Capacity Management
– Explain why standard hours are used to measure capacity.
– Describe the four steps of capacity planning.
– Calculate available capacity.
– Explain the difference between rated and demonstrated capacity.
– Calculate load.
– Explain the five elements of manufacturing lead time.
– Describe the three steps of capacity requirements planning (CRP).
– Backward schedule an order from receipt into inventory to arrival at
the first work center operation.
Introduction
Business planning
Resource
Capacity planning
S&OP
Priority planning
planning
MRP CRP
Execution
Execution
Input/output
control
PAC
Order
sequencing
PAC
Capacity Management
Planning phase
– Determine resources needed for the priority plan.
– Validate that they will be available and select methods to ensure
availability when needed.
– The planning phase occurs at all priority planning levels: S&OP,
master scheduling, and MRP.
Controlling phase
– Monitor output and comparing it to plan.
– Make adjustments as necessary.
– The controlling phase occurs during production activity control.
Calculation formula:
Available time =
number of machines (or workers) × hours per day × days per week
What is the weekly available time for a work center that has four
machines and works eight hours a day for five days a week?
Calculation formula:
Available time =
number of machines (or workers) × hours per day × days per week
What is the weekly available time for a work center that has four
machines and works eight hours a day for five days a week?
Solution:
Available time =
4 × 8 hours per day × 5 days per week = 160 machine hours
Elements of utilization
– Hours actually worked
– Hours of available time
Calculation formula:
hours actually worked
Utilization percent = × 100%
hours of available time
Calculation formula:
hours actually worked
Utilization percent = × 100%
hours of available time
What is the utilization rate of a work center whose available time is for
160 hours a week but whose actual hours worked is 120?
Calculation formula:
hours actually worked
Utilization percent = × 100%
hours of available time
What is the utilization rate of a work center whose available time is for
160 hours a week but whose actual hours worked is 120?
Solution:
120 hours
Utilization percent = × 100% = 75%
160 hours
Elements of efficiency
– Standard hours of output
– Hours actually worked
Calculation formula:
standard hours of work produced
Efficiency percent = × 100%
hours actually worked
Calculation formula:
standard hours of work produced
Efficiency percent = × 100%
hours actually worked
70
Utilization = × 100% = 87.5%
80
90
Efficiency = × 100% = 128.6%
70
Calculation formula:
Rated capacity (standard hours) =
available time × utilization × efficiency
Calculation formula:
Rated capacity (standard hours) = available time × utilization × efficiency
Over the previous four weeks, a work center produced 110, 140,
120, and 130 standard hours of work. What is the demonstrated
capacity?
Over the previous four weeks, a work center produced 110, 140,
120, and 130 standard hours of work. What is the demonstrated
capacity?
Solution:
Demonstrated 110 + 140 + 120 + 130
capacity = = 125 standard
4 hours
(standard hours)
Capacity
Requirements
Planning
Production plan:
product families
Priority plan:
for end items
RCCP
Master scheduling Capacity validation
Load
Planning data
Shop calendar
Lead time
Description Source
Open shop orders Shop order file
Planned order releases MRP
Where work is done Routing file
Time needed (standard hours) Routing file
Lead times Routing or work center file
Work center capacity Work center file
2 3 4 5 6 7 8
27 123 124 125 126
9 10 11 12 13 14 15
28
127 128 129 130 131
July 16 17 18 19 20 21 22
29
132 133 134 135 136
23 24 25 26 27 28 29
30
137 138 139 140 141
30 31 1 2 3 4 5
31
142 143 144 145 146
2
July 2 Work day—123 Defines non-work days
123
Lead time
Operation
Queue Time waiting before operation begins time
Setup Time getting ready for operation
Run Time performing operation
Wait Time waiting after operation ends
Move Time physically moving between operations
Adapted from Material and Capacity Requirements Planning Certification Review Course, 1993, APICS
8 2 1 1
9 4 1 1
Schedule
Operation Work Arrival Queue Operation Finish Wait and
center date (days) (days) date move
10 8 2
20 9 2
Store Stores 120
8 2 1 1
9 4 1 1
Schedule
Operation Work Arrival Queue Operation Finish Wait and
center date (days) (days) date move
10 8 103 2 3 108 2
20 9 110 4 4 118 2
Store Stores 120
10 111 3 2 2
20 130 5 4 2
30 155 2 1 2
80
70
60
Hours 50 Uncommitted capacity
40
30 Required capacity:
All released orders
20 All firm planned orders
All planned orders
10
0
32 33 34 35 36
Week
Production Activity
Control
Resource
S&OP
planning
Capacity planning
Priority planning
Master
RCCP
scheduling
MRP CRP
Execution
Capacity
Purchasing PAC
control
Implement Control
• Gather information and prepare • Establish/maintain order priority.
shop packet. • Monitor/control WIP, lead time,
• Release orders to the shop floor and queues.
as authorized by MRP • Track and report production.
(dispatching).
• Report work center performance.
MANUFACTURING
?
Manufacturing lead times
Operations times Routing file
Work center capacity
Work center file
On-order quantity
BOMs Shop order file
Efficiency/utilization
Tools required
Quantity available
Scheduling
Objectives
– Meet delivery dates.
– Effectively use manufacturing resources.
Involves
– establishing start and finish dates for each operation needed to
complete an order.
Forward
Backward
Capacity
(120 hours)
Capacity
(120 hours)
Implementation
OK?
N Resolve or
reschedule
Y
Release
order
Source: Arnold et al., Introduction to Materials Management , 7th ed.
Reprinted by Permission of Pearson Education
Control
Objectives:
• Control progress of orders on the shop
floor.
• Control lead time, especially queue.
Control levers:
• Set the correct priority or sequence orders at
each work center.
• Control input/output of work at work centers.
• Control material flow rate in flow production.
Jobs coming:
145 7745 200 0.7 20 257 258
135 2832 20 1.2 1.0 259 259
Period 1 2 3 4 5 Total
Planned input 38 32 36 40 44 190
Actual input 34 32 32 42 40 180
Cumulative variance
Planned backlog 32
Actual backlog 32
Period 1 2 3 4 5 Total
Planned input 38 32 36 40 44 190
Actual input 34 32 32 42 40 180
Cumulative variance -4 -4 -8 -6 -10 -10
Planned backlog 32 30 22 18 18 22 --
Actual backlog 32 34 30 18 16 20 --
Period 1 2 3 Total
Planned input 38 36 42
Actual input 34 36 40
Cumulative variance
Planned output 40 40 40
Actual output 42 36 42
Cumulative variance
Planned backlog 30
Actual backlog 30
Period 1 2 3 Total
Planned input 38 36 42 116
Actual input 34 36 40 110
Cumulative variance -4 -4 -6 -6
Planned backlog 30 28 24 26
Actual backlog 30 22 22 20
Wrap-Up and
Homework
Capacity Management
– Explain why standard hours are used to measure capacity.
– Describe the four steps of capacity planning.
– Calculate available capacity.
– Explain the difference between rated and demonstrated capacity.
– Calculate load.
– Explain the five elements of manufacturing lead time.
– Describe the three steps of CRP.
– Backward schedule an order from receipt into inventory to arrival at
the first work center operation.
Available hours =
Actual hours worked =
Standard hours produced =
Utilization =
Efficiency =
Planned output 40 40 40 40
Actual output 38 36 40 38
Cumulative variance
Planned backlog 32
Actual backlog 32
Planned backlog 32 28 26 21 21
Actual backlog 32 28 24 16 20