Professional Documents
Culture Documents
Page 2 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
TABLE OF CONTENTS
1.0 SCOPE:…..………..……………………………….……………………………………….…..4
2.0 Purpose:……………………………….………………………………………………………..4
3.0 REFERENCES………………………………………..…………………………………...……4
3.1 Company HSSE Documents:………………………...……………………...……… 4
3.2 UJV HSSE Documents:………………………………………………………………..5
4.0 DEFINITIONS and ABBREVIATIONS……………………………………...…………...5
4.1 Definitions: …………………………………………...………………………………...5
4.2 Abbreviations…………………………………………………………………………..16
5.0 resposibilities & Authority………………………………………………………………17
5.1 SMME & Health, Safety, Security & Environment Manager…………………….17
5.2 Project/Construction Manager/Site Manager……………………………………..17
5.3 HSSE Manager………………………………………………………………………….17
5.4 Scaffold Manager/Senior/Superintendent (UJV & Subcontractor)……………17
5.5 Scaffolding Supervisor (UJV & Subcontractor)………………………………….18
5.6 Scaffolder (Subcontractor)…………………………………………………………..19
5.7 Scaffolding Inspector (UJV & Subcontractor)……………………………………19
5.8 Subcontractors…………………………………………………………………………19
6.0 TRAINING ASSESSMENT AND CERTIFICATION……………………………………19
7.0 General Instructions…………..…………………………………………………………20
7.1 GENERAL STANDARDS/REQUIREMENTS………………………..………………22
7.2 SCAFFOLD COMPONENTS……………………………………….…………………29
7.3 REQUIREMENTS COMMON TO ALL SCAFFOLDS……….……………………..34
7.4 REQUIREMENTS COMMON TO SYSTEM AND TUBE AND COUPLER…..…..46
SCAFFOLDS
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 3 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 4 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
1.0. SCOPE:
This procedure shall apply to all scaffolding activities on the CFP Project.
Procedure/Document is a controlled copy, only the Originator (Scaffolding
Subject Matter Expert)/UJV HSSE Approving Body has the authority to
amend/change/update this document and communicate his comments and
observations to the Originator (SSME) for review and incorporation as
applicable. HSSE Management will verify and cohabit with the SSME and
then send to the Project Management for approval.
2.0. Purpose:
This procedure covers the design, erection, modification, use and
dismantling of temporary elevated work areas and supported or under hung
scaffolds with fixed platform heights. The types of scaffolds covered in this
section are those commonly used within CFP facilities ( green field and
brown field), including tube and coupler, system, underhung, and manually
propelled mobile scaffolds.
The purpose of this procedure is to set standards for materials, erection,
modification, dismantling, use and inspection of the scaffolding.
This procedure sets the standards and recommendation to observe the
safety of all employees involved in erecting and working from scaffolds.
3.0. REFERENCES:
Page 5 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Base Plate A steel plate providing a flat bearing surface with a spigot or screw-
jack for distributing the load from standards It has an integral spigot
and fixing holes for use with sills. See Figure II.9.2 and Figure
II.9.3.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 6 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Structural Transom A transom scaffold member, from Standard to standard under the
ledger that may support platform units, and which is supported by
using Double/Right Angle Couplers ONLY, two ledgers or
connected directly to two standards. See Figure II.9.1 and Figure
II.9.3.
Cross Bracing Two diagonal braces joined at their center to form an “X.” Also
called “X” bracing or cross braces. connecting the inner and outer
ledgers with right angle couplers or the inner and outer standards
with swivel couplers fixed within 150mm from Node Point. See
Figure II.9.3 and Figure II.9.3.
Swivel Coupler A device used for connecting two tubes together at an angle other
than 90°. See Figure II.9.8. Swivel Coupler will not be allowed to be
used as load bearing coupler on Ledgers or Handrails.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 7 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Coupler A device used for fixing a transom to a ledger: See Figure II.9.13.
(Single or Putlog)
Sleeve Coupler A device used for externally joining two (2) scaffold tubes co-axially
end to end. The steel divider is located centrally to ensure equal
insertion of each tube. See Figure II.9.9.
Beam/Girder Coupler A device used for connecting a scaffold tube to a steel wide flange
beam (I-beam). Beam/Girder couplers shall only be used in pairs,
one on each opposite flange. Also called an “SK” (Steel-klamp).
See Figure II.9.16.
Band and Plate A coupler used for joining tubes at an angle other than a right angle
Coupler: (Double) Couplers
Diagonal Brace A scaffold tube placed diagonally with respect to the vertical and
horizontal members of a scaffold and fixed to them to give the
scaffold stability within 150mm from Node Point.
Facade (Sway) Diagonal braces Parallel to the building or area façade, either fixed
Bracing or installed to the standards using swivel couplers or connected to
the extended transoms with right angle couplers, every 4 bays
longer dimension (length) of the scaffold and fixed within 300mm
from Node Point. See Figure II.9.3 and Figure II.9.4.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 8 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Intermediate Transom A horizontal transverse scaffold tube upon which the scaffold
platform partially rests. Board transoms are supported by ledgers
and are not installed near a transverse line of standards. See Figure
II.9.2 and Figure II.9.4.
Ledger Brace Diagonal tubes connecting the inner and outer ledgers with right
angle couplers or the inner and outer standards with swivel couplers
every alternative standards longer dimension (length) of the scaffold
and fixed within 300mm from Node Point. See Figure II.9.1 and
Figure II.9.4.
Metal Scaffold Board A Metal Scaffold Board unit equipped with end hooks that engage
the scaffold transom. See Figure II.9.17.
Transom Horizontal tubes fixed above the ledgers and using putlog couplers
or double couplers, supporting the boards within 300mm from
standards. See Figure II.9.1 and Figure II.9.3.
Zigzag(Dog-leg) Diagonal braces placed end-to-end and that alternate back and forth
Bracing and within 150mm from Node Point See Figure II.9.4.
Full Body Harness A design of straps that may be secured about an individual in a
manner to distribute the fall arrest forces over the thighs, pelvis,
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 9 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Guys Tension members (i.e., wire ropes) used between the scaffold and
the ground, building, or structure to enhance the scaffold’s lateral
stability.
