PO Number#

Receipt Date Range

PO Line# Item Item Desc PO Creation Date


5-May-22

LOGIC
Non penalty delivery date =Receipt dat
APPROVED_DATE
Open Date Requested Delivery Date promised Delivery Date
7-May-22 25-May-22 25-May-22

if Open Date > PO Creation Date


alty delivery date =Receipt date- (promised date + (po Line approved date - PO Creation date)

Case 1 Case 2
PO Creation Date 5-May-22 5-May-22
Open Date 7-May-22 7-May-22
Requested Delivery Date 25-May-22 25-May-22
promised Delivery Date 27-May-22 27-May-22
PO Line Approved Date 7-May-22 7-May-22
Receipt Date 27-May-22 29-May-22

-2 0
APPROVED_DATE
PO Line Approved Date Receipt Date Delayed ?
7-May-22

Non penalty delivery date =Receipt date- (promised date + (po Line approved date - PO Creation date)
Case 3
5-May-22
7-May-22
25-May-22
27-May-22
7-May-22
31-May-22