You are on page 1of 5

D.

Vasanth Kumar1,*,
G. Madhan Mohan2,
Lean Tool Implementation in the Garment
K.M. Mohanasundaram3 Industry
DOI: 10.5604/01.3001.0012.9982
1
Dr N.G.P Institute of Technology, Abstract
Department of Mechanical Engineering, Garment Manufacturing is one of the oldest in the world, compromising a high number of
Coimbatore, India critical operations. The main issues in the garment industry are the lead time, production
* e-mail: vasanthmech09@gmail.com rate, very poor line balancing and fabric wastes. Productivity improvement is carried out
2
P.S.G College of Technology, by implementing the various lean tools in the industry, such as 5S, Value Stream Mapping
Department of Production Engineering, (VSM) and line balancing in the sewing section. After the implementation of lean tools in
Coimbatore, India the garment industry, the outcomes observed are a reduction in work-in-progress inventory,
increases in the production process and increased line efficiency. Similarly the before and
3
SVS College of Engineering, after implementation of 5S, which shows space utilisation in the sewing section, is increased.
Coimbatore, India In this research, an implementation study was conducted in only one organisation. Hence the
results extracted by the conduct of this implementation study are achievable and adaptable
in similar organisations.

Key words: lean tools, value stream mapping, 5S, line balancing.

Introduction implementation is essential to adapt it An ideal workstation can be effectively


in similar garment industries to identify utilised by using line balancing without
Global competition in the garment sectors improvements in small and middle scale an uninterrupted flow in the process [15].
makes garment manufacturing a most industries. An empirical study in the garment indus-
sensitive issue [1]. The trend which try gave a more in-depth validation of the
makes the garment industries look for The garment sector production process is ideas proposed [16]. Lean manufacturing
change in the manufacturing paradigm is always a short life cycle with a number tools can enhance productivity by a re-
the fluctuating demand in market condi- of sub-processes [6]. The fast change in duction in the lead time of the process
tions. Thus lean manufacturing emerged the fashion and customer-focused market through eliminating non-value added
as a paradigm to make the industry more creates the values in apparel manufactur- activities [17]. Productivity is an impor-
competitive by eliminating wastes [2]. In ing [7]. The garment industry is exposed tant parameter for any manufacturing in-
lean manufacturing, which encompasses to an inconsistent supply of raw materials dustry, comprising value added activities
various tools and techniques to enhance in the production process. Resource allo- and non-value added activities [18]. 5S
performances, some of the tools are 5S, cation is a major process in any organisa- is a basic lean manufacturing tool which
Value stream mapping (VSM) and line tion, which requires continuous analysis provides a pathway for other lean tools to
balancing [3]. The production process in of internal and external factors due to the implement in any organisation [19].
the garment industry involves four main inherent complexity [8]. Lean manufac-
processes, namely designing/pattern gen- turing focuses on waste reduction and
eration, cutting, sewing and packing. productivity improvement through var- Selection of a suitable manufacturing
The most important and critical factor in ious lean tools, value stream mapping, organisation for study
the garment industry is the sewing sec- line balancing and work standardisation
tion, which involves a greater number [9]. The combination of various lean
of operations [4]. This case study high- tools, such as 5S, line balancing, stand-
lights the various wastes in the garment ardised work and value stream mapping, Study of existing process
industry, such as inventory, lead time results in productivity improvement in • Develop current state map
and quality defects, which are reduced both labour intensivity and equipment • Analyse current state map
to improve productivity. Thus lean tools flexibility [10]. Successful implemen- • Derive proposal for future state map
such as VSM, 5S and line balancing tation of the lean manufacturing tool in
help in visualising the wastes occurring small and medium scale industries leads
in an organisation and possibilities for to increases in the workforce, machines
eliminating/reducing them. The applica- and methods of the manufacturing pro- Construction of future state map
tion of VSM initially attempts to reduce cess [11]. Value stream mapping is a key
waste and non-value activities, and find performance indicator that measures the
possible improvements in the lead time, performance of a manufacturing process
production time and inventory level [5]. [12]. Lean manufacturing, which reduces Lean tool implementation
Based on the existing study in the organ- the flow quality duration, increases the • 5S implementation
isation, a current state map is generated. operating speed and improves delivery • Line balancing in sewing section
Upon analysis of the current state map performances [13]. Line balancing is
with TAKT time calculation, a future a tool which enhances productivity and
state map is proposed with the possible improves the efficiency of the produc-
improvements, and an attempt is made on tion process, while Poka-Yoke is one of Empirical analysis based on study
the production line to balance the work the lean manufacturing tools which can
at each station. The understanding of this eliminate waste by pool proofing [14]. Figure 1. Research methodology.

