Professional Documents
Culture Documents
REPORT
on
Submitted By:
Table of Content
Annexes:
Bore Hole Logs
Laboratory Test Result
Figures and photographs
Soil Report: Landfill Site
Siraha
1. GENERAL INTRODUCTION
This report is prepared in accordance with the agreement between Siraha Municipality, Office of the Municipal
Executive, Siraha and Everest Engineering Consultant Pvt. Ltd., Baneshwor to determine the bearing capacity
and subsurface exploration of Landfill Site at Siraha Municipality, Siraha.
2. SCOPE OF INVESTIGATION
The scope of work includes the following:
Mobilizing necessary plant, equipments and personnel to the project site, setting up the equipment,
shifting of the equipment from one test location to another location.
Making 100 mm nominal diameter bore holes each of 12.0 m depth at two specified locations using
suitable approved method of boring.
Conducting standard penetration tests in the bore holes at 1.50 m interval in depth & at every change of
strata, whichever is earlier.
Collecting undisturbed soil samples from bore holes at 3.00 m interval in depth (if possible for
Undisturbed sampling) or at every change of strata, whichever is earlier.
Collecting disturbed soil samples from bore holes at regular interval and at every identifiable change of
strata to supplement the boring records.
Recording the depth of ground water table in all the bore holes if observed up to the depth of
exploration during boring work as per specifications.
Conducting the laboratory tests on selected disturbed / undisturbed soil samples collected from various
bore holes.
Preparation and submission of reports.
3. FIELD INVESTIGATIONS
Cone Penetration test are performed by a 50 mm cone. The method for DCPT is similar to that of SPT. First of
all the cone is driven 100 mm into the soil at the bottom of the bore hole. It is then driven further 200 mm and
the number of blows (Ncbr values) required to drive this distance is recorded.
The result i.e., Nc values first corrected to the Standard Penetration Test (SPT) value (N) and that provides and
estimation of degree of compaction of soil strata, values of angles of internal friction () and allowable bearing
capacity. The dynamic cone resistance is correlated with the SPT (N) as given below.
Nc = 1.5 N for depth up to 3 m
= 1.75 N for depth 3 to 6 m
= 2 N for depth greater than 6 m
3.2 Sampling
(i) Disturbed Sample:
Disturbed samples were collected from the split spoon after conducting SPT. Before any sample was taken, the
borehole was cleaned up of loose disturbed soil deposited during boring operation. The samples which were
obtained from bailer and in the SPT tube were preserved as representative disturbed samples for finding out
index properties. The samples thus obtained were placed in airtight double plastic bags, labeled properly for
identification and later transported to the lab for analysis.
4. LABORATORY TESTS
The laboratory tests were conducted on selected representative disturbed and undisturbed samples collected in
core boxes, were transported to lab in Mid Baneshwor, Kathmandu. All of the tests were conducted confirming
to the specifications as per IS codes. The following tests were conducted:
SN Type of Test IS Code Referred Remarks
1 Bulk and dry density By Calculations
2 Moisture content IS:2720 (Part-2)-1992
3 Grain size/ Hydrometer analysis IS:2720 (Part-4)-1992
4 Atterberg Limits IS:2720 (Part-5)-1992
5 Specific Gravity IS:2720 (Part-3)-1992
6 Unconfined compression test of soil IS:2720 (Part-10)-1991
7 Consolidation test IS:2720 (Part-15)-1986
8 Drained Direct shear test IS:2720 (Part-13)-1986
9 Unconfined Compressive strength of rock core IS:9143-1979
The results of laboratory tests have been presented in the annex section of this report.
