You are on page 1of 6

MONITORING PENGECORAN DAN BENDA UJI BETON PROYEK JALAN AKSES TOL MNP

VOLUME VOLUME VOLUME JUMLAH


TANGGAL SUPPLAIR MUTU Slump Tanggal Pengujian Rata2 Hasil Uji
No. LOKASI/POSISI ITEM PEKERJAAN RENCANA REALISASI KUMULATIF KODE BENDA UJI BENDA KET
COR BETON BETON
(cm) (m³) (m³) (m³) UJI 7 HARI 28 HARI 7 HARI 28 HARI
1 11-May-22 Borepile S1.39-BP57 Witon Borepile Fc 30 18+2 11.8 13.5 13.5 WK/MNP/S1.39-BP57/FC30 8 18-May-22 8-Jun-22 29.75 37.51 OK

2 11-May-22 Borepile S1.39-BP56 Witon Borepile Fc 30 18+2 11.8 13.5 27 WK/MNP/S1.39-BP56/FC30 8 18-May-22 8-Jun-22 29.63 38.32 OK

3 11-May-22 Widening P1.11-P1.12 Witon Jalan Akses Sementara Fc 30 10+2 70 70 97 WK/MNP/WD P1.11-P1.12(1)/FC30 24 18-May-22 8-Jun-22 29.95 36.29 OK

4 12-May-22 Borepile S1.39-BP55 Witon Borepile Fc 30 18+2 11.8 13.5 110.5 WK/MNP/S1.39-BP55/FC30 8 19-May-22 9-Jun-22 29.06 38.30 OK

5 13-May-22 Borepile S1.38-BP54 Witon Borepile Fc 30 18+2 11.8 14.5 125 WK/MNP/S1.38-BP54/FC30 8 20-May-22 10-Jun-22 28.10 37.92 OK

6 13-May-22 Widening P1.11-P1.12 Witon Jalan Akses Sementara Fc 30 10+2 70 44 169 WK/MNP/WD P1.11-P1.12(2)/FC30 12 20-May-22 10-Jun-22 28.46 35.17 OK

7 13-May-22 Borepile S1.36-BP46 Witon Borepile Fc 30 18+2 10.6 12.5 181.5 WK/MNP/S1.36-BP46/FC30 8 20-May-22 10-Jun-22 28.95 37.48 Rework

8 15-May-22 Borepile S1.36-BP46 Witon Borepile Fc 30 18+2 10.6 21 202.5 WK/MNP/S1.36-BP46/FC30 12 22-May-22 12-Jun-22 28.84 39.42 PDA

9 15-May-22 Borepile S1.38-BP52 Witon Borepile Fc 30 18+2 10.6 15 217.5 WK/MNP/S1.38-BP52/FC30 8 22-May-22 12-Jun-22 29.18 39.73 OK

10 16-May-22 Borepile S1.36-BP48 Witon Borepile Fc 30 18+2 10.6 15 232.5 WK/MNP/S1.36-BP48/FC30 8 23-May-22 13-Jun-22 32.43 37.81 OK

11 16-May-22 Widening P1.11-P1.12 Witon Jalan Akses Sementara Fc 30 10+2 32 38 270.5 WK/MNP/WD P1.11-P1.12(3)/FC30 12 23-May-22 13-Jun-22 33.08 38.20 OK

12 16-May-22 Borepile S1.38-BP53 Witon Borepile Fc 30 18+2 10.6 14 284.5 WK/MNP/S1.38-BP53/FC30 8 23-May-22 13-Jun-22 35.26 37.03 OK

13 17-May-22 Borepile S1.36-BP47 Witon Borepile Fc 30 18+2 10.6 15 299.5 WK/MNP/S1.36-BP47/FC30 8 24-May-22 14-Jun-22 36.20 38.09 OK

14 18-May-22 Borepile S1.35-BP45 Witon Borepile Fc 30 18+2 10.6 12.5 312 WK/MNP/S1.35-BP45/FC30 8 25-May-22 15-Jun-22 34.14 35.44 OK

15 18-May-22 Borepile S1.37-BP49 Witon Borepile Fc 30 18+2 10.6 13 325 WK/MNP/S1.37-BP49/FC30 8 25-May-22 15-Jun-22 33.66 37.62 OK

16 18-May-22 Borepile S1.35-BP43 Witon Borepile Fc 30 18+2 10.6 13 338 WK/MNP/S1.35-BP43/FC30 8 25-May-22 15-Jun-22 34.36 37.62 OK

17 19-May-22 Borepile S1.37-BP51 Witon Borepile Fc 30 18+2 10.6 13 351 WK/MNP/S1.37-BP51/FC30 8 26-May-22 16-Jun-22 37.72 38.32 OK

18 19-May-22 Borepile S1.35-BP44 Witon Borepile Fc 30 18+2 10.6 13 364 WK/MNP/S1.35-BP44/FC30 8 26-May-22 16-Jun-22 36.41 37.10 OK

