Professional Documents
Culture Documents
net/publication/284572339
CITATIONS READS
0 1,942
3 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Lani Cheenikal on 25 November 2015.
ABSTRACT
Australia is one of the largest iron ore producing countries in the world. As a result of increased international demand
for iron ore, development of new open pit mines with associated infrastructure has been on the rise in Western
Australia. Design and construction of new rail lines and duplication along existing rail lines have been one of the key
issues for timely delivery of iron ore from mine to port. This paper presents geotechnical issues associated with the
design and construction of a major rail duplication project in the Pilbara Region in Western Australia that include cuts
and embankments up to 20m height. The geotechnical issues include geotechnical investigation, sourcing borrow
materials for construction of embankments including sub ballast capping, slope stability, settlement and construction
methods. A variety of rock formations were encountered along the alignment comprising igneous, sedimentary and
volcanics with variable degree of weathering. Slope stability assessment was undertaken using limit equilibrium
method, kinematic analysis concept and visual assessment. Deformation analyses were undertaken using PLAXIS
computer program. Geotechnical investigation, selection of parameters for engineering analysis and method of design
during the construction stage are discussed in this paper.
1 INTRODUCTION
Australia is the world’s largest iron ore exporter and as a producer, ranks second behind China (Geoscience Australia,
2013). In 2009, Australia produced over 393.9 million tonnes predominantly for export. Although iron ore resources
occur in all the Australian States and Territories, almost 90% of identified resources (totalling 31.5 billion tonnes) occur
in Western Australia, 80% of which occurs in the Hamersley Province, one of the world’s major iron ore provinces.
The ores from major mines in Western Australia’s Hamersley Province of Pilbara region are hauled from working faces
to crushing and screening plants using heavy trucks. The processed ore is then transported for further blending to port
sites. Most of the iron ores are transported to the ports by rail. Construction of the rail results in the formation of deep
cuts and high embankments along the alignment. This paper presents design issues of a major duplication of a 290km
long railway in the Pilbara Region of Western Australia.
2 RAIL EMBANKMENT
Predominant loading on the rail embankment was the rail axle loading as noted in Table 1.
Description Value
Average dynamic sleeper/ballast contact 310 kPa (for TCI of 30) and
pressure 380 kPa (for TCI of 40)
1
TCI is an indicator of the rail track condition. TCI value ranges between 30 or less for very good track condition and 69
for a track in very bad condition. RSL is the proportion of dynamic wheel loads that are transferred to the rail seat of
the sleeper and then transferred through the sleeper to the ballast and formation.
The total rail formation typically comprised the following layers from top:
• Ballast layer under sleeper;
• Sub ballast capping (SBC) layer;
• Transition layer (750mm thickness below SBC);
• General Embankment;
• Prepared Foundation.
The ballast and SBC layers are generally considered as the main parts of the rail formation. The embankment
(including the transition layer i.e. top 750mm of embankment) is sometimes considered as part of ‘bulk earthworks’.
3 EMBANKMENT MATERIALS
2
Uniaxial Compressive Strength (UCS) values of 5MPa and 30MPa were adopted to assess the average angle of internal
friction value. The Granite rocks, with average UCS values greater than 30MPa, are likely to be stronger than Talc-
Chloride Schist rocks based on results of previous geotechnical investigation. .
Given the above, values of friction angle (phi Ø) noted in Table 2 were assessed based on Barton (2008) and adopted in
Limit Equilibrium (SLOPEW) analysis to assess the slope stability against circular slip failure. Sensitivity analyses
were undertaken using shear normal function for Talc-Chloride Schist rocks based on Barton (2008).
Table 2 Rock Properties
3
Rail Load on Sub Ballast Capping Layer
FOS = 1.45
Transition Layer
Embankment
Embankment Base/Foundation
2 Shallow slip failure of RS-XW Excess moisture, erosion. Likely Insignificant Low
materials within the cut batters.
4
4.4 SUBBALLAST CAPPING LAYER THICKNESS
5
Table 5 – Cover (Ballast/Subballast) Requirement over Embankment Fill
Method 1 2 3 1 2 3 1 2 3 1 2 3
Total Thickness 450 330 490 370 330 490 540 380 580 450 380 580
(Ballast +
Subballast)
(mm)
Ballast 200 160 250 160 160 250 240 200 300 200 200 300
Thickness
(mm) over
Subballast
Subballast 250 170 240 210 170 240 300 180 280 250 180 280
(CBR ≥ 40%)
Thickness
(mm)
Note: Method 1: Ravitharan et al (1997); Method 2:AREA (US)- Talbot; Method 3:AREA (US) - JNR
Description Value
The modulus values noted in Table 6 were adopted for analysis under dynamic loading. Based on the analysis, a vertical
elastic settlement of about 4mm was assessed under the sleeper due to the applied pressure of about 310 kPa at the
sleeper/ballast interface. It should be noted that a three-fold increase in the vertical displacement may be expected
under long term repeated loading. A PLAXIS output is presented as Figure 3.
6
Vertical Displacement mm
5 CONCLUDING REMARKS
The following conclusions were made based on the results of the slope stability and settlement analyses for rail
embankments.
• Limit Equilibrium and other analysis including visual assessment of slopes can be successfully adopted for
embankment design and risk assessment. This is subject to ongoing monitoring and regular maintenance
program.
• Finite Element Analysis method can be successfully adopted to assess deformation of embankment under rail
load.
• The construction of rail embankments were completed in 2012 and the performance of the rail track have been
satisfactory to date. It is acknowledged that the embankments are to go through a few wet seasons before
performance can fully be assessed. Erosion or minor shallow slip failures are to be addressed by ongoing
monitoring and maintenance program.
6 ACKNOWLEDGEMENT
Most of the information in this paper has come from geotechnical investigation reports prepared by Coffey Geotechnics
Pty Ltd on a major rail upgrade project in Pilbara Region of WA.
7 REFERENCES
1. Barton, N. and Kjærnsli, B. (1981) Shear Strength of Rockfill, ASCE Journal of Geotechnical Engineering,
Vol. 107, No. GT7
2. Barton, N. P. (2008) Shear Strength of Rockfill, Interfaces and Rock joints and Their Points of Contact in Rock
Dump Design, ISBN 978-0-9804185-3-8
3. Department of the Navy, USA (1982) NAVFAC DM-7.1
7
4. Fell, R., Macgregor, P. and Stapledon, D. (2005) Geotechnical Engineering of Embankment Dams, ISBN 90
5410 128 8
5. Ravitharan, S.S. and Martin, M. (1996) Reduced Track Maintenance Through Engineered Ballast and Sub-
Ballast Design, Proceedings of the 11th International Rail Track Conference, Adelaide, P 752
6. Ravitharan, S.S. and Martin, M. (1996) Reduced Track Maintenance Through Engineered Ballast and Sub-
Ballast Design, Proceedings of the 11th International Rail Track Conference, Adelaide, P 752
7. US Army Corps of Engineers (2003) Engineer Manual - Slope Stability
8. US Federal Highway Administration (2003) Report – FHWAD-IF-030017, Geotechnical Circular No. 7
9. Geoscience Australia (2013) Extracted from Geoscience Australia website (www.ga.gov.au/minerals/mineral-
resources/iron-ore.html)