You are on page 1of 10

16

CLOSURE AND RECLAMATION


Björn Weeks and Eduardo Salfate

16.1 Introduction The importance of early planning does not obviate


the need to deal appropriately with older, abandoned or
The closure of waste rock dumps presents a unique set
imprudently designed mine waste facilities. It is always
of engineering challenges that must be addressed in the
possible to find the best design for the situation that is
context of an overall site closure plan. Typical dump
at hand, taking into account the site-specific conditions.
construction practices result in waste rock dumps that
However, early planning for closure is particularly relevant
contain segregated materials stacked well above the
for waste rock facilities where the possible corrective
original topography, with slopes commonly at angle of
actions for key closure issues, such as acid rock drainage
repose. As discussed in Chapter 14, depending on site (ARD) or metal leaching (ML) control, become more
geology, the waste rock materials in the dumps may be limited as the project develops and design flexibility
chemically reactive, with the potential to affect the decreases. Where early planning is not undertaken,
composition and quality of contact waters. Many active and major issues are only identified close to the end of
waste rock dumps approach the end of their operating life operating life, costs tend to increase and the range of
without meeting requirements for the control of long-term effective solutions available decreases.
risks associated with chemical or physical stability, Much of the attention that has been focused on cover
resulting in the need for costly closure measures to design for waste rock dumps through the 1990s and 2000s
address these risks. In some cases, waste dumps have been was driven by the need to address waste rock dumps where
abandoned without consideration of the long-term impacts oxidation and the generation of acidic discharges were
and risks to the environment. fully underway, and soil covers were seen as an economic
Closure should be considered as an integral component solution that could be evaluated and applied in the last
of the life cycle of a waste rock dumps, with planning for years of operation. While soil covers remain an important
the ultimate closure of the facility being an active and design option for waste rock dump closure, learnings of
iterative process that is modified and adjusted as the past 20 years have tempered our expectations for
operations and construction of the dump progress. what can be achieved by a skin of relatively fine-grained
Progressive closure measures are implemented during the materials placed over tens or hundreds of metres of waste
life of the mine to provide reduction of final closure rock, especially when the impacts of erosion over hundreds
liabilities, as well as a proving ground for evaluating the of years are considered. Growing awareness of the
closure measures. Careful planning from the earliest importance of erosion processes has led directly to the
stages of design ensures that appropriate siting, material increased discussion in the closure literature of design
segregation (if needed) and dump shaping are undertaken approaches variously termed ‘the geomorphic approach’
to meet closure goals and provide appropriate risk control. or ‘landform engineering’.
Intelligent cost trade-off analyses are conducted early to A great deal of research attention and practical design
appropriately balance factors that affect operating costs experience has been focused on dealing with the issues
(such as haul distances) with the costs for implementation related to ARD and ML from waste rock piles. At sites
of closure measures such as dump reshaping, cover where issues related to ARD and ML are present, their
placement, water diversion and long-term water treatment. control tends to become the focus of closure and
280 Guidelines for Mine Waste Dump and Stockpile Design