19 19-May-22 Borepile S1.37-BP50 Witon Borepile Fc 30 18+2 10.6 13 377 WK/MNP/S1.37-BP50/FC30 8 26-May-22 16-Jun-22 36.22 38.02 OK

20 20-May-22 Borepile S1.34-BP42 Witon Borepile Fc 30 18+2 10.6 13 390 WK/MNP/S1.34-BP42/FC30 8 27-May-22 17-Jun-22 32.42 37.17 OK

21 20-May-22 Borepile S1.32-BP34 Witon Borepile Fc 30 18+2 10.6 13 403 WK/MNP/S1.32-BP34/FC30 8 27-May-22 17-Jun-22 36.22 37.23 OK

22 20-May-22 Borepile S1.34-BP40 Witon Borepile Fc 30 18+2 10.6 12.5 415.5 WK/MNP/S1.34-BP40/FC30 8 27-May-22 17-Jun-22 33.33 37.03 OK

23 20-May-22 Borepile S1.32-BP36 Witon Borepile Fc 30 18+2 10.6 13 428.5 WK/MNP/S1.32-BP36/FC30 8 27-May-22 17-Jun-22 38.81 38.17 OK

24 21-May-22 Borepile S1.34-BP41 Witon Borepile Fc 30 18+2 10.6 13 441.5 WK/MNP/S1.34-BP41/FC30 8 28-May-22 18-Jun-22 33.05 37.78 OK

25 21-May-22 Borepile S1.32-BP35 Witon Borepile Fc 30 18+2 10.6 13 454.5 WK/MNP/S1.32-BP35/FC30 8 28-May-22 18-Jun-22 31.32 35.39 OK

26 21-May-22 Borepile S1.33-BP37 Witon Borepile Fc 30 18+2 10.6 13 467.5 WK/MNP/S1.33-BP37/FC30 8 28-May-22 18-Jun-22 30.52 36.47 OK

27 22-May-22 Borepile S1.31-BP31 Witon Borepile Fc 30 18+2 10.6 13 480.5 WK/MNP/S1.31-BP31/FC30 8 29-May-22 19-Jun-22 30.15 44.39 OK

28 22-May-22 Borepile S1.33-BP39 Witon Borepile Fc 30 18+2 10.6 13 493.5 WK/MNP/S1.33-BP39/FC30 8 29-May-22 19-Jun-22 29.83 47.21 OK

29 22-May-22 Borepile S1.31-BP33 Witon Borepile Fc 30 18+2 10.6 13 506.5 WK/MNP/S1.31-BP33/FC30 8 29-May-22 19-Jun-22 29.27 43.10 OK

30 22-May-22 Borepile S1.33-BP38 Witon Borepile Fc 30 18+2 10.6 13 519.5 WK/MNP/S1.33-BP38/FC30 8 29-May-22 19-Jun-22 29.66 48.44 OK
MONITORING PENGECORAN DAN BENDA UJI BETON PROYEK JALAN AKSES TOL MNP
VOLUME VOLUME VOLUME JUMLAH
TANGGAL SUPPLAIR MUTU Slump Tanggal Pengujian Rata2 Hasil Uji
No. LOKASI/POSISI ITEM PEKERJAAN RENCANA REALISASI KUMULATIF KODE BENDA UJI BENDA KET
COR BETON BETON
(cm) (m³) (m³) (m³) UJI 7 HARI 28 HARI 7 HARI 28 HARI
31 23-May-22 Borepile S1.31-BP32 Witon Borepile Fc 30 18+2 10.6 13 532.5 WK/MNP/S1.31-BP32/FC30 8 30-May-22 20-Jun-22 36.88 37.99 OK

32 23-May-22 Borepile S1.30-BP29 Witon Borepile Fc 30 18+2 10.6 13 545.5 WK/MNP/S1.30-BP29/FC30 8 30-May-22 20-Jun-22 40.26 37.75 OK

33 23-May-22 Borepile S1.28-BP23 Witon Borepile Fc 30 18+2 10.6 13 558.5 WK/MNP/S1.28-BP23/FC30 8 30-May-22 20-Jun-22 34.80 39.34 OK

34 23-May-22 Borepile S1.30-BP28 Witon Borepile Fc 30 18+2 10.6 13 571.5 WK/MNP/S1.30-BP28/FC30 8 30-May-22 20-Jun-22 38.03 36.52 OK

35 24-May-22 Borepile S1.28-BP22 Witon Borepile Fc 30 18+2 10.6 13 584.5 WK/MNP/S1.28-BP22/FC30 8 31-May-22 21-Jun-22 36.90 38.05 OK

36 24-May-22 Borepile S1.30-BP30 Witon Borepile Fc 30 18+2 10.6 13 597.5 WK/MNP/S1.30-BP30/FC30 8 31-May-22 21-Jun-22 33.60 38.70 OK

37 24-May-22 Borepile S1.28-BP24 Witon Borepile Fc 30 18+2 10.6 13 610.5 WK/MNP/S1.28-BP24/FC30 8 31-May-22 21-Jun-22 35.17 35.58 OK

