You are on page 1of 57

BIRO KLASIFIKASI INDONESIA

RULES
FOR CONSTRUCTION AND CLASSIFICATION
OF OFFSHORE INSTALLATIONS

VOLUME 6
RULES FOR MOBILE OFFSHORE UNITS

EDITION 2011
ii Biro Klasifikasi Indonesia

The followingRules come into force on 1st May 2011

Reproduction in whole or in part by any means, is subject to


the permission in writing by Biro Klasifikasi Indonesia Head Office

Published by : Biro Klasifikasi Indonesia


Table of Contents iii

Table of Contents

Section 1 Scope, Definitions and Procedures


A. Scope, Application ..................................................................................................................... 1- 1
B. Definitions .................................................................................................................................. 1- 1
C. Design Review ........................................................................................................................... 1- 2
D. Supervision of Fabrication and Installation ................................................................................ 1- 6
E. Testing and Commissioning ....................................................................................................... 1- 7

Section 2 Self-elevating Units


A. General ....................................................................................................................................... 2- 1
B. Structure ..................................................................................................................................... 2- 1
C. Stability ...................................................................................................................................... 2- 3

Section 3 Column Stabilized Units


A. General ....................................................................................................................................... 3- 1
B. Structure ..................................................................................................................................... 3- 2
C. Stability ...................................................................................................................................... 3- 4

Section 4 Surface Drilling Units


A. General ....................................................................................................................................... 4- 1
B. Structure ..................................................................................................................................... 4- 2
C. Stability ...................................................................................................................................... 4- 2
D. Drilling Facilities ....................................................................................................................... 4- 2
E. Safety Aspects ............................................................................................................................ 4- 3

Section 5 Pipelaying Units


A. General ....................................................................................................................................... 5- 1
B. Movement and Position Keeping ............................................................................................... 5- 1
C. Structure ..................................................................................................................................... 5- 4
D. Watertight Integrity and Stability ............................................................................................... 5- 4
E. Pipe-laying Facility ...................................................................................................................... 5- 5

Section 6 Well Stimulation Units


A. General ....................................................................................................................................... 6- 1
B. Special Safety Aspects ............................................................................................................... 6- 1
C. Position Keeping ........................................................................................................................ 6- 1
D. Well Stimulation Equipment ...................................................................................................... 6- 1
iv Table of Contents

Section 7 Subdivision, Stability and Load Line


A. General Remarks, Scope ............................................................................................................. 7- 1
B. Righting and Heeling Lever Curves ............................................................................................ 7- 1
C. Intact Stability Criteria ................................................................................................................ 7- 2
1. Standard criteria .......................................................................................................................... 7- 2
D. Inclining Test .............................................................................................................................. 7- 3
E. Subdivision and Damage Stability .............................................................................................. 7- 3
F. Extent of Damage ....................................................................................................................... 7- 4
G. Watertight Integrity ..................................................................................................................... 7- 5
H. Load Line .................................................................................................................................... 7- 6

Section 8 Mooring Equipment


A. General ........................................................................................................................................ 8- 1
B. Temporary Mooring Equipment ................................................................................................. 8- 1
C. Positional Mooring Equipment ................................................................................................... 8- 6

Section 9 Life-Saving Appliances


A. General ........................................................................................................................................ 9- 1
B. Life-Saving Appliances ............................................................................................................... 9- 1
C. Arrangement of Lifeboats and Liferafts ...................................................................................... 9- 2
D. Rescue Boats ............................................................................................................................... 9- 4

Annex A List of Standards, Codes, etc. Quoted


Section 1-Scope, Definitions and Procedures A, B 1-1

Section 1
Scope, Definitions and Procedures

A. Scope, Application B. Definitions

1. Scope 1. Mobile offshore unit


A mobile offshore unit is any mobile offshore struc-
1.1 In this Volume the requirements for the ture or vessel, whether designed for operation afloat or
different types of mobile offshore units are defined. supported by the seabed, built in accordance with
these Rules and classed by BKI and includes the entire
1.2 Types of units structure and components covered by these Rules.

− units connected to the seabed by anchoring 2. Drilling unit


(mooring)
A drilling unit is any unit intended for use in offshore
− units kept on position by dynamic positioning/ drilling operations for the exploration or exploitation
of the sub-sea resources.
propelling system

− units connected by legs in jacked-up condition 3. Self-propelled unit


A self-propelled unit is an unit which is designed for
1.3 Materials used for construction of the hull un-assisted passage. All other units are considered as
non-self-propelled.
The following materials may be used for the main
structure/hull:
4. Length L
− steel, normally
4.1 Ship type units
− concrete, in exceptional cases The length L is the distance in metres on the summer
load waterline from the foreside of the stem to the
after side of the rudder post, or the centre of the rudder
2. Application stock, if there is no rudder post. L is not to be less than
96% and need not be greater than 97% of the extreme
2.1 The following types of employment have to length of the summer load waterline. In units with un-
be distinguished: usual stern and bow arrangement, the length L will be
specially considered.
− drilling/exploration
4.2 Other units
− self-elevating drilling units
The length L means 96 % of the total length on
− column stabilized drilling units a waterline at 85 % of the least moulded depth H
measured from the top of the keel, or the length from
− surface drilling units of ship or barge type the foreside of the stem to the axis of the rudder stock
− other types of drilling units on that waterline, if that be greater. In units designed
with a rake of keel, the waterline on which this length
− production, e.g. oil/gas is measured shall be parallel to the designed waterline.

− processing/treatment 5. Breadth B
− storage or loading on/off The breadth B is the greatest moulded breadth of the
unit.
− research, measurements
− construction / pipe-laying 6. Depth H
The depth H is the vertical distance, at the middle of
2.2 Manning the length L, from the base line to the top of the deck
beam at side of the uppermost continuous deck.
Only units continuously manned in operation mode
are considered.
1-2 Section 1-Scope, Definitions and Procedures C

In way of effective super structures the depth is to be documentation if that submitted is insufficient for an
measured up to the super structure deck for deter- assessment of the unit or essential parts thereof.
mining the unit’s scantlings. This may especially be the case for plants and equip-
ment related to new developments and/or which are
Effective super structures are extending into the range not tested on board to a sufficient extent.
of 0,4 L at midship and their length exceeds 0,15 L.
2.1.3 Once the documents submitted have been
7. Draught T approved by BKI they are binding on the execution of
the work. Subsequent modifications and extensions re-
The draught T is the vertical distance at the middle of
quire the approval of BKI before becoming effective.
the length L from base line to freeboard marking for
summer load waterline.
2.2 Plans for the hull and design data
8. Block coefficient CB General specifications with an indication of the
intended use, design life, location and environment,
The moulded block coefficient CB at load place(s) and period of construction and the main
d r a u g h t T, based on the length L is defined as:
stages of construction up to final assembly and/or
installation at sea.
moulded volume of displacement [m3 ] at T
CB = Plans showing the scantlings, arrangements and details
L‫ڄ‬B‫ڄ‬T
of the principal parts of the hull are to be submitted for
approval before construction commences. These
drawings have to clearly indicate the scantlings,
9. Frame spacing a
types and grades of materials, joint details and
The frame spacing a will be measured from moulding welding, or other methods of connection. These plans
edge to moulding edge of frames. are to include the following, where applicable:

10. Further definitions − general arrangement


For further definitions see Volume 1 – Rules for − specification of the assumed loads
Classification and Surveys, Section 1. − inboard and outboard profile
− summary of distributions of fixed and variable
weights
C. Design Review
− plan indicating design loads for all decks
1. Extent of review − transverse sections showing scantlings
Examination or verification of the following will be − longitudinal sections showing scantlings
under-taken:
− decks including helicopter deck
− design documents, such as load assessment and
stress analyses (as far as applicable), reports on − framing
model tests, design drawings − shell plating
− practical qualifications of manufacturing firms − watertight bulkheads and flats
and personnel suitability of the materials used
− structural bulkheads and flats
− erection procedure of the structure on land and
− tank boundaries with location of over flows
at the port
− structure in way of jacking or other elevating
− transportation procedures and jack-up
procedure, if applicable arrangements
− critical review of safety management − hulls, pontoons, legs, footings, pads or mats
system, see 4. − superstructures and deckhouses
− arrangement and details of watertight doors and
2. Documents for approval
hatches
2.1 General − anchor handling arrangements, mooring system
2.1.1 All documents have generally to be submitted − welding details and procedures, pre- and post-
to BKI in Bahasa Indonesia or English.
treatments
2.1.2 The general scope of documents is defined in − lines or offsets
2.2 to 2.6, the detailed scope will be defined case by
case. BKI reserve the right to demand additional − curves of form or equivalent data
Section 1-Scope, Definitions and Procedures C 1-3

− wind heeling moment curves or equivalent data 2.5 Calculations


− capacity plan
2.5.1 The following data and calculations are to be
− corrosion control arrangements
submitted in conjunction with the scantling plans, as
− methods and locations for non-destructive testing, may be applicable:
manufacturer’s quality control methods and test
procedures − structural analysis for relevant loading conditions
− where appropriate, general arrangement of equip- as agreed with BKI
ment including calculations associated with the
transfer/installation mode − resultant forces and moments from wind, waves,
current, mooring and other environmental loading
In addition an arrangement plan of watertight taken into account in the structural analysis
compartments shall be submitted as early in the design
stage as possible, for review of damage stability. This − effect of icing on structural loading, stability and
drawing is to indicate the watertight bulkheads, decks
windage area
and flats and all openings therein. Doors, hatches,
ventilators, etc. and their means of closure, are to be − stability calculations, both intact and damaged,
indicated. Piping and ventilation systems shall be
shown in sufficient detail to evaluate their effects on over the appropriate range of drafts, including the
the watertight integrity after incurring damage. transit conditions

− significant operational loads from drilling derrick


and associated equipment, industrial items, etc,
2.3 Plans for machinery and electrical equip- and other significant loadings
ment and design data
Plans are to be submitted showing the arrangement
− calculations substantiating adequacy of structure
and details of: to transmit forces between legs and hull through
the jacking or other elevating systems
− general arrangement of machinery installations
− evaluation of the ability to resist overturning while
and equipment bearing on the seabed
− general arrangement and design details of pro-
2.5.2 Submitted calculations are to be suitably
pulsion system referenced. Results from relevant model tests or
dynamic response calculations may be submitted as
− auxiliary machinery alternatives or as substantiation for the required
− steering gear calculations.
− boilers and pressure vessels
2.5.3 The choice of computer programs according
− general arrangement and particulars of the to the “State of the Art“ is free. It is recommended to
use computer programs which are approved by BKI in
electrical installation advance as appropriate to solve the actual problems. If
− jacking system including description the computer programs to be used are not known to
BKI, they may be checked by BKI through
− bilge and ballast systems comparative calculations with pre-defined test
− fire extinguishing systems examples. Reference applications, already achieved
approvals by other institutions and other relevant
− other pumps and piping systems information shall be provided in advance. A generally
− working gear as far as it has been agreed to be in- valid approval for a computer program is, however,
not given by BKI.
cluded in the design review
The calculations have to be compiled in a way which
allows to identify and check all steps of the calcu-
2.4 Safety aspects lations with regard to input and output in an easy way.
Hand written, easily readable documents are accept-
− hazardous areas plan able.

− arrangement plans of safety devices and Comprehensive quantities of output data shall be
equipment, e.g. fire extinguishing plan, escape presented in graphic form. A written comment to
routes, life-saving appliances, structural fire pro- the main conclusions resulting from the calculations
tection has to be provided.

− operating instructions, as far as related to safety 2.6 Further details

− safety management plans, where applicable The necessary documentation is indicated in further
detail in the relevant Rules and Sections.
1-4 Section 1-Scope, Definitions and Procedures C

2.7 Distribution of documents − representative examples of loading conditions for


The distribution of design documents according to each approved mode of operation, together with
2.2 – 2.6 will be agreed upon in each individual means for evaluation of other loading conditions
case, depending on the organization on owner's,
con-tractor's and/or fabricator’s side, and the − details of emergency shutdown procedures
mandatory requirements of responsible
− identification of the helicopter used for the
Administrations.
design of the helicopter deck and procedure for
For the needs of BKI, general descriptions, helicopter operations
calculations and test reports have to be submitted in
duplicate, structural plans, detail drawings and buil- − safety checks and maintenance work to be carried
ding/testing specifications in triplicate, one copy through
of each being returned to the remitter with the
approval or review Notation. − emergency procedures and rescue operations

− operating booklet for helicopter operation,


3. Operating instructions including helicopter data on which design is based

3.1 Operating Manual (Booklet) 3.2 Construction Portfolio (Booklet)


An Operating Manual or equivalent is to be placed A set of plan copies showing the exact location and
on board of each unit. The booklet shall include the extent of application of different grades and strengths
following information, as applicable in the of structural materials, together with a description of
parti-cular case, so as to provide suitable guidance the material and welding procedures involved, is to be
to the operating personnel with regard to safe placed on board. Any other relevant construction
operation of the unit: information is to be included in the booklet, including
restrictions or prohibitions regarding repairs or mo-
− general description / main characteristics difications.
− pertinent data for each approved mode of 3.3 The operating instructions will be subject to
operation, including design and variable loading, examination within the design review procedure only
environmental conditions for the execution of in so far as they are related to the specified loads and
certain operations, e.g. jacking, drilling, etc. load cases to be applied, and to other safety matters
− minimum anticipated atmospheric and sea tem- covered by these Rules.
peratures
4. Safety management system
− assumed seabed conditions and their control,
scouring, etc. 4.1 Safety management procedures 1, may be
− admissible draft, or required distance of subject to review by BKI either
certain parts from the water surface − based on an agreement with the owner/operator,
− general arrangement showing watertight com- or
partments, closures, vents, allowable deck
loading, etc.; if permanent ballast is used, the
− due to authorization and request by the competent
weight, location and substance used are to be national Administration.
clearly indicated
4.2 Safety management may be related to
− hydrostatic curves or equivalent data
− personal safety of operating personnel, i.e.
− capacity plan showing capacities of tanks,
centres of gravity, free surface corrections, etc. − accident prevention
− instructions for operation, including precautions − protection against exposure to toxic, radioac-
to be taken in adverse weather, changing mode tive or otherwise harmful substances
of operations, any inherent limitations of
operations, etc. − general preventive and health control measu-
− plans and description of the ballast system res (alcohol, drugs control, etc.)
and instructions for ballasting − protection of the environment (sea, sea floor,
− hazardous areas plan atmosphere surrounding the installation)

− light unit data on the results of an inclining


experiment, etc. ––––––––––––––
1 See IMO ISM (International Safety Manage-
− stability information in the form of maximum
KG draught curve, or other suitable parameters ment) procedures, to be introduced for
based upon compliance with the required intact mobile offshore units from 1 July 2002
and stability criteria
Section 1-Scope, Definitions and Procedures C 1-5

− operational safety/operability of the technical original plan, will be evaluated and duly incor-
installations/systems on board porated in a revised SMP
Obviously, an inter-relation exists with the operating − communication between operating personnel
manual according to 3., see also 4.4 and 4.6. and responsible company management is
ensured, including immediate and reliable
4.3 Safety Management Plan information on special/ abnormal incidents or
events defined in the SMP, see 4.4.2. In
4.3.1 Safety management procedures shall be relevant cases information to Authorities and
presented in the form of a Safety Management Plan BKI is ensured.
(SMP), to be set up in each individual case, bearing in
mind the particular operational and environmental − for any abnormal situations, e.g. repairs
conditions to be expected as well as the applicable requiring operational restrictions, the necessary
legislation and regulations. additional precautions are taken and any person
possibly involved is aware of the existing
4.3.2 Preparation of a SMP will essentially consist danger
in an assessment of all foreseeable risks emerging
from the planned activities, and in providing measures 4.4.2 The SMP shall indicate follow-up
and procedures to minimize these risks. The measures and procedures for each case of failure or
assessment will be based on existing experience and incident considered. Responsibilities shall be cle-
statistical infor-mation regarding similar installations arly attributed to members of the crew/installation
and activities. Pro-ven methods of risk and failure personnel within each contingency procedure, and
analysis including e.g. Fault-Tree or Event-Tree the paths or chains of information clearly stated for
diagrams may be used. the different cases.
4.3.3 Corrective measures and amendments to the
plan may be required following experience gathered 4.4.3 For the unit in service, it shall be
during the initial service period, see also 4.4. guaranteed by regular, and possibly additional,
unprecedented, checks, audits etc., that the mea-
4.3.4 The SMP should take into account separately sures provided by the SMP are actually being ob-
all relevant operational phases and situations and their served.
specific risks, such as
Relevant documentation is to be kept on board
− initial (start-up, test) period(s), also following im- and/or in the Operator’s headquarters for a period
to be defined by the Administration, but not less
portant changes
than 5 years.
− normal ("routine") operations
4.5 Types of hazards
− operations under restricting conditions, e.g.
Among aspects to be considered in assessing risks
− due to extreme environmental impact are the following:

− during repairs, conversions, etc. 4.5.1 Hazards to personnel


− explosion, fire
− periods following an accident or failure − exposure (through contact, inhalation, inges-
tion) to toxic, irritant or otherwise harmful gases,
4.4 Essential elements of a SMP liquids, chemicals etc.
− accidents due to operations with lifting gear/
4.4.1 The SMP shall clearly show, through
appliances and machinery or tools
adequate procedures and organizational provisions, that
− accidents due to environmental influences (icing,
− routine controls, checks, measurements etc. are unit’s motions, bad visibility etc.)
provided in order to ensure that physical properties − noise/vibrations exceeding given ("tolerable")
and chemical processes remain stable and within limits
prescribed limits, e.g. critical gas concentrations,
exposure limits, pressures, ppm values functioning 4.5.2 Hazards to the environment:
of alarms
− spills/loss of polluting (toxic or otherwise
− information and training of personnel is ensured, harmful) substances during "normal" - e.g.,
taking into account also possible language drilling – operations to the sea or sea floor,
problems, like information on danger zones, see 4.6.2
“hazardous areas“, alarms; handling of fire − spills of hydrocarbons, chemicals etc. during
fighting and rescue equipment, etc. transport/conveyance operations, see 4.6.1
− national regulations have been considered − collision and grounding hazard, depending on
weather and traffic conditions
− any (new) hazards becoming known, not taken into − release of polluting (e.g. exhaust) gases to the
account or not sufficiently covered in the atmosphere, see 4.6.2
1-6 Section 1-Scope, Definitions and Procedures C, D

− dropping of objects (e.g. wastes) to the regulations. Un-intentional escape of gases (leakage),
sea/sea floor, see 4.7 particularly in hazardous areas and to accommodation
spaces, shall be avoided by pre-cautions such as
− noise exceeding prescribed limits; may be suitable arrangement of piping, ducts and exhaust
rele-vant in certain cases, e.g. in sensitive, openings/intakes, sensors/measuring devices and
protected areas alarms, pressurizing, according to the Rules, see
Volume 4 - Rules for Machinery Installation and
4.6 Pollution prevention during production Volume 5- Rules for Electrical Installation.
and transport activities

4.6.1 Transport/conveyance and storing ope- 4.7 Waste management


rations
4.7.1 For sewage waste water the same applies as
4.6.1.1 Loading and unloading operations, e.g. stated under 4.6.2.3 for waste water originating from
using transport (supply) vessels and cargo handling the production process. The sewage residues shall be
equipment, shall be carried out observing weather discharged or transported to corresponding installa-
imposed restrictions, see "operating instructions", tions onshore.
and applicable safety and environment protection
regulations. 4.7.2 Generally, no solid wastes whatever
4.6.1.2 For the conveyance of oil/hydrocarbon (sanitary, food processing, production auxiliary mate-
products from a production unit to a (shuttle) rials such as for cleaning, etc.) shall be dumped from
tanker, using articulated piping, swivels, flexible an offshore unit. Crew information and strict
hoses etc., special pre-cautions e.g., emergency adherence shall be ensured by suitable measures such
shutdown and spill arresting devices may be as publication (posters), regular instruction and
necessary, depending on environment conditions supervision.
and regulations applicable to the location.
For import/export flow lines (hydrocarbons pro-
duction) see also 4.6.2. D. Supervision of Fabrication and Installation

