Client's PO No :
Project No :
Reference Drawing No : -
Holding Time : 24 H
Calibration Certificate No :
Observations
PT.PRIMA KARYA AGUNG PT.BHINEKA NIAGA NUSA LESTARI PT.TATA MULIA NUSANTARA
PT.TATA MULIA NUSANTARA
PRESSURE TEST
Document No. :
Revision :0
Record No. :
RESULT
60 Ada penurunan tekanan
dari 20 bar menjadi 19 bar
55
50
Pressure (Kg / cm²)
45
40
35 20 bar
30 19 bar
25
20
15
10
5
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Retention Time (Hours)
PT.TATA MULIA NUSANTARA
SINGLE PIPE
PRESSURE TEST JACKET
INNER PIPE
OUTER PIPE
28 june 2022
/
Date 27 / June / 2022
( )
Nama _________________________
1. Water Injection
1
2 20 Bar
2
3 19 bar
Page 4 of 4