100
where, C N = as per Liao and Whitman 1987
σz '
Dilatancy Correction (for fine sand and silts below water table)
Terzaghi and Peck (1976) gave correction for water pressure as,
If Nrec≤ 15, then Ncorr =Nrec
Nrec ≥ Ncorr = ½(Nrec-15)
Measured SPT Correction for
(N1)60
Depth (m) Hammer Rod
Overburden
BH1 BH2 efficiency length BH1 BH2
1.5 m 14 24 1.70 0.92 0.75 16.42 28.15
3.0 m 19 23 1.70 0.92 0.75 23.77 28.78
4.5 m 22 27 1.70 0.92 0.8 29.25 35.89
6.0 m 30 33 1.57 0.92 0.8 36.20 39.82
7.5 m 42 50 1.40 0.92 0.85 50.66 60.31
9.0 m 45 50 1.28 0.92 0.85 49.55 55.06
10.5 m 43 50 1.18 0.92 0.9 46.14 53.66
12.0 m 50 50 1.11 0.92 0.9 50.19 50.19
The site is located at Siraha district in the Terai region of Nepal. The Gangetic Plain is also called as Terai Zone
and it is the Nepalese portion of the Gangetic Plain that extends from the Indian Shield in the South to the Sub-
Himalayan (Siwalik) Zone to the North. The plain is in less than 200 meters above sea level and usually has
thick (nearly 1500 m) alluvial sediments. Mainly five different types of soil are found: loamy sand, sandy loam,
loam, silty loam and clay loam, boulders and gravels. The width of Terai Zone varies from 10 to 50 km and
forms a nearly continuous belt from east to west. Terai Zone is a foreland basin and has sediment originated
from peaks of Northern part. To the north, this zone is separated by an active thrust system called as the Main
Frontal Thrust (MFT) with Siwalik. At some places along MFT, the Siwalik rocks are observed to rest over the
recent sediments of the Terai.
decrease in vertical effective stress and shear strength. If the shear strength drops below the applied cyclic
shear loadings, the layer is expected to transition to a semi fluid state until the excess pore-water pressure
dissipates. When liquefaction takes place in a particular soil then the bearing capacity of the soil disappears and
the structure built on it gets tilts or even sinks..The past big earthquakes, have shown that saturated sandy soils
in a loose to medium dense condition were liquefied during earthquakes varying in magnitude from 5.5 to 8.5
(Richter scale) and epicenter distance from several miles to hundreds of miles.
Analysis of Liquefaction
The stress-based approach for evaluating the potential for liquefaction triggering, initiated by Seed and Idriss
(1967), compares the earthquake-induced cyclic stress ratios (CSR) with the cyclic resistance ratios (CRR) of
the soil. The soil's CRR is usually correlated to an in-situ parameter SPT blow count.
Factor of safety is evaluated as,
𝐶𝑅𝑅7.5
𝐹𝑂𝑆 =
𝐶𝑆𝑅7.5,𝜎
where, CRR7.5 = Cyclic Resistance Ratio for earthquake of magnitude 7.5
CSR7.5,σ = normalized cyclic stress ratio for earthquakes of magnitude 7.5 and effective
overburden pressure of 100kPa.
𝜎𝑣 𝑎𝑚𝑎𝑥 𝑟𝑑 1
𝐶𝑆𝑅7.5,𝜎 = 0.65
𝜎′𝑣 𝑔 𝑀𝑆𝐹 𝐾𝜎
where, σv = the total vertical sress at depth z
σ’v= the effective vertical sress at depth z
amax/g = maximum horizontal acceleration (as fraction of gravity) at ground surface,
rd = shear stress reduction factor that accounts for the dynamic response of the soil.
𝑟𝑑 = 𝑒𝑥𝑝[𝛼(𝑧) + 𝛽 (𝑧). 𝑀]
𝑧
𝛼(𝑧) = −1.012 − 1.126𝑠𝑖𝑛 ( + 5.133)
11.73
𝑧
𝛽 (𝑧) = 0.106 + 0.118𝑠𝑖𝑛 ( + 5.142)
11.28
−𝑀
MSF= magnitude scaling factor= 6.9𝑒𝑥𝑝 ( ) − 0.058 ≤ 1.8 for sands
4
−𝑀
= 1.12𝑒𝑥𝑝 ( ) + .828 ≤ 1.13for clays
4
𝜎′
Kσ = overburden correction factor = 1 − 𝐶𝜎 𝑙𝑛 ( 𝑃 𝑣) ≤ 1.1
𝑎
1
𝐶𝜎 = ≤ 0.3
18.9 − 2.55√(𝑁1)60𝑐𝑠 )
(𝑁1)60𝑐𝑠 = (𝑁1)60 + ∆(𝑁1)60
2
9.7 15.7
∆(𝑁1)60 = 𝑒𝑥𝑝 (1.63 + −( ) )
𝐹𝐶 + 0.01 𝐹𝐶 + 0.01
Cyclic resistance ratio (CRR), the capacity of soil to resist liquefaction, can be obtained from
the corrected blow count and soil’s fine content.
