Professional Documents
Culture Documents
By
IAN McRAEl
~ CLOSED MINES
The AuslMM Sydney Branch, Second Project Development Symposium, October 1986
241
242 I MCRAE
Mines in the Tennant Creek area have no exception. For example, in two holes 8m
generally been very small and only six mines apart, one hole recorded three intersections,
have each produced over 200 000 tonnes of the longest being 3.6m and the highest grade
ore. Before 1940, 113 mines were in being 10 g/tonne Au, while the other hole had
production, in 1950 25 mines operated and a 17m intersection grading 36 g/tonne Au.
today there are three major operations, Similarly, two consecutive one metre
namely PWOL, Australian Development Limited analytical results returned 3 g/tonne Au and
(ADL) and Cuprex Limited. 130 g/tonne Au.
TENURE It was not possible to guarantee
continuity of gold grades over several
A magnetic anomaly 4 km SE of Tennant metres, and as such any attempt at an ore
Creek first identified in June 1980 was resource calculation was at best an estimate
pegged as Mineral Lease 388E in August 1967 based on a number of assumptions.
and named Explorer 46. Subsequently eight
mineral leases completely surrounding ML 388E GEOTECHNICAL
were granted to ADL.
A geotechnical investigation was under-
In November 1978 the Warumungu Land taken by Barrett, Fuller and Partners to
Claim was lodged. However the hearings on assess design parameters for roads and
this claim have yet to be completed. buildings through a programme of shallow pits
Subsequently the Tennant Creek Town Planning and laboratory testing.
Boundary was altered placing the Explorer 46
lease which is 2 km outside the town boundary Conditions for shaft sinking were
well within the new Planning Boundary. There assessed through test pits at the surface
is still uncertainty whether the Aboriginal plus an examination of relevant diamond drill
Land Claim will take precedence over the core.
revised boundary.
The investigation recommended that major
Exploration Licence 2535 which covered foundations be founded on the strata 2m below
the Explorer 46 prospect and probable road, the surface and that the shaft be concrete
power and water accesses was applied for in lined to 45m. It further recommended that
March 1980. Although it would be necessary dry excavation techniques be used with a
to cross over leases held by ADL they maximum wall exposure of 2m. From 45m to
indicated their willingness to assist 140m the weathered rock would be highly
wherever possible. fractured and immediate bolting and meshing
with shotcrete or early placement of the
EXPLORATION final lining would be required. Below 140m,
bolting and meshing would be required with
Drilling commenced in July 1969 and 2.4m full lining in the vicinity of shear zones.
of 7 g/tonne Au was intersected in the first Shotcreting over large areas could be
hole and 4.8m of 5 g/tonne Au in a wedge run required depending on the tightness of the
off. Better values were intersected in the joints in situ.
second hole, drilled in 1970 and the
programme was suspended in 1972 after four MINE PLANNING
holes and nine wedge run offs were completed.
A resource of 61 000 tonnes of ore at 11 PWOL proposed a mining plan using only a
g/tonne was computed but that resource could single entry and initiated discussions with
not justify the development required to the Chief Government Mining Engineer of the
extract it. N.T. Department of Mines and Energy (DME) in
1980.
The significant rise in the gold price
in early 1980 revived interest in Explorer 46 The idea of a single entry is not new
and by the end of that year a resource and many mines have bratticed shafts to
approaching 200 000 tonnes was outlined. The separate intake and fresh air, particularly
Peko Walls end Limited Annual Report for 1982 in South Africa. The following points
stated "further drilling of the Explorer 46 summarise the arguments supporting the case.
anomaly did not add to the existing resource
of 200 000 tonnes of lode at a gold grade of 1. Many orebodies in the Tennant Creek
18 grams per tonne". field are relatively small.