4.6.1.3 Any harmful substances subject to 1. General


controlled handling shall be allocated to defined,
properly sheltered and marked spaces. Liquids or 1.1 Supervision of the fabrication of individual
substances capable of releasing harmful liquids components and of the installation of the hull will
under certain conditions shall be stored in such a generally take the form of inspections by the autho-
way that spills are prevented. rized BKI Surveyor to the extent considered neces-
sary by BKI at any given time.
4.6.1.4 Reception/receiving, use/consumption and
return/un-loading of harmful or polluting subs-
tances shall be constantly controlled and their 1.2 BKI Branch O ffices will receive, for their
volumes or weight noted. supervisory work, previously examined, documents
from the Head Office, see C.2.7. Additionally all
4.6.2 Production and treatment processes technical documents connected with the relevant
construction project shall be made available to the
4.6.2.1 Suitable controls using measuring and Surveyors on request.
monitoring techniques shall be provided to ensure
safe conveyance of hydrocarbons and other 1.3 BKI will assess the production facilities
polluting substances to and from the offshore and procedures of the yard and other fabricators as to
unit, through flow lines, risers, hoses, etc. whether they meet the requirements of BKI Rules. In
general, approvals based on such assessments are
4.6.2.2 For safe conveyance/transport of liquid conditional for acceptance of products subject to
and gaseous substances on board of the production testing.
unit, between the different processing stations, the
provisions of Volumes 4 and 5 have to be observed 1.4 Materials, components, appliances and
(material selection, design requirements, safety, installations subject to inspection are to comply with
monitoring and alarm devices, etc.). the relevant rule requirements and be presented for
4.6.2.3 Waste water, in connection with the inspection and/or construction supervision by BKI
production process, shall be either collected in Surveyors, unless otherwise provided as a result of
storage tanks and discharged via auxiliary vessels special approvals granted by BKI.
or pipeline, or if allowed by the competent
Authority pumped to the sea after prescribed 1.5 It shall be the duty of the fabricator to inform
treatment/purification and under controlled the competent inspection office of the completion of
conditions (monitoring of ppm values). important stages of the construction or of trials and
inspections due.
4.6.2.4 Release of gaseous substances to the
atmosphere, including flaring operations, shall 1.6 In order to enable the Surveyor to fulfil his
occur under controlled conditions and according to duties, he is to be given free access to the unit and the
the applicable
Section 1-Scope, Definitions and Procedures D, E 1-7

workshop, where parts requiring approval are fabri- E. Testing and Commissioning
cated, assembled or tested. For performance of the
tests required, the yard or fabricators are to give the
1. Program
Surveyor every assistance by providing the staff and
equipment necessary for such tests. An overall test or commissioning program including
the complete, combined function of the unit as well as
2. Supervision of fabrication partial tests of the different systems has to be
established. The detailed requirements for the overall
2.1 Aim of supervision function and the functioning of the different systems
are defined in the following Volumes and Sections.
During the phase of fabrication of an unit BKI will The test program has to be approved by BKI.
ensure by surveys and inspections that:
2. Tests at fabricators
− parts for hull and machinery and/or special equip-
As far as practicable, machinery and equipment will
ment requiring approval have been constructed in be subjected to operational trials on the fabricator's
compliance with the approved drawings and par- test bed to the scope specified in the Construction
ticulars Rules. This applies also to engines produced in large
series. Where the machinery, equipment or electrical
− all tests and trials stipulated by BKI Rules are installations are novel in design or have not yet
performed satisfactorily sufficiently proved their efficiency under actual
service conditions on board ships or units , BKI may
− workmanship is in compliance with current require performance of a trial under particularly
engineering standards and/or BKI Rule require- severe conditions.
ments Upon completion of work, compartments, decks,
bulkheads, etc. are to be tested as specified in the
− welded parts are produced by qualified welders following Volumes and Sections.
having undergone tests
3. Sea trials
− test Certificates have been presented for
components requiring approval (the fabricator Upon completion of the unit and/or the system/
will have to ensure that any parts and materials equipment to be classed, all structure/hull, machinery
requiring approval will only be delivered and and electrical installations will be subjected to
installed, if the appropriate test Certificates have operational trials in the presence of the BKI Surve-
been issued) yor, prior to and during the sea trial. This will
comprise, e. g.:
− where no individual Certificates are required, type − tightness, operational and load tests of tanks,
tested appliances and equipment are employed in covers, shell ports, ramps, etc.
accordance with rule requirements
− operational and/or load tests of the machinery and
2.2 Marking and attestation of individual installations (propulsion plant, electrical installa-
components tions, steering gear, anchor equipment, etc.) of
importance for safe operation
2.2.1 In so far as it is necessary to identify mate- During a final survey, checks will be made to ensure
rials or components during the fabrication process or that any deficiencies found, for instance during the sea
possibly also after commissioning, e.g. because of trial, have been eliminated.
special properties of the material, a permanent mark is
to be made by means of a stamp.
4. Report
2.2.2 The construction supervision, survey
and/or final inspection of materials, parts supplied or A test or commissioning report has to be established
installation components, corresponding to the relevant by the fabricator or owner and to be agreed with the
specifications and BKI Rules, will be attested by the BKI Surveyor.
Surveyor concerned on special forms, or informally,
as agreed in the individual case. 5. Corrective actions
If the tests according to the established test program,
3. Industrial equipment see 1., are partially or totally not satisfactory to the
BKI Surveyor, corrective actions have to be provi-
Regarding working gear and special equipment, ded by the fabricator or owner and the relevant part of
supervision of construction and testing will be agreed the tests repeated until a satisfactory result has been
upon from case to case. reached.
Section 2 - Self–elevating Units A, B 2-1

Section 2
Self-elevating Units

A. General 2.6 Towing and elevating


Conditions for towing, for the elevating and lowering
1. Definition procedures and for operating phases while standing on
Self-elevating units have hulls with sufficient the seafloor, shall be clearly indicated in the Opera-
buoyancy to safely transport the unit to the desired ting Manual, compare Section 1, C.3.1.
location, after which the hull is raised to
a predetermined elevation above the sea surface on its 2.7 Drilling
legs, which are supported on the sea-bed. Equipment Drilling derricks shall be designed according to
and supplies may be transported on the unit, or may be recognized codes/standards and/or applicable national
added to the unit in its elevated position. The legs of regulations. The rated capacity for each reeving shall
such units may penetrate the sea-bed, may be fitted be included in the Operating Manual.
with enlarged sections or footings (spud cans) to
reduce penetration, or may be attached to a bottom Permanently installed piping systems for drilling
pad or mat. Self- elevating units are also known as operations are to comply with recognized standard
Jack-up units. or code.

The Class Notation SELF ELEVATING UNIT will These Rules do not include requirements for the
be assigned for this type, see Volume 1 – Rules for drilling of subsea wells or procedures for their control.
Classification and Surveys, Section 2. Such drilling operations are subject to control by the
coastal state.
2. Scope

2.1 This Section covers those specific design B. Structure


criteria and features of self-elevating mobile offshore
units which are not dealt with in the special Sections 1. General
as referred to in the following.
1.1 The buoyant main structure (hull) of a
self-elevating unit shall be designed to resist the loads
2.2 Subdivision and watertight integrity
and stresses arising in the floating condition and while
Subdivision and watertight integrity are dealt with in elevated. Volume 2 – Rules for Structures, Sections 1
Section 7. Regarding stability see C. to 4 apply.

2.3 Machinery and electrical installations 1.2 The unit is to be designed for a clearance of
either 1,2 m, or 10 % of the combined storm tide,
Machinery and electrical installations shall be astronomical tide and height of the maximum wave
designed according to Volume 4 - Rules for Machinery crest above the mean low water level, whichever is
Installations and Volume 5 - Rules for Electrical less, between the underside of the hull in the elevated
Installations, respectively as far as applicable. For the position and the crest of the design wave. This crest
jacking installation, see Volume 4, Section 9 and elevation is to be measured above the level of the
Volume 5, Section 12, I. combined astronomical and storm tides. See also
Volume 2 – Rules for Structures, Section 2, B.4.10.
2.4 Auxiliary installations and equipment
1.3 Classification or Certification will be based
Special (auxiliary) installations and equipment are to upon the designer’s assumptions regarding the sea-bed
be designed according to the specific Sections as far as conditions. These assumptions shall be recorded in the
applicable. See also Volume 1 – Rules for Classifi- Operating Manual. It is the responsibility of the
cation and Surveys, Section 1. operator to ensure that actual conditions do not impose
more severe loading on the unit.
2.5 Lifting appliances
For the interaction of lifting appliances with the unit, 2. Hull
its foundations, etc. Volume 2 – Rules for Structures,
Section 8. 2.1 Structural elements such as the outer shell,
decks, bulkheads and girders shall be dimensioned
The requirements for offshore cranes and other lifting according to the principles outlined in Volume 2 –
appliances themselves are defined in the Regulations Rules for Structures, Section 3. Rules for Hull , Volu –
for the Construction and Survey of Lifting Appli-
ances.
2-2 Section 2 - Self–elevating Units B

me II may be used as a basis where applicable, e.g. 4. Legs


dimensioning of tank boundaries.
4.1 Leg types
2.2 The hull is to be considered as a complete
structure having sufficient strength to resist all Legs may be either shell type or truss type. Shell type
induced stresses while in the elevated position and legs may be designed as either stiffened or un-
supported by all legs. All fixed and variable loads stiffened shells. According to the sea-bed conditions
are to be distributed, by an accepted method of envisaged, the legs may be designed with fixed or
rational analysis, from the various points of detachable footings, or bottom mats.
application to the supporting legs. The scantlings of
the hull are then to be determined consistent with
this load distribution, but are not to be less than those 4.2 Lower end
required by the Rules defined in 2.1. Scantlings of
Where footings or mats are not fitted, proper
units having other than rectangular hull configurations
consideration shall be given to the leg penetration of
will be subject to special consideration.
the sea-bed and the corresponding end fixity of the
legs. Depending on the mat and type of connection, a
2.3 Deckhouses located near the boundary of the rotational restraint of the leg may exist also in this
unit shall be designed to resist the possible impact of case.
sea wash during conveyance.

Deckhouses are to have sufficient strength for their 4.3 Dimensioning


size, function and location and are to be constructed to
approved plans. Their general scantlings are to be as 4.3.1 The legs of self-elevating units shall be
indicated in the Rules according to 2.1. Where they designed to resist the forces and bending moments
are close to the side shell of the unit, their scantlings resulting from the following operational conditions.
may be required to conform to the requirements for The safety factors according to loading condition 2
bulkheads of unprotected deckhouse fronts. according to Volume 2 – Rules for Structures, Sec -
tion 3, C. and D. apply. Fatigue may have to be
2.4 Special attention is to be paid to the specially considered, particularly for legs of truss
foundations and fastening of drilling derrick(s) and type. For fatigue criteria, see Volume 2 – Rules for
cranes, also with regard to transit conditions. Structure, Section 3, H.

4.3.2 Ocean transit condition

3. Structure in way of jacking Legs shall be designed for acceleration and gravity
moments resulting from the motions in the most
severe anticipated environmental transit conditions,
3.1 Load carrying members which transmit loads together with corresponding wind moments. Calcu-
from the legs to the hull are to be designed for the lation or model test methods, acceptable to BKI, may
maximum design loads and are to be arranged that be used. Alternatively, legs may be designed for a
loads transmitted from the legs are properly distri- bending moment resulting from a 15° single
buted into the hull structure. amplitude of roll or pitch at a 10 second period, plus
120 % of the gravity moment caused by the legs angle
3.2 For the elevated position, special attention is of inclination (minimum design criteria).
to be paid to the distribution of the loads from the
supporting points (legs) into the hull structure, taking For ocean transit conditions, it may be necessary to
account also of possible load redistributions resulting reinforce or support the legs, or to remove sections of
from lack of support at one leg. them. The approved condition is to be included in the
Operating Manual.
The structure surrounding the legs (points of support)
shall be designed with particular regard to the 4.3.3 Field transit condition
introduction of local concentrated forces; main load
bearing elements should be continuous in the vertical Legs are to be designed for a bending moment
direction. resulting from a 6° single amplitude of roll or pitch at
the natural period of the unit, plus 120 % of the
gravity moment caused by the legs angle of inclina-
Regarding the maximal force to be transmitted,
tion.
pre-loading of the legs shall be considered, see 4.5
below.
The legs are to be investigated for any proposed leg
arrangement with respect to vertical position during
3.3 For loose elements, e.g. bars, rods, bolts, field transit moves, and the approved positions are to
pins, serving for transmission of forces to support the be specified in the Operating Manual.
unit, special requirements may be imposed regarding
dimensioning (safety factors) and testing. Such investigation should include strength and
stability aspects.
Section 2 - Self–elevating Units B 2-3

Field transit moves may only be undertaken when the 4.4.2 The envelope plating of tanks which are not
predicted weather is such that the anticipated motions vented freely to the sea is not to be less in thickness
of the unit will not exceed the design condition. The than would be required by the rules for tanks, using
duration of a field transit move may be for a a head to the design water level taking into account the
considerable period of time and should be related to astronomical and storm tides, see 2.1.
the accuracy of weather forecasting in the area
concerned. Such a move should not normally 4.4.3 The effects of scouring on the bottom bearing
exceed a twelve hour voyage between protected surface should be considered. The effects of skirt
locations, or locations where the unit may be safely plates, where provided, have to be especially consi-
elevated; however, during any portion of the move, dered.
the unit is not normally to be more than a six hour 4.4.4 Mats are to be designed to withstand the
voyage away form a protected location or a location loads encountered during lowering including the
where the unit may be safely elevated. The approved shock of touching bottom while the unit is afloat and
condition is to be included in the Operating Manual. subject to wave motions.
4.3.4 Condition while lowering legs 4.4.5 Provisions for ballasting and de-ballasting the
mat have to be installed. These may be pipelines
Legs are to be designed to withstand the dynamic and running down each leg into the mat to vent off trapped
current loads which may be encountered along their air during ballasting or to induce air for displacing the
unsupported length just prior to touching bottom, and water and thus de-ballasting the mat. These pipelines
also to withstand the shock of touching bottom while may also be used to blow air under the bottom of the
the unit is afloat and subject to motions caused by mat with the aim of facilitating the lifting of the mat
waves and wind. from the bottom of the sea.
The maximum design motions, water depth, bottom 4.5 Preload capability
conditions and sea state while lowering legs are to be For units without bottom mats, all legs are to have the
clearly indicated in the Operating Manual, and the legs capability of being preloaded to the maximum
are not to be permitted to touch bottom when the site applicable combined gravity plus overturning load.
conditions exceed the allowable. The approved pre-load procedure shall be included in
the Operating Manual.
4.3.5 Condition while elevating the unit
Regarding the preloading capability of the elevating
The legs are to be designed to withstand the loads machinery, see Volume 4 – Rules for Machinery
acting on both, the unit’s hull and the legs themselves, Installations, Section 9.
during the elevating procedure. The environmental
conditions are the same as foreseen for lowering of the
legs (4.3.4). C. Stability

The analysis may have to be done for several 1. General


intermediate positions of the hull. The general requirements for stability are defined in
Section 7. Additional aspects are given in the follo-
wing.
4.3.6 Elevated (working) condition
2. Overturning Stability
The largest possible overturning moments shall be 2.1 The unit, when resting on the sea-bed, is to
considered, using the most adverse combination(s) of have sufficient downward gravity loading on the
applicable variable and environmental and gravity support footings or mats to withstand the overturning
loadings. Forces and moments due to lateral frame moment of the combined environmental forces from
deflections of the legs are to be taken into account. any direction, for each design loading condition. The
overturning safety, defined as the sum of the restoring
Eccentricity of support or partial restraint of the lower
moments divided by the sum of the overturning
leg ends may have to be considered (e.g. for spud can
moments, should not be less than:
design), depending on the soil conditions. The analysis
will usually have to be carried through for several − 1,5 for loading condition 2
water depths and corresponding site and environ-
mental conditions. − 1,3 for loading condition 3
according to Volume 2 – Rules for Structures, Sec-
4.4 Bottom mat tion 3, C.
2.2 It is assumed that noticeable inclinations of
4.4.1 If the sea-bed conditions are characterized by the unit will not occur or will be corrected
very soft mud and silt, the lower ends of the legs are to immediately, and that the effects of any dangerous
be attached to a mat. Particular attention is to be given changes of the sea-bed will be kept under control.
to the attachment and the framing and bracing of the Corresponding instructions shall be contained in the
mat, in order that the loads are properly distributed. Operating Manual.
Section 3 – Column Stabilized Units A 3-1

Section 3
Column Stabilized Units

A. General 2.4 Positional mooring equipment


Mooring equipment for position keeping at the work-
1. Definition ing location is defined in Section 8, C.
Column stabilized units depend upon the buoyancy of
widely spaced columns for floatation and stability for 2.5 Dynamic position keeping
all afloat modes of operation or in the raising or Dynamic position keeping at the working location
lowering of the unit, as may be applicable. The means maintaining a desired position within the
columns are connected to an upper structure support- normal excursions of the control system and under
ing e.g. drilling equipment or accommodation quar- defined environmental conditions. The required
ters. Lower hulls or footings may be provided at the position tolerances during drilling operations have to
bottom of the columns for additional buoyancy or to be defined by the owner/operator.
provide sufficient area to support the unit on the sea-
bed. Bracing members of tubular or structural sections The complete dynamic positioning system requires the
may be used to connect the columns, lower hulls or following sub-systems:
footings, and to support the upper structure. − power system
Operations may be carried out in the floating − thruster system
condition, in which condition the unit is described
as a Semi-Submersible Unit, or when the unit is − control system
supported by the sea-bed, in which condition the unit is Thrusters used as sole means of position keeping shall
described as a Submersible Unit. A Semi-Submersible provide a level of safety equivalent to that provided
Unit may be designed to operate either floating or for mooring arrangements to the satisfaction of BKI.
supported by the sea-bed, provided each type of
operation has been found to be satisfactory and suit- The Class Notations DP 1 to DP 3 will be assigned if
able. the unit is equipped with such a system, compare
Volume 1 – Rules for Classification and Surveys,
The Class Notation COLUMN STABILIZED UNIT Section 2.
will be assigned for this type, compare Volume 1 –
Rules for Classification and Surveys, Section 2. Further details are defined in the Volume 4 – Rules
for Machinery Installations, Section 6, E.
2. Scope
2.6 Auxiliary installations and equipment
2.1 This Section covers those specific design Special (auxiliary) installations and equipment are to
criteria and features of column stabilized mobile be designed according to the specific Sections as far as
offshore units which are not dealt with in other applicable. See also Volume 1 – Rules for Classifi-
Sections, as referred to in the following. cation and Surveys, Section 1, D.2.

2.2 Subdivision and watertight integrity 2.7 Lifting appliances


Subdivision and watertight integrity are dealt with in For the interaction of lifting appliances with the unit,
Section 7. Regarding stability see C. their foundations, etc. see Volume 2 – Rules for Struc-
tures, Section 8.
2.3 Machinery and electrical installations Each elevator cabin in a column shall provide for an
Machinery and electrical installations shall be emergency exit with an escape ladder in the hoistway.
designed according to Volume 4 - Rules for Machinery The requirements for offshore cranes and other lifting
Installations and Volume 5 - Rules for Electrical appliances themselves are defined in the Regulations
Installations, respectively, as far as applicable. For for the Construction and Survey of Lifting Appli-
ballast and bilge pumping arrangements see Volume ances.
4, Section 13e, H. and I. and Volume 5, Section 12, J.
2.8 Towing and ballasting
Propulsion installations, designed for conveyances
under own power or for towage assistance, and/or for Conditions for towing, for ballasting and de-ballasting
positioning, shall also be designed according to procedures and for mooring operations shall be clearly
Volume 4 and 5 also according to the Rules for indicated in the Operating Manual, compare Sec-
Machinery Installations - Volumes III and Rules for tion 1, C.3.1.
Electrical Installation – Volume IV, as applicable.
3-2 Section 3 – Column Stabilized Units B

2.9 Drilling 1.4 Stress and motion analysis

Drilling derricks shall be designed according to 1.4.1 As the design of column stabilized units is
recognized codes/standards and/or applicable national governed by both, structural and motion behaviour,
regulations. The rated capacity for each reeving shall calculations will have to be presented for approval
be included in the Operating Manual. covering both aspects. The investigation shall be
carried out for a sufficient number of draughts and
Permanently installed piping systems for drilling environmental conditions in order to determine the
operations are to comply with an recognized standard most severe cases of stressing and the associated
or code. motions, and vice versa.