38 24-May-22 Borepile S1.29-BP25 Witon Borepile Fc 30 18+2 10.6 13 623.5 WK/MNP/S1.29-BP25/FC30 8 31-May-22 21-Jun-22 35.78 30.95 OK

39 24-May-22 Borepile S1.27-BP19 Witon Borepile Fc 30 18+2 10.6 13 636.5 WK/MNP/S1.27-BP19/FC30 8 31-May-22 21-Jun-22 32.69 35.30 OK

40 25-May-22 Borepile S1.29-BP27 Witon Borepile Fc 30 18+2 10.6 13 649.5 WK/MNP/S1.29-BP27/FC30 8 1-Jun-22 22-Jun-22 29.75 37.74 OK

41 25-May-22 Borepile S1.27-BP21 Witon Borepile Fc 30 18+2 10.6 13 662.5 WK/MNP/S1.27-BP21/FC30 8 1-Jun-22 22-Jun-22 31.42 35.76 OK

42 25-May-22 Borepile S1.29-BP26 Witon Borepile Fc 30 18+2 10.6 13 675.5 WK/MNP/S1.29-BP26/FC30 8 1-Jun-22 22-Jun-22 33.49 34.90 OK

43 25-May-22 Borepile S1.27-BP20 Witon Borepile Fc 30 18+2 10.6 13 688.5 WK/MNP/S1.27-BP20/FC30 8 1-Jun-22 22-Jun-22 34.41 36.69 OK

44 26-May-22 Borepile S1.23-BP8 Witon Borepile Fc 30 18+2 10.6 13 701.5 WK/MNP/S1.23-BP8/FC30 8 2-Jun-22 23-Jun-22 39.63 37.99 PDA

45 26-May-22 Borepile S1.26-BP16 Witon Borepile Fc 30 18+2 10.6 13 714.5 WK/MNP/S1.26-BP16/FC30 8 2-Jun-22 23-Jun-22 39.37 38.14 OK

46 26-May-22 Borepile S1.24-BP10 Witon Borepile Fc 30 18+2 10.6 13 727.5 WK/MNP/S1.24-BP10/FC30 8 2-Jun-22 23-Jun-22 35.94 36.58 OK

47 26-May-22 Borepile S1.26-BP18 Witon Borepile Fc 30 18+2 10.6 13 740.5 WK/MNP/S1.26-BP18/FC30 8 2-Jun-22 23-Jun-22 34.13 35.46 OK

48 27-May-22 Borepile S1.24-BP12 Witon Borepile Fc 30 18+2 10.6 13 753.5 WK/MNP/S1.24-BP12/FC30 8 3-Jun-22 24-Jun-22 29.47 37.66 OK

49 27-May-22 Borepile S1.22-BP6 Witon Borepile Fc 30 18+2 10.6 13 766.5 WK/MNP/S1.22-BP6/FC30 8 3-Jun-22 24-Jun-22 29.44 36.25 OK

50 27-May-22 Borepile S1.26-BP17 Witon Borepile Fc 30 18+2 10.6 13 779.5 WK/MNP/S1.26-BP17/FC30 8 3-Jun-22 24-Jun-22 30.66 35.24 OK

51 28-May-22 Borepile S1.24-BP11 Witon Borepile Fc 30 18+2 10.6 13 792.5 WK/MNP/S1.24-BP11/FC30 8 4-Jun-22 25-Jun-22 29.54 38.46 OK

52 30-May-22 Widening Detour P1.11 Witon Jalan Akses Sementara Fc 30 10+2 21.5 25.5 818 WK/MNP/WD.P1.11/FC30 12 6-Jun-22 27-Jun-22 34.31 37.32 OK

53 30-May-22 Borepile S1.22-BP4 Witon Borepile Fc 30 18+2 10.6 13 831 WK/MNP/S1.22-BP4/FC30 8 6-Jun-22 27-Jun-22 34.45 37.38 OK

54 30-May-22 Borepile S1.25-BP13 Witon Borepile Fc 30 18+2 10.6 13 844 WK/MNP/S1.25-BP13/FC30 8 6-Jun-22 27-Jun-22 36.21 38.67 OK

55 31-May-22 Borepile S1.23-BP7 Witon Borepile Fc 30 18+2 10.6 13 857 WK/MNP/S1.23-BP7/FC30 8 7-Jun-22 28-Jun-22 30.73 39.07 OK

56 31-May-22 Borepile S1.25-BP15 Witon Borepile Fc 30 18+2 10.6 13 870 WK/MNP/S1.25-BP15/FC30 8 7-Jun-22 28-Jun-22 38.18 39.78 OK

57 31-May-22 Temporary Cover saluran Witon - Fc 30 10+2 3 3 873 - 8 7-Jun-22 28-Jun-22

58 31-May-22 Borepile S1.23-BP9 Witon Borepile Fc 30 18+2 10.6 13 886 WK/MNP/S1.23-BP9/FC30 8 7-Jun-22 28-Jun-22 32.73 39.08 OK