reclamation activities. Even at sites where ARD and ML Regardless of the framework adopted, the closure and
are not expected, the scale and importance of such issues rehabilitation of a waste rock dump normally have the
to mining on a worldwide basis generate a need to conduct following three goals, as a minimum:
the studies to demonstrate their absence. An overview of
■ protect public health and safety
the range of techniques to control ARD is presented in
■ prevent or reduce environmental degradation
chapters 14 and 15 of this book. This chapter includes
■ allow for productive future land use (either its original
a discussion on how these issues fit into an overall
use or an acceptable alternative).
framework for closure and reclamation.
This chapter also provides an overview of some of the Variations on these concepts are enshrined in
key issues associated with the closure of waste rock dumps, regulations in most mining jurisdictions around the globe.
along with possible measures that could be implemented From an engineering point of view, closure design is also
during design, operations and closure phases to reduce shaped by a desire to attain the preceding objectives in the
long-term risks and liabilities. It should be noted that this most cost-effective way possible, considering both the
chapter does not address the social implications of capital expenditures needed to attain the closure and the
planning for closure and issues such as the input of operating expenditures needed (if any) in the period after
stakeholders or rights-holders. While these issues are of implementation of the principal closure works. As the
critical importance to the overall closure, the social closed site will exist in some form for the foreseeable
dimension does not normally have a specific impact on future, the financial burden (and potential liability)
the closure of the waste rock facilities separate from the implied by any needed operating expenditures can greatly
closure of other mine facilities. exceed the capital expenditures. The desire to control or
eliminate this cost and associated liability is often expressly
stated as the desire for ‘walk-away’ closure solutions.
16.2 Approach to closure and Finally, the closure of any waste rock facility may also
reclamation planning be defined by local regulations.
Various schools of thought exist for closure and 16.2.1 Conceptual models for closure
reclamation planning, both for waste rock dumps and for
Once a general understanding of the design objectives is
mining operations in general. These include the objectives-
obtained, developing a conceptual model of the waste
based approach and the risk-based approach. In the
rock facility is a practical approach to developing and
objectives-based approach, closure objectives are defined
evaluating a closure and reclamation plan. The conceptual
and criteria established. Closure measures are then
model allows the designer to focus on the key issues that
developed to meet these criteria. In the risk-based
will affect the closure measures and on the variables that
approach, the risks posed by the facility are first identified.
need to be evaluated in the design process. The conceptual
Measures to control the risks are then identified and
model can be developed rapidly, based on available
evaluated in terms of their effectiveness and risk reduction
information, and refined as more information becomes
potential. These two approaches are not mutually exclusive
available. The first questions to be answered in developing
and can be combined. An example and clear description
the model are as follows:
of the objectives-based approach can be found in the
Guidelines for the Closure and Reclamation of Advanced ■ Is the waste rock prone to generating ARD or ML?
Mineral Exploration and Mine Sites in the Northwest ■ Where is the waste rock located? (For an existing site,
Territories (MVLWB/AANDC 2013), while the risk-based the answer is set – but when closure planning is
approach is well introduced in the International Council considered early in the design stage there may be an
on Mining & Metals Toolkit (ICMM 2008), which forms opportunity to incorporate closure considerations in
part of a practical framework for closure planning siting.)
throughout the mining life cycle. The objectives-based ■ What is the underlying hydrogeology? This includes
approach is also illustrated in the ANZMEC and MAC depth to the groundwater table, direction of
(2000) Strategic Framework for Mine Closure, which groundwater flow and hydraulic conductivity of the
incorporates risk-based considerations as part of a material under the dump and in the aquifer matrix.
planning stage. The interested reader is directed to these ■ What is the surface water setting? This includes the
documents (which are freely available on the internet) for a size and topography of the watershed in which the
more in-depth discussion, including examples of the types facility is located, any channels, streams or diversion
of objectives that are typically desired for a wide range of structures in the watershed and any water bodies
mining installations. downstream. Ideally, this will include a
16 – Closure and reclamation 281

characterisation of surface water flows and a range of ■ Is there a risk for physical instability (slope failures
design floods. with significant consequences, erosion)?
■ What is the downstream use of groundwater and ■ What would be a final land form or land use
surface water? This includes both human use and compatible with the surrounding conditions?
sensitive environments.
As mentioned previously, working through these
■ What is the climate? At a minimum, this should
questions may generate design modifications and initiate
include average annual and monthly precipitation and
an iterative process of refining the design. Experience has
evaporation numbers, and how many months per year
shown that the answers to these three questions tend to
of sub-zero temperature. Ideally, historical rainfall data
define the majority of the closure and rehabilitation
should be analysed to develop estimates of storm events
for various return periods. In permafrost regions, measures needed. Depending on site-specific conditions,
characterisation of the current and projected future it may be necessary to delve into some issues in greater
depths of the active layer may be relevant to the closure depth, while others can be treated at a more superficial
design. level.
Properly applied, the conceptual model approach
The above questions all relate to water, the allows a rapid evaluation of the waste rock facility (existing
management of which is typically key in the closure or proposed) and identification of the key design
design. For physical stability, relevant questions for the challenges that will be faced at a specific facility. This
conceptual model include the following: allows a high-level consideration of different closure
■ What is the seismicity of the site? approaches and their interactions, and different
■ What is the geometry of the waste rock facility (for approaches can be considered, as well as the impacts
closure of existing facilities), including overall slopes, of more radical or out-of-the-box approaches. A more
benches and general configuration? methodical approach to working through individual risk
■ What are the strength properties of the waste rock issues and their treatment with individual control
(friction angle, cohesion)? Is the material prone to rapid measures can be applied at a later stage to ensure that
degradation and change in the material properties? important risks have not been overlooked in the design
■ What are the foundation conditions under the existing and to provide documentation of design rational.
or proposed waste rock dump?
16.2.2 Closure criteria
Many of the above considerations are design variables, This section introduces the concept of design life for
and the process of evaluating these questions may be closure, and the implications on criteria for aspects such
iterative as the design evolves. as water quality, geotechnical stability and the design of
For rehabilitation considerations, the following hydraulic structures.
questions are relevant:
■ What is the natural vegetation in the surrounding 16.2.2.1 Design life
areas? Density and type of vegetation? Thickness and At some point in the development of the closure and
quality of soil? reclamation plan, it may be necessary to state a ‘design life’
■ Is soil available in the surrounding areas for use in for closure. There is relatively little agreement about what
revegetation, or can it be scalped and stockpiled for constitutes an appropriate design life for closure, and
future use? considerable variation in the understanding of the concept.
■ What is the surrounding land use: agricultural, In talking about design life for waste rock dump
residential, traditional hunting grounds, other? closure and reclamation, it can be useful to separate the
■ What is the surrounding topography and how does it discussion into the following three concepts:
compare to the shape of the waste rock facility? ■ the design life of the overall closure system
With these basic questions answered, one should be ■ the design life of a specific closure component (e.g.
able to develop a good overall conceptual model of the concrete used in a spillway)
waste rock facility for closure and/or an understanding of ■ the recurrence interval of a design event (e.g. a 1:200 or
the information gaps that need to be addressed before 1:1000 year storm).
advancing with the closure plan.
It is possible that all three of these can be different for
The conceptual model can be probed with questions
a single closure and rehabilitation plan. For example, a
such as these:
closure period of 1000 years may have been selected as the
■ Is there a potential for adverse impacts on water quality design life for the waste rock facility. The design storm
(geochemical stability)? used to size water diversion studies may be the 1:200 year,
282 Guidelines for Mine Waste Dump and Stockpile Design