These Rules do not include requirements for the Model tests may serve as additional basis for design.
drilling of subsea wells or procedures for their control.
1.4.2 For units of this type, the highest stresses
Such drilling operations are subject to control by the
may be associated with less severe environmental
coastal state.
conditions than the maximum specified by the owner-
/designer. Where considered necessary by BKI,
account shall be taken of the consequent increased
possibility of encounter of significant stress levels, by
B. Structure either or both of the following:
− suitable reduction of the allowable stress levels for
1. General combined loading defined in Volume 2 – Rules for
Structures, Section 3, D.
1.1 Structural design shall be based on the − detailed investigation of fatigue properties
principles described in Volume 2 – Rules for
Particular attention shall also be given to the details of
Structure, Sections 1 to 4, see also 1.4. Particular
structural design in critical areas such as bracing
attention should be given to structural details in critical
members, joint connection, etc.
areas such as connections of bracing members, where
high local loads are acting, see also 3.7 and Volu -
me 2 – Rules for Structure, Section 3, B. and Sec- 1.5 Structural redundancy
tion 4, B. – D.
1.5.1 When assessing structural redundancy for
column stabilized units, the following assumed
damage conditions shall apply:
1.2 For the dimensioning of ship-like structural
members such as decks, bulkheads, deck houses, 1.5.1.1 The unit’s structure shall be able to withstand
girders and pillars, Rules for Hull - Volume II may the loss of any slender bracing member without
be used as a design basis. causing overall collapse of the unit’s structure.
\

1.5.1.2 Structural redundancy will be based on the


1.3 Wave clearance applicable requirements of Volume 2 – Rules for
Structures, Sections 2 to 4, except:
1.3.1 Afloat condition − maximum calculated stresses in the structure
remaining after the loss of a slender bracing
Unless deck structures are designed for wave impact, member are to be in accordance with Volume 2 –
to the satisfaction of BKI, reasonable clearance Rules for Structures, Section 3, D. These criteria
between the deck structures and the wave crests is to may be exceeded for local areas, provided
be ensured for afloat modes of operation, taking into redistribution of forces due to yielding or buckling
account the predicted motion of the unit relative to the is taken into consideration.
surface of the sea. Calculations, model test results or
reports on past operating experience with similar − When considering environmental factors, a one
configurations showing that adequate provision is year return period may be assumed for intended
made to maintain this clearance are to be submitted. areas of operations, see Volume 2 – Rules for
Structures, Sections 2.
1.3.2 On-bottom condition 1.5.2 The structural arrangement of the upper hull
is to be considered with regard to the structural
The unit is to be designed for a clearance of either 1,2 integrity of the unit after the failure of any primary
m, or 10 % of the combined storm tide, astronomical girder.
tide and height of the maximum wave crest above the
mean low water level, whichever is less, between the
underside of the hull in the elevated position and the 2. Upper structure
crest of the design wave. This crest elevation is to be
measured above the level of the combined 2.1 The scantlings of the upper structure are not
astronomical and storm tides. See also Volume 2 – to be less than those required by the Rules mentioned
Rules for Structures, Section 2, B.4.10. above, in association with the loading indicated on the
deck loading plan. In addition, when the upper
Section 3 – Column Stabilized Units B 3-3

structure is considered to be an effective member of the scantlings are not to be less than required for
the overall structural frame of the unit, the scantlings watertight bulkheads in association with a head equi-
are to be sufficient to withstand actual local loading valent to the maximum waterline in damaged condi-
plus any additional loading superimposed due to frame tion; for all areas subject to wave immersion, a
action, within the stress limitations given in Volume 2 minimum head of 6,0 m shall be used.
– Rules for Structures, Section 3, D.
3.3 Where columns, lower hulls or footings are
2.2 When an approved mode of operation or designed as shells, either un-stiffened or ring stiffened,
damage condition in accordance with the stability the minimum scantlings of shell plating and ring
requirements allows the upper structure to become stiffeners are to be determined on the basis of esta-
waterborne, special consideration shall be given to the blished shell analysis using the appropriate safety
resulting structural loading. factors and the design heads as given in 3.2, see also
Volume 2 – Rules for Structures, Section 3, G.4.
2.3 Tanks
3.4 Openings in columns, like portlights or
2.3.1 Tanks for fresh water or fuel oil, or other windows, including those of the non-opening type,
tanks which are not intended to be kept entirely filled or other similar openings are not to be fitted in
in service, are to have divisions or deep swashes as columns.
may be required to minimize the dynamic stress on the Regarding openings in external and internal walls,
structure. Tight divisions and boundary bulkheads of bulkheads, etc. see also Section 7, G.
all tanks are to be constructed in accordance with the
Rules according to 1.2. The arrangement of all tanks, 3.5 Scantlings of columns, lower hulls or
together with their intended service, and the height of footings as determined according to 3.2 and 3.3 are
the over-flow pipes are to be clearly indicated on the mini- mum requirements for hydrostatic pressure
plans submitted for approval. Consideration is to be loads. Where wave and current forces, or bottom
given to the specific gravity of the liquid in the tank. contact pressure in case of units resting on the sea-bed
are superimposed, the local structure of the shell is to
2.3.2 Tanks are to be tested in accordance with the be increased in scantlings as necessary, to meet the
Rules and/or specifications. strength requirements mentioned in 1.1 above.
Scantlings in tanks are to be determined for both, full
2.4 Deckhouses fitted to the upper structure are and empty conditions.
to be designed in accordance with the Rules defined in
1.2, with due consideration given to their location and 3.6 When the column, lower hull or footing is an
to the environmental conditions in which the unit will effective member of the overall structural frame of the
operate. unit, the scantlings are to be sufficient to meet the
requirements of this paragraph plus any additional
2.5 Local structures in way of fairleads, winches, stress superimposed due to frame action, within the
etc., forming part of the positional mooring system, stress limitations of Volume 2 – Rules for Structures,
shall be designed to the breaking strength of the Section 3, D.
moor ing line.
3.7 Particular consideration is to be given to
2.6 Special attention is to be paid to the structural details, reinforcements, etc., in areas subject
foundations (supporting structure) and fastening of to high local loading, or to such loading that may
drilling derrick(s), cranes (see also Volume 2 – Rules cause shell distortion, for example:
for Structures, Section 8) and similar installations.
− sloshing in partially filled tanks
− bracing connection forces
3. Columns, lower hulls and footings
− loads due to mooring operations
3.1 Main stability columns and lower hull or − wave impact
footings may be designed as either framed or un-
framed shells. In either case, framing, ring stiffeners, − bottom bearing loads, where applicable
bulkheads or other suitable elements used are to be
sufficient to maintain shape and stiffness under all the 3.8 Consideration shall be given to objects falling
anticipated loading. down from the platform onto the lower hull or footing.
The size of objects and the potential area where
3.2 Where columns, lower hulls or footings are objects may fall down has to be determined under
designed with stiffened plating, framing, girders, etc., special consideration of crane operations. From there
may be determined in accordance with the the following angles of fall direction may be assumed:
requirements for tanks. Where an internal space is a
void compartment, the design head used is not to be − in air, unit floating : 10°
less than that corresponding to the maximum allow- − in air, unit supported on sea-bed : 5°
able waterline of the unit in service. In general,
− in water : 15 °
3-4 Section 3 – Column Stabilized Units C

The endangered main structural elements of the lower and roundness of shape. The necessary buckling
hull determined in this way have to be reinforced to investigation has to consider axial stresses and stresses
withstand the impact energy of fallen objects. caused by hydrostatic pressure, where applicable, see
Volume 2 – Rules for Structures, Section 3, G.4.
3.9 When a unit is designed for operations while
supported by the sea-bed, the footings shall be 4.5 Where braces are designed to be buoyant,
designed to withstand the shock of bottom contact due they shall be designed to prevent collapse from
to wave action on the hull. Such units shall also be hydrostatic pressure. They shall be accessible for
evaluated for the effects of possible scouring action internal inspection, or else adequate means should be
(loss of bottom support). The effect of skirt plates, provided in order to detect leakage at an early stage.
where provided, shall be given special consideration.

4. Bracing members C. Stability

4.1 Arrangement of braces


1. General
Where braces are essential for the structural integrity
of the unit, see 1.5, they should be so arranged that The general requirements for stability are defined in
they are protected as far as possible against boat Section 7. Additional aspects are given in the
impact (collisions) and other forces resulting from following.
normal operations.
2. Stability of units resting on the sea-bed
4.2 Bracing members are to be designed to
transmit loading due to environmental and inertia Units designed to rest on the sea-bed are to have
forces acting on the structure. When the unit is sufficient downward gravity loading on the support
supported by the sea-bed, the possibility of un-even footings or lower hull to withstand the overturning
bearing loads shall also be considered. Although moment of the combined environmental forces from
designed primarily as brace members of the overall any direction, for each applicable design loading
structure under the designated loading, the bracing condition.
shall also be investigated, if applicable, for The overturning safety factor, defined as the sum of
superimposed local bending stresses due to buoyancy, the restoring moments divided by the sum of the
wave and current forces. overturning moments, should not be less than:

4.3 Where relevant, consideration is to be given − 1,5 for loading condition 1


to local stresses due to wave impact.
− 1,3 for loading condition 2
4.4 When bracing members are of tubular according to Volume 2 – Rules for Structures, Sec-
section, ring frames may be required to maintain
stiffness tion 3, C.
Section 4 – Surface Drilling Units A 4-1

Section 4
Surface Drilling Units

A. General 2.4 Positional mooring equipment


An arrangement drawing for the mooring system has
1. Definition to be submitted. Mooring forces and permissible
mooring directions are to be defined.
As surface drilling units are to be understood:
In the drawings for the hull structure the foundations
1.1 Ship type drilling units for the mooring winches and the fairleads have to be
shown. As maximum mooring forces the breaking
Ship type drilling units are seagoing ship-shaped units strength of the mooring cables defined in the mooring
having a displacement-type hull or hulls, of the single, arrangement has to be assumed.
catamaran or trimaran types, which have been
designed or converted for drilling operations in the Mooring equipment for position keeping at the
floating condition. Such types have propulsion working location is defined in Section 8, C.
machinery.
The Class Notation DRILLING VESSEL will be 2.5 Dynamic position keeping
assigned for this type, compare Volume 1 - Rules for
Classification and Surveys, Section 2. Dynamic position keeping at the drilling location
means maintaining a desired position within the
1.2 Barge type drilling units normal excursions of the control system and under
defined environmental conditions. The required
Barge type drilling units are seagoing units having position tolerances during drilling operations have to
a displacement type hull or hulls, which have been be defined by the owner/operator.
designed or converted for drilling operations in the
floating condition. These units have no propulsion The complete dynamic positioning system requires the
machinery. following sub-systems:

The Class Notations PONTOON EQUIPPED FOR − power system


DRILLING will be assigned for this type, compare
Volume 1 - Rules for Classification and Surveys, − thruster system
Section 2. − control system
1.3 Other types of surface drilling units Thrusters used as sole means of position keeping shall
Units which are designed as mobile offshore drilling provide a level of safety equivalent to that provided
units and which do not fall into the categories for mooring arrangements to the satisfaction of BKI.
according to 1.1 and 1.2 will be treated on an indivi- The Class Notations DP 1 to DP 3 will be assigned if
dual basis and be assigned an appropriate Classifi- the unit is equipped with such a system, compare
cation designation. Volume 1 – Rules for Classification and Surveys,
Section 2.
2. Scope
2.1 This Section covers those specific design Further details are defined in the BKI Rules for
criteria and features of surface drilling units which are Dynamic Positioning Systems.
not dealt with in other Sections, as referred to in the
following.
2.6 Lifting appliances
2.2 Subdivision and watertight integrity Drawings showing the location and support of foun-
dations for cranes and davits have to be submitted.
Subdivision and watertight integrity of surface drilling
The forces to the hull structure have to be defined.
units are dealt with in Section 7. Regarding stability
see C.
For the interaction of lifting appliances with the unit,
their foundations, etc. see Volume 2 – Rules for
2.3 Machinery and electrical installations Structures, Section 8.
Machinery and electrical installations shall be The requirements for offshore cranes and other lifting
designed according to Volume 4 – Rules for appliances themselves are defined in the Regulations
Machinery Installations and Volume 5 – Rules for for the Construction and Survey of Lifting Appli-
Electrical Installations respectively, as applicable. ances.
4-2 Section 4 – Surface Drilling Units B-D

2.7 Towing 3.3 The local structure in way of elements of the


position mooring system and of the towing system, if
If the unit is towed by tugs, a general arrangement applicable, has to be reinforced accordingly, compare
drawing of the towing system has to be submitted. A.2.4 and A.2.7.
Towing forces and permissible towing directions are
to be defined.
In the drawings of the hull structure the measures to
transfer the towing forces into the hull have to be C. Stability
shown. As maximum towing forces the breaking
strength of the towing ropes or cables defined in the Stability according to the requirements defined in
towing arrangement has to be assumed. Section 7 has to be investigated for the three occurring
modes of operation:
Conditions for towing shall be clearly indicated in the
Operating Manual, compare Section 1, C.3.1. − drilling operation under defined environmental
conditions

− severe storm conditions


B. Structure − transit conditions between different drilling
locations
1. General
Scantlings of the hull structure are to meet the Rules D. Drilling Facilities
for Hull - Volume II. For barge type according to
A.1.2 especially Section 31 has to be observed. 1. Scope
Special consideration however is to be given to items These Rules do not include requirements for the
which may require some deviation or additions to drilling of subsea wells or procedures for their control.
these Rules, in particular the items indicated in 2. - 5. Such drilling operations are subject to control by the
coastal state.
2. Drilling well
2. Drawings to be submitted
2.1 The required strength of the unit shall be The planned interaction of the drilling systems with
maintained in way of the drilling well and particular hull has to be clearly documented, e.g. by:
attention shall be given to the transition between
fore- and -aft members so as to maintain continuity of − drawings showing the arrangement of the drilling
the longitudinal material. Stress concentrations have to derrick including weights and moments
avoided by a favourable structural detailed design. In
addition, the plating of the well is to be suitably − drawings showing the pipe storage and handling
stiffened to prevent damage due to foreign objects
which may become trapped in the well when the unit − drawings showing mud tanks, cement silos, etc.
is in transit.
3. Operating manual
2.2 The drilling well is to be surrounded by
cofferdams. Such cofferdams may temporarily be The rated capacity for each reeving shall be included
used also as tanks for liquids related to drilling in the Operating Manual.
operations, if they can be easily emptied for
inspection. 4. Drilling equipment

3. Deck area 4.1 Drilling derricks shall be designed according


to recognized codes/standards and/or applicable
3.1 The deck area in way of large hatches is to be National Regulations.
suitably compensated where necessary to maintain the Permanently installed piping systems for drilling
strength of the unit. operations are to comply with a recognized standard
or code.
3.2 The structure in way of heavy concentrated
loads resulting from the drilling derrick, pipe rack, set 4.2 Requirements for drilling systems are
back, drilling mud storage, etc., is to be suitably contained in Volume 4 – Rules for Machinery Instal-
reinforced. lations, Section 11.
Section 4 – Surface Drilling Units E 4-3

E. Safety Aspects 2. Fire protection


The requirements for structural fire protection and
means of escape are defined in Volume 4 – Rules for
1. Hazardous areas Machinery Installations Section 10, B.

3. Fire detection and extinguishing


The general classification in hazardous and non-
hazardous areas is contained in Volume 4 – Rules for The requirements for fire detection and alarm systems
Machinery Installations, Section 2, whereas the area are defined in Volume 4 – Rules for Machinery
classification requirements to be observed for drilling Installations, Section 10, J. The requirements for fire
are defined in Volume 4 – Rules for Machinery extinguishing systems and equipment are summa-
Installations, Section 11, B.2. rized in Volume 4 – Rules for Machinery Instal-
lations, Section 10, C. – I.

The requirements for explosion protection of electrical 4. Life-saving appliances


equipment in hazardous areas are defined in The number, size and arrangement of life-saving
Volume 5 – Rules for Electrical Installations, Sec- appliances for the complete crew shall follow the
tion 13. requirements defined in Section 9 of this Volume.
Section 5 – Pipe-laying Units A, B 5-1

Section 5
Pipe-laying Units

A. General 2.3.2 If the lifting appliances shall be included into


the Certification or Classification by BKI, the requi-
rements for offshore cranes and other lifting appli-
1. Definition
ances are defined in the BKI Regulations for the
As pipe-laying vessels are to be understood: Construction and Survey of Lifting Appliances.

1.1 Pipe-laying vessels


Pipe-laying vessels are seagoing ship-shaped units 3. Safety aspects
having a displacement type hull or hulls, of the single
or catamaran types, which have been designed or
converted for pipe-laying. Such types have propulsion 3.1 Hazardous areas
machinery and a dynamic positioning system or The general classification in hazardous and non-
positional mooring equipment. hazardous areas is contained in Volume 4 – Rules for
The Class Notation PIPE-LAYING VESSEL will be Machinery Installations, Section 2.
assigned for this type, compare Volume 1 - Rules for The requirements for explosion protection of electrical
Classification and Surveys, Section 2. equipment in hazardous areas are defined in
Volume 5 – Rules for Electrical Installations, Sec-
1.2 Pipe-laying barges tion 13.
Pipe-laying barges are seagoing units having a
displacement type hull or a semi-submersible configu- 3.2 Fire protection
ration, which have been designed or converted for
pipe-laying. These units have no propulsion machi- The requirements for structural fire protection and
nery, but may have positional mooring equipment, means of escape are defined in Volume 4 – Rules for
adequate tug assistance or dynamic positioning. Machinery Installations, Section 10, B.

The Class Notations PONTOON EQUIPPED FOR 3.3 Fire detection and extinguishing
PIPE-LAYING will be assigned for this type,
compare Volume 1- Rules for Classification and The requirements for fire detection and alarm systems
Surveys , Section 2. are defined in Volume 4 – Rules for Machinery
Installations, Section 10, J. The requirements for fire
extinguishing systems and equipment are summa-
2. Scope rized in Volume 4 – Rules for Machinery Instal-
2.1 This Section covers those specific design lations, Section 10, C. – I.
criteria and features of pipe-laying units which are not
dealt with in other Sections, as referred to in the 3.4 Life-saving appliances
following.
The number, size and arrangement of life-saving
appliances for the complete crew shall follow the
2.2 Machinery and electrical installations
requirements defined in Section 9 of this Volume.
Machinery and electrical installations shall be
designed according to Volume 4 – Rules for Machi-
nery Installations and Volume 5 – Rules for Elec- B. Movement and Position Keeping
trical Installations respectively, as applicable.

