You are on page 1of 4

Da -t

( MJ/e;}.
Power to LijI- Quality to Last

5560 Ulmerton Road • Clearwater, Florida 33760


1-800-878-5560 • (727) 573-4414 • Fax:(727) 572-0590

BOAT DAVIT INSTAllATION INSTRUCTIONS


(MODELS: 600 LB. - 8,000 LB.)

IMPORTANT: Readthis manual carefully before installing the DavitMaster Boat Davit system. REFER TO LOCAL BUILDING
CODES FOR EXACT REQUI REMENTS. The following instructions indicate the minimum requirements neces-
saryfor installing DavitMaster Davits onto a seawall, bulkhead, dock or piling foundation. Eachsituation must be
evaluated based on existing conditions. DavitMaster is NOT responsible for the installation nor the integrity of
the seawall, bulkhead, dock or pilings.

INSTAlliNG DAVITS ONTO A CONCRETE SEAWAll


locating Placement of Davit Foundations
1. DavitMaster recommends placing the foundations 2 feet further apart than the centerline length of the boat (refer to Fig.1).
2. Dig a hole according to size of lift and how much concrete is needed. (see Chart A). The hole should be dug directly in back of
the seawall cap in order to obtain maximum reach. The hole must be of sufficient size to accommodate the amount of
concrete needed.

Installing Rebar and Base Bolts


1. Install REBAR(W') and anchor BASEBOLTS(refer to bolt hole pattern [Chart BJ,on back) per local building code requirements.
Use a base template to hold base bolts in their proper position while attaching the base bolts to the rebar.
NOTE: The base template (representing the actual base) must be placed as near to the forward edge of the seawall cap as possible.
2. Holes should be drilled in the seawall cap to accommodate the front bolts (Fig.1).

Pouring a Flat, level Concrete Foundation and Installing the Bases


1. Pourthe concrete, then level the concrete even with the seawall cap using front to back and side to side strokes.
NOTE: The foundation MUST BELEVELfor proper inboarding.
2. Allow concrete to cure overnight before installing the davit bases.
NOTE: The davit basescan be bolted down the next day, but NO WEIGHT should be placed on the foundation until the concrete
has cured for at least a week.

INSTAlliNG DAVITS ONTO WOOD! BLOCK OR METAL BULKHEADS


Pouring concrete for Wood, Block or Metal Bulkheads
1. On all foundations poured behind wood, block or metal bulkheads it is important to use more concrete than with a concrete
seawall. We recommend using approximately 3f4 to 1 yard additional concrete or more depending on the specific conditions
of the bulkhead.
2. To maximize the davit's reach on a wood bulkhead, we recommend a raised foundation extending over the wood bulkhead.

Installing Steel Beams for 4,000 Davit Systems and Heavier


1. For boats 4,000 pounds and over it is recommended that one or two steel I-Beams, about 10 feet long be incorporated into
each foundation and extended back into the yard to be a "dead-man" foundation.
NOTE: The "dead-man" foundation supports the primary foundation.
2. Normally 112 to 3f4 yards of concrete in each "dead-man" foundation is required.
POURING THE CONCRETE FOUNDATION

TOTAL CUBIC YARDS


TOTAL WT. OF BOAT OF CONCRETE (PER HOLE)* VARIATIONS

600 - 800 Ibs. yard


1/4 If extended davit arms
800 - 14001bs. yard
1/4 are used, add additional
1400 - 2500 Ibs. 3f4 yard y, yard of concrete to each
2500 - 3500 Ibs. foundation to counter-out
1 yard
additional cantelever
3500 - 5000 Ibs. 11/4 to 11/2 yards
5000 - 7000 Ibs. loading on the extended
1 % to 2 yards
davit system.
7000 - 10000 Ibs. 2 yards (minimum)
'(CONCRETE: 3000 tensile. 4" slump)

FIG.1

~:

/
'-./ /

I
FIG.2

FOUNDATION II
:': I II II
II I:
[i'fWfJB-t(
• :::100i;/I'
11/:' II II I
I
~~~~I--;%-
." i:~:~"
: .. ,_\ ...., __ ~'SEAWALL.
v 0 Q" b)
,l.v":-o1"'
"". I ,
I,I
,
, ...•. 1
.,: "':'.:".:<:"':
, ..•. ",.,:.<':\,'-:1 I
I
~t!dI/~1
/ ,.
•• - -.0lO
'\ .G. )l \
I REBAR ::'0)0 V'V~b

;' 5/S" x 3-4' o. 0 0°: ~


:;. ..•• \")
I t>CJ.g~ O· " l."I
o •
/ " 'Q 0 0) (. "
I
/
~ •••."'-
~~ ~O'\) ••b1)
.0'6 v) 000
G •• "
I ~ •.• 0 v o t)" \ , /\••..

I ~ ...-
....~ 0.0)
I ~ ••••~
ol,·qo':\ •
~.\,,<> l'o~~"
""I I
I ~...- 1.>·0
~oU..,'O~·
<.
I
I
f-.~ \.c~· 0°
""Q..",o-:)'I~ oo~ /
u" .•\)••,) /
Raised Pour Foundation O~O)
.~ c»
/
.0 0,·0
, . . Yo")
°u,c"
.........
/
A Raised Pour Foundation should '4) ~
..•.•••....•..
..... I
.~O·)
~Do(lo) J("~
be used if additional height is 00 ")00
needed for the boat to clear the c)O .•~
seawall (i.e. deep hull boats).
~ ')0 0
..
~~;0-
• 0 ~
)~'O

-----------JI
INSTAlliNG DAVITS ONTO A DOCK

CAUTION: It is recommended that dock mounted davits be restricted to 1,000 pound loads, assuming dock is of sufficient size
(i.e., not just a cat walk) and is in good condition. DavitMaster is NOT responsible for the integrity of the
dock construction.

1. Position davit base where you want it, then place bolts thru bolt hole located in the davit base.
2. Position a 4 x 4 board parallel with base bolts so that it runs between the first and second dock stringers (perpendicular to the
stringers), (Fig. 3).
3. Mark position of each bolt on the board and drill. Fasten 2 x (depth of stringers) boards between each base bolt (Fig. 3). Now bolt
the 4 x 4's into place (using base bolts). The extra stringers between each bolt will help to prevent warping of the deck boards.

FIG.3 FRONT VIEW SIDE VIEW

DAVIT BASE

BASE BOLTS

,:

~\ii~
"". "
'-.~
\ ~ ::\s; \-- ~ DOCK STRINGERS
~llllt
""
i
r+h---
" "

" "

~
4x4L&-J Lb-J 4 x 4

INSTAlliNG DAVITS TO PiliNGS

CAUTION: It is strongly recommended that pile mounted davits be restricted to 4,000 pound loads. It is also recommended
that a competent marine contractor assess the requirements needed for proper installation of davits onto pilings.
We do not recommend pivoting davits installed to pilings. It i~ very important that heavier boats (1,000 Ibs. and
up) not be pivoted on piling installations. DavitMaster is NOT responsible for integrity of pilings.

1. It is necessary to make sure that any pilings used for davit installation be at least 40" taller than the dock level. This is so that the
davit pile mount bases can be properly installed.
NOTE: Depending upon the structure and integrity of the dock, pilings and boat weight, bater pilings may be needed to reinforce
primary davit pilings.
2. Stand pile mount davit base up against the piling and mark the location of the bolt holes.
NOTE: DavitMaster strongly recommends inboard mounting of the pile mount bases (Fig. 4).
3. Drill thru piling (refer to Fig. 4 and 5 for bolt pattern).
4. Stand base up against piling and push bolts thru the mounting feet and piling. Tighten nuts down on the bolts.
NOTE: On new piling installations shrinkage should be expected. Bolts should be re-tightened at a later date.

FIG.4 PROFilE FIG.5 TOP VIEW

(600 lb. system) (800-4,000 lb. system) (800-4,000 lb. systems)


DAVIT "FLAT BASE" HOLE PATTERN CHART

CHART 8

MODEl: 8-5500, 8-6500, 8-8000 MODEl: 8-1000, 8-1850

@ @ ED ffi

c±> c±>
c±> - ®-L 41/2" ffi
1 'Is" HOLES PIVOT
1'18" HOLES

20"
24"
_@---L 12"
PIVOT
E9
ffi'i
411/'
@ c±>
11f/'
@'T6" ~
f- 41f2"--1
I
ffi 11f2"

~6"~
1 MODEl: 8-800
20" j

~6"-1 12"------1I
I

I 24" ffi c±>

(f) c±)
1" HOLES
MODEl: 8-3000, 8-4000

@ ffi -@ PIVOT
61/4" 18"

_@-L
PIVOT
5"
EB
c±> ffi EB'T
11fa" HOLES 411/'
1114"

24"
ffi
.1
18" ~41/2" ~

MODEl: P-600

@ ~ =W 10" 61/4"

~ ly,"-r-~ I~,',
PIVOT ...0-
@'T I 61/4"

~~ ~lf1
~ HOLES c±>
6" + 16"
I
ffi 111/'

1-6"~
1
~6"--1
I 12"------1 I
IL---- 24"

DM-1

You might also like