24 h storm, based on an analysis that shows that if Even if the Uranium Mill Tailings Radiation Control Act
the design storm flow is exceeded, the overflow of the formulation is not explicitly being followed, that document
diversion system will have acceptable consequences. At the outlines the limits of our current ability to design,
same time, a concrete structure needed for some aspect of independent of what is said in the governing regulations.
closure may be constructed with concrete that has a design Analytical design can be taken to its limit (which is
life of 50 years, with the understanding that this structure probably of the order of 100–200 years), and longer periods
will need to be periodically renovated throughout the can be considered in a qualitative way.
design life of the overall system.
There is no consensus on what is an appropriate design 16.2.2.2 Water quality criteria
life for the overall closure. This arises from the tension Water quality criteria for closure are generally the most
between the limits on what we can reasonably design based straightforward of all closure criteria, at least in terms of
on engineering experience and the self-evident reality that theory, if not in application. In general terms, chemical
a waste rock facility can be expected to remain more or constituents that are released from the waste rock dump
less where it has been placed for the foreseeable future, to downstream surface water or groundwater should not
barring a massive relocation program or the action of endanger public, wildlife or environmental health and
geological processes over thousands (or tens of thousands) safety, and should not result in the inability to achieve the
of years. When a closure period that seems somewhat water quality objectives in the receiving environment over
credible based on engineering experience (such as 100 or the long-term.
200 years) is postulated, it will fall short when compared to Water quality objectives are commonly defined by
the reality of geological time scales. When a period that local regulations, and the closure design is obligated to
attempts to take into account the geological time scale work within that. There are two categories of effluent
(1000 or 10 000 years, for example) is postulated, we are regulations: (1) end-of-pipe standards for the quality of the
left without proven engineering tools. effluent at the point of discharge and (2) receiving water
While set periods such as 1000 years or more have standards, which govern the quality of a natural water
entered into practice (or at least regulations), there are very body downstream of a discharge point after a mixing zone.
few engineering experiences available with which to Many jurisdictions have regulations governing both.
meaningfully evaluate such design periods. This is Receiving water quality standards recognise that the
especially true for designs that make use of material such assimilative capacity of the environment is a factor in
as geosynthetics that have only existed for a few decades. determining the design removal efficiency of a treatment
And while closure periods of over 10 000 years have system. A larger receiving water body may require less
been discussed, this is beyond the reach of what we can strict treatment requirements.
meaningfully analyse with models calibrated against real In the absence of local regulations, ecological and
world experience. In periods of time of the order of human health risk assessments provide a useful and
10 000 years, one can quite reasonably expect the impact defensible tool for the establishment of site-specific water
of geological processes and significant climate change on quality goals. Alternatively, it is also common practice
any closure design, especially taking as context that the to adopt as a guideline the water quality regulations of
last major period of glaciation (or ‘ice age’) ended a recognised jurisdiction.
~11 000 years ago. Where possible, proper definition of baseline
Jurisdictional mandates for design life need to be taken conditions in the areas upgradient and downgradient of
into account, although the reasonableness of definitions the waste rock facility is highly recommended. The lack of
such as ‘perpetuity’ are questionable. In the absence of such information can lead to demands to achieve water
another specific formulation, one approach that has gained quality that may meet a regulatory guideline but is beyond
some acceptance was developed for the US Uranium Mill
what was observed under baseline conditions.
Tailings Radiation Control Act of 1978, which required
closure measures to be effective ‘for up to 1000 years to the 16.2.2.3 Geotechnical criteria
extent reasonably achievable and, in any case, for at least
Typical closure criteria for waste rock facilities call for
200 years’ (EPA 1983). According to Logsden (2013), the
dumps to be physically stable. The interpretation of ‘stable’
EPA guideline was formulated to cover the ‘periods over
can vary, but includes concepts such as the following:
which climatological and geomorphic processes could
reasonably be predicted, given current knowledge of earth ■ Slopes have an adequate factor of safety against
sciences and engineering’. The 200 year period can be seen significant failure. The nature of a ‘significant’ failure
as being reasonably within reach of analytical or predictive is tied to the use of the dump and the surrounding land
engineering approaches, while the 1000 year span enters post-closure (this may be evaluated semiquantitatively
into the realm of qualitative evaluations (Logsden 2013). through risk assessment).
16 – Closure and reclamation 283