2.3 Lifting appliances 1. Possibilities


For the movement and position keeping of the unit
2.3.1 Drawings showing the location and support
during pipe-laying the following possibilities may be
of foundations for cranes and davits have to be
established:
submitted. The forces to the hull structure have to
be defined. − positional mooring with cables and anchors
Rules for the interaction of lifting appliances with the
− dynamic positioning by a greater number of
unit, their foundations, etc. are defined in Volume 2 –
thrusters on the unit
Rules for Structures, Section 8.
− combination of mooring and dynamic positioning
5-2 Section 5 – Pipe-laying Units B

2. Dynamic analysis of the pipe-laying 4. Dynamic position keeping


system
4.1 Dynamic position keeping at the pipe-laying
A dynamic analysis has to be submitted to BKI, which route means maintaining a desired position within the
has to consider: normal allowance of the control system and under
defined environmental conditions. The required posi-
− Arrangement of positional mooring system consi- tion tolerances during pipe-laying operations have to
dering elasticity of cables, if applicable be defined by the owner/operator.
− function of dynamic positioning system,if appli- Thrusters used as sole means of position keeping shall
cable provide a level of safety equivalent to that provided
for mooring arrangements to the satisfaction of BKI.
− influence of the laid pipe and forces at the ten-
sioners 4.2 The complete dynamic positioning system
− influence of sea state, wind and current condi- requires the following sub-systems:
tions, see Volume 2 – Rules for Structures, − power system
Section 1
− thruster system
3. Positional mooring equipment − control system

3.1 If the Class Notation “EQUIPPED WITH 4.3 The Class Notations DP 1 to DP 3 will be
POSITION MOORING SYSTEM” will be assigned if the systems complies with the require-
assigned, such a system consisting of: ments of the BKI Rules Dynamic Positioning
Systems, see also Volume 1 - Rules for Classification
− heavy anchors belonging to the unit and regularly and Surveys, Section 2.
changed in position by anchor handling tugs
5. Combination of positional mooring systems
− safe stowage of the anchors on the unit and
with dynamic positioning
appliances to hand them over to the tugs
− anchor cables as wire ropes or chain cables from 5.1 Also a combination of the positional mooring
the anchors to fairleads and winches on the unit system according to 3. with a dynamic positioning
including accessories like shackles, quick release system according to 4. may be established, if it is of
devices, wire rope terminations, etc. advantage for a special task.

− a winch or windlass for each anchor cable 5.2 It shall be secured that all elements of the
including tension control and measuring of cable combined system are operated from one control
length paid out station overlooking the unit and the mooring area.
− central control of all winches to keep position and 5.3 The detailed requirements for such a combi-
allow forward movement of the unit on the nation will be defined case by case.
planned track
has to be provided, see also Volume 1 - Rules for 6. Towing
Classificartion and Surveys, Section 2.
6.1 If the unit is towed by tugs, a general
3.2 An arrangement drawing for the mooring arrangement drawing of the towing system has to be
system has to be submitted. Mooring forces and submitted. Towing forces and permissible towing
permissible mooring directions are to be defined. An directions are to be defined.
example for a mooring system with 10 anchors is
shown in Fig. 5.1 and Fig. 5.2 for the two phases of 6.2 Towing arrangements and procedures shall be
starting of the operation and after a travel of such as to reduce to a minimum any danger to
abt. 600 m. personnel during towing operations. The design and
arrangement of towing fittings shall have regard to
both normal and emergency conditions.
3.3 In the drawings for the hull structure the
foundations for the mooring winches and the fairleads
have to be shown. The acting forces on the 6.3 In the drawings of the hull structure the
foundations are to be calculated for 100 % of the measures to transfer the towing forces into the hull
nominal breaking load of the mooring cables. For the have to be shown. As towing forces 100 % of the
supporting structure under this equipment 100 % of nominal breaking load of the towing lines have to be
the minimum yield stress ReH is to be observed as considered. For the supporting structure under this
acceptance criteria in the calculation. equipment 100 % of the minimum yield stress ReH
is to observed as acceptance criterion in the
3.4 The mooring equipment for position keeping calculation.
on the pipeline track is defined in Section 8, C.
Section 5 – Pipe-laying Units B 5-3

Fig. 5.1 Example for a typical position mooring system in abt. 100 m water depth (starting phase)

Fig. 5.2 Example for a typical position mooring system in abt. 100 m water depth (after 600 m travel)
5-4 Section 5 – Pipe-laying Units C, D

7. Operating manual 3. Special aspects for the hull structure


For the positioning and towing systems the following The following requirements, which are characteristic
aspects have to be included in the Operating Manual, for pipe-laying, have to be considered for the design
compare Section 1, C.3.1: of the hull structure, e.g.:

− principal functioning and co-operation of the − slot in the rear part of the main deck to lead the
different elements of the system pipe with the necessary bending radius to the
stinger
− procedure for the start of pipe-laying
− transmission of the forces from the stinger to the
− procedure for normal pipe-laying operation stern of the unit and of the forces from the
with advancing unit a frame for holding the stinger back and
adjusting the inclination of it to the main deck
− stopping or finishing the pipe-laying operation − transmission of the pipeline forces pulling the
with disconnecting and abandoning of the
(two) tensioners horizontally to the stern into the
pipeline midship section of the hull
− towing conditions − considerable mooring forces from different di-
rections at stern and bow
− procedures in the event of failure of the systems
− various loads from the pipe-laying facility as
− emergency measures described in E.

8. Sea trials

8.1 A schedule for the proposed tests of the D. Watertight Integrity and Stability
positioning and towing systems has to be submitted
for approval to BKI Head Office in due time before 1. Watertight integrity
the sea trials.
For subdivision into watertight compartments
see Section 7, E.
8.2 All procedures defined in the Operating
Manual have to be tested as far as practicable in this
stadium. 2. Stability

8.3 The trials have to be executed in presence of 2.1 Load cases


the BKI Surveyor who will sign a detailed trials The following load cases have to be considered:
protocol to be prepared by the builder, if the tests are
successful. The duplicate of this protocol has to be 2.1.1 Standard load cases
sent to BKI Head Office for final approval.
− normal pipe-laying operation up to defined
environmental limit conditions
− severe storm and seaway conditions with pipe
C. Structure disconnected and abandoned at the sea-bed.

1. General design 2.1.2 Special load cases

Scantlings of the hull structure are to meet the BKI


− ocean towage for long distances without or with
stinger, if applicable
Rules for Hull - Volume II. For barge type according
to A.1.2 especially Section 31 has to be observed. − field towage for short distances with stinger
Special consideration however is to be given to items − inspection or repair of existing pipelines by lifting
which may require some deviation or additions to up a part of the pipeline from the sea-bed to
these Rules, in particular the items defined in the the units side
following.
− influences from crane operation and positional
mooring have to be considered
2. Loads
2.1.3 Other load cases
The loads established in the dynamic analysis of the
pipe-laying system according to B.2. have to be Depending on the type of pipe-laying unit and the
considered. method of operation other load cases may be consi-
dered case by case.
Section 5 – Pipe-laying Units E 5-5

2.2 Stability criteria − general arrangement of the pipe-laying facility and


description of the main functions, definition of the
2.2.1 Intact stability environmental conditions up to which the facility
Concerning stability criteria the Code of Intact is able to operate
Stability for All Types of Ships Covered by IMO
Instruments Resolution A.749(18) as amended by − facilities for lifting the pipes from the supply
resolution MSC 75(69) shall be applied 1. vessels to the storage area and pipe transport on
the unit defining all created moments and forces
Special considerations shall be given to an unusual
arrangement of units, which also may lead to − plans showing the arrangement of the pipe
additional stability criteria. storage/racks, the maximum weights and the inten-
ded foundations on the upper deck
2.2.2 Damage stability
− plans defining the foundation forces of the facility
The criteria of the Code of Safety for Special Purpose for pipe connections
Ships acc. to IMO Res.A.543(13) and of the Code for
the Construction and Equipment of Mobile Offshore − plans showing the arrangement of the pipe
Drilling Units (MODU Code) shall be used as far as tensioners and the maximum tension forces
applicable.
− plans showing the support arrangement on the pipe
ramp and the maximum forces to be experienced

E. Pipe-laying Facility − plans showing the integration of the stinger at the


stern of the hull and definition of the forces to be
transferred into the hull, if applicable
1. Scope
In general the facility directly used for pipe storage, − plans showing the stinger including length
fabrication of the pipe connections, pipe fixing and variation , if applicable and its floating support, if
delivering/recovering to/from the sea-bed are not applicable
subject to Classification or Certification by BKI. But
the characteristics of the facilities, which influence: − plans showing the A-frame for variation of the
stinger inclination, if applicable
− overall design of the unit
− BKI reserve the right to ask for any other docu-
− overall safety of the unit mentation necessary to define the interaction of the
− weights and forces on all foundations facility with the unit

− floating and stability behaviour, etc.


3. Operating Manual
will be considered by BKI. Therefore BKI has to
be fully informed by the documents defined in 2. The Operating Manual of the unit, compare Section 1,
C.3.1, shall include all safety aspects created by the
facility and has also to be submitted to BKI. This
2. Documents to be submitted
manual shall include e.g.:
A complete set of documentation to define the
influences on the unit has to be submitted by the − functions of the pipe-laying facility including repair
builder/operator of the facility, consisting of e.g.: of existing pipelines, if applicable

− influence of pipe-laying on unit operation


––––––––––––––
1 In addition the criteria of the Code of Safety for Special Pur-
− special hazards to the unit
pose Ships acc. to IMO Res.A.543(13) and of the Code for the
Construction and Equipment of Mobile Offshore Drilling − emergency measures if a failure happens in the
Units (MODU Code) shall be used as far as applicable. pipe-laying facility, etc.
Section 6 – Well Stimulation Units A- D 6-1

Section 6
Well Stimulation Units

A. General 3. Emergency shut down

For all vessels/units an emergency shut down and


1. Definition quick well disengagement concept has to be developed
distinguishing different shutdown levels according to
Well stimulation vessels or units are self-propelled the used procedures of well stimulation. The requi-
ship type vessels equipped for intervention at subsea rements for relevant safety systems are defined in
wells with the aim to improve the operational well Volume 4 – Rules for Machinery Installations,
performance. Section 17.
The Class Notations WELL STIMULATION
4. Evacuation
VESSEL or WELL STIMULATION UNIT will be
assigned for this type, compare Volume 1 – Rules for If the stimulation procedures fail and the crew will be
Classification and Surveys, Section 2. in extreme danger the equipment for a quick and
smooth evacuation shall be available. The requi-
2. Stimulation service rements for such equipment are defined in Section 9.

The service of well stimulation vessels/units may be 5. Documentation


distinguished in:
All safety aspects have to be clearly defined in written
− stimulation of subsea wells using various form, such as a Safety Management Plan, and shall be
operating procedures included in the Operating Manual of the vessel/unit,
compare Section 1, C.3.1.
− stimulation of subsea wells including handling and
storage of well fluids
C. Position Keeping
3. Scope
1. As the well stimulation vessel/unit has to stay
In this Section the overall and special aspects for this near or above the well within a very restricted location
type of vessel/unit are summarized and references are allowance, the position keeping will be a major
given to the different Volume and Sections of the pre-requisite.
Rules where the detailed requirements are defined.
2. Position keeping may be established by the
following methods:

− positional mooring with anchors, cables and


B. Special Safety Aspects
mooring winches according to Section 8 and
Volume 4 − Rules for Machinery Installations,
1. Area classification Section 8, C.

For all types of vessels/units hazardous and − dynamic positioning with propulsion systems
non-hazardous areas have to be investigated and according to Volume 4 − Rules for Machinery
a complete area classification has to be performed, as Installations, Section 6, E. For this type of
far as needed. For the relevant criteria of such vessel/unit the requirements for Class Notation
a classification see Volume 4 - Rules for Machinery DP 2 are recommended.
Installations, Section 2.

D. Well Stimulation Equipment


2. Fire protection
1. The foundations for such equipment have to
Special attention shall be given to fire protection and
be integrated into the structure of the vessel/unit
measures for fire fighting. Relevant methods are
considering extreme loads likely to occur during the
summarized in Volume 4 − Rules for Machinery stimulation process.
Installations, Section 10.
6-2 Section 6 – Well Stimulation Units D

2. Well stimulation equipment is in general not 3. Especially equipment to be installed in


subject to Classification by BKI. Nevertheless this hazardous areas shall meet the necessary safety
equipment shall be designed and built according to standards. For electrical installations reference may
recognized regulations and safety standards. given to Volume 5 – Rules for Electrical Installations,
Section 13.
Section 7 – Subdivision, Stability and Load Line A, B 7-1
 

Section 7
Subdivision, Stability and Load Line

A. General Remarks, Scope F = 0, 5 ⋅ CS ⋅ C H ⋅ ρ ⋅ v 2 ⋅ A [ N ]

1. This Section refers to the subdivision, F = wind force [N]


stability and load line requirements for mobile off-
shore units and covers, essentially, the relevant CS = shape coefficient depending on the shape of
regulations of the IMO "Code for the Construction and the structural member exposed to the wind,
Equipment of Mobile Offshore Drilling Units (MODU see Table 7.1 [–]
Code)", as amended.
CH = height coefficient depending on the height
2. Any additional National Regulations should above sea level of the structural member
be observed, where applicable. exposed to wind, see Table 7.2 [–]

3. Regarding the effects of (maximum) angles ρ = air mass density (1,25) [Ns²/m4]
of inclination on machinery installations see Volu- v = wind velocity [m/s]
me 4 – Rules for Machinery Installations, Sec-
tion 1 C. and Volume 5 – Rules for Electrical A = projected area of all exposed surfaces in either
Installations, Section 1, E. the upright or the heeled condition [m²].

B. Righting and Heeling Lever Curves 4. Wind forces shall be considered from any
direction relative to the limit and the value of the wind
1. Curves of righting levers and of wind heeling velocity shall be as follows:
levers similar to Figure 7.1 with supporting
calculations shall be prepared covering the full range 4.1 In general a minimum wind velocity of
of operating draughts including those in transit 36 m/s (70 knots) for offshore service shall be used for
conditions, taking into account the maximum deck normal operating conditions and a minimum wind
cargo and equipment in the most unfavourable velocity of 51,5 m/s (100 knots) shall be used for the
position applicable. The righting lever curves and severe storm conditions. Loading conditions 2 and 3,
wind heeling lever curves shall be related to the most respectively see Volume 2 – Rules for Structures,
critical axes. Account shall be taken of the free surface Section 3, C.
of liquids in tanks.

Table 7.1 Values of the coefficient CS

Shape CS
Spherical 0,4
Cylindrical 0,5
Large flat surface (hull, deckhouse,
1,0
smooth under deck areas)
Drilling derrick 1,25
Wires 1,2
Fig. 7.1 Righting and heeling lever curves
Exposed beams and girders under
1,3
2. Where equipment is of such a nature that it deck
can be lowered and stowed, additional wind heeling Small parts 1,4
lever curves may be required; such data shall clearly
indicate the position of such equipment. Isolated shapes (cranes, beams, etc.) 1,5
Clustered deckhouses or similar
3. The curves of wind heeling levers shall be 1,1
drawn for wind forces calculated by the following structures
formula:
7-2 Section 7 – Subdivision, Stability and Load Line C

Table 7.2 Values of coefficient CH 7. Wind heeling moments derived from wind
tunnel tests on a representative model of the unit may
be considered as alternatives to the method given
Height above sea level [m] CH 1
in 3 to 5. Such heeling moment determination shall
0 – 15,3 1,00 include lift and drag effects at various applicable heel
angles.
15,3 – 30,5 1,10
30,5 – 46,0 1,20 C. Intact Stability Criteria
46,0 – 61,0 1,30
1. Standard criteria
61,0 – 76,0 1,37
76,0 – 91,5 1,43 1.1 The stability of a unit in each mode of
operation shall meet the following criteria, see also
91,5 – 106,5 1,48 Fig. 7.1.
106,5 – 122,0 1,52
1.2 For surface (ship-like) and self-elevating
122,0 – 137,0 1,56 units the area under the righting lever curve to the
137,0 – 152,5 1,60 second intercept or down-flooding angle, whichever is
less, shall be not less than 40 % in excess of the area
152,5 – 167,5 1,63 under the wind heeling lever curve to the same
limiting angle.
167,5 – 183,0 1,67
183,0 – 198,0 1,70 1.3 For column stabilized units the area under the
righting lever curve to the angle of down flooding
198,0 – 213,5 1,72
shall be not less than 30 % in excess of the area under
213,5 – 228,5 1,75 the wind heeling lever curve to the same limiting
angle.
228,5 – 244,0 1,77
244,0 – 256,0 1,79 1.4 The righting lever curve shall be positive
over the entire range of angles from upright to the
Above 256 1,80 second intercept.
1 The higher value of C has to be used.
H
2. Severe storm condition
4.2 Where a unit is to be limited in operation to Each unit shall be capable of sustaining a severe storm
sheltered locations (protected inland waters such as condition in a period of time consistent with
lakes, bays, swamps, rivers, etc.) consideration may be meteorological conditions. The procedures recom-
given to a reduced wind velocity of not less than mended and the approximate length of time required,
25,8 m/s (50 knots) for normal operating conditions. considering both operating conditions and transit
conditions, shall be contained in the Operating
Manual. It shall be possible to achieve the severe
4.3 In calculating the projected areas to the
storm condition without the removal or relocating of
vertical plane the area of surfaces exposed to wind due
solid consumables or other variable loads. However,
to heel or trim, such as deck undersides, etc., shall be
on application and with agreement of BKI, loading
included using the appropriate shape factor. Open
a unit past the point at which solid consumables
truss work may be approximated by taking 30 % of
would have to be removed or relocated to go to
the projected block area of both the front and back
severe storm condition may be permitted under the
section, i.e. 60 % of the projected area of one side.
following conditions, provided the allowable KG
requirement is not exceeded:
5. In calculating the wind heeling moments the
lever of the wind overturning force shall be taken − in a geographic location where weather conditions
vertically from the centre of pressure of all surfaces annually or seasonally do not become sufficiently
exposed to the wind to the centre of lateral resistance severe to require a unit to go to severe storm con-
of the underwater body of the unit. The unit shall be dition, or
assumed floating free of mooring restraint.
− where a unit is required to support extra deck-load
for a short period of time that is well within the
6. The wind heeling levers shall be calculated bounds of a favourable weather forecast
for a sufficient number of heel angles to define the
curve. For ship shaped hulls the curve may be − geographic locations, weather conditions and
assumed to vary as the cosine function of unit heel. loading conditions when this is permitted shall be
identified in the Operating Manual.
Section 7 – Subdivision, Stability and Load Line D, E 7-3

3. Alternative stability criteria 4. A record of all changes to machinery,


structure, outfit and equipment that affect the light
Alternative stability criteria may be accepted provided ship data, shall be maintained in the Operating
an equivalent level of safety is maintained, and if they Manual, or a light ship data alterations log, and be
are demonstrated to afford adequate positive initial taken into account in daily operations.
stability. The acceptability of such criteria will be
determined considering at least the following and
taking into account, as appropriate: 5. For column stabilized units, a dead
weight survey shall be conducted at intervals not
− Environmental conditions representing realistic exceeding five years. Where the deadweight survey
winds (including gusts) and waves appropriate for indicates a change from the calculated light ship
world wide service in various modes of operation. displacement in excess of 1 % of the operating
displacement, an inclining test shall be conducted.
− Investigate dynamic response of the unit.
The analysis shall include the results of wind
tunnel tests, wave tank model tests, and non-linear 6. The inclining test or deadweight survey shall
simulation, where appropriate. Any wind and wave be carried out in the presence of the BKI Surveyor.
spectra used shall cover sufficient frequency
ranges to ensure that critical motion responses are
identified. E. Subdivision and Damage Stability
− Potential for flooding taking into account dynamic
responses in a sea-way. 1. Surface and self-elevating units

− Susceptibility to capsizing considering the unit’s 1.1 The unit shall have sufficient freeboard and
restoration energy and the static inclination due to be subdivided by means of watertight decks and bulk-
the mean wind speed and the maximum dynamic heads to provide sufficient buoyancy and stability to
response. withstand in general the flooding of any one com-
partment in any operating or transit condition consis-
− An adequate safety margin to account for tent with the damage assumptions set out in F.
un-certainties.
1.2 The unit shall have sufficient reserve stability
in a damaged condition to withstand the wind heeling
moment based on a wind velocity of 25,8 m/s
D. Inclining Test (50 knots) imposed from any direction. In this
condition the final waterline, after flooding, shall be
below the lower edge of any down flooding opening.
1. An inclining test shall be carried out with the
first unit of a design, when as near to completion as
possible, to determine accurately the light ship data 2. Column stabilized units
(weight and position of centre of gravity).
2.1 The unit shall have sufficient freeboard and
2. For successive units which are identical by be subdivided by means of watertight decks and
design, the light ship data of the first unit of the series bulkheads to provide sufficient buoyancy and stability
may be accepted in lieu of an inclining test, provided to withstand a wind heeling moment induced by
the difference in light ship displacement or position of a wind of velocity of 25,8 m/s (50 knots) imposed
centre of gravity due to weight changes and minor from any direction in any operating or transit
differences in machinery, outfitting or equipment, condition, considering:
confirmed by the results of a deadweight survey, are
− The angle of inclination after the damage set out in
less than 1 % of the values of the light ship
displacement and principal horizontal dimensions as F.3. shall not be greater than 17°.
deter- mined for the first of the series.
− Any opening below the final waterline shall be
Particular care shall be given to the detailed weight made watertight, and openings within 4 m above
calculation and comparison with the original unit of the final waterline shall be made weather-tight.
a series of column stabilized semi-submersibles as
these, even though identical by design, are recognized − The righting lever curve after damage as set out
as being unlikely to attain an acceptable similarity of
above shall have, from the first intercept to the
weight or centre of gravity to warrant a waiver of the
lesser of the extent of weather-tight integrity
inclining test.
required above and the second intercept, a range
of at least 7°. Within this range the righting lever
3. The results of the inclining test, or dead curve shall reach a value of at least twice the wind
weight survey and inclining experiment adjusted for heeling lever curve, both being measured at the
weight differences, shall be indicated in the Operating same angle, see Fig. 7.2.
Manual.
7-4 Section 7 – Subdivision, Stability and Load Line F

− vertical extent: from the base line upwards with-


out limit

1.2 The distance between effective watertight


bulkheads or their nearest stepped portions, which are
positioned within the assumed extent of horizontal
penetration, shall be not less than 3 m. Where there is
a lesser distance one or more of the adjacent bulkheads
shall be disregarded.

