1. Technical Part
1.1 Engineering& Project management
1.2. Construction
1.3. HSE
1.4. Permitting:
1 N/A
2 N/A
1.5. Schedule
Organization Chart
1
Project Control
2
Document Control
3
Clarify by Owner
No QA/QC plan
No Construction Execution Plan
No Operation Plan
Clarify by Owner
Contractor shall align with the AP Five Star Behavioural Program for disciplinary action /
reward.
Contractor to plan and execute a formal EH&S audit on a quarterly basis. Contractor to
align with AP EH&S Audit work process.
Contractor to meet a ratio of 1 Safety Person for every 25 workers (1:25 ratio).
Any Work at height (above 1.8M, but below 6m), requires a personal inertia unit to be
incorporated into the body harness.
Clarify by Owner
Contractor to ensure that any persons are trained, competent and medically fit, prior to
entering a confined space.
All tools and equipment on Site shall be inspected by a competent person, included in a
register and colour coded. Contractor to align with AP Control of Temporary Plant and
Equipment procedure.
Safety shoes (under ankle) are not permitted at Site. Please refer to AP requirements in
EH&S Plan. Safety boots shall be used 'above' ankle with laces.
Any extended shifts / night shift works will require a dedicated Lighting Plan. The Plan
must include illumination levels for the different work activities / locations. Contractor
shall procure a luxmeter to assure compliance with the approved Lighting Plan.
Clarify by Owner
Contractor shall align with the AP Incident Reporting and Investigation procedure.
Contractor to ensure that any persons nominated to be part of the integrated Site
Emergency Response Team are trained and competent, prior to being nominated.
Contractor shall comply with AP Electronic Document Management System (Open Text
system) and AP Document Control Procedures.
Clarify by Owner
Information
NA
Contractor to confirm.
1 Organization chart
2 Project Control