vacuum valve boiler
. Calibration brewing system
. Repair Steamwand LH Leaking, Change seal Tst
2 -Change Vacuum Valve system / ad 400.000
- Change Water Level Sensor
450.000

- Change Temperature Sensor Delivery PID on


Grouphead PN.9985-1
-
Rp. 2.750.000

Total
11.600.000

Payment ToBCA Bank 5865115170


Budi Artanto
INTERVAL MAINTENANCE

1. For Cleaning Group Head Is Everyday Before Closing


2. Maintenance For Cleaning Inside Machine With Vacuum Cleaner Is Every One Week
3. Cleaning Body Every Day
4. Makesure For Your Barista In Pressure Pump Capasity Averange ( 9-10 ) Bar Is a Normal
5. Makesure For Steam Pressure Is 1,1-1,5 Bar Is a Normal
6. Dont Losse Water Supply To Inside Machine
7. Change Gasket And Screen Shower is 6 Month ( Recomended

Thanks,

You might also like