ESTIMATION DISMANTLE-SITE TEST OF THE IBT TRANSFORMER 500 KV√3 (6 UNIT TRANSFORMER @ 1 PHASE)

DAYS REMARK
No DESCRIPTION
1 2 3 4 5 6 7 8 9 10 11 12

1 Site Acceptance Test


1.1. SFRA
1.2. Tan Delta Winding and Bushing
1.3. Winding Resistance (RDC)
1.4. Turn Test Ratio ( TTR)
1.5. Excitation Current Test
1.6. Insulation Resistance And Polarization Index
1.7. Vector Group
1.8. Calibration OTI / WTI
1.9. Function Test Accessories And MK
1.10. BDV Test
2 Dismantle Cooling Radiator And Wiring Accessories
2.1. Open wiring cable all accessories
2.2. Dismantle cooling fan and support
2.3. Wiring cable insulation

3 Dismantle Mainconservator
3.1. Close all valves in the conservator pipe
3.2. Unstall Support for Mainconservator and pipe
3.3. Unstall Mainconservator
4 Un Install and Disk Connect HV Bushing ( 1 Set ) - Class 500/√3 KV
5 Un Install and Disk Connect LV Bushing ( 1 Set )
6 Un Install and Disk Connect Netral Bushing

Dismantle the Piping (Refer to Drawing the Number of Piping)


7 Un Install Pipe for Bucholz, Bucholz and Compartement
8 Un Install Drain Pipe for Mainconservator
9 Un Install Pipe for Air Escape HV-LV Turret
10 Un Install Airbreather pipe for Mainconservator
11 Un Install Draining and Gas Collecting Devices for Bucholz
12 Un Install Ladder for Maintank Transformer

13 Dismantle Radiator
13.1. Close all valves Radiator
13.2. Un Install support Radiator
13.3. Un Install all Radiator
13.4. Close the radiator valve using a blind flange
14 Install Regulator Valve and Nitrogen Bottle

15 Inject Nitrogen up to 0.4 Bar

16 Packing all accessories