Abstract
The following document will provide more information regarding the project

Wellington Collen, Muwashi


Email Address: muwashiwelly@gmail.com
Student Number: im2078mc
Project Proposal

System Request

Use Case Diagram

Resource Needs (Human, Hardware and Software)

QA/ Testing Plan

Work Breakdown Structure

Software Requirements Specification

Software Development Methodology

User Interface (UI) Screen Shots

Mobile Dashboard Designs

Glossary

Bibliography
Project Information: Learner Management System 1.0

Project Time Frame: 08/06/2022 – 08/11/2022

Summary: Multifunctional integrated Learner Management System that will be designed to keep
records, also used to update records kept of a particular subject. It will work as a database that will
hold learner’s academic results

Process Impact: This proposal will be used to motivation towards the approval of the project by the
supervisor and any other academic representative.

In the world of today, nobody holds an initiative to check for notices on the notification boards.
Many students skip details on some relevant news and updates about their projects for their final
year. Students are therefore unable to track their project activities. It's easy to obtain all the
information and updates of the project from guides and coordinators for the students. Managing
tasks manually for the final year is a very stressful task. But anyone with a simple web platform can
do project-related work which is the main objective of the learner management system (LMS)

Being in the Information Technology sector for many years It has come to my attention that several
IT and infrastructure based problems precisely the implementation of a proper information
management system which is fully integrated with organizational and national regulations.

Many Private training institutions and practitioners tend to have challenges instead of meeting new
or make rules with inadequate support provided by the relevant infrastructure. The LDMS (learner
database management system) should be designed to be provided across all platforms with
integration services such as the hosting of online examinations, statistical analysis and reporting,
financial services and facilitator reporting services amongst others.

Currently the institutions (FET/HET) are using software handling learner academic data and learner
financial data with no integration between the both. The LDMS will attempt to combine these to
pivotal services into a single application that will provide better decision making.

*SETA’s and CHE (Council of Higher Education) have outsourced their annual reporting services
hence minimizing customer support and response times due to redirection for support services. This
results in latencies and delays in task completion. The current practices do not integrate learner data
provided by institutions via annual reports to that provided by such institutions on the NLRD
(National Learner Records Database), neither does it provide easy verification of programme
accreditation details.
To develop an easy to use, integrated educational management system that supports both
organizational and national regulations.

- Assessment / Online Examinations with easy uploads from learner using mobile devices or
from their laptops/PCs.
- Financial Integration that will work to hand-in hand-out with S.A.F practices and it will be
fully tested by an auditor.
- Accreditation Integration that supports both FET (Further Education and Training) and HET
(Higher Education and Training) regulations.
- Mobile communication to a central database server (SQL/MySQL) for easy reporting and
uploading to the Questions bank.

- The application will focus on providing a complete learner management system that
connects facilitators and management to help enforce organizational and national
regulations and reporting practices.
- The software will allow easy reporting and uploading of assessment questions and reports.
- Provided across all platform.
- Allow facilitators access it via mobile apps.
- login security will be implemented.
- Provide secured communication path to the central database.
- Provide accreditation information via easy web links and updated accreditation information.

- Customizable educational management system aligned


to national and organizational requirements.
- Guide/Reference Manual. - Mobile App.

- Rapidly changing governmental regulations may pose a difficult task to support.


- Opposition from governmental officials and organizations in support of such an application.
- Technical and compatibility difficulties between various devices

- Meeting the time-scale to complete the various functional points or services mentioned.
- Should I accomplish this task I would have developed a fully functional and integrated
software that will be highly marketable and useful product across various Private FET and
HET institutions. This can result in revenue and the migration of the sector to such a system.

Background information of Sponsor and team members

Project Sponsor(s) : Mr. Mzamo Ndlovu and Mr. Watson, Jacobs

Background Information:

Sponsor 1: Mr. Mzamo Ndlovu


ID: 8611035603083
Address: 43 Mountview Rd , Cordoba Gardens , Verulam
Email Address: ndlovumzamo784@itsolutions.co.za
Cellphone: +27 78 409 7590
Qualification(s): Honours In Information Technology
Skills: Experienced Software Developer - has advanced skills in:
- Visual Basic
- Microsoft SQL Server Administration
- Database Management and Design
- Legislation and Policy Developer
-Qualified Systems Engineer
Experience: Include relevant Experience in terms of the project.
Personal Data

