PROJECT : REFURBISHMENT OF SERVICE COOLING WATER PUMP, JOB CARD NO: -10014653
CLIENT: SOHAR ALUMINIUM POWER PLANT, CONTRACTOR: GE MIDDLE EAST FZE
WORK DONE REPORT / ACTIVITY RECORD
5 Dismantled both shafts and carried out dismantling of all line bearings from housings.
Performed dimensional inspection and Runout check on both shafts and inspected impeller to casing wear ring
6
clearance.
7 Carried out sweep blasting on scution bell mouth and pickling on suction cone & top coloum.
8 Applied belzona on wear ring seat of suction bell mouth and machined to required dimension.
Carried out repair welding on suction bell mouth, impeller, suction cone and coloum with approved welding
9
procedure.
Removed old wear ring from suction bell mouth and installed new wear ring. After installation carried out
10
machining on wear ring to achieve required clearance.
Carried out Die Penetrant testing on all weld areas of impeller, suction bell mouth, suction cone & top coloum
11
to ensure the weld areas are free form defects.
12 Carried out Hydrotest of bearing housing cooling jacket and float valve.
13 Carried out machining of suction cone, suction bell mouth and top coloum spigot areas.
18 Replaced all line bearings, fasteners, gland packing, keys, coupling as per GE recommendations