𝐶𝑅𝑅7.5,1𝑎𝑡𝑚 = 𝑓 [(𝑁1)60 ), 𝐹𝐶 ]
2 3 4
(𝑁1)60𝑐𝑠 (𝑁1)60𝑐𝑠 (𝑁1)60𝑐𝑠 (𝑁1)60𝑐𝑠
𝐶𝑅𝑅7.5,1𝑎𝑡𝑚 = exp ( +( ) −( ) +( ) − 2.8)
14.1 126 23.6 25.4
Liquefaction Analysis for BH1 for PGA =0.25g, M=7.5, GWT at 3.0 m from surface
Liquefaction Analysis for BH2 for PGA =0.25g, M=7.5, GWT at 3.0 m from surface
For cohesion less soil with eshear failure, for eovalue less than 0.55, values are computed for General
values between 0. 55 to 0.75 the values are computed by linear interpolation between local and general shear
failure, and for eo value greater than 0.75 the values are computed for local shear failure.
where,
Se = net allowable settlement
𝑞
C1 = correction factor for the depth of foundation = 1 − 0.5 ∆𝑞
𝑡𝑖𝑚𝑒 𝑖𝑛 𝑦𝑒𝑎𝑟
C2= correction factor to account into creep in soil = 1 + 0.2𝑙𝑜𝑔 ( )
0.1
11.98N60 3.28B 1
2
qsafe = S
f d x R w1
3.28 B 25
Where,
N60 = Standard Penetration Value for Average energy ratio of 60%
B = width (m)
S = Settlement (mm)
fd = 1+0.33 (D/B) ≤ 1.33
Rw1 = water correction factor = 0.5
For cohesive soil,
If the clay layer is encountered, the settlement is calculated as:
𝐻 (𝑃𝑜 + ∆𝑃
𝑠𝑒 = 𝐶𝑐 log10 ( )
1 + 𝑒0 𝑃𝑜
where, se = consolidation settlement (m)
As per IS: 8009 clause 9.5, correction factors for rigidity and depth are applied
Notes:
1) Nγ factor is taken for general shear failure as per IS: 6403
2) Nq factor is obtained from Fig. 1. Annex B, of IS 2911 (Part 1/sec2): 2010
3) Ki, the earth pressure coefficient depending on the nature of soil strata, type of pile, spacing of pile
and its method of construction.
4) δ, angle of wall friction may be taken equal to friction angle of soil around pile stem
5) The maximum effective overburden at the pile tip should correspond to the critical depth, which
may be taken as 15 times the diameter of the pile shaft for Ф≤ 30˚ and increasing to 20 times for Ф
≥ 40˚
𝑄𝑢 = 𝐴𝑝 𝑁𝑐 𝑐𝑝 + ∑ 𝛼𝑖 𝑐𝑖 𝐴𝑠𝑖
𝑖=1
where,
Ap = cross-sectional area of pile tip (m2)
Nc = bearing capacity factor, taken as 9
cp = average cohesion at pile tip (kN/m2), taken from UCS of soil
∑𝑛𝑖=1 = summation for pile installed layers 1 to n and contributing positive skin friction
αi = adhesion layer for the ith layer depending on the consistency of soil
ci = average cohesion for the ith layer (kN/m2)
Asi = surface area of pile shaft in the ith layer
For non-plastic silt or very fine sand, pile capacity is modified as:
𝐿 ̅̅̅
𝑁 𝐴𝑠
𝑄𝑢 = 10𝑁 𝐴𝑝 +
𝐵 0.60
9. SAMPLE CALCULATION
The allowable bearing capacity (kN/m2) for isolated footing of 2.4 m x 2.4 m and 3.0 m x 3.0 m at depths of 1.5
m and raft foundation of 15.0 m x 15.0 m at depth of 3.0 m (measured from existing ground level) for all BHs is
presented below. For other size and depths, the bearing capacity values are summarized as per table.