Create account

Stuff Admin
Search

Snr Admin Edit Account

Student
Data Import/Export
iImport/Export

Stuff Admin Academic Info

Search Student

manually
Capture Marks
Snr Admin

Generate Reports

Read-only
Read-only
View Academic Info

Export Data Student

Stuff Admin
Auto Update
Examination

Student exam admission

System Login

Stuff Admin Manage Exam

\ Manage Question Bank


Student

Examination

Lecturer
Generate Reports

Financials

Login

Manage Financial
data/Transaction
s Read-only
Generate Financial
Student
Clerk report

Export Data
Learner Management System - Resource Needs
Project Information – Learner Management System
Project: Learner Management System (LMS)
Internal Release 1.0
Number:
Project Time-frame: 08/06/2022 – 08/08/2022
Related Documents: Project proposal
Software development methodology, Glossary

Process impact: Based on the project plan and the worksheet below, this project will need the following
resources to meet its goals. If fewer resources are available, the scope of the release should be reconsidered or
the process must be changed.

Human Resources
Needs
Needs Resources Amount Status Comments/Responsibilities
hours
Project Manager Mr Muwashi 15 Assigned Oversee the development
process
Consultation with topic Mr Manukuza 5 Assigned
experts of similar
systems
Training on use of M.S.Wenantu/ 10 Assigned Mr Manukuza an expert in API
component/technology
Mr Manukuza usage will help by teaching
integration methods
Overall Design M.S Wenantu 15 Assigned Self-Development with the
overall design reviewed by the
Project Manager
Detailed UI Design Mr Manukuza 15 Assigned
Detailed Database M.S.Wenantu 10 Assigned SQL foundation with cross
Design
platform integration with
database systems
Development Mr Muwashi 35 Assigned
Technical writing M.S.Wenantu 10 Assigned
QA Planning Mr Manukuza 5 Assigned
QA/Defects Testing Mr Manukuza 5 Assigned Subject Matter Expert and an
administrator to conduct testing
Technical
Resources Needs
Needs Resources Amount Status Comments

Training material Android and 2 Satisfied Downloaded


VB.net books
Workstation(s) CPU i5 , 1 TB , 8GB 3 Satisfied Developers will use current
Ram systems
DB Server CPU i5 , 1 TB , 8GB 1 Provided DB Server will be developed on
Ram the same machines
Server Name :
ROA_DB
Load Test Server CPU i5, 500gb HDD, 1 Pending
8GB Ram
ServerName: ROA
Load Test Clients 1.5ghz CPU, 320GB 1 Satisfied QA agents will use the same
HDD, 4GB machine for testing.
Ram
IDE Licences Standard N/A Satisfied Utilise open source tools where
development licenses possible. Purchased VB.net
suite/SDK
SCM Licences Standard N/A Satisfied Utilise use open source tools
development licenses

Testing Tool Standard N/A Satisfied Utilise open source tools where
development licenses possible
Licenses
Coding Language VB.net, C# and Java 1 Satisfied Purchased
(s)
Software VB.Net and Android 1 Satisfied Purchased
Plug ins
Development
Environment
Learner Management System - QA/ Testing Plan
Release Information – Quality Assurance Plan

Project: Learner Management System (LMS)


Internal Release 1.0
Number:
Release Audience: Customer-specific release: Nominated Training Centre/Person for Testing
Developer release (Internal usage only for testing)

Attached Worksheets:
Related Documents: Software Requirements Specification
Design
Project plan
Software development methodology

Process impact: This document specifies quality goals, selects strategies for assuring that those goals have
been met, and details a plan of action to carry out those strategies.

Introduction
Why is this QA plan needed?
"Quality" refers to all the good effects that I would like to see in my product. I have to
develop a quality product and ensure that it is of high quality by keeping quality as a key
factor all the time and performing the selected activities below. Testing is one QA activity,
but it is not the best or only one, other QA activities include the use of style guides and
checklists, review meetings, use of analysis tools, and careful quality measurements and
estimates. A plan is needed to select and coordinate all the QA activities.
What QA lessons were learned in previous
releases? None as yet. This is the first edition
release.

What is the scope of this QA plan?


The major components and aspects of the system will be evaluated in this release.
I will focus on the following Components/Modules:

• Personal Data
• Academic Data
• Examination Module
• Financial Data
• User Portal

What is the summary of this plan?