Hanger Tube Vertical tube similar to and serving the same load-carrying purpose
as standards, except that hanger tubes are hung from an existing
structure and loaded in tension. Distance from Node point must not
exceed 300mm. See Figure II.9.34.
Joint Pin (Expanding An expanding fitting placed in the bore of a scaffold standard to
Spigot) connect one standard to another coaxially. This device is used to
connect standards in tube and coupler scaffolds vertically and
handles compression, but not tension, loads. See Figure II.9.14
Shock-absorbing A specially designed lanyard with a built-in shock absorber (to allow
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 10 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Base Lift A lift erected near to the ground consisting of the first set of ledgers
and transoms. Also known as “foot lift”, “foot tie”, and “kicker lift.”
Lift Head Room The clear distance between a platform and the tubular assembly of
the lift above.
Lift Height The vertical distance between two lifts and is similar to a story in a
building.
Load Rating Live load for scaffold design and maximum intended loading shall
be per the following categories
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 11 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Light Duty Scaffold designed and constructed to carry the weight of light
materials, tools and workmen. Uniformly distributed maximum
intended load is 150 kg/m² (1.5 kN/m²) (50 lb/ft²). (See Attachment
6: Scaff Tag Page: 1234)
Medium Duty Scaffold designed and constructed to carry the weight of light
materials, tools and workmen. Uniformly distributed maximum
intended load is 200 kg/m² (2.0 kN/m²) (50 lb/ft²). (See Attachment
6: Scaff Tag Page: 1234)
Heavy Duty Scaffold designed and constructed to carry the weight of light
materials, tools and workmen. Uniformly distributed maximum
intended load is 250kg/m² (2.5 kN/m²) (50 lb/ft²). (See Attachment 6:
Scaff Tag Page: 1234)
Maximum Intended The maximum load of all persons, equipment, tools, materials,
Load transmitted loads, and other live loads reasonably anticipated to be
applied to a scaffold or scaffold component at any one time (does
not include scaffold or plank self-weight).
Node Point A theoretical intersection point where two or more members are
connected together, although they are not actually in the same
place, usually the intersections between a standard and a ledger, or
a standard and structural transom. See Figure II.9.56
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 12 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Outrigger Beam A cantilevered structural member that supports a scaffold where the
point of attachment to the scaffold is out and away from the face of
the structure or building.
Platform An elevated work area composed of one or more platform units and
a guardrail system. See Figure II.9.4
Standards Vertical scaffold tube that bears the weight of the scaffold. See
Figure II.9.1.
Puncheon (False A vertical tube supported at its lower end by another scaffold tube
Standard) or beam and not by the ground or deck. See Figure II.9.54.
Raker An inclined load bearing tube that braces the scaffold against the
ground. See Figure II.9.22.
Reveal Tie An assembly of a reveal tube, reveal pin, and pads, if required, fixed
between opposing faces of an opening in a wall to provide an
anchor point for scaffold tie tubes. See Figure II.9.21.
Reveal Pin A fitting used for tightening a reveal tube between two opposing
surfaces. See Figure II.9.11.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 13 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Reveal Tube A tube fixed by means of a threaded fitting (reveal pin) between two
opposing surfaces of a building or structure to form a solid
anchorage to which a scaffold may be tied. See Figure II.9.20.
Birdcage Scaffold A scaffold with more than two lines of standards or hanger tubes (if
underhung) across the width of the scaffold.
Bracket (Tank A scaffold supported by bracket straps welded to the tank wall.
Builder’s) Scaffold Upright brackets are hooked to the straps. See Figure II.9.26
Independent Run A scaffold that has two lines of standards, one line supporting the
(Façade or outside of the scaffold platform(s) and one line supporting the inside
Independent Tied) of the platform(s). The transoms are not built into the wall of the
Scaffold building. It is usually tied to the building for stability. See Figure
II.9.4.
Mobile Scaffold A rigid scaffold assembly supported by casters that can be manually
moved horizontally. See Figures II.9.27 and II.9.30.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 14 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
System Scaffold A scaffold consisting of standards with fixed connection points that
accept ledgers, transoms, and braces that can be interconnected at
predetermined levels. See Figure II.9.31.
Tower Scaffold A supported scaffold consisting of only four (4) standards connected
together longitudinally with ledgers and transoms at right angles to
each other, forming a square or rectangular tower. A tower scaffold
may be constructed of tube and coupler, or system scaffolding. See
Figure II.9.33.
Tube and Coupler A scaffold constructed of steel tubing that serves as standards,
Scaffold ledgers, transoms, braces, and ties; a base supporting the
standards; and specially designed scaffold couplers that serve to
connect the various members. See Figures II.9.3.
Sill (Sole Board or A timber spreader used to distribute the load from a base plate to
Sole Plate) the softer ground such as soil, sand or asphalt. See Figure II.9.1
and Figure II.9.2.
Special Scaffold A scaffold that meets any of the following conditions and for which a
structural engineering review of the scaffold plan is required:
Page 15 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
4. Over 30 sq. meters (320 sq. ft.) total platform area and
supported by or hung from an existing structure or building
(e.g., roof, pipe rack, offshore platform), or
Spigot Pin A pin or bolt placed transversely through the spigot and the scaffold
standard to prevent the spigot from pulling out of the tube. Also
known as tension pin, dowel pin, and coupling pin. See Figure
II.9.15.
Page 16 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Tie Tube A tube used to connect the scaffold to a tie anchor point (i.e., box
tie, reveal tie, two-way tie). See Figure II.9.21.
Trapeze Tube A horizontal scaffold tube measuring between 450 and 600 mm (1m
to 1.5m) in length and installed at the bottom portion of the hanger
tubes approximately three feet beneath the ledgers. It is used in
erection, modification, and dismantling of an underhung scaffold. It
also serves as a secondary support if the runner slips. See Figure
II.9.34.
4.2. Abbreviations:
Page 17 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
5.0. RESPONSIBILITIES:
5.1. SSME & Health, Safety, Security & Environment Manager is responsible for
the development of this procedure and monitoring compliance.