For 2.4 m x 2.4 m isolated footing at depth of 1.5 m
Friction angle =28.5˚, cohesion=0.0 kN/m2, Bulk density = 17.0 kN/m3, GWT at surface
Shape factors Depth Factors Inclination Factors Bearing Capacity factors
Sq 1.54 dq 1.19 iq 1.00 Nq 15.55
Sc 1.58 dc 1.25 ic 1.00 Nc 26.81
Sγ 0.60 dγ 1.00 Nγ 11.85
Shear failure criteria IS code qallowable = 122.91 kN/m2
qsafe=11.98N60 3.28B 1
2
S
f d x R w1
3.28 B 25
10. RECOMMENDATION
i The allowable bearing capacity (kN/m2) for various size of isolated foundations at varying depths
(measured from existing ground level) are below:
Size of isolated Depth of foundation (m)
foundation (L=B) 1.5 1.8 2.1 2.4 2.7 3.0
1.5 125 143 168 193 217 242
1.8 123 150 167 192 216 241
2.1 123 148 175 191 215 240
2.4 123 147 173 200 215 239
2.7 124 147 172 198 225 239
3.0 125 148 172 197 223 250
3.3 126 149 172 196 221 248
3.6 128 150 173 196 221 246
iii The foundation Design Engineer does not need to strictly follow the depth and dimension of foundation
selected in the bearing capacity analysis of this report. Designer is free to select any other foundation dimension
and depth depending upon the load of the structure. Therefore, once the size and depth of the foundation is
finalized the calculation may need to be refined during design phase based on the parameters obtained from
this investigation.
Care should be taken for the following during excavation and construction of the building foundation.
The slope of the excavation should be maintained at about 45˚ to prevent the slope from collapsing
during excavation or construction period.
Presence of seepage water and consideration of probable rise in water table in monsoon, sidefall
is eminent. So, at the time of construction of foundation, it is recommended to design the
appropriate site protection measures based on soil properties as obtained on this report.
During excavation near to hill slope (>30˚) as well as near to steep valley side, stability of slope
should evaluated before the excavation by the contractor.
Sample No
Depth 'm'
and Type
N. Value
Soil Discription
Symbol
G.W.T
15 cm
15 cm
15 cm
10 20 30 40 50
0
0.5
c 1
6 5 9 14
1.5
c 2.5
cc 9 11 8 19
3
3.5
Medium dense coarse sand with fine gravels
4
9 15 7 22
4.5
5.5
17 11 19 30
6
6.5
21 29 13 42
7.5
8.5
9.5
10
Sample No
Depth 'm'
and Type
N. Value
Soil Discription
Symbol
G.W.T
15 cm
15 cm
15 cm
10 20 30 40 50
10
32 26 17 43
10.5
11
Dark brown clay loam
11.5
21 34 18 52
12
12.5
13
13.5
14
14.5
15
15.5
16
16.5
17
17.5
18
18.5
19
19.5
20
Borehole terminated at 12 m depth
Checked by: Log by: Drilling by:
Sample No
and Type
Depth 'm'
N. Value
Soil Discription
Symbol
G.W.T
15 cm
15 cm
15 cm
10 20 30 40 50
0
0.5
1
c
11 9 15 24
1.5
c 2.5
cc 11 13 10 23
3
3.5
Gray brown to dark brown silty clay loam
4
14 9 18 27
4.5
5.5
17 12 21 33
6
6.5
29 34 22 56
7.5
8.5
9.5
10
Sample No
and Type
Depth 'm'
N. Value
Soil Discription
Symbol
G.W.T
15 cm
15 cm
15 cm
10 20 30 40 50