59 31-May-22 Borepile S1.21-BP2 Witon Borepile Fc 30 18+2 10.6 13 899 WK/MNP/S1.21-BP2/FC30 8 7-Jun-22 28-Jun-22 33.03 38.96 OK

60 1-Jun-22 Borepile S1.25-BP14 Witon Borepile Fc 30 18+2 10.6 13 912 WK/MNP/S1.25-BP14/FC30 8 8-Jun-22 29-Jun-22 30.31 37.03 OK
MONITORING PENGECORAN DAN BENDA UJI BETON PROYEK JALAN AKSES TOL MNP
VOLUME VOLUME VOLUME JUMLAH
TANGGAL SUPPLAIR MUTU Slump Tanggal Pengujian Rata2 Hasil Uji
No. LOKASI/POSISI ITEM PEKERJAAN RENCANA REALISASI KUMULATIF KODE BENDA UJI BENDA KET
COR BETON BETON
(cm) (m³) (m³) (m³) UJI 7 HARI 28 HARI 7 HARI 28 HARI
61 1-Jun-22 Borepile S1.21-BP3 Witon Borepile Fc 30 18+2 10.6 13 925 WK/MNP/S1.21-BP3/FC30 8 8-Jun-22 29-Jun-22 32.67 36.90 OK

62 1-Jun-22 Borepile S1.21-BP1 Witon Borepile Fc 30 18+2 10.6 13 938 WK/MNP/S1.21-BP1/FC30 8 8-Jun-22 29-Jun-22 33.48 37.87 OK

63 1-Jun-22 Borepile S1.22-BP5 Witon Borepile Fc 30 18+2 10.6 13 951 WK/MNP/S1.22-BP5/FC30 8 8-Jun-22 29-Jun-22 31.29 36.24 OK

64 2-Jun-22 Sudetan Direksi Keet Witon Rigid Sudetan Fc 30 10+2 18 18 969 - 8 9-Jun-22 30-Jun-22 31.63 35.23 OK

65 3-Jun-22 Sudetan Direksi Keet Witon Rigid Sudetan Fc 30 10+2 21 16 985 - 8 10-Jun-22 1-Jul-22 33.25 36.22 OK

66 4-Jun-22 Sudetan Direksi Keet Witon Rigid Sudetan Fc 30 10+2 12 13 998 - 8 11-Jun-22 2-Jul-22 29.91 36.65 OK

67 4-Jun-22 Widening AF.2 Witon Jalan Akses Sementara Fc 40 10+2 50 50.5 1,048.50 WK/MNP/WD AF.2/FC30(1) 20 11-Jun-22 2-Jul-22 38.49 44.24 OK

68 5-Jun-22 Widening AF.2 Witon Jalan Akses Sementara Fc 40 10+2 12.5 12.5 1,061.00 WK/MNP/WD AF.2/FC30(2) 8 12-Jun-22 3-Jul-22 40.88 45.92 OK

69 5-Jun-22 Akses Fabrikasi Besi Witon - Fc 25 10+2 13 12.5 1,073.50 - 8 12-Jun-22 3-Jul-22 31.11 32.41 OK

70 6-Jun-22 Sudetan Direksi Keet Witon Rigid Sudetan Fc 30 10+2 12 13 1086.5 - 8 13-Jun-22 4-Jul-22 30.88 35.92 OK

71 6-Jun-22 Borepile P1.12-B Witon Borepile Fc 30 18+2 35 36 1122.5 WK/MNP/P1.12-B/FC30 20 13-Jun-22 4-Jul-22 32.00 37.58 OK

72 7-Jun-22 Akses Fabrikasi Besi Witon - Fc 25 10+2 20 20 1,142.50 - 12 14-Jun-22 5-Jul-22 24.52 38.80 OK

73 7-Jun-22 Borepile P1.11-B Witon Borepile Fc 30 18+2 35 40 1182.5 WK/MNP/P1.11-B/FC30 20 14-Jun-22 5-Jul-22 32.35 37.18 OK

74 8-Jun-22 Borepile P1.11-C Witon Borepile Fc 30 18+2 35 38.5 1221 WK/MNP/P1.11-C/FC30 20 15-Jun-22 6-Jul-22 31.97 36.23 PDA

75 8-Jun-22 Akses Fabrikasi Besi Witon - Fc 25 10+2 12 12 1,233.00 - 8 15-Jun-22 6-Jul-22 24.88

76 8-Jun-22 Sudetan Direksi Keet Witon Rigid Sudetan Fc 30 10+2 30 22 1255 - 14 15-Jun-22 6-Jul-22 31.93 38.40 OK

77 8-Jun-22 Borepile P1.12-D Witon Borepile Fc 30 18+2 35 36 1291 WK/MNP/P1.12-D/FC30 20 15-Jun-22 6-Jul-22 31.90 37.01 OK

