MATERIAL COST LABOR COST W/ VAT LABOR
QTY UNIT UNIT UNIT AND
AMOUNT AMOUNT
COST COST MATERIALS
CONCRETE
WORKS
40kg
Cement 624 P280.00 P174,280.00 P64.00/hr P2,816.00
bag
Sand 34.325 c.m. P1,100.00 P37,757.00 P64.00/hr P2,816.00
Gravel 68.64 c.m. P440.00 P30,201.60 P64.00/hr P2,816.00 P252,238.60
Testing of
1 P1,470.00 P1,470.00
sample cylinder
Others
SUB TOTAL P242,238.60 P9,918.00

SOLUTIONS:
STAIRS

“Main Stairs”
Diagonal
.90 x .40 x 1.50 = .54 x 2sides = 1.08 c.m
Tread
(.27 x .25)/2 = .03375 x .90 = 0.030375 x 8 = 0.243
0.243 x 2 = 0.486 c.m

“Entrance”
Diagonal
1.25 x .29 x 0.15 = 0.054375 x 2 sides = 0.10875 c.m
Tread
(.15 x .25)/2 =0.01875 x 1.25 = 0.0234375 x 3 = 0.0703125 c.m

“Patio”
Diagonal
4.5 x 0.33 x 0.15 = 0.22275 x 3 = 0.66825 c.m
Tread
(.15 x .30)/2 = 0.0225 x 4.5 = 0.0999 x 3 = 0.2997 c.m.

Total Diagonal
1.08 + 0.10875 + 0.066825 = 1.26 c.m.

Total Tread
0.486 + 0.0703125 + 0.02997 = 0.59 c.m.

1.26 + 0.59 = 1.85 (Class A - 40kg bag)


1.85 x 9.0 = 16.65 bags of 40kg cement
1.85 x 0.5 = 0.925 c.m. sand
1.85 x 1.0 = 1.85 c.m. gravel