10
39 27 38 65
10.5
11
e
11.5
48 31 39 70
12
12.5
13
13.5
14
14.5
15
15.5
16
16.5
17
17.5
18
18.5
19
19.5
Sample No. No 1 2 3 1 2 3
Wt. of Container + Wt. of Wet Soil gm 259.52 351.92 207.23 273.39 280.95 219.67
Wt. of Container + Wt. of Dry Soil gm 253.77 339.66 197.08 259.45 277.53 217.86
Temerature 0C 25 25 25
Wet Soil gm 50 50 50
Temerature 0C 25 25 25
Wet Soil gm 50 50 50
100
90
80
Percentage passing
70
60
50
40
30
20
10
0
1000.00 100.00 10.00 1.00 0.10 0.01 0.00
Particle size mm
100
90
80
Percentage passing
70
60
50
40
30
20
10
0
1000.00 100.00 10.00 1.00 0.10 0.01 0.00
Particle size mm
Gravel: 0.00 Sand: 99.82 Silt/Clay: 0.18 D-50: 0.49
Everest Engineering Consultant
P.O. Box 19103, Mid-Baneswor, Kathmandu, Nepal
Tel.: 977-1- 4493785, 4481449, Fax 977-1-4481449
100
90
80
Percentage passing
70
60
50
40
30
20
10
0
1000.00 100.00 10.00 1.00 0.10 0.01 0.00
Particle size mm
Gravel: 0.00 Sand: 99.50 Silt/Clay: 0.50 D-50: 0.5
Everest Engineering Consultant
P.O. Box 19103, Mid-Baneswor, Kathmandu, Nepal
Tel.: 977-1- 4493785, 4481449, Fax 977-1-4481449
100
90
80
Percentage passing
70
60
50
40
30
20
10
0
1000.00 100.00 10.00 1.00 0.10 0.01 0.00
Particle size mm
Gravel: 0.00 Sand: 99.78 Silt/Clay: 0.22 D-50: 0.28
Everest Engineering Consultant
P.O. Box 19103, Mid-Baneswor, Kathmandu, Nepal
Tel.: 977-1- 4493785, 4481449, Fax 977-1-4481449
100
90
80
Percentage passing
70
60
50
40
30
20
10
0
1000.00 100.00 10.00 1.00 0.10 0.01 0.00
Particle size mm
Gravel: 0.00 Sand: 97.68 Silt/Clay: 2.32 D-50: 0.42
Everest Engineering Consultant
P.O. Box 19103, Mid-Baneswor, Kathmandu, Nepal
Tel.: 977-1- 4493785, 4481449, Fax 977-1-4481449
100
90
80
Percentage passing
70
60
50
40
30
20
10
0
1000.00 100.00 10.00 1.00 0.10 0.01 0.00
Particle size mm
Gravel: 0.00 Sand: 99.00 Silt/Clay: 1.00 D-50: 0.6
Everest Engineering Consultant
P.O. Box 19103, Mid-Baneswor, Kathmandu, Nepal
Tel.: 977-1- 4493785, 4481449, Fax 977-1-4481449
100
90
80
Percentage passing
70
60
50
40
30
20
10
0
1000.00 100.00 10.00 1.00 0.10 0.01 0.00
Particle size mm
Gravel: 0.00 Sand: 98.68 Silt/Clay: 1.32 D-50: 0.27
LIQUID LIMIT & PLASTIC LIMIT
Project Landfill site
Location Siraha
Date: 10/2/2078
Borehole No.:- 1 L/B
Sample No.:-
Depth :-0m to 3.0m Liquid Limit Plastic Limit
1 Specimen No. 1 2 3 4 1 2
2 No. of Blows 13 24 27 36
3 Wt. of Container + Wet Soil gms 34.24 36.00 35.00 34.10
4 Wt. of Container + Dry Soil gms 30.20 31.30 31.20 30.60
5 Wt. of Water Present gms 4.04 4.70 3.80 3.50
6 Wt. of Empty Container gms 15.10 13.70 14.20 13.20
7 Wt. of Dry Soil gms 15.10 17.60 17.00 17.40
8 Moisture Content % 26.75 26.70 22.35 20.11
30.00
25.00
Axis Title
20.00
15.00
1 10 100
Axis Title
Results :
Liquid Limit : 23.59 %
Plastic Limit : - %
Plasticity Index : 23.6 %
LIQUID LIMIT & PLASTIC LIMIT
Project Landfill site
Location Siraha
Date: 10/2/2078
Borehole No.:- 1 L/B
Sample No.:-
Depth :-3m to 6.0m Liquid Limit Plastic Limit
1 Specimen No. 1 2 3 4 1 2