■ The waste rock dump will not undergo deformations P = 1 – e–t/T (Eqn 16.1)
under the design seismic load that are significant (as
where:
per the previous definition of ‘significant’).
P = probability of exceedance
■ The final surface does not erode significantly under
t = design life
natural events (such as storms or earthquakes) or other
T = return period.
disruptive forces (e.g. all-terrain-vehicle use) after
closure. For example, using a closure design life of 1000 years,
the return period calculated for a 5% probability of
The required factors of safety for long-term geotechnical
exceeding the design value would be ~20 000 years.
stability are frequently defined in regulations. In the
Similarly, a 10% probability of exceeding the design
absence of local regulations, global practices (such as
criteria would result in a return period of ~10 000 years.
those summarised in Chapter 8) should be referenced Numerical techniques are also often used to develop a
in the development of site-specific criteria. probable maximum flood (PMF).
For seismic stability, some jurisdictions mandate Closure works are often designed to accommodate the
consideration of the maximum credible earthquake, and PMF, the rationale presumably being that given the very
that the structures and slopes should sustain the maximum long design life, the probability of any design storm
credible earthquake largely intact, and that designed occurring approaches 100% (P = 1). This approach may be
landforms should be maintained without significant enshrined in regulations. However, it presents at least two
changes. Other jurisdictions require less stringent criteria, conceptual difficulties. The first is that, in some instances,
such as the 1:475 year return period event, or even the the consequences of sporadically exceeding the design
1:100 year return period event. Acceptable deformation flow in a control structure may be manageable. It may
levels are less commonly defined, and should be evaluated be that the net present value of periodic repair and
based on site conditions and performance goals. Chapter 8 maintenance works is far more acceptable than the capital
provides some guidance regarding acceptable deformation expenditures implied by the construction of works sized to
criteria under seismic loading. handle the PMF.
Erosion criteria are less often stipulated in regulations, A second issue is the reliability of PMF estimates.
but are relevant for reclamation design in waste rock Especially when working at remote sites or in developing
dumps where soil covers and/or revegetation is planned. regions, the period of historical rainfall data may be quite
There are now a considerable number of examples where limited. It is not uncommon to work on design at remote
high-intensity rainfall events have led to significant mine sites where 10 or 20 years of rainfall data would be
erosion or complete failure of soil covers. While some level considered outstanding. In contrast, obtaining a prediction
of soil loss due to hydraulic processes is to be expected, of just the 25 year storm with 90% confidence would
this erosion rate should be balanced against long-term require 59 years of data. The statistical validity of even a
rates of soil generation. 1:200 year estimate developed based on 10 or 20 years of
data is questionable. Using these limited data to estimate a
16.2.2.4 Surface water management criteria PMF, and then investing millions of dollars in structures
Water management features that are to remain following sized on these extrapolated numbers is a practice that
closure should be designed and built considering return should be carefully considered.
periods prescribed by applicable regulations for closure This issue has not been adequately resolved in current
and reclamation. practice. In the absence of clear design practices, it
Design storm events are generally specified in terms of is recommended to consider the site-specific closure
storm duration and a return period, such as (for example) conditions/requirements and limitations on precision
a 24 h storm with a 1:200 year return period. Typically of estimates when developing hydrological criteria.
regulations specify only the return period, and the most
critical duration will depend on the specific climate and 16.2.2.5 Other criteria
catchment characteristics. Regulations typically either do A wide range of other criteria may be defined, depending
not mention the event duration or specify that most on the specific needs of the closure design. For instance,
critical durations should be considered in the design. covers may be designed to maintain a minimum level of
The return periods for the design criteria to be applied saturation to prevent oxygen entering the waste rock. The
for the design life can be estimated on the basis of compliance with these criteria can be monitored with
assuming a probability of exceedance. The probability of properly maintained probes that measure the degree of
exceeding the design value during the design lifetime may saturation in the soil cover, and with oxygen probes
be calculated assuming that the occurrence of events (e.g. measuring oxygen percentages in the waste rock. If
seismic, floods) follows a Poisson process (ICOLD 2013): vegetation is part of the final rehabilitation plan, a variety
284 Guidelines for Mine Waste Dump and Stockpile Design