78 9-Jun-22 Akses Fabrikasi Besi Witon - Fc 25 10+2 20 20 1311 - 14 16-Jun-22 7-Jul-22 24.94 71.52 OK

79 9-Jun-22 Borepile P1.12-A Witon Borepile Fc 30 18+2 35 36 1347 WK/MNP/P1.12-A/FC30 20 16-Jun-22 7-Jul-22 31.94 38.29 OK

80 11-Jun-22 Sudetan Direksi Keet Witon Rigid Sudetan Fc 30 10+2 12 12 1359 - 8 18-Jun-22 9-Jul-22 33.04 38.93 OK

81 11-Jun-22 Borepile P1.11-A Witon Borepile Fc 30 18+2 35 38 1397 WK/MNP/P1.11-A/FC30 20 18-Jun-22 9-Jul-22 31.58 38.97 OK

82 11-Jun-22 Borepile P1.13-D Witon Borepile Fc 30 18+2 28 28 1425 WK/MNP/P1.13-D/FC30 14 18-Jun-22 9-Jul-22 32.10 38.65 OK

83 12-Jun-22 Borepile P1.11-D Witon Borepile Fc 30 18+2 38.5 38.5 1463.5 WK/MNP/P1.11-D/FC30 20 19-Jun-22 10-Jul-22 37.73 40.31 OK

84 13-Jun-22 Fabrikasi Besi Witon - Fc 10 10+2 24 24 1487.5 - 8 20-Jun-22 11-Jul-22 14.13 18.17 OK

85 13-Jun-22 Sudetan Direksi Keet Witon Rigid Sudetan Fc 30 10+2 13 13 1500.5 - 8 20-Jun-22 11-Jul-22 33.52 40.58 OK

86 21-Jun-22 Borepile P1.10-C Witon Borepile Fc 30 18+2 38.5 41 1541.5 WK/MNP/P1.10-C/FC30 20 28-Jun-22 19-Jul-22 31.24

87 21-Jun-22 Borepile P1.9-C Witon Borepile Fc 30 18+2 38.5 40 1581.5 WK/MNP/P1.9-C/FC30 20 28-Jun-22 19-Jul-22 31.97

88 21-Jun-22 Akses Gudang Witon - Fc 10 10+2 15 15 1596.5 - 8 28-Jun-22 19-Jul-22 10.38

89 21-Jun-22 PJU AF2 Witon Pondasi PJU Fc 40 10+2 4 4 1600.5 WK/MNP/PJU/FC30 8 28-Jun-22 19-Jul-22 38.49

90 22-Jun-22 Akses Gudang Witon - Fc 10 10+2 6.5 6.5 1607 - 8 29-Jun-22 20-Jul-22 13.14
MONITORING PENGECORAN DAN BENDA UJI BETON PROYEK JALAN AKSES TOL MNP
VOLUME VOLUME VOLUME JUMLAH
TANGGAL SUPPLAIR MUTU Slump Tanggal Pengujian Rata2 Hasil Uji
No. LOKASI/POSISI ITEM PEKERJAAN RENCANA REALISASI KUMULATIF KODE BENDA UJI BENDA KET
COR BETON BETON
(cm) (m³) (m³) (m³) UJI 7 HARI 28 HARI 7 HARI 28 HARI
91 22-Jun-22 Borepile P1.8-D Witon Borepile Fc 30 18+2 38.5 40 1647 WK/MNP/P1.8-D/FC30 20 29-Jun-22 20-Jul-22 32.43

92 23-Jun-22 Borepile P1.10-A Witon Borepile Fc 30 18+2 38.5 39 1686 WK/MNP/P1.10-A/FC30 20 30-Jun-22 21-Jul-22 33.31

93 23-Jun-22 Borepile P1.9-A Witon Borepile Fc 30 18+2 38.5 39 1725 WK/MNP/P1.9-A/FC30 20 30-Jun-22 21-Jul-22 32.28

94 24-Jun-22 Borepile P1.8-B Witon Borepile Fc 30 18+2 38.5 39 1764 WK/MNP/P1.8-B/FC30 20 1-Jul-22 22-Jul-22 32.15

95 24-Jun-22 Borepile P1.10-D Witon Borepile Fc 30 18+2 38.5 39 1803 WK/MNP/P1.10-D/FC30 20 1-Jul-22 22-Jul-22 32.08

96 24-Jun-22 Borepile P1.9-D Witon Borepile Fc 30 18+2 38.5 39 1842 WK/MNP/P1.9-D/FC30 20 1-Jul-22 22-Jul-22 32.48

97 27-Jun-22 Borepile P1.10-B Witon Borepile Fc 30 18+2 38.5 39 1881 WK/MNP/P1.10-B/FC30 20 4-Jul-22 25-Jul-22 31.79

98 27-Jun-22 Borepile P1.9-B Witon Borepile Fc 30 18+2 38.5 39 1920 WK/MNP/P1.9-B/FC30 20 4-Jul-22 25-Jul-22 31.91