In this release I will utilise the development approaches that support all of my quality goals,
but I will focus on functional correctness and robustness of each component. I will achieve
this by undertaking the following activities:

• using statements to test preconditions and error statements to test blocks of codes
• conducting frequent reviews of source codes including desk checking of functional
blocks of code
• performing automated unit and regression testing with Junit or NUnit
• carrying out structured manual system testing of functional areas or modules
• database and interface testing as per functional area or module
Quality Goals for the Beta Release

• Essential
• Correctness (Semantic and Syntax)
• Robustness (Stability of the software)
• Expected
• Accuracy
• Compatibility

o Semantic and Syntax correctness


o Understand ability and Readability
o Learnability and Memorability
o Security and restricted access to
sensitive data
o Efficiency
o Consistency and Familiarity
• Desired
• o Consistency under load
• o Consistency under concurrency
o Availability under load
o Longevity
o Efficiency
o Scalability
o Performance under load
o Large data volume
o Interoperability with cross
platforms essentially mobile
devices
o Easy to use and understand
o Adaptability to changes in
market and legislation
o Testability
Quality
Assurance
Activity Coverage Description

Preconditions Every method in each Utilise if-statements at the beginning of public methods
component to validate each argument value. Helps to document
All public methods that assumptions and catch invalid values before they can
modify data cause faults.

Automated 100% of UI The QA team will utilise the system test automation tool
system screens and fields to write and maintain a suite of test scripts to test the
testing 100% of specified entire system through the user interface.
requirements
Regression Run all unit tests before each I will adopt a policy of frequently running all automated
testing commit tests, including those that have previously been
Run all unit tests successful. This will help catch regressions.
Buddy review All changes to each Whenever changes must be made to code the change
component will be reviewed by another developer before it is
All changes committed. The goal is to ensure that fixes do not
introduce new defects.
Static Strict compiler warnings I will utilise source code analysis tools to automatically
analysis Detect common errors detect errors. Generally, those that allow testing on the
VB.net and the Android frameworks.

Unit testing Methods and Statements We will develop and maintain a unit test suite using the
Junit/NUint framework.

Also utilise TypeMock to test unit codes.


Assertions Every private method in each Assertions will be used to verify all arguments to private
component methods. Since these methods are only called from our
All private methods that other methods, arguments passed to them should always
modify data be considered true, unless our code is defective.
Assertions will also be used to test class invariants and
some post conditions.

Regression Run all unit tests before each I will adopt a policy of frequently running all automated
testing commit Run all unit tests tests, including those that have previously been
successful. This will help catch regressions (bugs that we
thought were fixed, but that appear again).
QA Evaluations

Goal Preconditions Buddy Unit Manual Overall assurance


review testing system
testing
Functionality High Medium Low Medium Strong

Correctness Medium Medium Medium High Strong

Robustness Medium Medium Low High Strong

Usability Low Medium Low Medium Weak

Security None Low Low Medium Strong

Reliability High High Medium Medium At-Risk

Efficiency Medium None Medium High Strong

Reliability Medium High Low High Weak

Efficiency Low Medium High Medium Strong

Scalability Low Medium Medium Medium Strong

Interoperability None None Medium High At-Risk

Maintainability Medium Low Medium High Strong

Key
 High: This activity gives a strong assurance that the goal has been met in development.
 Medium: This activity gives a medium assurance that the goal has been met in development.
 Low: This activity gives only a little assurance that the goal has been met in development.
 None: This activity does not address the goal.

 Strong: The set of activities together provide strong assurance that the goal has been met in
development.

 Weak: The activities together provide limited assurance that the goal has been met in development.
 At-Risk: There is little or no assurance that this goal has been met.
Step Description Estimate

1. Preparation

1.1 Developer training 45h

2. Inception

2.1 Requirements gathering 40h

2.2 Requirements specification 20h

2.3 Requirements validation 10h

3. Elaboration

3.1 High-level design 15h

3.2 Low-level design (break down by component) 15h

3.2A Object design 15h

3.2B User interface design 20h

3.2C Database design 15h

3.3 Design review and evaluation 20h

4. Construction

4.1A System implementation/Development 15h

4.1.A.1 Implement/Develop PersonalData 20h

4.1.A.2 Implement/Develop AcademicData 10h

4.1.A.3 Implement/Develop FinancialData 10h

4.1.A.4 Implement/Develop ExamModule 20h

4.1.A.5 Integrate Components 15h


(mostly done during component
implementation)