Kumar DV, Mohan GM, Mohanasundaram KM. Lean Tool Implementation in the Garment Industry. 19
FIBRES & TEXTILES in Eastern Europe 2019; 27, 2(134): 19-23. DOI: 10.5604/01.3001.0012.9982
Current state.igx

20
SEWING
SECTION

Figure 2. Current state map.


Firs t
Rib piping Sec ond Label Sleev e hem Sleev e Side seam
Shoulder Nec k Binding Bottom hem Peak
ov erloc k Shoulder attach attach lower attachment ov erloc k
attach

1 1
Defect = 5% 1 Defect = 1% 100 pcs 1 100 pcs 1 100 pcs 1 1 1 100 pcs
1 1 100 pcs 100 pcs 100 pcs
100 pcs 100 pcs 30 minutes 20 minutes 30 minutes 60 minutes Total C/T = 200 seconds Total C/T = 200 seconds
Total C/T = 200 seconds Total C/T = 130 seconds Total C/T = 180 seconds Total C/T = 125 seconds Total C/T = 240 seconds Total C/T = 350 seconds
Total C/T = 108 seconds 10 minutes 60 minutes Value Add: 180 seconds 60 minutes Value Add: 175 seconds
Total C/T = 68 seconds 2 minutes 20 minutes
Value Add: 188 seconds Value Add: 120 seconds Value Add: 165 seconds Value Add: 110 seconds Value Add: 225 seconds Value Add: 300 seconds
Value Add: 60 seconds Value Add: 100 seconds NVA = 20 seconds NVA = 25 seconds
NVA = 12 seconds NVA = 10 seconds NVA = 15 seconds NVA = 1 seconds NVA = 15 seconds NVA = 50 seconds
NVA = 8 seconds NVA = 8 seconds Defect = 1% Defect = 0%
Defect = 3% Defect = 1% Defect = 1% Defect = 1% Defect = 1% Defect = 4%
Defect = 3% Defect = 3% C/O = 3 mins. C/O = 2 mins.
C/O = 20 secs. C/O = 20 secs. C/O = 1 mins. C/O = 2 mins. C/O = 1 mins. C/O = 3 mins.
C/O = 30 secs. C/O = 20 secs. Uptime = 99% Uptime = 99%
Uptime = 99% Uptime = 99% Uptime = 99% Uptime = 99% Uptime = 99% Uptime = 99%
Uptime = 99% Uptime = 99% Availability: 99% Availability: 99%
Availability: 99% Availability: 99% Availability: 99% Availability: 99% Availability: 99% Availability: 99%
Availability: 99% Availability: 99%

Future state.igx
Lead Time = 322 minutes
1.13 minutes 2 3.33 minutes 20 1.8 minutes 30 2.17 minutes 20 3 minutes 30 2.08 minutes 10 4 minutes 60 5.83 minutes 60 3.33 minutes 60 3.33 minutes
(1 minutes) minutes (3.13 minutes) minutes (1.67 minutes) minutes (2 minutes) minutes (2.75 minutes) minutes (1.83 minutes) minutes (3.75 minutes) minutes (5 minutes) minutes (3 minutes) minutes (2.92 minutes) VA / T = 27.1 minutes
In-plant Time = 322 minutes
Transport Time = 0 seconds

SEWING
SECTION

Figure 3. Future state map.