S1.29-BP25 & S1.29-BP26


99 30-Jun-22 Witon Extension Pile Fc 35 14+2 4.5 4.5 1924.5 WK/MNP/EX/S1.29-BP25-26/(1)FC30 8 7-Jul-22 28-Jul-22 38.42
(Stage-1)
LC Temporary Akses SOP
100 2-Jul-22 Witon - Fc 10 10+2 18 18 1942.5 - 6 9-Jul-22 30-Jul-22 11.36
AF.2

101 4-Jul-22 Head BP P1.9-D Witon - Fc 35 14+2 3 3 1945.5 - 6 11-Jul-22 1-Aug-22 36.24

S1.28-BP22 & S1.28-BP23


102 5-Jul-22 Witon Extension Pile Fc 35 14+2 4.5 4.5 1950 WK/MNP/EX/S1.28-BP22-23/(1)FC30 8 12-Jul-22 2-Aug-22 36.59
(Stage-1)
S1.27-BP19 & S1.27-BP20
Witon Extension Pile Fc 35 14+2 4.5 4.5 1954.5 WK/MNP/EX/S1.27-BP19-20/(1)FC30
(Stage-1)

103 7-Jul-22 S1.29-BP25 & S1.29-BP26 8 14-Jul-22 4-Aug-22 33.60


Witon Extension Pile Fc 35 14+2 3.5 3.5 1958 WK/MNP/EX/S1.29-BP25-26/(2)FC30
(Stage-2)

S1.26-BP16 (Stage-1) Witon Extension Pile Fc 35 14+2 2.5 2.5 1960.5 WK/MNP/EX/S1.26-BP16/(1)FC30

104 8-Jul-22 Borepile S1.1-BP15 Witon Borepile Fc 35 18+2 10.6 11 1971.5 WK/MNP/S1.1-BP15/FC30 8 15-Jul-22 5-Aug-22 35.89

105 8-Jul-22 Borepile S1.2-BP17 Witon Borepile Fc 35 18+2 10.6 11 1982.5 WK/MNP/S1.2-BP17/FC30 8 15-Jul-22 5-Aug-22 35.13

106 8-Jul-22 S1.26-BP17 (Stage-1) Witon Extension Pile Fc 35 14+2 2.5 3 1985.5 WK/MNP/EX/S1.26-BP17/(1)FC30 8 15-Jul-22 5-Aug-22 37.38

107 8-Jul-22 Borepile S1.3-BP19 Witon Borepile Fc 35 18+2 10.6 11 1996.5 WK/MNP/S1.3-BP19/FC30 8 15-Jul-22 5-Aug-22 35.86

108 9-Jul-22 Borepile S1.4-BP21 Witon Borepile Fc 35 18+2 10.6 11 2007.5 WK/MNP/S1.4-BP21/FC30 8 16-Jul-22 6-Aug-22 36.92

109 9-Jul-22 Borepile S1.5-BP23 Witon Borepile Fc 35 18+2 10.6 11 2018.5 WK/MNP/S1.5-BP23/FC30 8 16-Jul-22 6-Aug-22 34.48

110 11-Jul-22 Borepile S1.6-BP25 Witon Borepile Fc 35 18+2 10.6 11 2029.5 WK/MNP/S1.6-BP25/FC30 8 18-Jul-22 8-Aug-22

S1.25-BP13 & S1.25-BP14


111 11-Jul-22 Witon Extension Pile Fc 35 14+2 4.5 4.5 2034 WK/MNP/EX/S1.25-BP13-14/(1)FC30 8 18-Jul-22 8-Aug-22
(Stage-1)

112 11-Jul-22 Borepile S1.7-BP27 Witon Borepile Fc 35 18+2 10.6 11 2045 WK/MNP/S1.7-BP27/FC30 8 18-Jul-22 8-Aug-22

113 12-Jul-22 Borepile S1.8-BP29 Witon Borepile Fc 35 18+2 10.6 12 2057 WK/MNP/S1.8-BP29/FC30 8 19-Jul-22 9-Aug-22

114 12-Jul-22 Borepile S1.9-BP31 Witon Borepile Fc 35 18+2 10.6 11 2068 WK/MNP/S1.9-BP31/FC30 8 19-Jul-22 9-Aug-22

115 12-Jul-22 Borepile S1.10-BP33 Witon Borepile Fc 35 18+2 10.6 11 2079 WK/MNP/S1.10-BP33/FC30 8 19-Jul-22 9-Aug-22

116 12-Jul-22 Borepile S1.11-BP35 Witon Borepile Fc 35 18+2 10.6 11 2090 WK/MNP/S1.11-BP35/FC30 8 19-Jul-22 9-Aug-22