• Ensure that all scaffolders are aware of and work in compliance to best
industry practice for the erection of scaffolds.
• Arrange for and provide adequate training, in co-operation with the UJV
HSSE Manager.
• Liaise with the engineering group for designing any special and purpose
built scaffolds.
• Ensure that materials are checked before use and are of sound condition.
Page 18 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Ensure all scaffold personnel have valid Third Party Inspection training
certificates and deemed competent
• Ensure that all scaffolding personnel under his authority fully comply with
this procedure and PTW requirements.
• Ensure that all scaffolding is erected to the standards in this scaffolding
procedure, must inform the scaffolding inspector when the scaffold is
ready for inspection
• Scaffolding Supervisor on the CFP Project will not be a scaffolding
inspector.
• Shall have valid TP certification and competent
• Supervisors minimum 7 years ‘proven experience CISRS supervision
certificate/ with scaffolding experience
Page 19 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
5.8. Subcontractors
• All scaffolding work in shall be covered under the Permit to Work (PTW)
System.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 20 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Materials
• Tubes, System, timbers etc. shall be straight to the eye and shall be free
of cracks, splits, excessive corrosion or other defects. The ends shall be
cut square with the axis of the tube.
• All scaffold material brought onto CFP project shall be approved by UJV,
substandard scaffold material not meeting industry standards shall not be
permitted.
Page 21 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Scaffolding Boards
• Scaffolding boards are not acceptable if they have a knot larger than
50mm diameter.
• Edge knots shall not exceed 50% of the thickness of the board.
• There shall be no cut outs (checks), burns, oil stains or projecting nails.
• Boards shall not be painted or treated in any other way which may conceal
defects.
• Boards shall be secured to the scaffolding transom with board clamps only
Page 22 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Guardrail Systems
Page 23 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 24 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• At hoisting areas, a guardrail system at least 1.2 meters (4 feet) long shall
be erected (if possible) on each side of the access point through which
material is hoisted. A chain or gate shall be properly secured across the
opening between the guardrail sections when hoisting operations are not
taking place.
Page 25 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Ladder shall extend at least 1 meter (3 ft) above the platform or platforms
shall be provided with adequate grab-rails and be so positioned to permit
direct platform access/egress.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 26 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Whenever the horizontal travel distance to the nearest exit (i.e., ladder)
exceeds 15 meters (50 feet), each elevated work area shall have at least
two means of exit. A means of exit shall be provided at least every 30
meters (100 feet).
• Temporary Stairways
• Temporary stairways shall have landings at not more than every 3.7
meters (12 feet) of vertical rise. Such landings shall be at least 760 mm
(30 inches) long, in the direction of travel, and be at least 600 mm (23.5
inches) wide.
Page 27 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Riser height and tread depth shall be uniform within each flight of stairs,
including any foundation structure used as one or more treads of the
stairs. In any stairway system, variations in riser height and tread depth
shall not be over 6 mm (¼-inch).
• Temporary stairways having four or more risers or rising more than 760
mm (30 inches) in height, whichever is less, shall have a sloping handrail
and mid-rail system on all open sides, or one (1) handrail on enclosed
stairways on the right-side descending.
• The height of handrails for temporary stairways shall not be more than
1.150 mm (42 inches) nor less than 950 mm (38 inches) from the upper
surface of the handrail to the surface of the tread, in line with the face of
the riser at the forward edge of the tread. Mid-rails shall be located at a
height midway between the handrail and the stairway steps.
Page 28 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Temporary Ramps
• Ramps and walkways 1.8 meters (6 feet) or more above lower levels
shall have guardrail systems.
• If the slope of a ramp or walkway is steeper than one (1) vertical in four
(4) horizontal, the ramp or walkway shall have cleats not more than 350
mm (14 inches) apart which are securely fastened to the planks to
provide footing.
Page 29 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• High Winds
• Where men work on, over, or near water, a guardrail system shall be
provided. Wherever a guardrail system is impractical, or when men are
outside the protection of these safeguards, a personal fall arrest system
shall be worn.
• An approved personal flotation device (life vest) shall be worn at all times
by each person working above or near water. Personal flotation devices
shall be inspected prior to each use.
• Floatation rings shall be provided at intervals not greater than 15 meters
(50 feet) apart when personnel are working above or near water. The
number of floatation rings and the length of the rope depend on the
location and the vertical distance above the water.
• A continuous man-watch shall be provided when personnel are working
above or near water.
• General
• The components used to assemble scaffolds shall be inspected before
each use and shall conform to requirements of this section regarding
materials, strength, dimensions, etc.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 30 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 31 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• BS 1139, Part 1, Section 1.1; 235 N/mm2 (34 ksi) (24 kg/mm²) minimum
yield stress; 4.0 mm nominal wall thickness (EN 39, thickness type 4, is
equivalent).
• BS EN 39 Type 4 (4mm) Galvanized steel tubes with a diameter of
48.3mm, thickness of 3.2mm, in accordance with BS EN 10210-1
• All tubing produced shall meet the testing and inspection requirements of
ASTM A500, including flattening test.
• Actual yield and tensile strengths shall be verified by Purchaser of
Galvanized scaffold tubing by: (1) receipt from Supplier and review of
certified inspection test reports for each lot of tubing produced from the
same heat of steel, and (2) by independent mechanical testing, per ASTM
A370, of test specimens taken from two lengths of tubing for each lot of
500 lengths, or fraction thereof, received. All mechanical properties shall
meet minimum requirements after galvanizing. All test reports shall be
written in English.