4.1B Technical documentation (break down by 10h


component)
4.1C User documentation (break down by 25h
component)

4.1D Testing 30h

4.1.D.1 Test planning 15h

4.1.D.2 Test code implementation (break down by 20h


component)

4.1.D.3 Test execution 25h

4.2 Implementation review and evaluation 20h

5. Transition

5A Release packaging 5h

5B Documentation for other groups 5h

6. Reflection

6.1 Postmortem report 15h

Total 495h
Software Requirements Specification (SRS)
Project: Learner Management System
Internal Release
Version 1.0
Number:
Attached worksheets:
Related Documents: Project proposal
Glossary

Process impact: The SRS specifically defines the software product that will be developed. Decisions made in
writing the SRS are based on information in the project proposal and needs documents. The SRS sets
requirements that must be satisfied by the system design. The SRS is verified and validated by activities
outlined in the QA plan.

Being a part of the South African education sector for many years I have had experience with several
IT and infrastructure based problems shared by educators and others. Problems lie in the
implementation of a proper information management system that provides easy integration and
compliance with organizational and national regulations.

Many private training centres and practitioners tend to have problems in respect of meeting new or
established regulations with inadequate support provided by the relevant structures. The LMS
(learner management system) will be designed to provide cross platform interoperability with
learner integration services such as the hosting of online examinations, online libraries, statistical
analysis and reporting, financial services and facilitator reporting services amongst others.

The initial project requirement was to provide a simple fully integrated and easy to use application
that allows users to access information readily in terms of organizational requirements.
After much review all stakeholders fully agreed on the need for transparency in the software to help
ensure its integrity. The need was further made bigger for possible integration with national
requirements and reporting structures to help reduce administrative workloads and human error. It
was agreed on to having the product interface or interact with mobile devices and services.
The physical requirements of the system include a dedicated SQL Server that provides 24x7
controlled access. A secondary SQL server will be setup to provide load balancing and fault-
tolerance. The servers will sit in a DMZ behind a firewall and authentication server running at
minimum Microsoft Windows Server 2000 with Active Directory.
Most users to the system will be from their laptops or desktops however the application should be
able to run on hand held devices (mobile).
The primary functional requirements of the proposed project/software include the feature(s):

Module1: Student Biographical Data

F101: Student
Registration
F102: View Student
Profile
F103: Edit Student Profile
F104: Import Images and scans
F105: Export to Excel for EDUDex import to HEQCIS and NRLD (National Records Learner
Database)
F106: Print Profile information

Module 2: Examination/Assessment Management


F201: Register an Examination to obtain authorization code
F202: View Examination schedules or timetables
F203: Edit an Examination Booking
F204: Access the Question bank
F205: Upload or Append questions to the Question Bank (QB)
F206: Link and monitor live examinations
F207: Backup and restore features

Module3: Student Academic Data


F301: Search for Student by name, ID or Student Number
F302: Generate Academic Reports {passed, failed, comprehensive}
F303: View Academic progress
F304: Provide feedback on results {Assessor or Moderator feedback}
F305: Generate Progress Charts
F306: Export Results in Read-Only format

Module4: Lecturer Teaching and Reporting


F401: Register an Academic Staff Member
F402: Append Registration Details and level of Access
F403: Upload teaching plans and progress reports
F404: View latest teaching and learning policies and regulations
F405: Upload weekly OHS, Academic and Technical reports
F406: Generate consolidated charts and reports
F407: Export reports in different formats

Module5: Financial Data


F501: Search for Student by name, ID or student number
F502: Create or append Student invoices (Qualification, apparel, books, student cards etc)
F503: Create or append payment entries
F504: Generate Financial Reports (Daily, 3 months, 12 months
etc)
F505: Export to Excel/RTF for Pastel Accounting
Non -Functional Requirements

Usability requirements?
The ease of use of the software will sorely depend on the UI guidelines and layout of popular applications. I
will maintain common interfaces where possible. Drop-down lists, toolbar options and other controls in order
to allow faster and easier interaction with the software will be employed.