5S INSPECTION 5S 5S 5S 5S
INSPECTION INSPECTION INSPECTION
5S INSPECTION
Firs t
Rib piping Sec ond Label Sleev e hem Sleev e Side seam
Shoulder Nec k Binding Bottom hem Peak
ov erloc k Shoulder attach attach lower attachment ov erloc k
attach

3 3
Defect = 5% 3 Defect = 1% 10 pcs 2 10 pcs 3 100 pcs 2 4 5 100 pcs
1 2 100 pcs 100 pcs 100 pcs
10 pcs 50 pcs 10 minutes 5 minutes 30 minutes 30 minutes Total C/T = 68 seconds Total C/T = 67 seconds
Total C/T = 66 seconds Total C/T = 60 seconds Total C/T = 58 seconds Total C/T = 62 seconds Total C/T = 59 seconds Total C/T = 70 seconds
Total C/T = 52 seconds 10 minutes 30 minutes Value Add: 56 seconds 30 minutes Value Add: 59 seconds
Total C/T = 66 seconds 2 minutes 5 minutes
Value Add: 63 seconds Value Add: 55 seconds Value Add: 53 seconds Value Add: 58 seconds Value Add: 52 seconds Value Add: 61 seconds
Value Add: 64 seconds Value Add: 50 seconds NVA = 12 seconds NVA = 8 seconds
NVA = 3 seconds NVA = 5 seconds NVA = 5 seconds NVA = 4 seconds NVA = 7 seconds NVA = 9 seconds
NVA = 2 seconds NVA = 2 seconds Defect = 1% Defect = 0%
Defect = 3% Defect = 1% Defect = 1% Defect = 1% Defect = 1% Defect = 4%
Defect = 3% Defect = 3% C/O = 3 mins. C/O = 2 mins.
C/O = 20 secs. C/O = 20 secs. C/O = 1 mins. C/O = 2 mins. C/O = 1 mins. C/O = 3 mins.
C/O = 30 secs. C/O = 20 secs. Uptime = 99% Uptime = 99%
Uptime = 99% Uptime = 99% Uptime = 99% Uptime = 99% Uptime = 99% Uptime = 99%
Uptime = 99% Availability: 99% Availability: 99%
Uptime = 99% Availability: 99%
Availability: 99% Availability: 99% Availability: 99% Availability: 99% Availability: 99%
Availability: 99%
Availability: 99%

Lead Time = 162 minutes


1.1 minutes 2 1.1 minutes 5 52 seconds 10 60 seconds 5 58 seconds 30 1.03 minutes 10 59 seconds 30 1.17 minutes 30 1.13 minutes 30 1.12 minutes
(64 seconds) minutes (63 seconds) minutes (50 seconds) minutes (55 seconds) minutes (53 seconds) minutes (58 seconds) minutes (52 seconds) minutes (61 seconds) minutes (56 seconds) minutes (59 seconds) VA / T = 571 seconds
In-plant Time = 162 minutes
Transport Time = 0 seconds

FIBRES & TEXTILES in Eastern Europe 2019, Vol. 27, 2(134)


Research methodology Table 1. Reduction in each category.

The methodology followed during this Production cycle Non-value added


Inventory, min
time, sec time, sec
research project is shown in Figure 1. Time for operations
Current Future Current Future Current Future
Summarising a review of suitable organ- state state state state state state
isations for implementing the various One side shoulder attach 68 66 8 2 2 2
lean tools was undertaken to carry out
Rib piping overlock 200 66 12 3 20 5
the study. After identifying the organisa-
Second shoulder attach 108 52 8 2 30 10
tion, the existing products and processes
Neck binding 130 60 10 5 20 5
preformed in the organisation for man-
Neck binding finish (label) 180 58 15 5 30 30
ufacturing the products were classified.
Sleeve hem lower 125 62 15 4 10 10
A current state map was developed for
Sleeve attachment 240 59 15 7 60 60
formulated and further improvements
Side seem overlock 350 70 50 9 60 60
in lean tool implementation, discussed
Bottom hem (full length) 200 68 20 12 60 60
with the executives of the organisation
to develop a future state map. After the Peak (in sleeve and rib) 200 67 25 8 60 60

