Sr No Claim Description
Rupees
55,501,420
Clarification
4.0 EXCAVATION
Contractor shall maintain adequate drainage facilities at site
at all times during the execution of work. Additional ditches,
drains & such other temporary means to achieve this, over
and above what is shown in drawings, will be provided and
maintained by Contractor at his own cost. Adequate
dewatering facilities like dewatering pumps, piping etc will
also be provided by the Contractor for this work and also for
dewatering during excavation etc. at his own cost.