The user interface should be as familiar as possible to users who have used other Windows desktop
applications. E.g., I will follow the UI guidelines for naming menus, buttons, and dialog boxes whenever
possible.

Reducing the number of events, a user has to undergo in order to execute a task will also be one of the
primary methods in promoting usability and it will also reduce human error.

The software will include an online help feature and tool tips for support.

Security requirements?

• Access will be controlled with usernames and passwords (Login).


Details of Passwords:

Passwords must be 6-18 characters long


Passwords must be alphanumeric
Password Cannot be reused – maintain a Password History

• Only administrators will have access to administrative functions, typical users will not.
Details of Restrictions:
Only Administrators will be able to append Student results.
Only Administrators will be able to set or change qualification profiles and
prices
Only Administrators will be able to append Lecturer submissions or reports

What are the performance and scalability requirements?

• Performance and Scalability is made possible by using a Microsoft SQL Server for faster data
access and growth of the database.
• A deceit desktop/Laptop of minimum i3 Core CPU, at least 300GB HDD with a 100gbps Network
interface card.

Maintainability and upgradability requirements?

Maintainability the ability to make changes to the product over time. I would need a high degree of
maintainability in order to retain early customers. This will be addressed by anticipating several types of
changes, and by carefully documenting the design and implementation thereof.

Upgradability is the ability to cost-effectively deploy new versions of the product to customers with minimal
downtime or disruption. A key feature supporting this goal is automatic download of patches and upgrade of
the enduser's machine. Also, I shall use data file formats that include enough meta-data to allow us to reliably
transform existing customer data during an upgrade.
Supportability requirements?

Supportability is the ability to provide cost effective technical support. The user guide and product website will
include a troubleshooting guide and checklist of information to have at hand before contacting technical
support.

The Software development methodology chosen will be the Rapid Application Development
approach. The motivation behind the RAD it is speed and cost effectiveness in delivering a useable
prototype. RAD allows the software to be broken into smaller more manageable
components/segments. This will allow for quick and proper testing of the segment without
concentrating on the others.

The entire approach will encapsulate the iterative framework of development with feedback from
the client contributing to its development. This approach allows each component to focus on the
business needs more accurately promoting a Joint Application Development Approach by
concentrating on essential system elements from the user viewpoint.

The following diagram illustrates the RAD Development Cycle

Drawbacks of this approach:


- It can result in too many requirements from the user/client perspective limiting the time
required to complete the entire project.
- Due to the Rapid approach the product could miss a few of the business requirements.
- Speed of the project could lower the quality of the product.
Fig 1: Log-In

Fig 2: Dashboard
Fig 3: Add A Student

Fig 4: Add Admin/Supervisor

Fig 5: Search Student


Fig 6: Report Viewing

Fig 7: Mailing

Fig 8: Meeting Request


RTF Rich Text Format
RAD Rapid Application Development
GUI Graphic User Interface
QA Quality Assurance
LMS Learner Management System
DB Database
“Web Based Project Collaboration, Monitoring and Management System” (ICTer)-109-155/
2014 IEEE.
 Fundamentals of project management for development organization, 2 nd edition, PDEVM,
Project Management for Development Organization, pp. 13-20.
Software project management: from concept to deployment / Kieron Conway. Scottsdale
(Ariz.) : Coriolis, c2001
 Software project management / Bob Hughes and Mike Cotterell, London [etc.]: McGraw-Hill,
c2002, 3rd Ed.
 Information systems project management: methods, tools and techniques / John McManus
and Trevor Wood- Harper, Harlow [etc.] : Prentice Hall, c2003
 Subversion version control: using the Subversion version control system in development
projects / William Nagel, Upper Saddle River (N.J.): Prentice Hall/PTR, c2005
 Systems Analysis and Design Shelly Cashman Adamski Boston 1991
 Software Engineering Roger S.Pressman UK, c2000, 5th Ed.
Samakova J, Koltnerova K, & Rybansky R, (2012). Project Communication in Functions, Process
and ProjectOriented Industrial Companies,20(Special Number):120-125.
 Aladwani, A.M. (2002). IT project uncertainty planning and success: An empirical investigation
from Kuwait. Information Technology & People, 15(3), 210-226.
S.R.Bharmagoudar, Geeta R.B, Totad S.G, (2013). Web based student information system,
International Journal of Advanced Research in Computer and Communication Engineering
2278-1021

You might also like