of criteria can be used to evaluate the development of infiltration may have higher concentrations, resulting in
vegetation, such as measurements of the density of plants equivalent mass loadings of the contaminants of concern
per square metre, or biodiversity measurements. to downstream receivers, when compared to the loadings
The definition of these criteria forms part of the that would have resulted from a higher flow at lesser
development of the closure plan for the waste rock facility concentrations. For this reason, geochemical
and needs to be established based on the closure measures characterisation and prediction of mass loading is key in
selected. the evaluation of designs for ARD/ML reduction.

16.3.3 Acid rock drainage/metal leaching


16.3 Geochemical stability treatment
As discussed in Chapter 14, avoiding unacceptable impacts Acid rock drainage/metal leaching treatment will, in
on downgradient water quality that result from ARD/ML general, be required at sites where (1) there is a net positive
can be a critical issue in the closure design of waste rock water balance and (2) the geochemical stability following
facilities. Where ARD and/or ML are present or have the application of prevention and reduction measures is not
potential to develop, closure measures are needed to sufficient to ensure that the excess water meets the
prevent their development (where possible), to minimise required criteria for discharge to the environment. The
them, or to treat them. These three approaches are need for an integrated management approach to waste
described briefly below. rock handling and excess water treatment is increasing.
This need is highlighted by increasingly higher costs
16.3.1 Acid rock drainage/metal leaching for compliance with the required criteria, including an
prevention increasing number of constituents of concern in discharges
The techniques commonly applied that have the potential and stricter regulations, as well as an increase in
to completely prevent the generation of ARD/ML were competing uses for receiving water bodies, which reduces
previously described in Chapter 14, and include the assimilative capacity of the environment and increases
subaqueous disposal, blending and encapsulation. Each regulatory pressure. For example, the removal of heavy
of these techniques has a greater chance of success if metals, acid or excess cyanide in mining effluents has long
incorporated into the early design and construction of the been practised, but the regulations governing these
waste rock facility. Several of the innovative approaches discharges are becoming stricter. Furthermore, as recently
identified in Chapter 15 also have the potential to prevent as a decade ago, the treatment of waste rock leachate or
ARD/ML generation. These innovative approaches also runoff for the removal of selected constituents such as
generally require early incorporation for the most cost- sulphate or selenate was rare. Today, we see specific cases
effective implementation. of treatment plants for sulphate or selenate removal having
capital costs of over one hundred million US dollars, and
16.3.2 Acid rock drainage/metal leaching the implementation of stricter regulations governing these
reduction constituents is becoming increasingly common. These
Even where control techniques fail to result in complete costs may be debilitating to mine operators and reinforce
elimination of ARD/ML, they may result in the reduction the need for a holistic approach and a careful analysis of
of the volumes generated. Mixing potentially acid forming the trade-offs between treatment and prevention. An area
waste with limestone or non-acid forming material that of recent research involves the incorporation of treatment
does not result in complete neutralisation or elimination chemistry into waste dump design, such as incorporation
of ARD may still result in the treatment or elimination of of reactive elements into the design of waste dump toes
a large portion of the net reactivity. and the use of saturated granular media as a biochemical
Barriers and seals (discussed in Chapter 14) are reactor.
considered viable techniques for the reduction of ARD/ML While a wide range of proven treatment options exist,
as the various types of barrier covers have generally been all of them imply a level of ongoing care and maintenance,
shown to reduce net infiltration into waste disposal piles, resulting in ongoing operating costs after closure. A review
but not eliminate it. Some percentage of percolation of case studies of treatment practices for 110 mine
through the cover is to be expected, with the net sites (Zinck and Griffith 2013) is provided by Mine
percolation being a function of the overall cover system Environment Neutral Drainage, a program funded by the
design, including soil profiles, climate and site topography/ Canadian Ministry of Natural Resources and the Mining
exposure. As discussed in Chapter 15, reduction in Association of Canada. An alternative review of treatment
infiltration rates may not be sufficient to achieve the theory is provided in The Global Acid Rock Drainage
desired benefits from a cover. Lower volumes of (GARD) Guide, funded by International Network for Acid
16 – Closure and reclamation 285