Development of these bodies might
The distribution of gold both spatially not be possible if they had to bear
and in abundance in Tennant Creek orebodies the full capital cost of two shafts.
is often very erratic. Distribution of
economic gold grades in the Argo orebody is 2. With very small tonnages, the amount
The AuslMM Sydney Branch, Second Project Development Symposium, October 1986
I MCRAE 243
Initial requirements of the DME included The preferred option was therefore to
the following. supply power from diesel generators on site,
either three 600 kW sets, two running and one
1. A brattice in the shaft to separate on standby or four 400 kW sets, three running
the intake and upcast air streams. and one on standby.
2. An enclosed ladderway the full
length of the shaft. However a decision was taken to cease
3. Electric power to the winder to be operations at Gecko Mine at the end of 1983
supplied from two separate sources and surplus power became available from the
and by two separate cables. 20 MW Warrego Station, 60 km to the north-
4. An independently powered auxiliary west.
emergency cage.
5. Diesel powered equipment and an The line, which had not been in use for
explosives magazine would not be six years, had to be re-routed 2 km around
permitted underground. the Mary Ann Dam Recreation Reserve and a 6
6. Minimum use of flammable materials. km line established from Peko Mine, using
salvaged power poles and aerials from the
Consulting Engineers (H&R) were engaged line to Juno Mine.
by PWOL to assist with mine planning and
shaft design to meet the requirements of the A 600 kW skid mounted generator was
DME. installed adjacent to the winderhouse as an
independent and emergency power supply.
A submission by the PWOL and H&R design
team to the DME resulted in Departmental COMPRESSED AIR
approval in principle for the project.
Air consumption was estimated to peak
A full feasibility study was prepared about 1 100 litre/s but to have a wide
and three further drill holes were completed fluctuation in demand. Two Atlas Copco ER6
in 1983 and a revised resource of 224 700 compressors, each with a capacity of 510
tonnes at 13.5 g/tonne Au was calculated. litre/s, and two Atlas Copco ZR3 compressors,
each with a capacity of 300 litre/s, were
The proposal to develop the orebody was installed. This would enable demand to be
approved by the Board of Peko Walls end met with one compressor off line. Total load
Limited in September 1983 and the project could be varied between 300 litre/s and 1 620
named Argo Mine. litre/s and so air power requirements could
be minimised at weekends. An air receiver of
SERVICES 8 000 litre capacity was installed at the
surface. All the compressors and the air
POWER receiver were surplus from operations within
the Peko Wallsend group.
The peak power load was estimated for
each major component of electrical plant WATER
without any diversity factor as it was
thought probable that in a small mine all Water was available from either of two
machines would be on load simultaneously for sources,
significant periods of time.
1. the Waggaridge Dams 5 km NE of Argo
Three sources of power were considered, Mine, or
from the Warrego Power Station, from the 2. the Tennant Creek Town supply.
The AuslMM Sydney Branch, Second Project Development Symposium, October 1986
244 I MCRAE
Both sources were considered as earlier H&R prepared tender documents for the
discussions with the Area Manager for the shaft in four phases.
Department of Transport and Works (T&W)
estimated that only 50 kilolitres per week 1. Sink a 4.5m diameter shaft to a
would be available from the Tennant Creek depth of 400m and develop four
Town supply with the balance therefore to be plats.
provided through a pipeline from the 2. Install all shaft equipment and
Waggaridge Dams. convert the winder and headframe
from a sinking to a production
In 1983 an agreement was reached with mode.
T&W to supply all the mine water requirements 3. Lease the winder and head frame to
at commercial rates fom the Tennant Creek PWOL.
Town supply. 4. Demobilise and remove all equipment.
to meet
conform
the
with
proposed duty and
new regulations
...J0 - - - - -1-- . -
-
The AuslMM Sydney Branch, Second Project Development Symposium, October 1986
I MCRAE 245
The AuslMM Sydney Branch, Second Project Development Symposium, October 1986
246 I MCRAE
The AuslMM Sydney Branch, Second Project Development Symposium, October 1986
I MCRAE 247
The AuslMM Sydney Branch, Second Project Development Symposium, October 1986