21 Painting of the store walls 605 m2 12,000 7,260,000
Excavate and construct block wall
22 foundation 13.2 m2 25,000 330,000
23 Supply and install exhaust fan 6 No 250,000 1,500,000
24 Grills for ventilation 6 No 185,000 1,110,000
Supply and rectify all damaged floor
25 Second floor Items Items 800,000 800,000
Supply, install and paint air lock
26 chambers Second floor 44.4 m2 17,000 754,800
Supply and install air lock chambers
27 First floor 21 m2 17,000 357,000
Supply and rectify all damaged floor
28 First floor Items Items 800,000 800,000
Supply and construct air lock
29 chambers Ground floor 44 m2 17,000 748,000
Supply and install plastic curtains
2.7*2.4mtrs to plant gate Ground
30 floor 6.5 m2 50,000 325,000
Supply and rectify damaged floor
31 Ground floor Items Items 800,000 800,000
32 Supply and fabricate storage cage 110 m2 12,000 1,320,000
The amount charged for project as summarized above is for materials and Labor charge.
Terms of this contract are subject to changes that may arise at any time during the contract
period and all the changes or variations as well as work undertaken in the next phases will be
charged separately.
Duration: We expect to undertake the project for a period of two months provided each part will
fulfil its obligation.
Page 2 of 3
Invoicing arrangement:
DAJU BUSINESS INVESTMENT LTD will only issue receipts for supervision and Labour
charge only while receipts for costs of materials will be directly addressed in the name of
TRIDEA COSMETICS LTD for VAT claim purposes.
Under this option, all the requested amount for purchase of materials should be paid in cash or
advance cheques in the name of Juma F Korongo to avoid the unnecessary inconvenience, for
easy and timely supply of materials. This will also mitigate tax liabilities to DAJU BUSINESS
INVESTMENT LTD in respect of the amount relating to materials.