1.3 Where damage of a lesser extent than given


in 1.1 results in a more severe condition, such lesser
extent shall be assumed.

1.4 All piping, ventilation systems, trunks, etc.,


within the extent of damage referred to in 1.1 shall be
Fig. 7.2 Righting and heeling lever curves for assumed to be damaged. Positive means of closure
damage stability shall be provided at watertight boundaries to preclude
the progressive flooding of other spaces which are
2.2 The unit shall provide sufficient buoyancy intended to be intact.
and stability to withstand, in any operating or transit
condition, the flooding of any watertight compartment 2. Self-elevating units
wholly or partially below the waterline in question,
which is a pump room, a room containing machinery 2.1 In assessing the damage stability of self-
with a salt water cooling system or a compartment elevating units, the following extent of damage shall
adjacent to the sea, considering: be assumed between effective watertight bulkheads:
− The angle of inclination after flooding shall not be − horizontal penetration: 1,5 m
greater than 25°.
− vertical extent: from the base line upwards
− Any opening below the final waterline shall be without limit
made watertight.
Where a bottom mat is fitted, assumed damage
− A range of positive stability shall be proven, penetration simultaneous to both the mat and the upper
hull need only be considered when the lightest
beyond the calculated angle of inclination in this draught allows any part of the mat to fall within 1,5 m
condition, of at least 7°. vertically of the waterline, and the difference in
horizontal dimension of the upper hull and mat is less
3. All types of units than 1,5 m in any area under consideration. If damage
of a lesser extent results in a more severe final
3.1 The requirements of 1.1 and 1.2 shall be equilibrium condition, such lesser extent shall be
determined by calculations which take into conside- assumed.
ration the proportions and design characteristics of the
unit and the arrangements and configuration of the
2.2 The distance between effective watertight
damaged compartments. In making these calculations,
bulkheads or their nearest stepped portions, which are
it shall be assumed that the unit is in the worst
positioned within the assumed extent of horizontal
anticipated service condition as regards stability and is
penetration, shall be not less than 3 m. Where there is
floating free of mooring restraints.
a lesser distance one or more of the adjacent bulkheads
shall be disregarded.
3.2 The ability to reduce heeling angles by
pumping out or ballasting compartments, or by
application of mooring forces etc., shall not be 2.3 Where damage of a lesser extent than given
considered as alleviating the requirements. in 2.1 results in a more severe condition, such lesser
extent shall be assumed.

2.4 All piping, ventilation, systems, trunks, etc.


F. Extent of Damage within the extent of damage referred to in 2.1 shall be
assumed to be damaged.
1. Surface units
2.5 Positive means of closure shall be provided at
1.1 In assessing the damage stability of surface watertight boundaries to preclude the progressive
units, the following extent of damage shall be assumed flooding of other spaces which are intended to be
between effective watertight bulkheads: intact. In addition, the compartments adjacent to the
− horizontal penetration: 1,5 m bottom shell are also to be considered flooded
individually.
Section 7 – Subdivision, Stability and Load Line G 7-5
 

2.6 The recessed ends and sides of the drilling G. Watertight Integrity
slot need not be subject to horizontal penetration if
warning signs be posted on each side of the vessel 1. Openings and penetrations
stating that no boats be allowed inside the drilling slot.
Instructions to this effect should be included in the The number of openings in watertight subdivisions
Operating Manual. shall be kept to a minimum compatible with the design
and proper working of the unit. Where penetrations of
watertight decks and bulkheads are necessary for
access, piping, ventilation, electrical cables, etc.,
3. Column stabilized units arrangements shall be made to maintain the watertight
integrity of the enclosed compartments.
3.1 In assessing the damage stability of column
stabilized units, the following extent of damage shall 2. Valves
be assumed.
2.1 Where valves are provided at watertight
3.2 Only those columns, underwater hulls and boundaries to maintain watertight integrity, these
braces on the periphery of the unit shall be assumed to valves shall be capable of being operated from a
be damaged, and the damage shall be assumed in the pump-room or other normally manned space, a
exposed portions of the columns, underwater hulls and weather deck, or a deck which is above the final
braces. waterline after flooding. In the case of a column
stabilized unit this will be the central ballast control
station. Valve position indicators shall be provided at
3.3 Columns and braces shall be assumed to be
the remote control station.
flooded by damage having a vertical extent of 3 m
occurring at any level between 5 m above and 3 m
below the draughts specified in the Operating Manual. 2.2 For self-elevating units the ventilation system
Where a watertight flat is located within this region, valves required to maintain watertight integrity shall
the damage should be assumed to have occurred in be kept closed when the unit is afloat. Necessary
both compartments above and below the watertight ventilation in this case shall be arranged by alternative
flat in question. Lesser distances above or below the approved methods.
draughts may be applied to the satisfaction of
BKI, taking into account the actual operating 3. Internal openings
conditions. However, the extent of required damage
region should be at least 1,5 m above and below the 3.1 The means to ensure the watertight integrity
draughts specified in the Operating Manual. of internal openings shall comply with the following
requirements:
3.4 No vertical bulkhead shall be assumed to be
damaged, except where bulkheads are spaced closer
− Doors and hatch covers which are used during the
than a distance of one eighth of the column’s perime- operation of the unit while afloat shall be remotely
ter at the draught under consideration, measured at the controlled from the central ballast control station
periphery, in which case one or more of the bulkheads and shall also be operable locally from each side.
shall be disregarded. Open/shut indicators shall be provided at the
control station.
3.5 Horizontal penetration of damage shall be − Doors or hatch covers which are normally closed
assumed to be 1,5 m.
while the unit is afloat are to be provided with an
alarm system (e.g. light signals) showing
3.6 Underwater hulls or footings shall be as- personnel both locally and at the central ballast
sumed to be damaged while the unit is operating in a control station whether the doors or hatch covers
transit condition, in the same manner as indicated in in question are open or closed. A notice shall be
3.2, 3.3, 3.5 and having regard to their shape, either affixed to each such door or hatch cover to the
3.4 or between effective watertight bulkheads. effect that it is not to be left open while the unit is
afloat.
3.7 If damage of a lesser extent results in a more
severe damage equilibrium condition, such a lesser 3.2 The means to ensure the watertight integrity
extent shall be assumed. internal openings which are kept permanently closed
during the operation of the unit, while afloat, shall
3.8 All piping, ventilation systems, trunks, etc., comply with the following requirements:
within the extent of damage shall be assumed to be
damaged. − A notice shall be affixed to each such closing
appliance to the effect that it is to be kept closed
3.9 Positive means of closure shall be provided at while the unit is afloat, except that manholes fitted
watertight boundaries to preclude the progressive with close bolted covers need not be so marked.
flooding of other spaces which are intended to be
intact.
− On self-elevating units, an entry shall be made in
the official log book or tour report, as applicable,
7-6 Section 7 – Subdivision, Stability and Load Line H

to the effect that all such openings have been 1.7 Special consideration shall be given to small
witnessed closed before the unit becomes hatches with an opening area of 2,5 m² or less at the
waterborne. exposed deck over the forward 0,25 L on seagoing
units of length 80 m or more, that are contracted on or
4. External openings after 1st January 2004, where the height of the exposed
deck in way of the hatch is less than 0,1 L or 22 m
above the summer load waterline, whichever is the
4.1 All down-flooding openings, the lower
lesser. For design details see Rules for Hull, Volu-
edge of which are submerged when the unit is
me II, Section 17, D.2.
inclined to the first intercept between the righting
lever and wind heeling lever curves in any intact or
damaged condition, shall be fitted with a suitable
watertight closing appliance, such as closely spaced 1.8 Special consideration shall be given to air
bolted covers. pipes, ventilator pipes and their closing devices at the
exposed deck over the forward 0,25 L on seagoing
units of length 80 m or more, that are contracted on or
4.2 Where flooding of chain lockers or other
after 1st January 2004, where the height of the exposed
buoyant volumes may occur, the openings to these
deck in way of the pipes is less than 0,1 L or 22 m
spaces shall be considered as down-flooding points for
above the summer load waterline, whichever is the
calculating intact stability.
lesser. For design details see Rules for Hull, Volu-
me II, Section 21, E.5.
H. Load Line

1. General requirements
2. Surface units
1.1 The requirements of the 1966 Load Line
Convention, as amended shall in principle apply to all
units. The minimum freeboard of units which cannot 2.1 Load lines shall be assigned to surface units
be computed by the normal methods laid down by that as calculated under the terms of the 1966 Load Line
Convention shall be determined on the basis of Convention and shall be subject to all the conditions
meeting the applicable intact stability, damage of assignment of that Convention.
stability and structural requirements for transit
conditions and drilling operations while afloat. The
freeboard shall not be less than that computed from the 2.2 Where it is necessary to assign a greater than
Convention where applicable. minimum freeboard to meet intact or damage stability
requirements, or due to any other restriction, seasonal
1.2 The requirements of the 1966 Load Line marks above the centre of the ring shall not be
Convention with respect to weather tightness and marked, and any seasonal marks below the centre of
water tightness of decks, superstructures, deckhouses, the ring shall be marked.
doors, hatchway covers, other openings, ventilators,
air pipes, scuppers, inlets and discharges, etc., shall be
taken as a basis for all units in the afloat condition.
2.3 Where moonpools are arranged within the
hull in open communication with the sea, the volume
1.3 In general, heights of hatch and ventilator of the moonpool shall not be included in calculation of
coamings, air pipes, door sills, etc., in exposed any hydrostatic properties. An addition shall be made
positions and their means of closing shall be to the geometric freeboard, if the moonpool has
determined by consideration of both intact and damage a larger cross-sectional area above the water line at
stability requirements. 0,85 H than below, corresponding to the lost
buoyancy (H = depth). This addition for the excess
1.4 All down-flooding openings which may portion above 0,85 H shall be made as prescribed for
be- come submerged, before the angle of inclination at well/recesses below. If an enclosed superstructure
which the required area under the intact righting arm contains part of the moonpool, deduction shall be
curve is achieved, shall be fitted with weather-tight made for the effective length of the superstructure.
closing appliances.

1.5 With regard to damage stability, the


requirements in E.2.1 (2nd item), E.2.2 and G.4.1 shall Where open wells/recesses are arranged in the
apply. freeboard deck, a correction equal to the volume of the
well/recess up to the freeboard deck divided by the
waterplane area at 0,85 H shall be made to the
1.6 Special consideration shall be given to the
freeboard obtained after all other corrections except
position of openings which cannot be closed in
bow height correction have been made. Free surface
emergencies, such as air intakes for emergency
effects of the flooded well/recess shall be taken into
generators, having regard to the intact righting arm
account in stability calculations.
curves and the final waterline after assumed damage.
Section 7 – Subdivision, Stability and Load Line H 7-7
 

2.4 The procedure described in 2.3 shall also of the unit when floating since its vertical position
apply in cases of small notches or relatively narrow relative to the upper hull may be critical. See also
cut-outs at the stern of the unit. Section 2.

2.5 Narrow wing extensions at the stern of the 4. Column stabilized units
unit shall be considered as appendages and excluded
for the determination of length L and for the 4.1 The hull form of this type of unit makes the
calculation of freeboards. calculation of geometric freeboard in accordance with
the provisions of Chapter III of the 1966 Load Line
Convention impracticable. Therefore the minimum
3. Self-elevating units freeboard of each column stabilized unit shall be
determined by meeting the applicable requirements for
3.1 Load lines shall be assigned to self-elevating − the strength of unit’s structure
units as calculated under the terms of the 1966 Load
Line Convention taking into account 2.2 to 2.5. When − minimum clearance between passing wave crests
floating or when in transit from one operational area to
another, units shall be subject to all the conditions of and deck structure, see Section 3, B.1.3.
assignment of that Convention unless specifically − intact and damage stability requirements
excepted, e.g. from Reg. 39 (minimum bow height).
However, these units shall not be subject to the term 4.2 The minimum freeboard shall be marked in
of that Convention while they are supported by the appropriate locations on the structure.
sea-bed or are in the process of lowering or
raising their legs. 4.3 The enclosed deck structure of each column
stabilized unit shall be made weathertight.
For the consideration of moonpools see 2.3.
4.4 Windows, sidescuttles and portlights, inclu-
3.2 The minimum freeboard of units which due ding those of the non-opening type, or other similar
to their configuration cannot be computed by the openings shall not be located below the deck structure
normal methods laid down by the 1966 Load Line of column stabilized units.
Convention shall be determined on the basis of
meeting applicable intact stability, damage stability
4.5 Special consideration shall be given to the
and structural requirements in the afloat condition.
position of openings which cannot be closed in
emergencies, such as air intakes for emergency
3.3 Some self-elevating units utilize a large mat generators, having regard to the intact righting arm
or similar supporting structure which contributes to curves and the final waterline after assumed damage.
the buoyancy when the unit is floating. In such cases the
mat or similar supporting structure shall be ignored
in the calculation of freeboard. The mat or similar 5. Pipe-laying units
supporting structure shall, however, always be taken For the special requirements for watertight integrity
into account in the evaluation of the stability and stability of pipe-laying units see Section 5, D.
Section 8 – Mooring Equipment A, B 8-1

Section 8
Mooring Equipment

A. General 3. Documents to be submitted


Plans showing the arrangement and complete details
of the anchoring system, including anchors, shackles,
1. Definitions anchor lines consisting of chain, wire or rope, together
with details of fairleads, windlasses, winches and any
1.1 Temporary mooring equipment other components of the anchoring system and their
foundations are to be submitted to BKI.
Temporary mooring equipment in the context of this
Section is the mooring equipment consisting of
anchors, cables, winches etc. intended to be used
while the mobile offshore unit is not in a working B. Temporary Mooring Equipment
condition but during voyages and location moves, and
for anchoring within harbours or in sheltered areas. 1. General
The equipment is to be designed to hold a unit in
position when exposed to moderate environmental 1.1 Temporary mooring equipment fitted in
loads. accordance with the provisions of this Section is to be
designed for quick and safe operation in all
foresee-able service conditions and for holding the
1.2 Positional mooring equipment unit at anchor.

Positional mooring equipment in the context of this Note:


Section is a system for position keeping on the
1. Temporary mooring equipment is, therefore,
working location. The system is intended to keep the
not intended to hold a unit off fully exposed coasts in
unit in position, i.e. maintaining the prescribed limits
rough weather or to stop a unit which is moving or
of movement during the work envisaged and
drifting. In this condition, the loads on the mooring
preventing the unit or other floating bodies from
equipment increase to such a degree that its
drifting under all anticipated sea and weather
components may be damaged or lost owing to the high
conditions. energy forces generated, particularly for large units.
2. In good holding ground the temporary
2. Scope mooring equipment required by this Section is
intended to hold a unit in conditions such as to avoid
2.1 As a condition of Class and for assigning the dragging of the anchor. In poor holding ground,
Class Notation , the unit is to be provided with the holding power of the anchors will be significantly
temporary mooring equipment complying with the reduced.
provisions of B. Deviations from this general require-
3. The Equipment Numeral formula for the
ment will be stated in the Class Certificate.
temporary mooring equipment required in this Section
is based on an assumed current speed of 2,5 m/sec,
2.2 Positional mooring equipment, usually a wind speed of 25 m/sec, and a scope of chain cable
provided for ship type and column stabilized units, is between 6 and 10, the scope being the ratio between
to comply with the provisions of C. An appropriate length of chain paid out and water depth.
Notation may be affixed to the Character of
Classification, see C.1.2. 1.2 The temporary mooring equipment shall
consist of anchors, chain cables, windlass or winches,
2.3 When separate temporary mooring equipment chain stoppers, chain lockers (if chains are fitted) and
is not fitted, consideration will be given to accepting wire ropes.
the positional mooring equipment as equivalent to the The equipment of anchors and chain cables is to be
rule requirements for temporary mooring equipment, determined from Table 8.1.
if the provisions of B. are complied with.
1.3 The anchors are to be effectively stowed and
2.4 Where positioning of the unit on the working secured to prevent any movement at sea. If the
location is achieved by a dynamic positioning system, anchors are stowed at the shell, the shell plating is to
the Notation DP will be affixed to the Character of be increased in thickness and the framing may have to
Class, see C.7. In that case separate temporary be strengthened.
mooring equipment according to B. will be required.
8-2 Section 8 – Mooring Equipment B

1.4 The arrangements are to be such as to provide However, upon case-by-case consideration a reduced
an easy lead of chain cable/wire rope from the anchor projected area of leeward structures may be accep-
to the windlass/winch and to ensure that the anchor ted.
can be dropped by its own weight without assistance.
Reduction factors on account of the particular shape of
structures are normally not to be applied.
1.5 Dimensioning

1.5.1 For the supporting structure under 3. Anchors


windlasses, chain stoppers, fairleads, sheaves and any
other items of equipment subjected to loads from the
3.1 Number
anchor cables as determined in accordance with the
provisions of 1.5.2 or 1.5.3, the following permissible Two rule power anchors according to Table 8.1 are to
stresses are to be observed: be connected to their chain cables and positioned on
− axial, bending stress : σb ≤ 0,8 x ReH board ready for use. It is to be ensured that each
anchor can be stowed in the hawse and hawse pipe in
− shear stress : τ ≤ 0,5 x ReH such a way that it remains firmly secured in seagoing
− equivalent stress : σeq = σb 2 + 3 x τ 2 ≤ R eH conditions.

1.5.2 Where chain cables are led through hawse 3.2 Construction
pipes, the acting forces are to be taken as 80 % or
45 % of the rated breaking load of the chain cable, i.e. 3.2.1 The anchors are to be made of materials and
are to be tested as required in accordance with the
− for chain stoppers : 80 % Rules for Materials – Volume V, Section 12.
− for windlasses : 80 % where no chain
3.2.2 The anchors shall be of approved design. The
stoppers are fitted
mass of the heads of patent anchors (stockless
− for windlasses : 45 % where chain stoppers anchors), including pins and fittings, shall comprise
are fitted not less than 60 % of the total mass of the anchor.

1.5.3 Where hawse pipes are not installed and the 3.2.3 In case of stock anchors, the total mass of the
chain cables are guided by fairleads and sheaves, the anchor including the stock shall comply with the
acting forces are to be taken as 100 % or 50 % of the values given in Table 8.1. The weight of the stock
rated braking load of the chain cable, i.e. should be approximately 20 % of this total mass.
− for chain stoppers : 100 %
3.2.4 The mass of each individual anchor may
− for windlasses : 100 % where no chain deviate from the tabular mass by up to 7 % as long as
stoppers are fitted the total mass of the anchors fitted and attached to the
− for windlasses : 50 % where chain stoppers chain cables is not less then twice the tabular mass of
are fitted one anchor.