Prevention (INAP 2009). The available treatment systems Water flow through passive systems is typically by
are often broadly categorised as active, passive and hybrid gravity drainage, and can offer greatly reduced level of
(combined active and passive). complexity and greatly reduced staffing levels and skills; as
Active treatment refers to a range of facilities that a result, it potentially offers cost savings. Passive treatment
require the input of energy and/or treatment chemicals systems are designed for low maintenance, with the
on an ongoing basis and require ongoing supervision to possible exception of periodic reconstruction or
ensure correct functioning. Active treatment plants can replenishment of active components over the long-term
be sized to accommodate most flow rates and acidity (normally periods of the order of years to decades between
loadings, with costs being a function of factors such as replenishments). Some of the typical passive water
flow, flow variability, mass loadings, types of contaminants treatment systems include wetlands (both aerobic and
to be removed and final desired discharge concentration. anaerobic), biochemical sulphate-reducing reactors, anoxic
Typical treatment plants for ARD/ML include low-density limestone drains, vertical flow wetlands, limestone leach
sludge and high-density sludge plants, where the collected beds and open limestone channels.
water is dosed with an alkaline reagent to neutralise pH Passive treatment of ARD is no longer an emerging
and promote metal precipitation in the form of hydroxides. technology, and there exists a considerable base of practical
Typical alkaline reagents include lime, caustic soda, soda experience to guide designs. Passive treatment research
ash and ammonia. The precipitates form a sludge, which and development have been carried out over a period of
will require collection and disposal on an ongoing basis. decades. Skousen and Ziemkiewicz (2005) provide a review
There exists considerable documentation in the literature of the performance of 116 passive treatment systems for
on experiences with the treatment of ARD and ML with acid drainage. In general, passive treatment requires a
active treatment systems (e.g. Skousen et al. 2000). much larger land area than active treatment and, as a
With increasing treatment costs, and higher metal result, the process has not been frequently applied to large
values, ARD/ML treatment operators have implemented flow rates. An important drawback of certain passive
systems designed to recover metals. Such systems can treatment systems is the undesired release of nutrients
reduce net operating costs through the sale of the from the reactors.
recovered metals, and in some cases operate treatment The costs associated with both passive and active
systems at a profit (Bratty et al. 2006). Metal recovery treatment systems can be significant. The long-term costs,
systems are normally implemented for waste streams with especially for active treatment systems, have the potential
relatively high levels of metals, in cases where relatively to exceed all other closure costs for a given mine site. As
little prevention effort has been implemented. However, a result, the requirement for treatment systems should be
case studies exist where metal recovery is economically carefully evaluated and mechanisms to avoid the need for
justified at trace levels. water treatment given full consideration.
While generally reliable and effective, the operating
expenses for an active treatment plant need to be properly
dimensioned, taking into account the requirements for
16.4 Physical stability
energy, reagents, labour and sludge disposal. In addition, The approach to geotechnical stability analysis of waste
the needed treatment period will very likely exceed the rock facilities has been described in depth elsewhere in
design life of many treatment plant components. As a this book. The applicable analytical techniques are
result, long-term operating expense estimates should described in Chapter 8, and the applicable criteria have
include periodic refurbishment of the plant. Because of the been discussed earlier in this chapter. It is increasingly
cost implications of these considerations, there can be a common that waste rock dumps are designed for closure,
strong motivation to design waste rock dumps in such a at least in terms of using stability criteria in the design that
way as to avoid active treatment. are suitable for closure. However, additional, long-term
stabilisation measures for waste rock facilities are required
Passive treatment involves the use of natural
in the following cases:
geochemical, biological and physical reactions that result
in the improvement of water quality. Since, by definition, ■ The original design or ‘as-built condition’ of the waste
passive systems run unattended for extended periods, such rock facility does not meet suitable closure criteria for
systems typically exhibit variability in process parameters long-term stability (e.g. the selected design earthquake
and in effluent results. Therefore, passive systems are is smaller than that required for closure purposes).
ideally suited to applications where load reduction takes ■ Changes of material properties that could affect
preference over meeting high removal efficiency long-term behaviour of the facility are expected (e.g.
specifications. the presence of residual waste that may be subject to
286 Guidelines for Mine Waste Dump and Stockpile Design

