QUOTATION OF BILL OF MATERIALS & LABOR

FOR TRUSSES & COLOR ROOFING

AREA:
L: 800 cm / 780 cm
W: 1,120 cm / 380 cm
H: 1.10 cm
TRUSSES:
ANGLE BAR 3/16 X 2 X 6m. 35 LENGTH 31,850
ANGLE BAR 3/16 X 1 ½ X 6m. 35 LENGTH 19,950
FLAT BAR 3/16 X 1 X 6m. 20 LENGTH 4,800
C- PURLINS 2X3X 6m. 1.2 60 LENGTH 37,380
WELDING ROD FUJI 6012 25 KLS. 3,100
PRIMER RED OXIDE 2 KLS. 1,220

ACC. CONSUMABLES
CUT OF WHEEL #4
PAINT BRUSH
GRINDING DISC
5,000
ROOFING: 150 LM (.40)
COLOR ROOFING (DESIRED COLORED) 63,000
GUTTER 22,000
FASIA PLATE 22,000
RIDGE ROLL 11,760
ACC. CONSUMABLES
TEX SCREW
CUT OF WHEEL #4 3,500
TOTAL AMOUNT 225,560
MANPOWER /
LABOR COST 35% 78,946
MARK UP 15% 33,834
GRAND TOTAL AMOUNT 338,340

NOTE: 50% DOWN PAYMENT UP TO


75% AND THE REST
25% FINISH CONTRACT

WALTER P. / EDDIE C.
OWNER / RESIDENTIAL PRIVATE CONTRACTOR