3.3 High holding power anchors


2. Equipment numeral
3.3.1 Where anchors with increased holding power
The equipment numeral Z is to be calculated as are intended to be used, a special approval procedure
follows: is required, as described in 3.4. The following reduced
Z= D Z= 2/3
+D
fW + fW masses may be admitted:

D = moulded displacement [t] in seawater having − for ‘High Holding Power’ (HHP)
a density of 1,025 t/m³ when at anchor anchors: 75 % of the tabular mass
fW = projected area of all surfaces above the water − for ‘Very High Holding Power’ (VHHP)
line [m²] perpendicular to the wind direction anchors: 50 % of the tabular mass
when at anchor
3.3.2 The dimensions of the chain cable and
The masking effect of structures located behind each windlass are to be based on the tabular anchor
other is normally not to be taken into account. mass as given in Table 8.1.
Section 8 – Mooring Equipment B 8-3

Table 8.1 Definition of anchors and chain cables

2 stockless
bower Stud link chain cables
Number. for. Equipment anchors
Reg. numeral Z Diameter
Mass per
Total length
anchor d1 1 d2 d3
[− ] [− ] [kg] [m] [mm] [mm] [mm]
120 720 – 780 2280 467,5 48 42 36
121 780 – 840 2460 467,5 50 44 38
122 840 – 910 2640 467,5 52 46 40
123 910 – 980 2830 495 54 48 42
124 980 – 1060 3060 495 56 50 44
125 1060 – 1140 3300 495 58 50 46

126 1140 – 1220 3540 522,5 60 52 46


127 1220 – 1300 3780 522,5 62 54 48
128 1330 – 1390 4050 522,5 64 56 50
129 1390 – 1480 4320 550 66 58 50
130 1480 – 1570 4590 550 68 60 52

131 1570 – 1670 4890 550 70 62 54


132 1670 – 1790 5450 577,5 73 64 56
133 1790 – 1930 5610 577,5 76 66 58
134 1930 – 2080 6000 577,5 78 68 60
135 2080 – 2230 6450 605 81 70 62

136 2230 – 2380 6900 605 84 73 64


137 2380 – 2530 7350 605 87 76 66
138 2530 – 2700 7800 632,5 90 78 68
139 2700 – 2870 8300 632,5 92 81 70
140 2870 – 3040 8700 632,5 95 84 73

141 3040 – 3210 9300 660 97 84 76


142 3210 – 3400 9900 660 100 87 78
143 3400 – 3600 10500 660 102 90 78
144 3600 – 3800 11100 687,5 105 92 81
145 3800 – 4000 11700 687,5 107 95 84

146 4000 – 4200 12300 687,5 111 97 87


147 4200 – 4400 12900 715 114 100 87
148 4400 – 4600 13500 715 117 102 90
149 4600 – 4800 14100 175 120 105 92
150 4800 – 5000 14700 742,5 122 107 95
8-4 Section 8 – Mooring Equipment B

Table 8.1 Definition of anchors and chain cables (Continuous)

2 stockless
bower Stud link chain cables
Number. for. Equipment anchors
Reg. numeral Z Diameter
Mass per
Total length
anchor d1 1 d2 d3

[− ] [− ] [kg] [m] [mm] [mm] [mm]


151 5000 – 5200 15400 742,5 124 111 97
152 5200 – 5500 16100 742,5 127 111 97
153 5500 – 5800 16900 742,5 130 114 100
154 5800 – 6100 17800 742,5 132 117 102
155 6100 – 6500 18800 742,5 120 107

156 6500 – 6900 20000 770 124 111


157 6900 – 7400 21500 770 127 114
158 7400 – 7900 23000 770 132 117
159 7900 – 8400 24500 770 137 122
160 8400 – 8900 26000 770 142 127

161 8900 – 9400 27500 770 147 132


162 9400 – 10000 29000 770 152 132
163 10000 – 10700 31000 770 137
164 10700 – 11500 33000 770 142
165 11500 – 12400 35500 770 147

166 12400 – 13400 38500 770 152


167 13400 – 14600 42000 770 157
168 14600 – 16000 46000 770 162
d1 = chain diameter Grade KI-K1 (ordinary quality)
d2 = chain diameter Grade KI-K2 (special quality)
d3 = chain diameter Grade KI-K3 (extra quality)
1 not recommended for offshore use

3.4 Approval procedure 3.4.2 The chain length used in the tests should be
approx. 6 to 10 times the depth of water.

3.4.1 For approval as a "High Holding Power


Anchor", satisfactory tests are to be made on 3.4.3 The tests are normally to be carried out from
various types of bottom and the anchor is to have a a tug, however, alternative shore based tests (e.g. with
holding power at least twice that of a patent anchor suitable winches) may be accepted.
("Admiralty Standard Stockless") of the same mass.
The mass of anchors to be tested should be Three tests are to be carried out for each anchor and
representative of the full range of sizes intended to be type of bottom. The pull shall be measured by means
manufactured. The tests are to be carried out on at least of a dynamometer or recorded by a recording instru-
two sizes of anchors in association with the chain ment. Measurements of pull based on rpm/bollard pull
cables appropriate to the weight. The anchors to be curve of the tug may be accepted. Testing by compari-
tested and the standard stockless anchors should be of son with a previously approved HHP anchor may be
approximate the same mass. accepted as a basis for approval.
Section 8 – Mooring Equipment B 8-5

3.4.4 The maximum mass of an anchor thus kept on board to facilitate fitting of the spare anchor at
approved may be 10 times the mass of the largest size any time.
of anchor tested.
4.7 Attachment of cable ends
3.5 Positional anchors
4.7.1 The inboard ends of the chain cables are to be
Anchors used as positional anchors in accordance with secured to the structure. The attachment is to be able
C., which shall be specially laid the right way up or to withstand a force not less than 15 % nor more than
which require flukes and profile to be adjusted to meet 30 % of the rated breaking load of the chain cable.
sea-bed conditions, will not normally be approved for
temporary mooring purposes. 4.7.2 The attachment of the inboard ends of the
chain cables to the unit’s structure is to be provided
4. Mooring chain cables and accessories with suitable means to permit, in case of emergency,
an easy slipping of the chain cables to sea from an
4.1 The chain cable diameters given in Table 8.1 accessible position outside the chain locker.
apply to chains complying with the requirements of
the Rules for Materials - Volume V, Section 13, 4.8 Wire ropes
where
Where wire ropes are fitted in lieu of chain cables, the
− Grade KI-K1 (ordinary quality) following applies:
− Grade KI-K2 (special quality) − The length of ropes is to be equal to 1,5 times the
− Grade KI-K3 (extra special quality) corresponding tabular chain cable length.
− The ropes breaking strength is not to be less than
are defined.
the breaking strength of the tabular Grade
KI-K1 chain cable. Strength according to Grade
4.2 Grade KI-K1 chain cable should not be used
KI-K2 chains is recommended.
for offshore applications. Where the installation of off-
shore quality mooring chains is intended, the provi- − A short length of chain cable is to be fitted
sions of C.4. apply. between anchor and wire rope. Wire rope
winches are to be fitted which comply with the
4.3 Grade KI-K2 and KI-K3 chain cables shall rules for windlasses, see Volume 4 – Rules for
be post production quenched and tempered and shall Machinery Installations, Section 8, A.
be purchased only from recognized manufacturers.
5. Chain locker
4.4 Chain cables or wire ropes, if fitted, are to be
made of materials and tested in accordance with the 5.1 The chain locker is to be of adequate capacity
BKI Rules mentioned under 4.1. and depth to facilitate an easy direct lead of the cables
through the chain pipes and to permit self-stowing of
4.5 Where the total mass of anchors is divided the cables. The chain locker is to be provided with
into three or four anchors, see 3.1, the chain cable internal divisions so that the chain cables may be fully
diameter and lengths are to be determined from Table and separately stowed.
8.1 for the mass of the anchor actually fitted. The The minimum required stowage capacity without mud
box for the two bower anchor chains is as follows:
chain cable length is to be determined by dividing the
tabular length by two and then multiplying by the
number of anchors actually fitted, unless specified
otherwise by the owner/operator.
d = chain diameter [mm] according to Table 8.1
4.6 Accessories l = total length of stud link chain cable according to
Table 8.1
4.6.1 Anchor shackles shall be of an approved type
and the material(s) shall conform to the Rules The total stowage capacity is to be distributed on two
mentioned under 4.1. Kenter-type shackles are chain lockers of equal size for the port and starboard
recommended. chain cables. The shape of the base areas shall as far
as possible be quadratic with a maximum edge length
4.6.2 A forerunner with swivel is to be fitted of 33 ⋅ d. As an alternative, circular base areas may be
between anchor and chain cable. In lieu of a forerunner selected, the diameter of which shall not exceed
with swivel, an approved swivel shackle may be fitted. (30 – 35) . d.
However, swivel shackles are not to be connected Above the stowage of each chain locker in addition a
directly to the anchor shank unless specially approved. free depth of
4.6.3 Where a spare anchor is fitted, see 3.1, a H = 1500 [mm]
sufficient number of suitable spare shackles is to be is to be provided.
8-6 Section 8 – Mooring Equipment C

5.2 The chain locker boundaries and their access 2. Anchoring systems
openings are to be watertight to prevent flooding of
adjacent spaces, where essential installations or 2.1 Approval documents
equipment are arranged, in order to not affect the
proper operation of the unit after accidental flooding 2.1.1 Plans showing the arrangement and complete
of the chain locker. details of the anchoring system, including anchors,
shackles, anchor line components, wires, together with
details of fairleads, windlasses, winches, controls and
5.3 Where the chain locker boundaries are also instrumentation, as well as any other components of
tank bulkheads, the scantlings of plating and stiffeners the anchoring system and its foundations, are to be
are to be determined as for tanks. submitted to BKI for approval.

2.1.2 An analysis of the anchoring arrangements


5.4 Special requirements to minimize the expected to be utilised during the unit’s operation is to
ingress of water be submitted to BKI. Among items to be addressed
are:
− design environmental conditions: waves, wind,
5.4.1 Spurling pipes and cable lockers are to be currents, tides, and ranges of water depth
watertight up to the weather deck.
− anchor holding capacities for various sea-bed soil
conditions
5.4.2 Where means of access is provided, it is to be − air and sea temperature
closed by a substantial cover and secured by closely
spaced bolts. − ice conditions, if applicable
− description of analysis method
5.4.3 Spurling pipes through which anchor cables
2.1.3 Plans showing the towing arrangement(s) and
are led are to be of suitable diameter and shall be
provided with permanently attached closing appliances equipment are to be submitted for information.
to minimize water ingress.
2.2 Design conditions, safety factors

2.2.1 Redundancy
5.5 Adequate drainage facilities are to be provi-
ded. The anchoring system should be designed such that a
sudden failure of any single anchor line will not cause
progressive failure of the remaining lines.

2.2.2 Loads
C. Positional Mooring Equipment
Anchoring system components should be designed
utilizing adequate safety factors and a design
1. General methodology suitable to identify the most severe
loading condition for each component. In particular,
sufficient numbers of heading angles together with the
1.1 All units, except self-elevating units and most severe combination of wind, current, and waves
submersible units, should be provided with positional are to be considered, usually from the same direction,
mooring equipment designed to maintain the floating to determine the maximum tension in each mooring
unit on station in all design conditions valid for its line.
intended area(s) of operation.
When a particular site is being considered, any
applicable cross sea conditions are also to be taken
1.2 Units provided with positional mooring into account in the event that they might induce
equipment in accordance with 1.1 will be eligible to higher mooring loads.
the special optional Class Notation "EQUIPPED
WITH POSITION MOORING SYSTEM" added to 2.2.3 Quasi static methods
the Character of Classification in accordance with the When the Quasi static method is applied, the tension
Rules, see Volume 1 – Rules for Classifications and in each anchor line is to be calculated at the maximum
Surveys, Section 2. excursion for each design condition defined in 2.2.4,
combining the following steady state and dynamic
responses of the unit:
1.3 Units provided with thrusters serving (also)
for position keeping will be eligible for the special a) Steady mean offset due to the defined wind,
Notations DP1 to DP3, see 7. current, and steady wave forces.
b) Most probable maximum wave induced motions of
the moored unit due to wave excitation.
Section 8 – Mooring Equipment C 8-7

For relatively deep water, the effect from damping and unit, unless BKI is satisfied that lesser conditions may
inertia forces in the anchor lines is to be considered in be applicable to specific sites.
the analysis.
2.2.6 In general, the maximum wave induced mo-
The effects of slowly varying motions are to be tions of the moored unit about the steady mean offset
included for column stabilized units when the should be obtained by means of model tests. BKI may
magnitudes of such motions are considered to be accept analytical calculations provided that the pro-
significant. posed method is based on a sound methodology which
has been validated by model tests.
2.2.4 When the Quasi Static Method outlined in
2.2.3 is applied, the minimum factors of safety at the Wind loads shall be determined according to the
maximum excursion of the unit for a range of principles shown in Volume 2 – Rules for Structures,
headings should be considered according to Table 8.2 Section 1, B. and Section 2, B.2. The results of
wind tunnel tests, as well as other recognized
criteria, may be considered.
Table 8.2 Minimum factors of safety
2.2.7 BKI may accept different analysis methodo-
Design condition Safety factor logies provided that a level of safety equivalent to
the one obtained by 2.2.3 and 2.2.4 is ensured.
Operating 2,7
Severe storm 1 1,8 2.2.8 BKI may give special consideration to an
arrangement where the anchoring systems are used in
Operating – one line failed 1,8 conjunction with thrusters to maintain the unit on
station, see 1.3 and 7.
Severe storm – one line failed 1 1,25
1 see Volume 2, Section 3, C.: Extreme environ- 3. Anchors
mental loads
3.1 General
Type/design, materials, manufacture and testing of
PB anchors used for position mooring shall comply with
Safety factor =
Tmax the BKI Rules mentioned under B.3., if Certification
by BKI is requested.

Tmax = characteristic tension in the anchor line, equal Anchors specially designed for position mooring are
to the maximum value obtained according to normally not to be used for temporary mooring,
2.2.2 and 2.2.3 see B.3.5.
PB = minimum rated breaking strength of the
anchor line 3.2 Testing
Anchors shall be subjected to load tests according to
2.2.4.1 Operating the Rule requirements, in approved testing
For the most severe design environmental condition installations. After application of the test load, it
for normal operations as defined by the owner or shall be shown that the anchor is free of any defects/
designer see Volume 2 – Rules for Structures, Sec- deformations resulting from testing, and fully opera-
tion 3, C.4.2. ble.
Test loads are shown in Table 8.3. For anchors with
2.2.4.2 Severe Storm increased holding capacity, the following test loads
For the most severe design environmental condition have to be applied:
for severe storm as defined by the owner or designer
HHP anchors : A load corresponding to 1,33 x mass
see Volume 2 – Rules for Structures, Section 3, C.4.3.
of anchor.
2.2.4.3 Operating - One Line Failed VHHP anchors : A load corresponding to 2 x mass
Situation which follows a failure of any one mooring of anchor.
line in the operating condition.

2.2.4.4 Severe Storm - One Line Failed 3.3 Anchors are to be securely stowed on board
to prevent movement during transit/towage.
Situation which follows a failure of any one mooring
line in the severe storm condition.
4. Anchor lines (mooring chain cables)
2.2.5 Dynamic analysis
4.1 General requirements
When a dynamic analysis is employed, other safety
factors may be considered to the satisfaction of BKI. 4.1.1 BKI are to be ensured that the anchor lines are
of a type/composition that will satisfy the design con-
The defined operating and severe storm conditions are
ditions of the anchoring system. In general anchor
to be the same as those identified for the design of the
8-8 Section 8 – Mooring Equipment C

cables may be of wire, rope, chain or any combination Table 8.3 Test loads for anchors 1
thereof. For wire ropes see B.4.8.
Mass Test load Mass Test load
4.1.2 Means are to be provided to enable the
[kg] [kN] [kg] [kN]
anchor lines to be released from the unit after loss
of main power. 2200 367 7800 861
2300 388 8000 877
2400 401 8200 892
4.1.3 Means are to be provided for measuring 414
2500 8400 908
anchor line tensions.
2600 427 8600 922
2700 438 8800 936
4.1.4 Anchor lines are to be of adequate length to
2800 450 9000 949
prevent up-lift of the anchors under the maximum 462
design load condition for the anticipated area(s) of 2900 9200 961
operation. 3000 474 9400 975
3100 484 9600 987
3200 495 9800 998
4.2 Offshore mooring chain cables - material 506
3300 10000 1010
requirements
3400 517 10500 1040
3500 528 11000 1070
4.2.1 General Requirements 537
3600 11500 1090
3700 547 12000 1110
4.2.1.1 Scope
3800 557 12500 1130
These Rules apply to the materials, design, 3900 567 13000 1160
manufacture and testing of offshore mooring chains 4000 577 13500 1180
and accessories intended to be used for applications 4100 586 14000 1210
such as: mooring of mobile offshore units, mooring of 595
floating production units, mooring of offshore loading 4200 14500 1230
4300 604 15000 1260
systems and mooring of gravity based structures 613
4400 15500 1270
during fabrication. 4500 622 16000 1300
Mooring equipment covered are common links, 4600 631 16500 1330
connection common links (splice links), enlarged 4700 638 17000 1360
links, end links, detachable connecting links 4800 645 17500 1390
(shackles), and shackles, swivels and swivel shackles. 4900 653 18000 1410
5000 661 18500 1440
4.2.1.2 Chain cable grades 5100 669 19000 1470
5200 677 19500 1490
Depending on the nominal tensile strength of the 5300 685 20000 1520
steels used for manufacture, chain cables are to be
subdivided into three grades, i.e.: KI-R3, KI-R3S, 5400 691 21000 1570
KI-R4. 5500 699 22000 1620
5600 706 23000 1670
5700 713 24000 1720
4.2.1.3 Approval of chain cable manufacturers
5800 721 25000 1770
4.2.1.3.1 Offshore mooring chain cables are to be 5900 728 26000 1800
manufactured only by works approved by BKI. For 6000 735 27000 1850
this purpose approval tests are to be carried out, the 6100 740 28000 1900
scope of which is to include proof and breaking load
6200 747 29000 1940
tests, measurements and mechanical tests including 754
6300 30000 1990
fracture mechanic tests. 6400 760 31000 1030
6500 767 32000 1070
4.2.1.3.2 Manufacturers are to submit for review and
approval the sequence of operations from receiving 6600 773 34000 2160
inspection to shipment, and details of the following 6700 779 36000 2250
manufacturing processes: 6800 786 38000 2330
6900 794 40000 2410
a) Bar heating and bending including method, 804
7000 42000 2490
temperature control and recording. 7200 818 44000 2570
b) Flash welding including current, force, time and 7400 832 46000 2650
dimensional variables as well as control and 7600 845 48000 2730
recording of parameters. 1 Intermediate values can be determined by linear interpolation

c) Flash removal including method and inspection.


