Professional Documents
Culture Documents
MAY 2019
1
TABLE OF CONTENT
Content Page
Introduction 3
Process flow 9 - 12
Daily activities 13 - 16
Task assigned 17
Conclusion 18
2
INTRODUCTION
The main purpose of this industrial training is to give students a vast exposure
to the real industrial environment. In addition, students were able to apply their skills
that they have learned through their academic years. Besides, students were able to
widen their knowledge and abilities as well as soft skills at the companies they will
be performing their industrial training by interacting with colleagues and customers.
Several task need to be done along our industrial training which are field
related activities and outside field activities. All the task and work progress directly
reported to Mr Faris Abd Halim, Process Engineer for heavy separation area.
3
ORGANIZATION CHART
4
5
HISTORY OF COMPANY
6
Intent between Union Carbide Corporation and Petroliam National Berhad
(PETRONAS). After two years of wait, in 1998 a Joint Venture Agreement was
finally signed between the two. The group was formed under the name OPTIMAL
group companies. Work began soon after with the clearing of the grounds for the
future OPTIMAL petrochemical plant in Kerteh, Terengganu, Malaysia.
In 2002, Union Carbide Corporation’s stake in the group was taken over by the
Dow Chemical Company (Dow), a diversified industry-leading global giant with a
portfolio of specialty chemicals, advanced materials, agro sciences and plastics
business that delivers a broad range of technology-based product and solutions.
January 2002, marked a momentous occasion for the Group. The first on-spec
ethylene was produce-the new chapter from project stage to a fully operational
petrochemical company had begun. The operation of the finals reactor in the
OPTIMAL complex in October 2000 recorded the completion of the project phase
and named the OPTIMAL Group Companies.
There are total of 13 companies which were wholly-owned and six companies
that are partly-owned by PCG management as shown in Table 2.0. Apart from
managing companies from Malaysia, PCG also responsible to manage company from
India. It clearly shows the management responsibility which is not easy and could
never be ignored. In Malaysia most of PCG plants are focused on the East Coast side
which is Kerteh, Terengganu.
7
Comprising both Malaysians and expatriates. The plant is led by En. Wan
Syahrul Anuar Wan Zin as the Head of Department. There are 3 areas of operations
which are Hot Side, Heavy Separation and Light Separation. Table below shows the
operation details of Olefin Department.
Hot Side comprises Furnace area, Hot Rover and Quench area.
Heavy Separation consists of Cracked Gas Compressor and Heavy
Separation.
Light Separation consists of Light Separation and Cold Rover.
8
- 1st Plant Turn Around
(TA) on 2003.
- 2nd Plant TA on 2005
Empowerment stage one, May
2008.
- 3rd Plant TA on 2009
- 4th Plant TA on 2013.
9
In general, process flow for olefins plant divided into three section which are
hot side (furnace, quench, hot rover), heavy separation (cracked gas compressor,
heavy separation) and light separation (cold rover, light separation).
The Olefins unit at PCOGD will crack Ethane and Propane into Ethylene and
Propylene and other hydrocarbon products. Ethylene product will be consumed in the
Ethylene Oxide and Glycol unit. The Ethylene product also will be exported via the
Ethylene Grid to supply Ethylene to Petlin (LDPE unit) and other Ethylene product
consumers (VCM & PEMSB). Propylene product will be consumed in the Butanol
unit and also exported to Petlin. Other products will either be consumed as fuel or
exported. In addition to hydrocarbons, HHP Steam will be generated in the Furnace
TLES to supply most of the steam needs for Olefins, and the excess exported to
Utilities as MP Steam and LP Steam.
10
The basic process of producing Ethylene includes thermal decomposition
(cracking) in the Furnaces, Quenching the cracked gas to remove the heavier
components before Compression, compressing the cracked gas to high pressure to
facilitate the final process of Gas Separation. The major equipment and columns to
produce Ethylene and Propylene are listed below. There are many other heat
exchangers, pumps and smaller processes involved in the overall process to
accommodate the by-products produced from cracking Ethane and Propane.