weathering or breakdown in the long term, or thawing adequate geotechnical stability, and will very likely
of previously frozen soil), and were not taken into exacerbate erosion due to the longer slope length, smooth
account in the original design. flattened surface and placement of topsoil (Williams 2016).
■ Settlements that would adversely affect drainage Depending on the differences between the constructed
patterns and/or long-term landforms are expected. configuration and the desired final landform, slope
flattening may also involve significant expense for earth
Closure activities to ensure long-term stability of waste
moving and increase the facility footprint. As such, it
rock facilities generally consist of reshaping or buttressing
should not be undertaken lightly, or simply to meet
of the facility slopes to achieve an adequate factor of safety
vaguely defined perceptions.
under the selected closure criteria for long-term stability.
From a construction point of view, slope angles of the
The design of adequate buttressing or reshaped slope
order of 2.5H:1V or 3H:1V (of the order of 20°) represent a
geometry to ensure slope stability in the long term should
practical limit on the steepness of slope on which heavy
be assessed based on the results of stability analysis. This
equipment can be used to place soil for revegetation. As a
includes addressing factors such as weathering of the
result, some facilities have been designed with benches set
materials within the facility and resulting reductions in
back such that, at closure, successive angle of repose lifts
strength expected in the long term.
can be flattened out to an overall 20° slope without
affecting the final facility footprint.
16.5 Land forms and erosion For the long-term stability of vegetated waste rock
dump covers, the geomorphic approach has gained
control increasing attention since the mid 2000s, arising as an
The traditional construction of waste rock facilities by the alternative to the more traditional ‘structural’ approach. In
loose end dumping of waste rock from the tip heads of both approaches, the importance of surface runoff as an
multiple lifts results in uniform slopes at the angle of erosional agent is recognised. In the structural approach,
repose of the material (typically 37° or ~1.3H:1V), water movement is controlled and channelled over the
separated by flat benches. As part of waste rock facility waste rock facility using benches, berms and other
closure and reclamation, the angle of repose slopes may be traditional water control structures. In the geomorphic
flattened, contour drains constructed on the benches, approach, natural analogues are sought out through
downslope drains constructed to deliver rainfall runoff to observation of the landscape in the area of the facility, with
the toe, and the slope surface topsoiled and revegetated. hill slope forms and gradients, watershed characteristics
Typical motives for this are stated as being improved and vegetation observed and measured. These data are
geotechnical stability, safe access, facilitation of then used to develop surface contours and systems that,
revegetation efforts and post-mining land use, and using the facilities existing configuration as a base, will to
meeting stakeholder and regulatory demands. However, some degree mimic the natural landforms and provide a
the flattening of the angle of repose slopes that are made structure that will permit discharge without excessive
up of durable waste rock is not typically required to ensure erosion.

Figure 16.1: Waste dump with structural closure on south side and geomorphic approach on north (Washington, USA). Source: Google
Earth Pro (2015)
16 – Closure and reclamation 287