Section 8 – Mooring Equipment C 8-9

d) Stud insertion method. 4.2.2 Materials


e) Heat treatment including furnace types, means of 4.2.2.1 Scope
specifying, controlling and recording of tem-
perature and chain speed and allowable limits, These requirements apply to rolled steels, forgings and
quenching bath and agitation, cooling method after castings used for the manufacture of offshore mooring
exit. chain cables and accessories.
f) Proof and break loading including method/
machine, means of horizontal support, if appli- 4.2.2.2 Rolled steel bars
cable, method of measurement recording.
4.2.2.2.1 Steel manufacture
g) Non-destructive examination procedures.
The steels are to be manufactured by basic oxygen,
4.2.1.3.3 Calibration of furnaces shall be verified by electric furnace or such other process as may be
measurement and recording of actual link temperature specially approved. All steels are to be killed and fine
(surface and internal). grain treated.
4.2.1.4 Approval of quality system at chain cable
manufacturers 4.2.2.2.2 Chemical composition

Chain cable manufacturers are to have a documented For acceptance tests, the chemical composition of
and effective quality system approved by BKI, e.g. ladle samples of each heat is to be determined by the
according to ISO 9001. steel maker and is to comply with the approved
specification.
4.2.1.5 Approval of steel mills for rolled bars
4.2.2.2.3 Mechanical tests
4.2.1.5.1Bar material intended for chain and
accessories are to be manufactured only by works 1. Bars of the same nominal diameter are to be
approved by BKI. The approval is limited to a presented for test in batches of 50 tonnes or fraction
nominated supplier of bar material. If a chain cable thereof from the same heat. Test specimens are to be
manufacturer wishes to use material from a number of taken from material heat treated in the same manner as
suppliers, separate approval tests shall be carried out intended for the finished chain.
for each supplier.
2. Each heat of Grade KI-R3S and KI-R4 steel
Approval will be given only after successful testing of bars is to be tested for hydrogen embrittlement. In
the completed chain cable. The approval will normally case of continuous casting, test samples representing
be limited to a thickness equal to that of the bars the beginning and the end of the charge shall be taken.
tested. In case of ingot casting, test samples representing two
different ingots shall be taken.
4.2.1.5.2 The steel maker is to submit a specification
of the chemical composition of the bar material, which Two (2) tensile test specimens shall be taken from the
shall be approved by BKI and by the chain cable central region of bar material which have been
manufacturer. simulated heat treated. The specimens shall preferably
have a diameter of 20 mm, alternatively 14 mm. One
For Grade KI-R4 chain cables the steel should con- specimen is to be tested within max. 3 hours after
tain a minimum of 0,20 per cent molybdenum. machining. For a 14 mm diameter specimen, the time
limit is 1,5 hours. Alternatively, the specimen may be
4.2.1.5.3 A heat treatment sensitivity study simulating cooled to – 60 °C immediately after machining and
chain cable production conditions shall be applied in kept at that temperature for a period of max. 5 days.
order to verify mechanical properties and establish The other specimen is to be tested after baking at
limits for temperature and time combinations. 250°C for 4 hours, alternatively 2 hours for 14 mm
diameter specimen.
4.2.1.5.4 The bar manufacturer is to provide evidence
that the material is resistant to strain ageing, temper A slow strain ≤ 0,0003 s-1 shall be used during the
embrittlement and hydrogen embrittlement. entire test, until fracture occurs. This means
approx.10 minutes for a 20 mm diameter specimen.
4.2.1.6 Approval of forges and foundries for ac-
cessories Tensile strength, elongation and reduction of area are
to be reported. The requirement for the test is:
4.2.1.6.1 Forges and foundries intending to supply
finished or semi-finished accessories are to be Z1
approved by BKI. The scope of approval is to be ≥ 0, 85
Z2
agreed with BKI.
Z1 = reduction of area without baking
4.2.1.6.2 Manufacturers intending to supply acces-
sories in machined condition (e.g. Kenter-type Z2 = reduction of area after baking
shackles) are to submit detailed drawings for approval.
8-10 Section 8 – Mooring Equipment C

If the requirement Z1 / Z2 ≥ 0,85 is not met, the bar The frequency of non-destructive examinations may
material may be subjected to a hydrogen degassing be reduced at the discretion of BKI provided it is
treatment after agreement with BKI. New tests shall verified by statistical means that the required quality is
be performed after degassing. consistently achieved.
3. For all grades, one tensile and three Charpy
V-notch specimens are to be taken from each sample 4.2.2.2.6 Marking
selected. The test specimens are to be taken at Each bar is to be stamped with the steel grade
approximately one-third radius below the surface, as designation and the charge number (or a code
shown in Fig. 8.1. indicating the charge number) on one of the end
The results of all tests are to be in accordance with the surfaces. Other marking methods may be accepted
appropriate requirements of Table 8.4. subject to agreement.
4. If the tensile test requirements are not
achieved, a retest of two further specimens selected 4.2.2.3 Forged steels
from the same sample shall be permissible. Failure to
4.2.2.3.1 Forged steels used for the manufacture of
meet the specified requirements of either or both of
the additional tests will result in rejection of the batch accessories shall be in compliance with specifications
represented, unless it can be clearly attributed to submitted and approved.
improper simulated heat treatment.

4.2.2.2.4 Dimensional tolerances


The diameter and roundness shall be within the
tolerances specified in Table 8.5, unless otherwise
agreed.

4.2.2.2.5 Non-destructive examination and repair


The bars shall be free from pipe, cracks and flakes.
Bar material is to be subjected to ultrasonic examina-
tion at an appropriate stage of the manufacture.
One hundred percent of the bar material is to be exam-
ined by magnetic particle or eddy current methods.
The bars shall be free of injurious surface imperfec-
tions such as seams, laps and rolled-in mill scale.
Provided that their depth is not greater than 1 % of the
bar diameter, longitudinal discontinuities may be Fig. 8.1 Location of test specimens
removed by grinding and blending to a smooth
contour.

Table 8.4 Mechanical properties of offshore mooring chain cables

Charpy V-notch impact tests


Tensile Elongation Reduction Average
Yield stress Test Average
strength A5 of area 3 energy flash
Grade temperature energy
weld
[N/mm2] [N/mm2] [%] [%] [J] [J]
[°C] 2
minimum Minimum minimum minimum minimum minimum
0 60 50
KI-R3 410 690 17 50
- 20 40 30
0 65 53
KI-R3S 490 770 15 50
- 20 45 33
KI-R4 580 860 12 50 - 20 50 36
1 Aim value of yield to tensile ratio: 0,92 max
2 At the option of Society the impact test of Grade KI-R3 and KI-R3S may be carried out at either 0 °C or minus 20 °C.
3 Reduction of area of cast steel is to be:
− for grades R3 and R3S: min. 40 %
− for grades R4: min 35 % - cf. item 4.2.2.3.4
Section 8 – Mooring Equipment C 8-11

Table 8.5 Dimensional tolerances of bar stock 4.2.2.4.4 Mechanical properties


material
The castings shall comply with the mechanical
properties given in Table 8.4.
Nominal Tolerance on Tolerance on
diameter diameter roundness 4.2.2.4.5 Mechanical tests
(dmax - dmin) For test sampling, castings of similar dimensions
[mm] [mm] [mm] originating from the same heat treatment charge and
below 25 -0 + 1,0 0,60 the same heat of steel are to be combined into one test
unit. From each test unit one tensile and three impact
25 – 35 -0 + 1,2 0,80 test specimens are to be taken and tested. For the
36 – 50 -0 + 1,6 1,10 location of the test specimens see Fig. 8.1.
51 – 80 -0 + 2,0 1,50 4.2.2.4.6 Ultrasonic examination
81 – 100 -0 + 2,0 1,95 The castings are to be subjected to ultrasonic examina-
101 – 120 -0 + 3,0 2,25 tion in compliance with the standard submitted and
approved.
121 – 160 -0 + 4,0 3,00
4.2.2.4.7 Marking
4.2.2.3.2 Chemical composition 4.2.2.3.7 applies.
4.2.2.2.2 applies. 4.2.2.5 Materials for studs
The studs are to be made of steel corresponding to that
4.2.2.3.3 Heat treatment
of the chain or in compliance with specifications
Finished forgings are to be properly heat treated in submitted and approved. In general, the carbon content
compliance with specifications submitted and should not exceed 0,25 per cent if the studs are to be
approved. welded in place.

4.2.2.3.4 Mechanical properties 4.2.3 Design and chain cable manufacture


4.2.3.1 Design
The forgings shall comply with the mechanical
properties given in Table 8.4, when properly heat Drawings giving detailed design of chain cables and
treated. accessories made by or supplied through the chain
cable manufacturer are to be submitted for approval.
4.2.2.3.5 Mechanical tests Typical designs are given in ISO 1704: 1991.
For test sampling, forgings of similar dimensions, that In addition, drawings showing the detailed design of
means that diameters do not differ by more than the stud shall be submitted for information. The stud
25 mm, originating from the same heat treatment shall give an impression in the chain link which is
charge and the same heat of steel are to be combined sufficiently deep to secure the position of the stud, but
into one test unit. From each test unit one tensile and the combined effect of shape and depth of the impres-
three impact test specimens are to be taken and tested. sion shall not cause any harmful notch effect or stress
For the location of the test specimens see Fig. 8.1. concentration in the chain link.
4.2.2.3.6 Ultrasonic examination Machining of Kenter shackles shall result in fillet
radius min. 3 % of nominal diameter.
The forgings are to be subjected to ultrasonic exami-
nation at an appropriate stage of manufacture and in 4.2.3.2 Manufacturing process
compliance with the standard submitted and approved. Offshore mooring chain cables shall be manufactured
in continuous lengths by flash butt welding and are to
4.2.2.3.7 Marking be heat treated in a continuous furnace; batch heat
Marking is to be similar to that specified in 4.2.2.2.6. treatment is not permitted.
The use of joining shackles to replace defective links
4.2.2.4 Cast steels is subject to the written approval of the end purchaser
in terms of the number and type permitted. The use of
4.2.2.4.1 Cast steels used for the manufacture of connecting common links is restricted to 3 links in
accessories shall be in compliance with specifications each 100 m of chain cable.
submitted and approved.
4.2.3.3 Manufacturing process records
4.2.2.4.2 Chemical composition
4.2.3.3.1 Documentation
4.2.2.2.2 applies.
Records of bar heating, flash welding and heat
4.2.2.4.3 Heat treatment treatment shall be made available for inspection by the
Surveyor.
All castings are to be properly heat treated in compli-
ance with specifications submitted and approved.
8-12 Section 8 – Mooring Equipment C

4.2.3.3.2 Bar heating 4.2.3.3.4 Heat treatment


For electric resistance heating, the heating phase shall Chain cables shall be austenitized above the upper
be controlled by an optical heat sensor. The controller transformation temperature, at a combination of
shall be checked at least once every 8 hours and temperature and time within the limits established.
records made. When applicable, chain cables shall be tempered at
For furnace heating, the temperature shall be a combination of temperature and time within the
controlled and continuously recorded using thermo- limits established.
couples in close proximity to the bars. The controls Temperature and time or temperature and chain speed
shall be checked at least one every 8 hours and shall be controlled and continuously recorded.
records made.
4.2.3.3.3 Flash welding 4.2.3.4 Mechanical properties
The mechanical properties of finished chain cables
The following welding parameters shall be controlled
and accessories are to be in accordance with Table 8.4.
during welding of each link:
For the location of test specimens see Figs. 8.1
a) Platen motion. and 8.2.
b) Current as a function of time.
4.2.3.5 Proof and break load tests
c) Hydraulic pressure.
Chain cables and accessories are to withstand the
The controls shall be checked at least every 4 hours proof and breaking load tests given in Table 8.6.
and records made.

Fig. 8.2 Location of test specimens

Table 8.6 Formulas for proof and breaking load tests, weight and length over 5 links

Grade KI-R3 Grade KI-R3S Grade KI-R4


Proof test load [kN] 0,0148 d2 (44-0,08d) 0,0180 d2 (44-0,08d) 0,0216 d2 (44-0,08d)
Break test load [kN] 0,0223 d2 (44-0,08d) 0,0249 d2 (44-0,08d) 0,0274 d2 (44-0,08d)
Chain weight [kg/m] 0,0219 d2
Length over 5 links
Min. [mm] 22 d
Max. [mm] 22,55 d
Section 8 – Mooring Equipment C 8-13

4.2.3.6 Freedom from defects 4.2.3.8.3 The stud ends shall have a good fit inside
the link and the weld is to be confined to the stud end
All chain cables are to have a workmanship like finish opposite to the flash butt weld. The full periphery of
consistent with the method of manufacture and be free the stud end is to be welded unless otherwise
from defects. Each link is to be examined in accor- approved.
dance with 4.2.4.5 using approved procedures.
4.2.3.8.4 Welding of studs at both ends is not
4.2.3.7 Dimensions and dimensional tolerances permitted unless specially approved.
4.2.3.7.1 The shape and proportion of links and
accessories shall conform to ISO 1704: 1991 or to the
designs specially approved.
4.2.3.7.2 The following tolerances are applicable to
links:
a) Nominal diameter measured at the crown:
up to 40 mm nominal diameter : – 1 mm
over 40 up to 84 mm nominal diameter : – 2 mm
over 84 up to 122 mm nominal diameter: – 3 mm
over 122 mm nominal diameter : – 4 mm
The plus tolerance may be up to 5 % of the nominal
diameter. The cross sectional area at the crown shall
have no negative tolerance.
b) Diameters measured at locations other than the
crown: The diameter is to have no negative
tolerance. The plus tolerance may be up to 5 % of
the nominal diameter. The approved manufacturer Fig. 8.3 Tolerances for stud position
specification is applicable to the plus tolerance of
the flash butt weld.
4.2.3.8.5 The welds are to be made by qualified
c) The allowable manufacturing tolerance on a length welders using an approved procedure and low-
of five links is + 2,5 %, but may not be negative. hydrogen approved consumables.
d) All other dimensions are subject to a manufactur-
ing tolerance of ± 2,5 %, provided always that all 4.2.3.8.6 The size of the fillet weld shall as a mini-
parts fit together properly. mum be as per API specification 2F.
e) Studs shall be located in the links centrally and at 4.2.3.8.7 The welds are to be of good quality and free
right angles to the sides of the link. The following from defects such as cracks, lack of fusion, gross
tolerances are acceptable provided that the stud fits porosity and undercuts exceeding 1 mm.
snugly and its ends lie flush against the inside of
the link: 4.2.3.8.8 All stud welds shall be visually examined.
Maximum off-centre distance "X" is 10 % of the At least 10 per cent of all stud welds within each
nominal diameter, Maximum deviation a" from the length of chain shall be examined by dye penetrant or
90°- position is 4°. magnetic particle after proof load testing. If cracks or
lack of fusion are found, all stud welds in that length
The tolerances are to be measured in accordance with are to be examined.
Fig. 8.3.
4.2.3.9 Connecting common links
4.2.3.7.3 The following tolerances are applicable to
accessories: 4.2.3.9.1 Single links to substitute for test links or
a) Nominal diameter : + 5,0 %, – 0 % defective links without the necessity for re-heat
b) Other diameters : ± 2,5 % treatment of the whole length are to be made in
accordance with an approved procedure. Separate
4.2.3.8 Welding of studs approvals are required for each grade of chain cables
and the tests are to be made on the maximum size of
4.2.3.8.1 A welded stud may be accepted for grade chain cables for which approval is sought.
KI-R3 and KI-R3S chains. Welding of studs in grade
KI-R4 chains is not permitted unless specially 4.2.3.9.2 Manufacture and heat treatment of connect-
approved. ing common links is not to affect the properties of the
adjoining links. The temperature reached by these
4.2.3.8.2 Where studs are welded into the links this is links is nowhere to exceed 80 % of the tempering
to be completed before the chain is heat treated. temperature.
8-14 Section 8 – Mooring Equipment C

4.2.3.9.3 Each link is to be subjected to the appropri- 4.2.4.3.2 The entire chain cable is to be checked for
ate proof load and non-destructive examination as the length, five links at a time. By the five link check
detailed in Table 8.6 and 4.2.4.5. A second link shall the first five links shall be measured. From the next set
be made identical to the connecting common link; the of five links, at least two links from the previous five
link shall be tested and inspected according to 4.2.4.4. links set shall be included. This procedure is to be
and 4.2.4.5. followed for the entire chain cable length. The
measurements are to be taken preferably while the
4.2.3.9.4 Each connecting common link is to be chain cable is loaded to 5 – 10 % of the minimum
marked on the stud in accordance with 4.2.4.7 plus an proof load. The links held in the end blocks may be
unique number for the link. The adjoining links are excluded from this measurement.
also to be marked on the studs.

Table 8.7 Frequency of breaking load and


4.2.4 Testing and inspection of finished chain
mechanical tests
cables

4.2.4.1 General Nominal chain Maximum sampling


diameter [mm] interval
[m]
All chain cables are to be subjected to proof load tests,
breaking load tests and mechanical tests after final Min – 48 91
heat treatment in the presence of the BKI Surveyor. 49 – 60 110
Where the manufacturer has a procedure to record
61 – 73 131
proof loads and the Surveyor is satisfied with the
adequacy of the recording system, he needs not 74 – 85 152
witness all proof load tests. The Surveyor is to satisfy 86 – 98 175
himself that the testing machines are calibrated and
99 – 111 198
maintained in a satisfactory condition.
112 – 124 222
Prior to test and inspection the chain cable is to be free
from scale, paint or other coating. The chain cable
shall be sand or shot blasted to meet this requirement.
4.2.4.4 Mechanical tests
4.2.4.2 Proof and breaking load tests
Links of samples detached from finished, heat treated
4.2.4.2.1 The entire length of chain cable shall with- chain shall be sectioned for determination of
stand the proof load specified in Table 8.6 without mechanical properties. A test unit shall consist of one
fracture and shall not crack in the flash weld. The load tensile and nine impact specimens. The tensile
applied shall not exceed the proof load by more than specimen shall be taken at the side opposite the flash
10 % when stretching the chain cable. Where plastic weld. Three impact specimens shall be taken across
straining is used to set studs, the applied load is not to the flash weld with the notch centred in the middle.
be greater than that qualified in approval tests. Three impact specimens shall be taken across the un-
welded side and three impact specimens shall be taken
4.2.4.2.2 A breaking load test specimen consisting of from the bend region.
at least 3 links is to be either taken from the chain or
produced at the same time and in the same manner as The test frequency is to be based on tests at sampling
the chain. The test frequency is to be based on tests at intervals according to Table 8.7 provided that every
sampling intervals according to Table 8.7 provided cast is represented. Mechanical properties shall be as
that every cast is represented. Each specimen shall be specified in Table 8.4.
capable of withstanding the break load specified with-
out fracture and shall not crack in the flash weld. It The frequency of impact testing in the bend may be
shall be considered acceptable if the specimen is reduced at the discretion of BKI provided it is verified
loaded to the specified value and maintained at that by statistical means that the required toughness is
load for 30 seconds. consistently achieved.

If the loading capacity of the testing machine is 4.2.4.5 Non-destructive examination


insufficient, another equivalent method shall be
agreed with BKI. 4.2.4.5.1 After proof load testing, all surfaces of
every link shall be visually examined. Burrs, irre-
4.2.4.3 Dimensions and dimensional tolerances gularities and rough edges shall be contour
ground. Links shall be free from mill defects, surface
4.2.4.3.1 After proof load testing measurements are to cracks, dents and cuts, especially in the vicinity where
be taken on at least 5 per cent of the links in gripped by clamping dies during flash welding. Studs
accordance with 4.2.3.7. shall be securely fastened.
Section 8 – Mooring Equipment C 8-15

4.2.4.5.2 Magnetic particle procedures shall be are to be subjected to the breaking load test. Based
employed to examine the flash welded area including upon satisfactory results of the additional tests and the
the area gripped by the clamping dies. Procedures results of the failure investigation, it will be
and equipment in accordance with those approved decided what lengths of chain cable can be accepted.
shall be used. The frequency of examination shall Failure of either or both of the additional tests will
be every link. Link surface at the flash weld shall be result in-rejection of the sampling length of chain
free from cracks, lack of fusion and gross porosity. represented, and 4.2.4.6.2 shall apply.