2 No. of Blows 14 23 29 38
3 Wt. of Container + Wet Soil gms 36.70 38.20 32.10 33.80
4 Wt. of Container + Dry Soil gms 31.40 33.30 28.39 29.80
5 Wt. of Water Present gms 5.30 4.90 3.71 4.00
6 Wt. of Empty Container gms 13.30 15.50 13.70 12.80
7 Wt. of Dry Soil gms 18.10 17.80 14.69 17.00
8 Moisture Content % 29.28 27.53 25.26 23.53
35.00
30.00
Axis Title
25.00
20.00
1 10 100
Axis Title
Results :
Liquid Limit : 26.26 %
Plastic Limit : - %
Plasticity Index : 26.3 %
LIQUID LIMIT & PLASTIC LIMIT
Project Landfill site
Location Siraha
Date: 10/2/2078
Borehole No.:- 1 L/B
Sample No.:-
Depth :-7.5M-16.5m Liquid Limit Plastic Limit
1 Specimen No. 1 2 3 4 1 2
2 No. of Blows 10 21 29 37
3 Wt. of Container + Wet Soil gms 35.80 34.20 33.70 34.90
4 Wt. of Container + Dry Soil gms 31.00 29.60 29.80 31.20
5 Wt. of Water Present gms 4.80 4.60 3.90 3.70
6 Wt. of Empty Container gms 14.20 12.00 13.60 14.50
7 Wt. of Dry Soil gms 16.80 17.60 16.20 16.70
8 Moisture Content % 28.57 26.14 24.07 22.16
34.00
32.00
30.00
Axis Title
28.00
26.00
24.00
22.00
20.00
1 10 100
Axis Title
Results :
Liquid Limit : 24.58 %
Plastic Limit : - %
Plasticity Index : 24.6 %
LIQUID LIMIT & PLASTIC LIMIT
Project Landfill site
Location Siraha
Date: 10/2/2078
Borehole No.:- 2 R/B
Sample No.:-
Depth :-0.0m to 3.0 m Liquid Limit Plastic Limit
1 Specimen No. 1 2 3 4 1 2
2 No. of Blows 14 24 29 38
3 Wt. of Container + Wet Soil gms 39.00 36.00 36.80 35.40
4 Wt. of Container + Dry Soil gms 33.20 31.30 32.20 31.60
5 Wt. of Water Present gms 5.80 4.70 4.60 3.80
6 Wt. of Empty Container gms 13.30 14.20 13.80 15.20
7 Wt. of Dry Soil gms 19.90 17.10 18.40 16.40
8 Moisture Content % 29.15 27.49 25.00 23.17
34.00
32.00
30.00
Axis Title
28.00
26.00
24.00
22.00
20.00
1 10 100
Axis Title
Results :
Liquid Limit : 26.12 %
Plastic Limit : - %
Plasticity Index : 26.1 %
LIQUID LIMIT & PLASTIC LIMIT
Project Landfill site
Location Siraha
Date: 10/2/2078
Borehole No.:- 2 R/B
Sample No.:-
Depth :-3m to 16.5 m Liquid Limit Plastic Limit
1 Specimen No. 1 2 3 4 1 2
2 No. of Blows 14 23 28 36
3 Wt. of Container + Wet Soil gms 33.80 35.20 33.00 31.60
4 Wt. of Container + Dry Soil gms 29.60 31.20 29.80 28.43
5 Wt. of Water Present gms 4.20 4.00 3.20 3.17
6 Wt. of Empty Container gms 14.20 15.30 16.20 13.50
7 Wt. of Dry Soil gms 15.40 15.90 13.60 14.93
8 Moisture Content % 27.27 25.16 23.53 21.23
35.00
33.00
31.00
29.00
27.00
Axis Title
25.00
23.00
21.00
19.00
17.00
15.00
1 10 100
Axis Title
Results :
Liquid Limit : 24.01 %
Plastic Limit : - %
Plasticity Index : 24.0 %
Everest Engienering Consultant
DIRECT SHEAR TEST
(Method: IS: 2720 (Part 13) 1986)
Project: Landfill site
Location: Siraha Date: 2078-02-10 Co-ordinate:
BH No.: BH # 01 Chainage: Tested by: S. Giri E= Elevation: m
Depth: 12m - 12.45m Checked by: S. Bakhrel N=
x0.002
x0.002
kg/cm 2
kg/cm 2
kg/cm 2
Shear Stress
Shear Stress
Shear Stress
Shear Load
Shear Load
Shear Load
Hoz. Disp.