The contrast between these two approaches is As presented in earlier sections of this chapter,
illustrated in a single waste dump at TransAlta’s Centralia addressing closure issues during design phases can be
Mine in Washington State, USA. As shown in Fig. 16.1, the beneficial in ensuring successful closure. Where possible,
south side of the dump was closed using the structural waste rock dumping should be planned to minimise
approach, with linear structural features clearly visible in material rehandling, controlling closure costs. If the
the satellite image. The northern and north-east side of desired landform is identified early through the
the facility were designed using the geomorphic approach, application of geomorphic principals, construction can
with curved surfaces and dendritic drainage patterns. be planned accordingly. This may involve early definition
The current approach for final landform design and of bench location, so that benches form a stepped outer
planning has been refined as a result of observation of the profile that can be easily reshaped into a stable landform
performance of historical reclamation practices and the at closure. A waste rock facility constructed using this
development of numerical models with the ability to approach may only require cut/fill movement of the waste
simulate the evolution of landforms under the action of rock between the setbacks, whereas a facility constructed
runoff and erosion over long periods of time. Some general without such advance planning may require significantly
design considerations to optimise waste rock facility more earthworks to achieve the desired closure
configurations at closure, based on observations at various configuration.
sites, are as follows (Environment Australia 1998; Sawatsky
2004; Ayres et al. 2006):
16.6 Revegetation
■ Where possible, it is preferable that final geometry Where technically and economically feasible, it is normally
resemble a ‘mature’ landform, which involves measures either desired or legally mandated to revegetate the closed
such as the following: facility surface. There are exceptions to this, such as in
→ designing the final landform using natural ana- extremely arid climates or cold climates, where it may be
logues (geometries and natural landforms of the standard practice to leave the closed waste rock facility
surroundings) surface with no vegetation.
→ avoiding benches, terraces, contour banks and Options for revegetation include direct revegetation of
abrupt changes in topography the waste rock (Fig. 16.2) or revegetation of some final
→ avoiding man-made materials (pipes, concrete, cover surface (typically a soil or soil blend) that has been
gabions) placed over the waste rock, either with or without a cover
→ using a ‘spur-end’ shape in plan with a concave– system.
convex profile if feasible Considerable experience in the revegetation of mine
→ providing appropriate distribution and quantity of waste facilities has been amassed in the last 50 years. It is
drainage features (function of climate, ‘soils’ and now common practice to salvage any existing topsoil at
slope) waste rock facility sites before construction and to either
→ situating watercourses in ‘valleys’ as opposed to use it to support the reclamation of existing waste rock
banks dumps (progressive closure) or stockpile it for use in future
→ establishing vegetation progressively. closure works. If stockpiled, the soil storage should be
■ The top surface should be sloped and minimised if designed and managed to maximise the long-term viability
practicable. A large flat surface at the top of a waste of the soil. Management to promote viability includes
facility may act as a temporary pond for incidental protecting the stockpiled topsoil from erosion and
rainfall. Especially in wet climates, ponding is a maintaining microbial communities, which are necessary
concern as accumulated water may find a low point on to provide nutrients to plants. This includes maintaining
the rim and discharge, leading to the formation of deep good aeration by avoiding compaction during stockpiling,
erosion gullies on the slopes. If a sloped or domed and discing or ripping to loosen the surface. It is also
shape is impractical, construction of small containment important to establish native vegetation on the stockpiles,
berms (bunding) on the top of the facilities may be since many of the soil organisms need to be in contact with
required to retain runoff. plant roots to survive (e.g. mycorrhiza).
■ When practicable, it may be desirable to include the Where topsoil (either previously stockpiled or from
construction of small lakes and wetlands upstream of borrow sources) is not available, or the impacts of taking
final surface water discharge points, provided they are topsoil from other sites are unacceptable, there may be
geomorphically compatible and stable. Such features workable alternatives, such as the application of organic
will attenuate surface runoff to reduce peak flows and matter (manure, compost, biosolids), chemical
increase sedimentation before reaching receiving amendments, soil conditioners, mulches and nitrogen
streams. fixing plant species to promote revegetation efforts.
288 Guidelines for Mine Waste Dump and Stockpile Design

Figure 16.2: Vegetation growing directly on a waste rock facility surface in an arid climate (135 mm precipitation average per year).
Source: B Weeks

While a variety of actions (including irrigation) may to concerns that tree roots will penetrate the barrier layer
be used to promote the initial establishment of vegetation and in time degrade the layer’s effectiveness. This has
on the facility surface, the normal goal is to attain a self- necessitated ongoing tree removal programs at sites where
sustaining (‘walk away’) ecosystem. As a general rule, the volunteer species would otherwise generate a succession
ecosystems in the surrounding area provide an indication of trees over the planted grasslands.
of the attainable final state for the cover. Vegetation Erosion control, as alluded to in the previous section,
densities in the surrounding area indicate the maximum is a key consideration in effective revegetation. There are
vegetation density that could reasonably be attained over many instances of covers that have failed due to erosion of
the longer term, although there may be some variations in the surface soil, occurring either because of design
attainable densities and species distributions as a function inadequacy or because of a low-frequency storm occurring
of factors such as substrate thickness and the direction of before the establishment of vegetation that would have
exposure. otherwise prevented the soil loss.
The establishment of self-sustaining vegetation on a Species selection for revegetation is a subject for
waste rock dump may take years. Factoring in species site-specific, specialist analysis. While it is not uncommon
succession at the site, it may be decades before the plant to see conceptual closure plans (or even regulations) that
communities reach their long-term ‘steady state’. The specify revegetation with native species, careful
species that dominate immediately after revegetation consideration should be given to both native and non-
efforts are generally replaced by other species over time. native species. Especially in the early stages of
Fortunately, plant species succession is a natural process revegetation, the lands to be rehabilitated are likely to
and in many instances does not require any human exhibit many conditions that are distinct from the
intervention to proceed (although weed control may be surrounding lands, and there may be strong arguments for
necessary). On the other hand, if the natural progression the use of non-native species to meet specific design goals.
results in conditions that would be contrary to the overall The development of revegetation programs for
closure design, controlling natural succession may rehabilitation is an area that benefits greatly from research
generate an ongoing care and maintenance need. The work conducted well in advance of closure. Test plots and
common example of this is vegetation on covers that have progressive closure give an opportunity to test alternative
an underlying barrier layer. While the vegetation provides approaches; evaluate seed mixes, seeding methods and
an important component of the cover (promoting seedbed preparation; and undertake preparation of the
evaporation), tree growth is generally not desirable due seed banks needed for closure.

You might also like