4.2.4.5.3 Ultrasonic procedures shall be employed to 4.2.4.6.7 If a link fails during proof load testing,
examine the flash weld fusion. Procedures and a thorough examination, with the Surveyor informed
equipment in accordance with those approved shall be in a timely manner, is to be carried out to identify the
used. On-site calibration standards for chain cable probable cause of failure of the proof load test. In the
configurations shall be approved. event that two or more links in the proof loaded length
fail, that length is to be rejected.
The frequency of examination shall be every link.
The above failure investigation is to be carried out,
The flash weld shall be free from defects causing especially with regard to the presence in other lengths,
ultrasonic back reflections equal to or greater than the of factors or conditions thought to be causal to failure.
calibration standard.
In addition to the above failure investigation,
4.2.4.6 Retest, rejection and repair criteria a breaking load test specimen is to be taken from each
side of the one failed link, and subjected to the
4.2.4.6.1 If the length over 5 links is short, the chain breaking load test. Based upon satisfactory results of
cable may be stretched by loading above the proof test both breaking load tests and the results of the failure
load specified provided that the applied load is not investigation, it will be decided what length of chain
greater than that approved and that only random can be considered for acceptance. Failure of either or
lengths of the chain cable need stretching. both of the breaking load tests will result in
If the length exceeds the specified tolerance, the over rejection of the proof loaded length.
length chain cable links shall be cut out and 4.2.4.6.2 Replacement of defective links is to be in accordance
shall apply. with 4.2.4.6.2.
4.2.4.6.2 If single links are found to be defective or 4.2.4.6.8 If the tensile test fails to meet the requi-
do not meet other applicable requirements, defective rements, a retest of two further specimens selected
links may be cut out and a connecting common link from the same sample shall be permissible. Failure to
inserted in their place. The individual heat treatment meet the specified requirements of either or both
and inspection procedure of connecting common links of the additional tests will result in rejection of the
is subjected to the BKI Surveyor’s approval. sampling length of chain cable represented, and
Other methods for repair are subject to the written 4.2.4.6.2 shall apply.
approval of BKI and the end purchaser.
4.2.4.6.9 If the impact test requirements are not
4.2.4.6.3 If a crack, cut or defect in the flash weld is achieved, a retest of three further specimens selected
found by visual or magnetic particle examination, it from the same sample shall be permissible. The results
shall be ground down no more than 5 % of the link shall be added to those previously obtained to form
diameter in depth and streamlined to provide smooth a new average. The new average shall comply with the
contours. The final dimensions shall still conform to requirements. Not more than two individual results are
the agreed standard. to be lower than the required average and not more
than one result is to be below 70 per cent of the
4.2.4.6.4 If indications of interior flash weld defects specified average value.
in reference to the accepted calibration standards are
detected during ultrasonic examination, 4.2.4.6.2 shall Failure to meet the requirements will result in
apply. rejection of the sampling length represented, and
4.2.4.6.2 shall apply.
4.2.4.6.5 If link diameter, length, width and stud
alignment do not conform to the required dimensions, 4.2.4.7 Marking
these shall be compared to the dimensions of 40 more 4.2.4.7.1 The chain cable shall be marked at the
links, 20 on each side of the affected links. If a single following places:
particular dimension fails to meet the required dimen-
sional tolerance in more than 2 of the sample links, all − at each end
links shall be examined, 4.2.4.6.2 shall apply. − at intervals not exceeding 100 m
4.2.4.6.6 If a breaking load test fails a thorough − on links next to shackles or connecting common
examination, with the Surveyor informed in a timely links
manner, is to be carried out to identify the cause of
failure. Two additional breaking test specimens All marked links shall be stated on the Certificate, and
representing the same sampling length of chain cable the marking shall make it possible to recognize lead-
8-16 Section 8 – Mooring Equipment C

ing and tail end of the chain. In addition to the above 4.2.5 Testing and Inspection of Accessories
required marking, the first and last common link of
each individual charge used in the continuous length 4.2.5.1 General
shall be adequately and traceably marked.
All accessories are to be subjected to proof load tests,
The marking shall be permanent and legible through- breaking load tests and mechanical tests after final
out the expected lifetime of the chain. heat treatment in the presence of a Surveyor. Where
the manufacturer has a procedure to record proof loads
The chain cable shall be marked on the link as and the Surveyor is satisfied with the adequacy of the
follows, compare Fig. 8.4: recording system, he need not witness all proof load
tests. The Surveyor is to satisfy himself that the testing
− chain cable grade machines are calibrated and maintained in a satis-
factory condition.
− Test Certificate No.
Prior to test and inspection the chain cable accessories
− KI Hard Stamp are to be free from scale, paint or other coating.
− month and year of test
4.2.5.2 Proof and breaking load tests
The Certificate number may be exchanged against an
4.2.5.2.1 All accessories are to be subjected to the
abbreviation or equivalent. If so, this shall be stated in
proof load specified for the corresponding chain.
the Certificate.

The chain cable Certificate shall contain information 4.2.5.2.2 Chain cable accessories are to be tested to
the breaking test loads prescribed for the grade and
on number and location of connecting common links.
The Certificate number and replacement link number size of chain cable for which they are intended. At
may be exchanged against an abbreviation or least one accessory out of every batch or every
equivalent. If so, this shall be stated in the Certificate. 25 accessories, whichever is less, is to be tested.
For individually produced accessories or accessories
produced in small batches, alternative testing will be
subject to special consideration. Accessories which
have been subjected to a breaking load test are to be
scrapped.

4.2.5.3 Dimensions and dimensional tolerances


At least one accessory (of the same type, size and
nominal strength) out of 25 is to be checked for
KI Hard Stamp
dimensions after proof load testing. The manufacturer
is to provide a statement indicating compliance with
the purchaser’s requirements.

Fig. 8.4 Stamping of chain cables


4.2.5.4 Mechanical tests
4.2.4.8 Documentation Accessories are to be subjected to mechanical testing
as described in 4.2.2.3 and 4.2.2.4. For individually
A complete Chain Cable Inspection and Testing produced accessories or accessories produced in small
Report in booklet form shall be provided by the chain batches, alternative testing will be subjected to special
cable manufacturer for each continuous chain cable consideration.
length. This booklet shall include all dimensional
checks, test and inspection reports, NDT reports, 4.2.5.5 Non-destructive examination
process records, photographs as well as details of any
non-conformity, corrective action and repair work. After proof load testing all chain cable accessories are
to be subjected to a close visual examination. Special
Individual Certificates are to be issued for each attention is to be paid to machined surfaces and high
continuous single length of chain cable. stress regions. All non-machined surfaces are to be
sand or shot blasted to permit a thorough examination.
All accompanying documents, appendices and reports All accessories are to be checked by magnetic particle
shall carry reference to the original Certificate or dye penetration methods.
number.
The manufacturer is to provide a statement that non-
The manufacturer will be responsible for storing, in destructive examination has been carried out with
a safe and retrievable manner, all documentation satisfactory results. This statement should include a
established for a period of at least 10 years. brief reference to the techniques and to the operator’s
qualification.
Section 8 – Mooring Equipment C 8-17

4.2.5.6 Test failures 5. Winch system


In the event of a failure of any test the entire batch
5.1 Winches
represented is to be rejected unless the cause of failure
has been determined and it can be demonstrated to the The requirements for mooring winches including their
Surveyor’s satisfaction that the condition causing the controls are defined in Volume 4 – Rules for Machi-
failure is not present in any of the remaining nery Installations, Section 8, C.
accessories.
5.2 Fairleads and sheaves
4.2.5.7 Marking
Fairleads and sheaves shall be designed to prevent
Each accessory is to be marked as follows: excessive bending and wear of the anchor lines. The
− chain cable grade attachments to the hull or structure are to be such as to
comply with the requirements of B.1.5.
− Test Certificate No.
− KI Hard Stamp 6. Quality control
− month and year of test Details of the quality control of the manufacturing
process of individual anchoring system components
All detachable component parts shall be stamped with are to be submitted. Components shall be designed,
a serial number to avoid mixing of components. The manufactured, and tested in accordance with
Certificate number may be exchanged against an recognized standards and, if included in the Classifi-
abbreviation or equivalent. If so, this shall be stated cation procedure according to 1.2, also in accor-
in the Certificate. dance with Rules. Equipment so tested shall, insofar
as practical, be legibly and permanently marked with
4.2.5.8 Documentation KI Hard Stamp and delivered with documentation
which records the results of the tests. Concerning
A complete Inspection and Testing Report in booklet details on chain cables see 4.2.
form shall be provided by the manufacturer for each
order. This booklet shall include all dimensional
7. Dynamic positioning systems
checks, test and inspection reports, NDT reports,
process records as well as any non-conformity, Thrusters used as a sole means of position keeping
corrective action and repair work. shall provide a level of safety equivalent to that
provided for anchoring arrangements, to the satis-
Each type of accessory shall be covered by separate faction of BKI, see also Volume 4, Section 6, E. and
Certificates. Volume 5 – Rules for Electrical Instalations, Sec-
All accompanying documents, appendices and reports tion 12, E.
shall carry reference to the original Certificate The Class Notations DP1 to DP3 will be assigned if
number. the offshore unit is equipped with such a system,
The manufacturer will be responsible for storing, in compare Volume 1 – Rules for Classification and
a safe and retrievable manner, all documentation Surveys, Section 2.
established for a period of at least 10 years. Further details are defined in the Rules for Dynamic
Positioning Systems.
Section 9 – Life-Saving Appliances A, B 9-1

Section 9
Life-Saving Appliances

A. General − IMO: 1974 SOLAS Convention, Resolution 6(48),


Chapter III
1. Scope

1.1 Life-saving appliances shall comply with the 2.2 BKI additional Rules
relevant applicable International Regulations accor-
ding to 2.1 and/or National Regulations and shall be − Regulations for Lifeboats and Rescue Boats
suitable for the type and use of the mobile offshore
unit. − Regulations for Live-Saving Launching Appli-
ances
1.2 The design and testing of lifeboats,
life-rafts and rescue boats with their launching
appliances is in general not within the scope of
Classification of mobile offshore units by BKI.
However, their arrangement in the overall design of 3. Emergency warnings and instructions
the unit and the structure in way of launching
appliances taking into account the forces from above 3.1 Alarm signals
appliances are always part of Classification.
For alarm and pubic address system see Volume 5 –
Rules for Electrical Installations, Section 9.
1.3 On special request lifeboats and rescue boats
and their launching appliances may be approved by
BKI on the basis of the BKI Rules defined in 2.2. 3.2 Operating instructions
Illustrations and instructions shall be provided on or in
1.4 For the requirements for life-jackets, the vicinity of lifeboats and liferafts and their
immersion suits, lifebuoys, radio life-saving appli- launching controls and shall:
ances, distress flares and line-throwing appliances, etc.
see B.1.5. These requirements have to follow the − illustrate the purpose of controls and the
regulations defined in 2.1. procedures for operating the appliance and give
relevant instructions or warnings
2. Rules and regulations − be easily readable under emergency lighting
conditions
2.1 International Regulations
− use symbols in accordance with the recommen-
− International Maritime Organisation (IMO): dations of SOLAS, MODU Code, National
International Convention for the Safety of Regulations, etc.
Life at Sea (SOLAS), Chapter III - Life-Saving
Appliances and Arrangements

− IMO : International Life-Saving Appliance B. Life-Saving Appliances


Code (LSA Code), Resolution MSC.48(66)

− IMO : Testing and Evaluation of Life-Saving 1. Type and equipment


Appliances, Resolution MSC.81(70), as amended
by MSC.200(80) 1.1 Life-saving appliances shall be suitable for
the type and use of the mobile offshore unit.
− IMO : Code for the Construction and Equip-
ment of Mobile Offshore Drilling Units (MODU 1.2 The lifeboats shall meet the requirements of
Code), Chapter 10 the LSA Code, Chapter IV and the Testing
Regulations defined in A.2.1 and shall be of the
− IMO : Code of Safety for Special Purpose Ships, following type:
Resolution A.534(13), Chapter 8
9-2 Section 9 – Life-Saving Appliances C

− totally enclosed lifeboats launched by falls with 2.2 Self-elevating and column-stabilized units
fire protection and self-contained air support sys-
tem considering LSA Code § 4.6, 4.8 and 4.9, or 2.2.1 Each unit shall carry lifeboats, installed in at
least two widely separated locations on different sides
− free-fall lifeboats with fire protection and self- or ends of the unit. The arrangement of lifeboats
contained air support system considering LSA should provide sufficient capacity to accommodate the
Code § 4.7 to 4.9 total number of persons on board if:

− if the unit is considered as “special purpose ship”, − all the lifeboats in any one location are lost or
the reduced requirements according to IMO rendered unusable, or
Resolution A.534 (13), Chapter 8 may be applied,
compare A.2.1. − all the lifeboats on any one side, any end or any
one corner of the unit are lost or rendered unusable
1.3 The liferafts shall meet the requirements for 2.2.2 In addition liferafts shall be carried of such
davit-launched liferafts of the LSA Code, Chapter IV aggregate capacity as will accommodate the total
and the Testing Regulations defined in A.2.1. number of persons on board.

1.4 Lifeboats and liferafts shall be fully equipped 2.2.3 In the case of a self-elevating unit where, due
as required by the LSA Code, Chapter IV defined in to its size or configuration, lifeboats cannot be located
A.2.1. However, for operation in restricted areas items in widely separated locations to satisfy 2.2.1 the
may be dispensed by the Administration of the state of Administration of the state of location or flag may
flag or location. permit the aggregate capacity of the lifeboats to
accommodate only the total number of persons on
1.5 Personal life-saving appliances shall meet the board. However, the liferafts should be served by
requirements of the LSA Code, Chapter II, of the launching appliances.
relevant Administration and of BKI considering
climatic conditions.

C. Arrangement of Lifeboats and Liferafts


2. Number and size
The number and size of life- saving appliances has to 1. Muster and embarkation arrangements
be defined according to the regulations mentioned in
A.2.1. 1.1 If separate, muster stations shall be provided
If not stated otherwise by the responsible Administra- close to the embarkation stations. Each muster station
tion, each manned unit should be provided with at shall have sufficient space to accommodate all persons
least the lifeboats and liferafts listed in the following: assigned to muster at that station.

1.2 Muster and embarkation stations shall be


2.1 Mobile surface units readily accessible from accommodation and work
areas.
2.1.1 Each unit shall carry on each side, one or
more lifeboats of such aggregate capacity as will
1.3 Muster and embarkation stations shall be
accommodate the total number of persons on board.
adequately illuminated by emergency lighting.
2.1.2 In addition, a liferaft or liferafts shall be
1.4 Alleyways, stairways and exits giving access
carried, capable of being launched on either side of
to the muster and embarkation stations shall be
a unit and of such aggregate capacity as will
adequately illuminated by emergency lighting.
accommodate the total number of persons on board. If
the liferaft or liferafts cannot be readily transferred for
launching on either side of a unit, the total capacity 1.5 Davit-launched survival craft muster and
available on each side should be sufficient to embarkation stations shall be so arranged as to enable
accommodate the total number of persons on board. stretcher cases to be placed in survival craft.

2.1.3 If lifeboats and liferafts are stowed in a 1.6 Survival craft embarkation arrangements
position which is more than 100 m from the stem or shall be so designed that:
stern, in addition to the liferafts as provided in 2.1.2, a − lifeboats can be boarded by their full complement
liferaft shall be stowed as far forward or aft, or one as
of persons within 3 minutes from the time the
far forward and another as far as aft, as is reasonable
instruction to board is given
and practicable. Notwithstanding C.3.3 such liferaft or
liferafts may be securely fastened so as to permit − lifeboats can be boarded and launched directly
manual release. from the stowed position
Section 9 – Life-Saving Appliances C 9-3

− davit-launched liferafts can be boarded and 3.2 Launching stations shall be in such positions
launched from a position immediately adjacent to as to ensure safe launching having particular regard to
the stowed position or from a position to which the clearance from any exposed propeller, if applicable.
liferaft is transferred prior to launching in Launching stations shall not be located near or even
compliance with 3.3 above working stations which would hinder the
launching at certain working conditions. The exact
− where necessary, means shall be provided for position shall be agreed with the Administration and
bringing the davit-launched liferaft to BKI.
structure/hull side and holding it alongside so that
persons can be safely embarked
3.3 Preparation and handling of survival craft at
2. Stowage any one launching station shall not interfere with the
prompt preparation and handling of any other survival
2.1 Each lifeboat and liferaft shall be stowed: craft or rescue boat at any other station.

− so that neither they nor their stowage arrange-


ments will interfere with the operation of any other 3.4 As far as possible, launching stations shall be
lifeboat or liferaft or rescue boat at any other located so that lifeboats and liferafts can be launched
launching station down a straight side of the structure/shell, except for:

− as near the water surface as is safe and practicable


− lifeboats and liferafts specially designed for free-
− in a state of continuous readiness so that two crew fall launching
members can carry out preparations for embarka-
tion and launching in less than 5 minutes
− lifeboats and liferafts mounted on structures
− as far as practicable, in a secure and sheltered intended to provide clearance from lower structures
position and protected from damage by fire and
explosion
3.5 Means shall be available to prevent any
discharge of fluids on to lifeboats or liferafts during
2.2 Lifeboats shall be stowed
abandonment.
− that they are protected from damage by heavy seas
− attached to launching appliances 3.6 During preparation and launching, lifeboats
and liferafts, its launching appliance and the area in
the water into which they are to be launched shall be
2.3 Liferafts shall be stowed:
adequately illuminated by emergency lighting.
− as to permit manual release from their securing
arrangements
3.7 Launching and recovery arrangements shall
− within reach of the lifting hooks, if liferafts are be such that the appliance operator on the unit is able
davit-launched; unless some means of transfer is to observe the survival craft at all times during
provided which is not rendered inoperable within launching and lifeboats during recovery.
the limits of trim and list prescribed in Section 7
for any damaged condition or by motion or power
failure 3.8 Falls, where used, shall be long enough for
the survival craft to reach the water with the unit
− every liferaft, other than those in B.2.1.3, shall be under un-favourable conditions, such as maximum
stowed with the weak link of its painter air gap, lightest transit or operational condition or any
permanently attached and with a float free damaged condition as described in Section 7. Only
arrangement complying with the requirements of one type of release mechanism shall be used for
the regulations defined in A.2. so that the liferaft similar survival craft on board and the opening of
floats free and, if inflatable, inflates automatically the mechanism shall be possible under load from
when the unit sinks. inside the boat.

3. Launching and recovery arrangements


3.9 In any case of damage defined in the previous
Sections, lifeboats with an aggregate capacity of not
3.1 Launching appliances shall be provided for less than 100 % of persons on board shall, in addition
all lifeboats and davit-launched liferafts. They shall to meeting all other requirements of launching and
meet the requirements defined in Rules and Regu- stowage defined in this Section, be capable of being
lation defined in A.2. launched clear of any obstruction.
9-4 Section 9 – Life-Saving Appliances D

D. Rescue Boats − in compliance with C.3, if they are lifeboats

1. Number and requirements


3. Embarkation and launching
Each unit shall carry at least one fast rescue boat
complying to the requirements of rules and regula- The rescue boat embarkation and launching arra-
tions defined in A.2. ngements shall be such that the rescue boat can
be boarded and launched in the shortest possible time.
2. Stowage
Launching arrangements shall include a single point
Rescue boats shall be stowed: hoist and release mechanism and in other aspects
comply with C.3.
− in a state of continuous readiness for launching in
not more than 5 minutes
4. Recovery
− in a position suitable for launching and recovery
− so that neither the rescue boats nor their stowage Rapid recovery of rescue boats shall be possible when
arrangements will interfere with the operation of loaded with its full complement of at least six persons
any lifeboat or raft of another launching station and the relevant equipment.
Annex A – List of Standards, Code, etc. Quoted A 2-1

Annex A

List of Standards, Codes, etc. Quoted

Table A.1 List of Standards, Codes, etc. Quoted

IACS
Volume / Section IMO ISO Others
UR
(D2.2)
2/1 (D2.1) ISM – 1 July 2002
(D1.6)
2/2 (D.4) (MODU)
2/3 (D.5) (MODU)
(D.3)
2/4 (D.6) (MODU)
(D.9)
A.749(18),
MSC.75(69),
2/5
A.543(13),
MODU
2/6
(D.3)
2/7 (D.4) MODU
(D.5) Load Line 66

1704
2/8 (D.3) MODU
9001
SOLAS Res 6(48)
LSA MSC.48(66)
MSC.81(70)
2/9
MSC.200(80)
A.534(13)

Explanation of abbreviations:
D1 – D12 Requirements concerning Mobile Offshore Drilling Units, Unified Requirements of IACS, 1996
IACS International Association of Classification Societies
IMO International Maritime Organization
ISM IMO International Safety Management Procedures, 1 July 2002
ISO International Standardization Organization
Load Line International Convention on Load Lines 1966
MODU Code for the Construction and Equipment of Mobile Offshore Drilling Units, issued by IMO
SOLAS Safety of Life at Sea, issued by IMO
(……) reference not explicitly declared in the text
 

You might also like