Hoz. Disp.
Hoz. Disp.
Load Dial
Load Dial
Load Dial
*0.01mm
*0.01mm
*0.01mm
"N"
"N"
"N"
mm
mm
mm
0.50 47.00 72.85 2.024 0.50 50.00 77.50 2.153 0.50 72.0 111.60 3.100 SOIL SPECIMENT MEASUREMENTS
1.00 62.00 96.10 2.669 1.00 83.00 128.65 3.574 1.00 103.0 159.65 4.435 Normal Load (kg/cm2): 4.91 9.8
1.50 82.00 127.10 3.531 1.50 115.00 178.25 4.951 1.50 135.0 209.25 5.813 Length, l cm. 6.00 6.00
2.00 100.00 155.00 4.306 2.00 130.00 201.50 5.597 2.00 165.0 255.75 7.104 Bredth, b cm. 6.00 6.00
2.50 117.00 181.35 5.038 2.50 153.00 237.15 6.588 2.50 190.0 294.50 8.181 Height, h cm. 2.58 2.58
3.00 121.00 187.55 5.21 3.00 151.00 234.05 6.501 3.00 215.0 333.25 9.257 Plan Area a=lxb cm2. 36.0 36.0
3.50 3.50 3.50 120.0 186.00 5.167 Volume v = a* h cm3 92.9 92.9
4.00 4.00 4.00 117.0 181.35 5.038 Weight of wet Soil + Container g 331.24 332.12
4.50 4.50 4.50 Weight of Container g 155.65 155.14
5.00 5.00 5.00 Weight of wet Soil w g 175.59 176.98
5.50 5.50 5.50 Wet Unit Weight, yT = w / v Kn/m 18.55 18.69
6.00 6.00 6.00 Dry Unit Weight yd = 100*yT/(100+W) Kn/m 16.68 10.58
6.50 6.50 6.50
7.00 7.00 7.00 WATER CONTENT DETERMINATION
7.50 7.50 7.50 Container No. C-16 C-3
8.00 8.00 8.00 Weight of Wet Soil + Container g 42.23 44.32
8.50 8.50 8.50 Weight of dry soil + contaoner g 39.21 30.25
9.00 9.00 9.00 Weight of water g 3.02 14.07
9.50 9.50 9.50 Weight of container g 12.17 11.91
10.00 10.00 10.00 Weight dry soil g 27.0 18.34
Water Content % 11.17 76.72
2 3
Normal Load (kg/cm ): 4.91 9.81 14.72 Average Moisture Contet (%): 32.87 Average Dry Unit Weight (kn/m ) 14.72
Max. Shear Stress kg/cm2: 5.21 6.59 9.26 Avereage Wet Uit Weight (km/m3): 18.65
Everest Enginnering Consultant
DIRECT SHEAR TEST (GRAPH)
9.0
9.0
8.0
8.0
7.0
7.0
shear Stress N/cm2
6.0
5.0
5.0
4.0
4.0
3.0
3.0
2.0 2.0
1.0 1.0
0.0 0.0
0 1 2 3 4 5 6 7 8 0 3 6 9 12 15 18 21
Normal Stress N/cm2
Hoz. Disp. *0.01mm
14.72
6.00
6.00
2.58
36.0
92.9
333.24
155.98
177.26
18.72
16.91
C-5
42.45
39.54
2.91
12.39
27.15
10.72
Everest Engineering Consultant
DIRECT SHEAR TEST
(Method: IS: 2720 (Part 13) 1986)
Project: Landfill site
Location: Siraha Date: 2078-02-10 Co-ordinate:
BH No.: BH # 02 Chainage: Tested by: S. Giri E= Elevation: m
Depth: 12m - 12.45m Checked by: S. Bakhrel N=
Load Scale K (N/div): 1.55 Plan Area (cm2) 36 Strain Rate: (mm/min) 1.25 Ø= 32.57 0
2
Normal Load (kg/cm2): 4.91 Normal Load (kg/cm2): 9.8 Normal Load (kg/cm2): 14.715 C= 2.939 N/cm
kg/cm 2
kg/cm 2
kg/cm 2
x0.002
x0.002
x0.002
Shear Stress
Shear Stress
Shear Stress
Shear Load
Shear Load
Shear Load
Hoz. Disp.