• Each piece of Galvanized scaffold tubing produced in accordance with the
above specifications shall be clearly, continuously, and permanently
marked to distinguish it from unacceptable, substandard tubing. All tubing
shall be marked, prior to galvanizing, with the pipe manufacturer’s name or
logo, applicable pipe fabrication specification (including Grade and
nominal wall thickness), and year of manufacture continuously along its full
length, in a position remote from any electric resistance weld (ERW) seam,
using a low stress rolling die embossed marking system. The marking
interval shall not exceed 1.5 meter, with characters a minimum of 4 mm
high and impression depth of at least 0.2 mm deep. Painted marking is
unacceptable.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 32 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 33 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Putlog Couplers
Force of the pull axially N/A 0.63 kN
(Single Coupler)
Tension Bending vertical
Sleeve Coupler A 3.6kN
and horizontal
Tension Bending vertical
Sleeve Coupler B 5.5kN
and horizontal
Joint Pin Tension N/A 0 kN
• Platform Units
▪ Scaffold platform units shall be either solid sawn wood planks, laminated
veneer lumber (LVL) wooden scaffold boards, fabricated wooden scaffold
boards, or fabricated platforms. See Figure II.9.17. All recommendations
by the platform unit manufacturer or the lumber grading association or
inspection agency shall be followed.
▪ Solid sawn wooden scaffold boards shall be of solid sawn timber and may
be either 2x10 inch (nominal), 2x9 inch (rough), 38mmx225mm (basic), or
50mmx225mm (basic).
▪ Solid sawn wooden scaffold boards shall be of a “scaffold board grade”
and shall be certified by and bear the grade stamp of the West Coast
Lumber Inspection Bureau (WCLB), Southern Pine Inspection Bureau
(SPIB), or other lumber-grading agency approved by the American Lumber
Standards Committee (See Certified Agencies and Typical Grade Stamps,
published by the American Lumber Standards Committee).
▪ Solid sawn wooden scaffold boards conforming to and marked in
accordance with BS 2482 are also acceptable.
▪ Laminated veneer lumber (LVL) planks shall measure 38 millimeters (1-1/2
inch) thick by 225 millimeters (9 inches) wide, or larger.
▪ All laminated veneer lumber (LVL) planks shall have the words “PROOF
TESTED SCAFFOLD BOARD” and “OSHA”, or UJV accepted equivalent,
continuously embossed along at least one edge.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 34 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ Solid sawn wood and LVL scaffold wooden boards shall conform to the
following (see Figure II.9.40):
• Scaffold wooden board ends shall not be split more than 25 mm (1 inch)
without metal banding. Even with banding, board ends shall not be split
over 300 mm (12 inches).
• Scaffold boards shall not be twisted from end-to-end or curled from side-
to-side more than 13 mm (1/2-inch).
▪ Scaffold wooden boards shall be inspected for defects, including damage,
decay and warping, prior to each use. boards that are split, warped,
twisted (more than allowed above), saw-cut, drilled, worn, decayed,
broken, or damaged shall not be used. See Figure II.9.41. However, the
defective parts may be cut off to produce shorter boards. In this case, the
cut end(s) shall be banded.
▪ Scaffold wooden boards shall not be painted, treated, or coated in any
way (except at the ends) that could conceal defects or obscure the top or
bottom surfaces.
▪ Scaffold wooden boards shall be properly stacked, off the ground, on a
suitable foundation. Where the height of a stack exceeds 20 planks,
measures shall be taken to tie or bond succeeding layers.
▪ Scaffold wooden boards shall not be stood on end unattended.
▪ Scaffold wooden boards shall not be used as concrete forms, trench
shoring, or as sills for scaffolds.
• Capacity
Page 35 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 36 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Note:
The total load on a scaffold base consists of the sum of the weight of the workers,
tools, equipment and materials on a scaffold plus the weight of the scaffold.
Page 37 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ All scaffold standards shall be pitched on steel base plates or screw jacks
at least 150 millimeters (6 inches) by 150 millimeters (6 inches) and 6
millimeters (1/4-inch) thick. See Figure II.9.3. For Special Scaffolds, the
base plate shall be designed to support the maximum scaffold standard
load. Timber sills shall be used where base plates may be exposed to
corrosive materials.
▪ Screw jacks shall be used to compensate for variations in ground level.
Screw jacks shall not be adjusted to more than two-thirds of the total
length of the threaded section. Screw jacks shall be used and loaded in
accordance with the manufacturer’s specifications (see Figure II.9.44).
Screw-jacks shall never have more than 300mm (12 in) of exposed thread.
• Screw-jacks shall only be used between the scaffold standard base and
the base plate
▪ Front-end loaders, forklifts, or pieces of equipment shall not be used to
support scaffolds.
▪ Scaffolds shall not be hung from or supported by guardrails or handrails.
• The foundations shall be level and adequate to carry the load imposed.
• Base plates shall be placed under every standard irrespective of the
foundation surface.
▪ Under no circumstances will scaffolds be undermined by excavation
stability
• Scaffold standards shall be erected and maintained vertical and plumb
and vertically braced in both directions to prevent swaying and
displacement. Plumpness shall be checked using a spirit level, plumb bob,
or by using vertical lines on an adjacent building or structure. See Figure
II.9.45 and Figure II.9.46.
▪ Where uplift or tension loads may occur in standards or (such as the back
side of cantilevered scaffolds), they shall be locked together by pins (not
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 38 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Ties or guys shall be installed adjacent to ledger bracing. See Figure II.9.47.
• The lowest level of ties or guys shall be installed at the lift located closest to
the height of 4 times the minimum base dimension (4:1 ratio). See Figure
II.9.47.
• The uppermost level of ties or guys shall be installed as close as feasible to
the top of the scaffold.
• Ties or guys shall be spaced vertically every 8 meters (26 feet) (4 lifts) or less.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 39 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Ties or guys shall be installed at both ends of the scaffold and at horizontal
intervals not to exceed 9 meters (30 feet) measured from one end toward the
other. See Figure II.9.47.
• Guys shall slope at approximately 45 degrees above the horizontal. The
strength of guy wires and of the anchorage used shall be calculated, having
due regard to the horizontal wind forces and other forces which may be
applied to the scaffold. See Figure II.9.25.
• Guys shall be installed on opposite sides of the scaffold.
▪ When used, reveal tubes shall be securely wedged, using reveal pins,
between opposing surfaces on the building or structure and coupled to tie
tubes. To ensure the security of reveal tubes, it is necessary to frequently
check for tightness. Ties to reveal tubes shall not exceed 50% of the total
number of ties used on the scaffold and shall be evenly distributed over the
scaffold area. See Figure II.9.20 and Figure II.9.21.
