Client:

SITE ACCEPTANCE REPORT


TRANSFORMER
PROTECTION RELAY

System : Transformer Differential Relay


Consultant:
Sr. No : Order Code:

PO No : Date : Page 1 of 4

INSPECTION AND SECONDARY INJECTION OF MULTIFUNCTION RELAY-

RELAY DETAILS
RELAY ANSI NO. 87T RELAY FUNCTION Trafo Diff

RELAY MAKE NOMINAL CURRENT


TYPE / STYLE AUX SUPPLY VOLTAGE 110 VDC

Visual and Mechanical inspection:

Item Description Checked

1 Check Name Plate data according to the drawings and specifications OK


2 Check For Transportation damage and correct positioning OK
3 Verify tightness of external wiring OK

Electrical Checks:
Item Description Checked
1 All connections checked according to the wiring diagram Ok
2 Auxiliary power supply checked for rating and polarity Ok
3 CT Shorting Checked Ok
4 Test Switch function Checked Ok
5 LEDs checked OK
6 Binary Input functions checked OK
7 Binary output functions checked Ok
8 Casing earth checked Ok

COMPANY THE FABRICATOR CHINT NESPAK NTDC


NAME
SIGNATURE
DATE
Client:

SITE ACCEPTANCE REPORT


TRANSFORMER
PROTECTION RELAY

System : Transformer Differential Relay


Consultant:
Sr. No : Order Code:

PO No : Date : Page 2 of 4

INSPECTION AND SECONDARY INJECTION OF MULTIFUNCTION RELAY-----

MEASUREMENTS:-
(3Phase Injection)

I.CURRENT MEASURMENT:

C.T RATIO:
INJ. EXP. MEASURMENT MEASURED VALUE
CURRENNT (A) (A)
A B C N

II. VOLTAGE MEASURMENT:

P.T RATIO:
INJ. EXP. MEASURMENT MEASURED VALUE
VOLTAGE (V) (V)
A B C N

1. 87T – TIMING TEST

Sr. SETTING
ACTUAL
No. ACTUAL
Idiff Tdiff TIME REMARK
CURRENT
1
2
3

COMPANY THE FABRICATOR CHINT NESPAK NTDC


NAME
SIGNATURE
DATE
Client:

SITE ACCEPTANCE REPORT


TRANSFORMER
PROTECTION RELAY

System : Transformer Differential Relay


Consultant:
Sr. No : Order Code:

PO No : Date : Page 3 of 4

2. 87T – SLOPE TEST

Sr. SETTING ACTUAL


TRIP
No. CURRENT Ibias Idiff
STATUS REMARK
LV
Is1 K1 Is2 K2 HV
1
2
3

3. OVER CURRENT – 51T

Sr. SETTING
Expected ACTUAL
No. ACTUAL
I> tI> Time TIME REMARK
CURRENT
1
2
3

4. REF – 64

Sr. SETTING
Expected ACTUAL
No. ACTUAL
I> tI> Time TIME REMARK
CURRENT
1
2
3

5. VOLT PROTECTION – 27, 59

Sr. SETTING
Expected ACTUAL
No. ACTUAL
V> t V> Time TIME REMARK
VOLTAGE
1
2
3

COMPANY THE FABRICATOR CHINT NESPAK NTDC


NAME
SIGNATURE
DATE
Client:

SITE ACCEPTANCE REPORT


TRANSFORMER
PROTECTION RELAY

System : Transformer Differential Relay


Consultant:
Sr. No : Order Code:

PO No : Date : Page 4 of 4

Sr. SETTING
Expected ACTUAL
No. ACTUAL
V< t V< Time TIME REMARK
VOLTAGE
1
2
3

6. FREQUENCY PROTECTION – 81F

Sr. SETTING
Expected ACTUAL
No. ACTUAL
F> t F> Time TIME REMARK
FREQUENCY
1
2
3

Sr. SETTING
Expected ACTUAL
No. ACTUAL
F< t F< Time TIME REMARK
FREQUENCY
1
2
3

7. INPUT CHECK
OPTO NO. Allocation Results
OPTO 1
OPTO 2
OPTO 3
OPTO 4
OPTO 5
OPTO 6
OPTO 7
OPTO 8

COMPANY THE FABRICATOR CHINT NESPAK NTDC


NAME
SIGNATURE
DATE
Client:

SITE ACCEPTANCE REPORT


TRANSFORMER
PROTECTION RELAY

System : Transformer Differential Relay


Consultant:
Sr. No : Order Code:

PO No : Date : Page 5 of 4

8. LED CHECK
LED NO. Allocation Results
LED H1
LED H2
LED H3
LED H4
LED H5
LED H6
LED H7
LED H8

Test Equipments Used:

Test Device:
Serial Number:
Make & Model:

COMPANY THE FABRICATOR CHINT NESPAK NTDC


NAME
SIGNATURE
DATE