development of the future state map, lean Total time 1801 628 178 57 352 302

tools such as 5S and line balancing were Percentage reduction, % 34.86 32.07 14.02

implemented in the organisation. Finally


empirical analysis was carried out with
the executives of the company on lean and resources. An average of sixteen pro- Future state map
tool implementation. cesses are carried out in completing the The future state map preparation is initi-
kid’s tees. The main processes include ated with the aid of the current state map.
About the organisation marking and cutting, sewing, inspec- The gaps and possible improvements are
tion, finishing and packing. The sewing identified from the current state map to
A study on lean implementation using
section is taken for analysis, in which propose a future state map. The differ-
VSM was carried out at the ABC gar-
more critical processes are carried out. ence made in the existing production cy-
ment factory located in Tiruppur, India.
The change over time between the pro- cle time is 30 minutes, which is reduced
It is an ISO certified organisation man-
cess is 10 minutes. The organisation to 10 minutes, which is proposed in the
ufacturing products for men, ladies and
works on three shifts every day (each future state map, as shown in Figure 3.
children. The company manufactures
shift of an eight-hour duration with The  existing inventory is reduced to
normal styles, trendy styles, night-wears
a thirty minute lunch break). The bundle 302 minutes in the future state from the
and value-added styles, with accessories
system of manufacturing currently I pro- current state of 352 minutes. The lead
made even at their customers’ choice.
gress is followed in the garment factory time for completing the process is re-
The ABC garment factory was started in
with a batch size of two hundred pieces. duced to 252 minutes from the current
the year 1999 with 10 employees. Pres-
state of 322 minutes in the future state
ently it employs 300 personnel, including
The available production time is calcu- proposed. 5S introduced is at every stage
management, with an annual turnover
lated as follows: of the operations in the organisation.
of about four crores Indian national ru-
Stage inspection is introduced, which
pees (INR). Some of the potential export Available time = Total production time –
eliminates the final inspection, and con-
countries include European ones: Italy, Planned down time
sequently the rejection of the product at
Germany, Switzerland, Hungary and
Available time = (60 × 8 × 3) – (30 × 3) the final stage is reduced.
Portugal.
= 1350 Minutes
Selection of the product Uptime = Actual operating time/Availa- Results and discussion
All the dates concerning the product ble time
Value stream mapping
were studied in terms of production vol- = (Available time – Changeover
time) × 100%/Available time Several improvements are identified
ume, demand, inventory and operations
= (1350 – 10) × 100/1350 based on the current state map for the
performed. A baby girl’s tee was select-
= 99.2% future state map for implementation.
ed as the product for study. Raw materi-
Significant changes are developed in the
als were supplied by an external vendor Available working time per day
Takt time = future state, such as a reduction in the
and a manufacturing process for pattern Custome demond rate per day production time, non- value added time
making, sewing, thread trimming and and inventory time, as shown in Table 1.
pressing, quality checks and packing was 1350
made to complete this product cycle. = 340 The change-over-time benefits the organ-
isation in shifting to a new product fam-
= 238 sec ily and helps in the delivery schedule.
Current state map The value added time gives an excess of
A current state map is developed for the The value added time for the current 18 hrs to the process.
kid’s tee as shown in Figure 2. Orders process is 27 minutes for all the process
are received from the customer regularly in the sewing section. The process dura- A comparison of cycle time modifica-
on a monthly basis of around 8500 piec- tion of the product of the daily demand tions is shown in Figure 4. Based on the
es. This information is shared with the is 322 minutes, and the idle time for the possible potentials identified during the
supervisor for the allocation of personnel process is 1000 minutes. analysis of the current state map, few ma-