S1.28-BP22 & S1.28-BP23


WK/MNP/EX/S1.28-BP22-23/(2)FC30
(Stage-2)
117 12-Jul-22 Witon Extension Pile Fc 35 14+2 4.5 4.5 2094.5 8 19-Jul-22 9-Aug-22
S1.27-BP19 & S1.27-BP20
WK/MNP/EX/S1.27-BP19-20/(2)FC30
(Stage-2)
MONITORING PENGECORAN DAN BENDA UJI BETON PROYEK JALAN AKSES TOL MNP
VOLUME VOLUME VOLUME JUMLAH
TANGGAL SUPPLAIR MUTU Slump Tanggal Pengujian Rata2 Hasil Uji
No. LOKASI/POSISI ITEM PEKERJAAN RENCANA REALISASI KUMULATIF KODE BENDA UJI BENDA KET
COR BETON BETON
(cm) (m³) (m³) (m³) UJI 7 HARI 28 HARI 7 HARI 28 HARI
118 12-Jul-22 Borepile S1.12-BP37 Witon Borepile Fc 35 18+2 10.6 11 2105.5 WK/MNP/S1.12-BP37/FC30 8 19-Jul-22 9-Aug-22

119 13-Jul-22 Borepile S1.13-BP39 Witon Borepile Fc 35 18+2 10.6 11 2116.5 WK/MNP/S1.13-BP39/FC30 8 20-Jul-22 10-Aug-22

120 13-Jul-22 Borepile S1.14-BP41 Witon Borepile Fc 35 18+2 10.6 11 2127.5 WK/MNP/S1.14-BP41/FC30 8 20-Jul-22 10-Aug-22

121 13-Jul-22 Head BP P1.10-B Witon - Fc 40 10+2 3 3 2130.5 - 8 20-Jul-22 10-Aug-22

122 13-Jul-22 Borepile S1.15-BP43 Witon Borepile Fc 35 18+2 10.6 11 2141.5 WK/MNP/S1.15-BP43/FC30 8 20-Jul-22 10-Aug-22

123 13-Jul-22 Borepile S1.16-BP45 Witon Borepile Fc 35 18+2 10.6 11 2152.5 WK/MNP/S1.16-BP45/FC30 8 20-Jul-22 10-Aug-22

124 14-Jul-22 Borepile S1.17-BP47 Witon Borepile Fc 35 18+2 10.6 11 2163.5 WK/MNP/S1.17-BP47/FC30 8 21-Jul-22 11-Aug-22

125 14-Jul-22 Borepile S1.14-BP42 Witon Borepile Fc 35 18+2 10.6 11 2174.5 WK/MNP/S1.14-BP42/FC30 8 21-Jul-22 11-Aug-22

126 14-Jul-22 Borepile S1.17-BP48 Witon Borepile Fc 35 18+2 10.6 11 2185.5 WK/MNP/S1.17-BP48/FC30 8 21-Jul-22 11-Aug-22

127 14-Jul-22 Borepile S1.13-BP40 Witon Borepile Fc 35 18+2 10.6 11 2196.5 WK/MNP/S1.13-BP40/FC30 8 21-Jul-22 11-Aug-22

128 14-Jul-22 Borepile S1.16-BP46 Witon Borepile Fc 35 18+2 10.6 11 2207.5 WK/MNP/S1.16-BP46/FC30 8 21-Jul-22 11-Aug-22

129 15-Jul-22 Borepile S1.12-BP38 Witon Borepile Fc 35 18+2 10.6 11 2218.5 WK/MNP/S1.12-BP38/FC30 8 22-Jul-22 12-Aug-22

130 15-Jul-22 Borepile S1.15-BP44 Witon Borepile Fc 35 18+2 10.6 11 2229.5 WK/MNP/S1.15-BP44/FC30 8 22-Jul-22 12-Aug-22

131 15-Jul-22 TRIAL RIGID Witon - Fc 40 10+2 7 7 2236.5 - 6 22-Jul-22 12-Aug-22

132 15-Jul-22 Borepile S1.8-BP30 Witon Borepile Fc 35 18+2 10.6 11 2247.5 WK/MNP/S1.8-BP30/FC30 8 22-Jul-22 12-Aug-22

133 15-Jul-22 Borepile S1.11-BP36 Witon Borepile Fc 35 18+2 10.6 11 2258.5 WK/MNP/S1.11-BP36/FC30 8 22-Jul-22 12-Aug-22

S1.25-BP13 & S1.25-BP14


WK/MNP/EX/S1.25-BP13-14/(2)FC30
(Stage-2)
134 16-Jul-22 Witon Extension Pile Fc 35 14+2 7 6.5 2265 8 23-Jul-22 13-Aug-22
S1.26-BP16 & S1.26-BP17
WK/MNP/EX/S1.26-BP16-17/(2)FC30
(Stage-2)

135 16-Jul-22 Borepile S1.10-BP34 Witon Borepile Fc 35 18+2 10.6 11 2276 WK/MNP/S1.10-BP34/FC30 8 23-Jul-22 13-Aug-22

136 16-Jul-22 Borepile S1.1-BP16 Witon Borepile Fc 35 18+2 10.6 11 2287 WK/MNP/S1.1-BP16/FC30 8 23-Jul-22 13-Aug-22