▪ When used, outrigger frames shall extend the base dimension(s) to more than
¼ of the scaffold height. See Figure II.9.23.
▪ The stability of a scaffold may be achieved by the use of rakers only if it is
impractical to provide ties, guys, or outrigger frames. Each raker shall be a
single piece of scaffold tubing not more than 6.4 meters (21 feet) in length.
Rakers shall not be joined (spliced) together. The raker angle above
horizontal shall not be greater than 75 degrees (4:1) or less than 65 degrees
(2:1). Only one additional lift may be installed on the scaffold above the raker
tie-in point. The top of the raker shall be coupled to the scaffold no higher
than the third lift. The bottom of the raker shall be coupled to a firmly
anchored ground stake or otherwise well anchored against movement in all
directions (including uplift). In addition, the bottom and midpoint of every raker
shall always be tied back to the scaffold by horizontal tubes coupled to the
raker and to at least two scaffold standards. See Figure II.9.22.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 40 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ When installation of ties, guys, or outrigger frames is not possible for scaffolds
that exceed a 4:1 height to base width ratio, the bottom corners may be
securely anchored against uplift. See Figure II.9.24. Such anchors shall be
properly designed by a qualified engineer, including consideration of the
capacity of the soil or foundation to resist uplift. These calculations shall be
reviewed by the UJV scaffold engineer beforehand.
▪ Ties, guys, or outriggers shall be used to prevent the tipping of supported
scaffolds in all circumstances where an eccentric load, such as a cantilevered
work platform, is applied or is transmitted to the scaffold.
▪ Where the means of access to the working platform (i.e., ladder) is outside
the scaffold structure, due consideration shall be given to the effect of such
means of access on the stability of the scaffold.
▪ All connections on a scaffold lift shall be made secure and fully tightened
before assembly of the next lift.
▪ When a scaffold is being dismantled, the components above each tie shall be
dismantled or removed before the tie is removed. Stability shall be maintained
while the scaffold is being dismantled.
• Scaffold Platform Construction and Use
▪ A complete guardrail system, including toe boards, shall be installed
around all open sides and ends of every scaffold boarded/platformed level
(even when not being used as a working platform) where a person could
fall 1.8 meters (6 feet) or more. Toe-boards shall not be nailed to scaffold
boards.
▪ If the front edge of a working platform is less than 200 mm (8 inches) from
the face of the wall or structure, guardrails do not need to be erected along
that edge. However, risk assessment must be done and falling object
protection may be provided by covering the gap with planks or by using
toe-boards, nets, barricades, etc.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 41 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 42 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ Ends of scaffold boards shall extend beyond the centerline of their end
support transom by at least 150 mm (6 inches), unless cleated or
otherwise restrained by equivalent means. See Figure II.9.51.
▪ Ends of scaffold boards shall not extend less than 50 mm (2 inches)
beyond the centerline of their end support transom. See Figure II.9.51.
▪ Scaffold boards overlaps shall occur only over supports (i.e., Transoms.
Scaffold boards lap lengths shall not be less than 300 mm (12 inches).
Scaffold boards shall not be nailed together. See Figure II.9.51.
▪ Scaffold boards shall be laid flush side-by-side to each other on all scaffold
platforms.
▪ On platforms where scaffold boards are placed end-to-end, each end shall
be independently supported. (Exception: this provision does not preclude
the use of common support members, such as “T” sections, to support
abutting the boards, or hook-on platforms designed to rest on common
supports).
▪ At all points of a scaffold where the scaffold boards change direction, such
as turning a corner, any scaffold boards that rest on a transom an angle
other than a right angle shall be laid first, and scaffold boards which rest at
right angles over the same transom shall be laid second, on top of the first
scaffold board.
▪ Each platform unit (Wooden Scaffold Board, Steel Scaffold Board) shall be
installed so that gaps between platform units are less than 50 mm (2 inch)
wide. When larger gaps are unavoidable, they shall be covered as follows:
• Gaps less than 600 mm (2 feet) in width shall be covered with at least 20-
millimeter (¾-inch) thick, exterior grade plywood. Such plywood coverings
shall be overlapped at least the width of the gap, 300 mm (12 inches)
minimum, on both sides of the opening and held in place with cleats.
• Gaps larger than 600 mm (2 feet) in width shall be covered with properly
secured (not nailed) cross scaffold boards.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 43 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ When moving platforms to the next level, the existing platform shall be left
undisturbed until the next lift has been fully installed and braced prior to
receiving the new platforms.
▪ Scaffold materials shall not be thrown or dropped from heights.
▪ Safe landings shall be provided at the top of all ladders and at least every
9 meters (30 feet) of ladder height. Landings shall be closed boarded and
protected by a guardrail system. See Figure II.9.52.
▪ If an internal ladder is used, the access opening in a landing or platform
through which the ladder passes shall be at least 675 mm (27 inches) (3
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 44 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
boards) wide and not less than 900 mm (36 inches) deep. See Figure
II.9.27 and Figure II.9.33. Access openings through working platforms
shall be protected by a sturdy guardrail system with a self-closing drop bar
(at top-rail height). Or, a hinged cover (trapdoor) may be used. Hinged
covers shall be kept closed at all times, except when workmen are passing
through.
▪ If an external ladder is used, a step-through opening in the guardrail
system (protected by a self-closing drop bar at top-rail height) is required
or Self closing access gate instead of workers having to climb over or
through the guardrails. The width of step-through openings in a guardrail
system shall not be less than 675 mm (27 inches) or more than 760 mm
(30 inches). See Figure II.9.1 and Figure II.9.54.
▪ External or internal where a worker can fall more than 4m Extra handrails
to be installed outside of the ladder for extra protection
▪ Ladders shall not be used on top of scaffold platforms.
• Clearances
Page 45 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Insulated Lines
Less than 300 volts 1 meter (3 feet) 2 times the length of the line
insulator, but never less than 3
300 volts to 50 kV 3 meters (10 feet) meters (10 feet).