FIBRES & TEXTILES in Eastern Europe 2019, Vol. 27, 2(134) 21


sewing machine,
sewing unneeded
machine, stock
unneeded between
stock workers,
between excess
workers, inventory
excess on on
inventory thethe
floor, improper
floor, flowflow
improper of of
needed equipment.
needed andand
equipment. no no
floor layout.
floor This
layout. is refined
This by by
is refined removing excess
removing inventory
excess andand
inventory introducing
introducing
a floor layout,
a floor as shown
layout, in Figure
as shown 4. 4.
in Figure

Figure 4. 5S Implementation.
Figure 4 –45S
Figure Implementation
– 5S Implementation
Table 2. Line balancing outcomes. Positional Weight (RPA) techniques are
SortSort
: All: All
useless items
useless areare
items sorted andand
sorted eliminated from
eliminated thethe
from sewing section
sewing usedfor
section smooth
for for smooth
balancing flow.
the Inthe
flow.
line in addition
Insewing
addition
Productivity variable Before line balancing After line balancing
section. The preference relationship be-
to that. the
to that. semi-finished
the
Labours per production line fabric
semi-finished is8sorted
fabric is sorted andand
Labours/line an an
order7 number
order number
Labours/line is given in the
is given
tween
cutting
ineach
the section
cutting
task
to ensure
section
and the to ensure
specific order in
Production target 44 tees/day/labour 41 tees/day/labour
proper fabric
proper identification
fabric in the
identification temporary
in the storage,
temporary created
storage, based
created which
on on
based the tasks
the are performed
processing
the processing istime
time calcu-
andand
Production capacity 350/day 352/day
lated. After the cycle time (C) is calcu-
Balancing loss 18% 12.48%
sequences of
sequences the operations
of the performed
operations in the
performed factory,
in the which
factory, whichresults in more
results in more
lated, space
the spaceavailability.
availability.
theoretical minimum number
of workstations is determined in order to
jor: changes are proposed and implement- smoothwastes satisfy the workstation cycle time:
Shine
Shine Dust, dirt,
: Dust, waste
dirt, fabrics
waste andand
fabrics otherflow.
other Inare
wastesaddition
are to that. Temporary
removed.
removed. the
ed to observe the changes made during semi-finished fabric is sorted and an or-
storage
Temporary tables
storage andand
tables floors
floors
Cycle time C = Total available period/
have been
the
have lean cleaned
been according
implementation.
cleaned to the
As a result,
according the time schedule.
der time
to the number AlltheAll
is given in
schedule. machines,
cutting sectiontools
machines, andand
tools work areas
work areas
Total areare
output cleaned
cleaned
required
production process at the inventory level to ensure proper fabric identification in = 1350/ 350
by the employee
byisthe employee
reduced at the endend
atwhich
by 14.02%, the isof the shiftshift
of the
achieved time.
the time. storage, created based on
temporary = 3.85 min/ tees
by regularising proper communications the processing time and sequences of
among the employees and the pull sys- the operations performed in the factory, Number of workstations required, N =
Order tem: and
Order All: All
itemsitemsareare
