You are on page 1of 1

Quality Control/Quality Assurance Procedure – AVIC – Astoria Residential Development Project

Pile Point Setting out Casing Setting out Soil Boring


• Done only with a licensed surveyor present on site • Pile Co-ordinates and casing verticality are checked by the contrator and are • Samples are inspected to determine the soil quality
• Pile point co-ordinates are observed, recorded and verified after cross observed and recorded in checklists
checking with license surveyor approved drawing
• Check the 10m radius, for ongoing/concreted piles within 48 hours before
approval is given to start boring

Reinforcement Cage Termination Rock Socketing


• The length of the RF cage is pre-calculated against the current depth of pile • After the pre-determined minimum socketing depth is achieved the final • According to the soil investigation report, the rock quality designation is
and the cut off level and is checked on site rock quality is inspected and after evaluating the boring log data the final evaluated and a contour map is developed to help determine the socketing
• The number of bars are checked against the issued structural drawings termination is determined by a senior structural engineer level
• Welding the required lap length and installation of the completed RF cage is • After termination is given the contractor is instructed to check the pile co- • Upon reaching rock start samples are visually inspected and casing top level
inspected ordinates for the 3rd time to make sure the pile location is unchanged. this is is recorded in checklists
• Link diameter & pitch is checked observed and recorded in the checklist • Bentonite level is monitored visually at site and kept well above the casing
bottom level
• Samples at every 500mm interval are inspected and related data are
recorded in a boring log

Pile well cleaning Concreting Casing removal/Concreted borehole filling/Concrete Testing


• A bentonite cycling system is used for this purpose and to ensure the quality • Concrete quantity is recorded in checklists along with • After the termination of concrete the casing removal is monitored visually to
of the cleaning process the density and viscosity of bentonite is monitored at slump/flow/temperature data make sure no tilting of casing takes place
the start and end of the cleaning process. These values are recorded in • Number of trucks and pouring sequence is also monitored and recorded for • Concreted borehole is filled with soil and a barricade tape is used to protect
checklists and the engineer determines the termination of cleaning if the quality control purposes the area
said values are well within pre-determined limits • Minimum of 10 test cubes are cast for each pile for testing • 2 cubes will be tested at 7 days and 6 cubes will be tested at 28 days to
• The pile toe level is checked agaist the values recorded in the boring log to • Tremie removal sequence is monitored and recorded determine the specified concrete strength is achieved
make sure no colapsing of soil has occured
• Final concrete level is measured on site between unloaded concrete trucks
• Casing top level is also checked to make sure no variation in that level has
• After the required concrete fill level is achieved the concrete is terminated
influenced the recorded depth values
• The co-ordinates are checked by the contractor again and is observed and
• The cleaning condition of the pile toe is also checked by dropping a weighted
recorded in relevant checklists by the consultant
cable and tapping on the bedrock to make sure no soft layer is deposited on
the bedrock before concreting is commenced

You might also like