Uninsulated Lines
Less than 50 kV 3 meters (10 feet) 2 times the length of the line
insulator, but never less than 3
More than 50 kV 3 meters (10 feet) plus 100 mm (4 inches) meters (10 feet).
for each 1 kV over 50 kV.
Note: UJV approval is required for any work within 6 meters (20 ft) of overhead lines.
Page 46 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Ledgers
Page 47 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 48 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ Quick-fix System
▪ Cup lock System
▪ Layer System
▪ ALL Round System
▪ Turner +8 System
• The locking-pin type of system scaffold shall not be used. See Figure II.9.32.
• Standards shall be connected by bolted spigots and shall be secured into place using
two spigot pins for situations where uplift may occur. The upper standards shall slide
over the spigot. See Figure II.9.15.
• Correct lengths of ledgers, transoms, and lift heights shall be used as required for
load rating of the scaffold. The applied loads on standards, ledgers, transoms, and
diagonal braces shall not exceed the load carrying capacity of the manufacturer’s
specifications.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 49 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Standards:
Page 50 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 51 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
lbs.). Only proper scaffold spanner wrenches shall be used. “Cheater bars”
or longer handled wrenches shall not be used, as they give greater
leverage than proper scaffold spanner wrenches and could damage the
coupler.
• Ledger Bracing:
Page 52 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
of ledger “X” braces shall be installed at both scaffolds ends and repeated
along the length of the scaffold at least every line of standards. See
Figures II.9.3, II.9.57, and II.9.58.
• Sway Bracing:
▪ Sway (facade) bracing for a scaffold whose length is greater than its
height: A diagonal brace shall be installed from the base of the first end
standard diagonally upward, at between 35 and 55-degrees, to the
extreme top of the scaffold. This longitudinal bracing shall be repeated
along the length of the scaffold at least every 5th standard. See Figure
II.9.59. This sway (facade) bracing shall be installed, in opposite
directions, along the front (inner) and rear (outer) lines of standards.
▪ Sway (facade) bracing for a scaffold whose length is less than its height:
The first diagonal brace shall be installed from the base of the first end
standard upward, at between 35 and 55 degrees, along the entire length
of the scaffold to the last end standard. Additional diagonal braces shall
then be installed, at between 35 and 55 degrees, in alternating directions
(“zigzag”) across the entire scaffold length until reaching the top of the
scaffold. See Figure II.9.60. This set of sway (facade) braces shall be
installed along the front (inner) and rear (outer) lines of standards.
▪ Interior sway “zigzag” bracing for a scaffold with multiple bays across its
width (“birdcage” scaffold): The first diagonal brace shall be installed from
the base of the first standard diagonally upward, at between 35 and 55
degrees, to the second standard at the first lift (across one bay in one lift
height). Additional diagonal braces shall then be installed in alternating
directions (“zigzag”) until reaching the top of the scaffold. Such longitudinal
“zigzag” bracing shall be repeated along the length of the scaffold such
that no more than 4 adjacent bays are open without sway braces. This set
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 53 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
of sway “zigzag” braces shall be repeated across the width of the scaffold
at least every third line of standards. See Figure II.9.61.
• Light-Duty Tube and Coupler Scaffolds
▪ For Light-Duty tube and coupler scaffolds constructed entirely of tubing
manufactured and embossed (stamped) and BS EN 39, the permitted
Ledger Standard spacing (transom span) and corresponding maximum
longitudinal standard spacing (ledger span) shall be as shown in Table IV.
See Figure II.9.68 and Figure II.9.69.
• For Light-duty tube and coupler scaffolds constructed using any tubing
which is does not have embossed (stamped) in accordance with
Section 7.2, the permitted transom spans and the corresponding
maximum ledger spans shall be reduced and shall be as shown in
Table V. See Figure II.9.70 and Figure II.9.71.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 54 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Light-duty tube and coupler scaffolds requiring more than the above
working or boarded levels, or over the maximum heights shown in
Table VI, shall be classified as a Special Scaffold and shall be properly
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 55 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• All tubing used to construct General Purpose and more heavily loaded
tube and coupler scaffolds shall be manufactured and embossed
(stamped). Scaffold tubing that is not properly embossed shall not be
used for Medium-duty or more heavily loaded tube and coupler
scaffolds.
• For General Purpose tube and coupler scaffolds constructed entirely of
tubing manufactured and embossed, the maximum ledger standard
spacing (transom span) is 1.2 meters (4 feet) and the maximum ledger
standard spacing (ledger span) is 1.8 meters (6 feet). See Figure
II.9.72.
• Larger standard spacing may be used if justified by structural
calculations or load tests submitted for review, along with material
tensile/yield stress test reports for the specific scaffold tubing to be
used.
• At least one board transom and intermediate transom shall be installed
in each bay of every platform boarded level. Alternately, double
transoms may be used only if the maximum allowable boarded spans
are not exceeded. See Figure II.9.72 and Figure II.9.73.
• General Purpose tube and coupler scaffolds may have a maximum of
two working levels in use at any one time only when there are no
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 56 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
1 7 38 m (125 ft.)
2 2 25 m (78 ft.)
• General purpose tube and coupler scaffolds requiring more than the
above working or boarded levels, or higher than the maximum heights
shown in Table VII, shall be classified as a Special Scaffold and shall
be properly designed and reviewed Preferably, a properly designed
system scaffold should be used instead of tube and coupler
construction for scaffolds over 16 meters (52 Ft 4 inches) high
• If the CFP Project has no SSME or UJV Senior Superintendent
Scaffolding onsite, A design and calculations is required if the
scaffolding is to be erected over 9m high.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 57 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ Mobile and tower scaffolds shall be plumb, level, and square and be
horizontally and vertically braced (in both directions) by diagonal braces.
See Figures II.9.27, II.9.27 and II.9.33.
▪ Plan (horizontal) bracing shall be installed at the base, at the top, and at
least every third lift of all mobile and tower scaffolds to prevent racking
(twisting). See Figure II.9.27 and Figure II.9.33.