Steam, Fuel and Electricity are the “big three” utilities necessary to operate the
Olefins Unit. Steam and fuel are generated by Olefins and the majority will be
consumed within the unit with the excess steam and fuel being exported to support
the other units utility needs. Two other processes that are necessary to provide
cooling and condensing for Olefins gas separation are the Ethylene and Propylene
Refrigeration cycles. Both cycles include a compressor and many heat exchangers
and vessels. Olefins will operate a closed Cooling Water cycle necessary for cooling
compressor discharges and other processes. Olefins will operate a BFW ( Boiler
Feedwater ) system which includes a Deaerator, BFW Pumps and a Water Polishing
unit for recycled condensate. Utilities such as Nitrogen, Instrument and Plant Air
and Portable Water will be supplied from CUF through Utilities.
11
PROCESS FLOW (HEAVY SEPARATION)
SYSTEM 20
12
SYSTEM 21
SYSTEM 26
SYSTEM 27
C3 SPLITTER: This is the final separation between Propylene and Propane, with
Propy- lene overhead product going to the Propylene Product Storage Tank for
delivery to Petlin and Butanol. Propane is recycled back as Furnace feed after being
vaporized and superheated.
SYSTEM 28
SYSTEM 33
13
DAILY ACTIVITIES
NEO modules:-
NMI modules:-
14
After all module in NEO & NMI completed, all intern allowed entering the
plant area with proper wear of personal protective equipment (PPE). Five PPE need
to be wear to enter the plant, which are fire resistance cloth, safety boot, safety glass,
mono-goggles, safety helmet, chemical resistance glove, earplug and earmuff. Given
the authorization, interns need to do line tracing task for each system that have been
assigned. Along with the line-tracing task, interns need to complete training package,
which is a set of question related to the system. These task need to be completed
around 1.5 month started from 17 March until 5 May. During the period, all intern
need to familiarize with the environment and working condition inside the plant.
Interns also can gain new knowledge by following the operator do their routine daily
checklist and equipment basic care. These are several knowledge that we gain during
line tracing session.
15
During completing the line-tracing task, a test, which is Operational Safety
Standard (OSS) and Critical Operating Parameter (COP), have been conducted.
There are 20 question in total for the test, which are 10 OSS & 10 COP. Passing
mark for this test is 100% and if failed intern need to retake the test. This test is
important to evaluate level of awareness about process & occupational safety and
hazard that may occur in plant.
After all intern have finish line tracing, performance test will be conducted by
process operator to evaluate the line tracing progress. This evaluation session start
from 24 April until 5 March. During this test, interns need to answer some question
in front of the operator inside the plant. These are some question asked by the
operator.
1. Location of control valve and hand valve for heavy separation area
2. Operating procedure for operate equipment
- Switching pump
- Preparation of equipment for maintenance of pump
- Warm up reactor
3. Location and function of utilities station
4. Location of deluge valve system and step to reset
5. Process flow all system
6. Identify isolation valve for hydrogenation reactor
7. Locate all chemical injection pump
Question that fail to be explain or answer will be taken as an action item after the
test. Interns will need to close the gap by meeting with engineer or boardman. The
action item question will be ask again during final presentation. This is to ensure that
the knowledge that we gain from the close gap session is correct.
16
Once performance test passed, interns will proceed to next evaluation, which is
area certification test. This test was conducted to evaluate the level of understanding
about the process occur in each system in the assigned area. The total question for
each area is different and the passing mark is 80%. Interns that fail to pass the
passing mark need to retake the area test again.
After passing the area certification test, intern need to proceed to the last task
which is final presentation. We need to prepare ourselves including these
knowledge:-
Any question that cannot be answered during final presentation will turn into
action item. This action item must be completed within a week after final
presentation. All the information related to the question can be asked directly to
control room boardman or process engineer. The total mark from all the test and task
given will be as a bench mark for interns to be selected as a contract staff. Interns
that was selected will have an opportunity to join the major turnaround of Olefins
plant, which start from 18 August until 2 October.
17
TASK ASSIGNED
Task Duration
18
CONCLUSION
This industrial internship also has broadened the knowledge and helps the
author to understand the real process that took place in the plant. The author was able
to see the equipment’s used in the plant and how optimization is applied in the whole
process. The experience and knowledge will surely help the author when graduating
from University Teknologi Mara (UiTM) Cawangan Terengganu, Kampus Bukit
Besi for completion in Diploma Chemical Engineering.
19