implementing placed
5S placed
in andand
the cuttingarranged
arranged in an
which results in appropriate
an
in more appropriate place
space availability. after
place aftersorting
= Sum sorting and
of task cleaning.
and time TheThe
cleaning.
time/Cycle
and sewing sections. The production pro- = 26.9/ 3.85
items
items areare arranged
arranged in such
in such a way
a waythatthat
theytheyareare based
based on onthethe degree
degree of usage
of usage in the production
in the production
cess is modified from a progressive bun- Shine: Dust, dirt, waste fabrics and oth- = 6.97 ≈ 7 Stations
process.
process. Semi-finished
dle system fabric
to a unit production
Semi-finished is arranged
system.
fabric in an
er wastes
is arranged are
in an ‘L’ ‘L’
shaped
removed. layout,
Temporary
shaped stor-which
layout, whichenables
enables thethe smooth
smoothflowflow
of of
age tables and floors have been cleaned Theoretical efficiency of the line TE =
materials.
5S tool To To
materials. ensure
ensuresafety safetyin in
theaccording
factory,
the factory, work
to the work
time surface
surface
schedule. borders,
All floor
borders,
ma- = Sfloor
umborders
of task time/(Number
borders for for of sta-
walkways,
walkways,
tions × cycle time )
The 5S tool helps everyone by making chines, tools and work areas are cleaned
workways
workways andand storage location
storage locationhave been
have introduced
been introduced in the section.
in the section. = 26.9/(7 × 3.85)
the opportunity to learn a culture of de- by the employee at the end of the shift
time. = 99.81%
veloping and maintaining a clean and
organised working environment. 5S is Actual efficiency of the line TA =
Line
Linebalancing
balancing
implemented in the sewing section and Order: All items are placed and arranged = Sum of task time/(Number of sta-
cutting section in the garment factory in an appropriate place after sorting and tions × cycle time )
as a model, since it is one of the most cleaning. The items are arranged in such = 26.9 /(8 × 3.85)
critical work areas. The complications a way that they are based on the degree of = 87.33 %
in the cutting and sewing section are usage in the production process. Semi-fin-
Balancing loss BL = 99.81 – 87.33
space utilisation, semi-finished fabric ished fabric is arranged in an ‘L’ shaped
layout, which enables the smooth flow of = 12.48%
around the sewing machine, unneeded
stock between workers, excess invento- materials. To ensure safety in the factory, Production target PT at 65% efficiency =
ry on the floor, improper flow of need- work surface borders, floor borders for = (7 labours × 1350 min/day)/26.9
ed equipment and no floor layout. This walkways, workways and storage location = 352 tees/day.
is refined by removing excess inventory have been introduced in the section.
and introducing a floor layout, as shown Total labour productivity in sewing sec-
in Figure 4. Line balancing tion = 352 / 21 = 17 tees/labour/day
Line balancing is the one of the important
Sort: All useless items are sorted and factors to make production flow smooth- Balancing in the line is made by chang-
eliminated from the sewing section for er as compared to the normal flow. Rank ing the traditional layout to a balanced