▪ Light-duty tube and coupler mobile and tower scaffolds (used only for
personnel access and inspection) that are one bay long by one bay wide
(only 4 standards) and constructed entirely of steel tubing manufactured
and embossed per Section 7.2 shall have a maximum standard spacing of
2 meters (6.5 feet) in both directions. In this case, at least two equally
spaced transoms and intermediate transoms shall be used.
▪ Light-duty tube and coupler mobile and tower scaffolds that are one bay
long by one bay wide (only 4 standards) and constructed with steel tubing
that is NOT manufactured and embossed shall have a maximum standard
spacing of 1.7 meters (5.5 feet) in both directions.
▪ General purpose tube and coupler mobile and tower scaffolds that are one
bay long by one bay wide (only 4 standards) shall be entirely constructed
of steel tubing manufactured and embossed and shall have a maximum
standard spacing of 1.5 meters (5 feet) in both directions.
▪ For mobile scaffolds, an internal ladder with a cover (preferably hinged)
over the access hole in the platform is preferred over an external ladder.
▪ External ladder NOT allowed on mobile scaffolds
Page 58 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ Mobile scaffolds rated for Light-duty shall have steel casters not less than
180 mm (6 inches) in diameter.
▪ Mobile scaffolds rated for General purpose shall have heavy-duty steel
casters not less than 200 mm (8 inches) in diameter.
▪ All casters shall be fitted with a positive wheel lock (which cannot be
accidentally released) to prevent movement while the mobile scaffold is
being used. See Figure II.9.30.
▪ Casters shall be securely fixed to the base of scaffold standards by locking
pins.
▪ The working area of any platform shall not extend outside the scaffold
base dimensions. Cantilevered working areas are not permitted for mobile
or tower scaffolds.
▪ Platform units (boards) shall be securely fixed in position.
▪ The uppermost work platform height shall not exceed 3 times the minimum
base dimension of any mobile or tower scaffold and outriggers shall be
installed on the scaffold to achieve this least base dimension, or provisions
(such as guys, ties, or rakers) shall be taken to stabilize the scaffold
against tipping.
▪ A complete guardrail system shall be provided at every platform.
▪ All mobile scaffolds shall conform to the industry standard basic
dimensions for guard rails, ladder access inside fabricated structure, toe
boards, out riggers based on height and support bracing.
▪ Mobile Tower Scaffolds will be erected to manufactures instructions.
Page 59 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 60 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
bends at the center for inserting brackets. The gap created by the bent
section of the bracket strap must be compatible in size with the bracket
to be inserted, with a 3 mm (1/8-inch) maximum clearance on the front
or back faces.
• Bracket straps shall be welded to the tank shell for a length of at least
150 mm (6 inches) along the top edge of the strap (two 75 mm welds
min.) and down 25 mm (1 inch) along each side of the strap, with a 5
mm (3/16 inch) fillet weld. No weld is required along the bottom edge of
the bracket straps. See Figure II.9.26.
• If 38 mm (1-1/2 inch) thick wood planks are used, the maximum
circumferential distance between brackets shall not be more than 1.5
meters (5 feet) on center. Except as noted in the following paragraph, if
50 mm (2-inch) thick wood planks are used, the maximum
circumferential distance between brackets shall not be more than 2.4
meters (8 feet) on center.
• Only if all brackets (frames), platform units (planks), etc. are certified to
meet all requirements in OSHA 1926.450, Appendix A, Section 2(z),
“Tank builder’s scaffold,” the maximum circumferential distance
between brackets may be 3.2 meters (10’-6”) on center. In this case,
planks shall be full-dimensioned 50 mm (2-inch) thick by 300 mm (12-
inch) wide Douglas Fir or Southern Yellow Pine of Select Structural
Grade or Scaffold Grade.
• Brackets shall be installed vertically. Only certified welders shall weld
bracket straps to the tank wall.
• Prior to welding on any tank, approval of welding procedures and
verification of tank integrity is required from the Proponent’s
Engineering Unit.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 61 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 62 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• All working levels shall be fully boarded. Working levels shall be at least 2
boards but not more 3 planks wide.
• Planks shall overlap in one direction only and the minimum overlap shall be
300 mm (12 inches).
• Platform units and boards shall be secured to the brackets in a manner that
will prevent movement.
• The area below bracket scaffolds shall be barricaded and warning signs
posted.
Page 63 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
▪ Ledgers and transoms shall be coupled to hanger tubes using right angle
(Double) couplers (not adjustable) couplers in a non-working lift.
▪ Structural transoms will be installed with Right Angle (Double) Couplers
under the ledgers.
▪ Transoms and intermediate transoms for the working lift can use
Putlog/Single Couplers
▪ Hanger tube spacing shall comply with the tube and coupler standard
spacing requirements for the load duty of scaffold (Design required).
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 64 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 65 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
7.9.1.1. Any physical damage that impairs the function or strength of the rope.
7.9.1.2. Abrasion, corrosion, scrubbing, flattening or peening which has caused
loss of more than one-quarter of the original diameter of the outside
wires.
7.9.1.3. Heat damage caused by a torch or any damage caused by contact
electrical wires.
▪ Spacing of wire ropes used to carry the scaffold load shall comply with the
standard spacing requirements for the duty of scaffold.
▪ Suspension wire ropes shall be shielded from heat-producing processes.
When acids or other corrosive substances are used on a scaffold, the
ropes shall be shielded, treated to protect against the corrosive
substances, or shall be of a material that will not be damaged by the
substance being used.
▪ Under-hung scaffolds supported by wire ropes shall be tied or otherwise
secured to prevent them from swaying.
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 66 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 67 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 68 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 69 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Working platforms will normally be five boards wide but may be reduced to
two boards Clear passage way where the scaffold has been erected for
inspection or access purposes only.
• All working platforms will be close boarded with boards. Board’s will NOT
be cut to fit around standards, pipe penetrations etc., must butt up to the
obstruction or have the gaps filled in with the use of suitable fixed wooden
boarding, i.e.: non-slip plywood.