137 16-Jul-22 Borepile S1.2-BP18 Witon Borepile Fc 35 18+2 10.6 11 2298 WK/MNP/S1.2-BP18/FC30 8 23-Jul-22 13-Aug-22

138 16-Jul-22 TRIAL RIGID Witon - Fs 4.5 6+2 7 7 2305 - 6 23-Jul-22 13-Aug-22

139 16-Jul-22 Borepile S1.3-BP20 Witon Borepile Fc 35 18+2 10.6 11 2316 WK/MNP/S1.3-BP20/FC30 8 23-Jul-22 13-Aug-22

S1.36-BP47& BP48
WK/MNP/EX/S1.36-BP47-48/(1)FC30
( Stage-1 )

140 17-Jul-22 S1.37-BP49 & BP 50 Witon Extension Pile Fc 35 14+2 6.5 6.5 2322.5 8 24-Jul-22 14-Aug-22
WK/MNP/EX/S1.37-BP49-50/(1)FC30
( Stage-1 )
S1.35-BP44, BP45 & BP46
WK/MNP/EX/S1.35-BP44-45-46/(1)FC30
( Stage-1 )

141 17-Jul-22 Borepile S1.4-BP22 Witon Borepile Fc 35 18+2 10.6 11 2333.5 WK/MNP/S1.4-BP22/FC30 8 24-Jul-22 14-Aug-22

142 17-Jul-22 Borepile S1.5-BP24 Witon Borepile Fc 35 18+2 10.6 11 2344.5 WK/MNP/S1.4-BP22/FC30 8 24-Jul-22 14-Aug-22

143 17-Jul-22 Borepile S1.6-BP26 Witon Borepile Fc 35 18+2 10.6 11 2355.5 WK/MNP/S1.6-BP26/FC30 8 24-Jul-22 14-Aug-22

144 17-Jul-22 Borepile S1.7-BP28 Witon Borepile Fc 35 18+2 10.6 12 2367.5 WK/MNP/S1.7-BP28/FC30 8 24-Jul-22 14-Aug-22
MONITORING PENGECORAN DAN BENDA UJI BETON PROYEK JALAN AKSES TOL MNP
VOLUME VOLUME VOLUME JUMLAH
TANGGAL SUPPLAIR MUTU Slump Tanggal Pengujian Rata2 Hasil Uji
No. LOKASI/POSISI ITEM PEKERJAAN RENCANA REALISASI KUMULATIF KODE BENDA UJI BENDA KET
COR BETON BETON
(cm) (m³) (m³) (m³) UJI 7 HARI 28 HARI 7 HARI 28 HARI
145 17-Jul-22 Borepile S1.9-BP32 Witon Borepile Fc 35 18+2 10.6 11 2378.5 WK/MNP/S1.9-BP32/FC30 8 24-Jul-22 14-Aug-22

146 18-Jul-22 Borepile S1.18-BP49 Witon Borepile Fc 35 18+2 10.6 11 2389.5 WK/MNP/S1.18-BP49/FC30 8 25-Jul-22 15-Aug-22

147 18-Jul-22 Borepile S1.19-BP51 Witon Borepile Fc 35 18+2 10.6 11 2400.5 WK/MNP/S1.19-BP51/FC30 8 25-Jul-22 15-Aug-22

148 18-Jul-22 Borepile S1.20-BP53 Witon Borepile Fc 35 18+2 10.6 11 2411.5 WK/MNP/S1.20-BP53/FC30 8 25-Jul-22 15-Aug-22

149 18-Jul-22 Borepile S1.18-BP50 Witon Borepile Fc 35 18+2 10.6 11 2422.5 WK/MNP/S1.18-BP50/FC30 8 25-Jul-22 15-Aug-22

150 18-Jul-22 Borepile S1.20-BP54 Witon Borepile Fc 35 18+2 10.6 11 2433.5 WK/MNP/S1.20-BP54/FC30 8 25-Jul-22 15-Aug-22

S1.36-BP47& BP48
WK/MNP/EX/S1.36-BP47-48/(2)FC30
( Stage-2 )
S1.37-BP49& BP50
WK/MNP/EX/S1.37-BP49-50/(2)FC30
( Stage-2 )
151 19-Jul-22 Extension Pile Fc 35 14+2 11 11 2444.5 8 26-Jul-22 16-Aug-22
S1.35-BP43,44& BP45
WK/MNP/EX/S1.35-BP43,44-45/(2)FC30
( Stage-2 )
S1.34-BP40,41& BP42
WK/MNP/EX/S1.34-BP41-42/(1)FC30
( Stage-1 )

152 19-Jul-22 Borepile S1.19-BP52 Witon Borepile Fc 35 18+2 10.6 11 2455.5 WK/MNP/S1.19-BP52/FC30 8 26-Jul-22 16-Aug-22

153 19-Jul-22 LC Ext.Pile Witon - Fc 10 10+2 3 3 2458.5 - 8 26-Jul-22 16-Aug-22

You might also like