Hoz. Disp.
Hoz. Disp.
Load Dial
Load Dial
Load Dial
"N"
"N"
"N"
*0.01mm
*0.01mm
*0.01mm
mm
mm
mm
0.50 43.00 66.65 1.851 0.50 49.00 75.95 2.110 0.50 68.0 105.40 2.928 SOIL SPECIMENT MEASUREMENTS
1.00 64.00 99.20 2.756 1.00 55.00 85.25 2.368 1.00 102.0 158.10 4.392 Normal Load (kg/cm2): 4.91 9.8
1.50 85.00 131.75 3.660 1.50 103.00 159.65 4.435 1.50 133.0 206.15 5.726 Length, l cm. 6.00 6.00
2.00 103.00 159.65 4.435 2.00 120.00 186.00 5.167 2.00 165.0 255.75 7.104 Bredth, b cm. 6.00 6.00
2.50 117.00 181.35 5.038 2.50 133.00 206.15 5.726 2.50 193.0 299.15 8.310 Height, h cm. 2.58 2.58
3.00 115.00 178.25 4.95 3.00 145.00 224.75 6.243 3.00 204.0 316.20 8.783 Plan Area a=lxb cm2. 36.0 36.0
3
3.50 3.50 145.00 224.75 6.243 3.50 201.0 311.55 8.654 Volume v = a* h cm 92.9 92.9
4.00 4.00 4.00 Weight of wet Soil + Container g 329.54 329.58
4.50 4.50 4.50 Weight of Container g 156.44 156.44
5.00 5.00 5.00 Weight of wet Soil w g 173.10 173.14
3
5.50 5.50 5.50 Wet Unit Weight, yT = w / v Kn/m 18.28 18.29
6.00 6.00 6.00 Dry Unit Weight yd = 100*yT/(100+W) Kn/m3 15.42 15.32
6.50 6.50 6.50
7.00 7.00 7.00 WATER CONTENT DETERMINATION
7.50 7.50 7.50 Container No. C-7 C-4
8.00 8.00 8.00 Weight of Wet Soil + Container g 43.54 43.97
8.50 8.50 8.50 Weight of dry soil + contaoner g 38.62 38.92
9.00 9.00 9.00 Weight of water g 4.92 5.05
9.50 9.50 9.50 Weight of container g 12.08 12.81
10.00 10.00 10.00 Weight dry soil g 26.5 26.11
Water Content % 18.54 19.34
Normal Load (kg/cm ):
2
4.91 9.81 14.72 Average Moisture Contet (%): 18.83 Average Dry Unit Weight (kn/m3) 15.42
2 3
Max. Shear Stress kg/cm : 5.04 6.24 8.78 Avereage Wet Uit Weight (km/m ): 18.32
9.0
9.0
8.0
8.0
7.0
7.0
shear Stress N/cm2
6.0
6.0
4.0
4.0
3.0
3.0
2.0 2.0
1.0 1.0
0.0 0.0
0 1 2 3 4 5 6 7 8 0 3 6 9 12 15 18 21
Normal Stress N/cm2
Hoz. Disp. *0.01mm
14.72
6.00
6.00
2.58
36.0
92.9
330.47
156.44
174.03
18.38
15.50
C-11
44.51
39.47
5.04
12.37
27.10
18.60