22 FIBRES & TEXTILES in Eastern Europe 2019, Vol. 27, 2(134)


layout model, which demonstrates the plemented which will provide even better 10. Karabay G. et al. Combining lean tools
amount of improvement considered in improvements for an organisation. application in kaizen: a field study on the
the process, as shown in Table 2. printing industry. FIBRES & TEXTILES
in Eastern Europe 2018; 26, 1(127):
8-12.
Conclusions References
11. Shah D, Patel P. Productivity Improve-
ment by Implementing Lean Manufac-
The lean tool is a potential means of  1. Goh A. Evolution of industrial poli- turing Tools In Manufacturing Industry
eliminating wastes in an organisation, cy-making in support of innovation: The 2018; 3-7.
and recommended for identifying pos- case of Singapore. Int. J. Innov. Learn. 12. Karabay G, Kurumer G. Managing
sible improvements in an organisation. 2006; 3, 1: 110-125. Through Strategic Performance Man-
 2. Mcdonald T, Van Aken E M. International agement in Apparel Companies. FI-
During the implementation of lean tools
Journal of Applications: A Leading Jour- BRES & TEXTILES in Eastern Europe
in the garment industry, many potentials 2012; 20, 4(93): 13-19.
nal of Supply Chain Utilising Simulation
have been identified with the analysis of 13. Dal V, Akçagün E, Yilmaz A. Using Lean
to Enhance Value Stream Mapping: A
the current state map. These possible im- Manufacturing Case Application. Int. J. Manufacturing Techniques to Improve
provements are mapped with the future Logist. Res. Appl. 2002; 5, 2: 213-232. Production Efficiency in the Ready Wear
state map proposed. 5S and line balanc-  3. Forno A J D, Pereira F A, Forcellini F A, Industry and a Case Study. FIBRES &
ing in a garment factory are implement- Kipper L M. Value stream mapping: A TEXTILES in Eastern Europe 2013; 21,
4(100): 16-22.
ed in the sewing and cutting section as study about the problems and challeng-
es found in the literature from the past 14. Suhaimi M F M, Salleh N A M. A case
a pilot run, which shows a considerable study on the improvement of productivi-
15 years about application of Lean tools.
improvement in the factory. Based on the ty and efficiency of a quality control line
Int. J. Adv. Manuf. Technol. 2014; 72,
outcomes achieved in this implementa- 5-8, 779-790. for a cutting tool manufacturer. Journal
tion, the following results are obtained:  4. Akçagün E, Dal V, Yilmaz A. Using Value of Mechanical Engineering 2018; 5(Spe-
Stream Mapping At Apparel Industry: a cialissue1), 222-239.
n A significant achievement is a 34% 15. Azizoğlu M, İmat S. Workload smoothing
Case Study, no. April, 2015.
reduction in the production cycle time,  5. Bhamu J, Sangwan K S. Lean manufac- in simple assembly line balancing. Com-
a 14% reduction in the inventory time, turing: Literature review and research put. Oper. Res. 2018; 89: 51-57.
and a 32% decrease in the non-value issues. Int. J. Oper. Prod. Manag. 2014; 16. Stojanović D, Bašić A. Extended supply
time. 34, 7: 876-940. chain and small and medium retail en-
 6. Grandys E. Production Cycle Model terprises in Serbian garment industry.
n 5S implementation in cutting and for Short Life Cycle Models. FIBRES & FIBRES & TEXTILES in Eastern Europe
sewing enables better utilisation of re- TEXTILES in Eastern Europe 2010, 18, 2013; 21, 3(99): 13-17.
sources in an effective manner. 1(78): 8-12. 17. Nallusamy S. Productivity enhance-
 7. Kaczorowska-Spychalska D. Shaping ment in a small scale manufacturing unit
n The efficiency of the line is increased consumer behaviour in the fashion in- through proposed line balancing and
by 12.5%, so that human resources dustry by interactive communication cellular layout. Int. J. Performability Eng.
can be well utilised. forms. FIBRES & TEXTILES in Eastern 2016; 12, 6: 523-534.
Europe 2018; 26, 4(130): 13-19. DOI: 18. Saravanan V, Nallusamy S, George A.
n The production system has been mod- 10.5604/01.3001.0012.1307. Efficiency Enhancement in a Medium
ified from a progressive bundle sys-  8. Zimon D, Domingues P. Proposal of a Scale Gearbox Manufacturing Company
tem to a unit production system. concept for improving the sustainable through Different Lean Tools - A Case
management of supply chains in the Study. Int. J. Eng. Res. Africa 2018; 34:
textile industry. FIBRES & TEXTILES in 128-138.
Lean tools have been employed to iden-
Eastern Europe 2018; 26, 2(128): 8-12. 19. Seddik KM. Studying the implementa-
tify waste, but it is well-known that tool tion of 5S system in egyptian garment
DOI: 10.5604/01.3001.0011.5732.
implementation is limited to a single enterprise. Int. J. Ind. Manuf. Eng. 2017;
 9. Nallusamy S. Enhancement of Produc-
product family. Further research can be tivity and Efficiency of CNC Machines in 11, 7: 1989-1992.
extended to implementing lean tools a Small Scale Industry Using Total Pro-
to the rest of the product families in an ductive Maintenance. Int. J. Eng. Res.
organisation. Other lean tools can be im- Africa 2016; 25, August: 119-126. Received 27.11.2017 Reviewed 06.11.2018

FIBRES & TEXTILES in Eastern Europe 2019, Vol. 27, 2(134) 23

You might also like