• Guardrails will be fixed to the inside of the standards on all working
platforms to a height of between 950 mm (minimum) and 1150 mm
(maximum). The space between the top of the toe-board and the
underside of the guardrail will not exceed 470mm.
• A mid guardrail will be fixed to the inside of standards in every instance
halfway between the handrail and the decking.
• Toe-boards including stop end boards will be fitted to all working platforms.
The minimum height will be 155mm.
• If materials are to be stacked above the height of the toe board, a suitable
barrier (brick guards) will be erected.
• Ladder access openings will not be more that 600mm wide (3 boards) and
will be as short as possible in the other direction.
• Where ladder opening is on the boarded lift, Ladder Hatch to be fitted or
fix handrail round the openings
Page 70 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• The minimum overhang of any board will not be less than 50 mm and the
maximum overhang will not exceed 150mm.
• No more than 2 board’s width will be supported on needle transoms unless
the transoms are fixed with right angle coupler and “picked up”
• Ladder Access Platforms
• The vertical height between ladder access platforms will not exceed 9
meters.
• Ladder Access platforms will have guardrail fully enclosing the open area
access points
• Ladder access platforms will be close boarded and will have guardrails
and toe-boards secured.
• Extra guardrails will be installed external for fall protection
10.0. Ladders
• Ladders will project beyond working platforms or ladder access platforms
by a minimum distance of 1meter (five rungs).
• Restricted Access for ladder where you cannot meet the 1m above
platform level, handrails must be installed.
• Ladders will be based on a sound footing. They will be lashed or secured
by a proprietary clamp at both the foot and near the top.
• The angle at which the ladder is set will (with the exception of scaffold
towers) be 75º or 300 mm out for every 1.2 meters of vertical length.
• The angle may vary due to the restricted height and access
• The ladder angle will NOT exceed 75° (Degree’s)
• Long ladders will be supported and lashed at their midpoint to remove any
bounce.
• Ladders shall be constructed of Aluminum, Wood, Steel and fiber glass.
Only property constructed and manufactured ladders shall be used. ‘Home
made” ladders are strictly forbidden.
• Use of light metal alloys in Hazardous Areas, light alloys / aluminum
ladders and scaffold shall not be used in Zone 1 Hazardous Areas. This is
because ignition of gas-air mixtures can occur as a result of impact or
rubbing of metals. Impact between light metal alloys and metals having an
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 71 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
oxygen containing surface (rust, painted with red lead) can produce sparks
of high energy due to the thermite reaction, which may ignite a flammable
mixture.
• Aluminum or metal ladder ladders shall not be used around live electrical
wiring. Fiberglass or wooden ladders shall be used in areas of electrical
hazards
• Metal Ladder clamps must Not be used for tie or fasten the Aluminum
Ladder
• Aluminum ladders must be fastened and secured with strong Nylon Rope.
• Ladders shall not be supported on their rungs, and rungs shall not be used
to support scaffold boards.
• Ladders shall not be extended by lashing two ladder sections together.
• All ladders will be of good repair and sound construction. They will be
checked for damage, faults and wear & tear, by the Approved Scaffolding
Supervisor, before use.
• Ladders may be on the outside of a scaffold for the first two lifts, above
ground level. In every other instance, the ladder shall be internal to the
scaffold.
• When supporting the ladder, the scaffolding tubes must have clearance
between the rungs avoiding losing grip or trapping the foot
• When Climbing ladders 3 point of contact always
• No carrying materials or equipment up the ladder at any time.
Page 72 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Scaffold Loadings
• It is the responsibility of the Scaffold Supervisor to ensure that the
scaffold is construction and the strength are suitable for its purpose.
• Design calculations shall be submitted to Field Engineering for any
scaffolding other than a common access scaffold. The calculation will
show both dead and live loadings.
• Scaffolding Loadings (Attachment 3: Scaffolding Load Classes Page
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 73 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 74 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
• Section Six:
• Scaffolding Inspector will record ALL Inspections as described
in Section 11.0. Scaffold Inspection.
• Section Seven:
• Scaffolding Inspector will complete if there has been any one-
time Modifications.
• Section Eight:
• Dismantling Authority will sign and approve the removal of the
Scaffolding (discipline in-charge)
• Once the scaffolding is no longer require and all the work is complete, the
Scaffolding Inspector will return the scaffolding request to the Scaffolding
Supervisor and he will seek the approval from the discipline in charge to
sign and date for dismantle,
• Scaffolding Supervisor will return the Scaffolding Request/Register along
with the Scaff Tag to the Scaffolding Inspector for his duty or care
• The scaffolding Inspector Must keep a record of all scaffolding activities
till the end of the project
Implementation of Modification Scaffolding Request/Register Form.
• All departments that requires Modifications to Scaffolding must complete
and use Modification Scaffolding Request/Register Form (See
Attachment 7: page ??)
• Section One:
• Requester will Complete this section by competing his Name,
Location, Department, Date, Permit Number, Marked-up
drawings and details of the requirements.
• Section Two:
• Scaffolding Supervisor will receive the Scaffolding
Request/Register from the Requester and together attend the
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 75 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 76 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 77 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Over 16
or (52ft)
“Special”
Yes
Yes
Yes PEC No
“Special
HSE/Construction
Scaffold”?
accept Plan?
No
Yes
No Structural
Pass
alteration
? No
Scaffold Supervisor does Field ?
Inspection
Yes No
Page 78 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 79 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Page 80 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 81 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 82 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 83 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 84 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 85 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 86 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 87 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 88 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 89 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 90 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 91 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 92 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 93 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 94 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 95 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 96 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 97 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 98 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Page 99 of 126
DOCUMENT TITLE: SCAFFOLDING SAFETY PROCEDURE Rev. A
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
นั่งร้ าน 3 ชัน้ ขึน้ ไปจะต้ องมีคา้ ยันในอัตราส่ วนของฐาน 3/5 ของความสูง / THREE LAYERS UP
SHOULD PROVIDE THE SCAFFOLD BRACN INCLINED AT
A RATIO OF 3/5 HIGH
นั่งร้ านได้ มีการยึดและติดตัง้ แผ่ นกันตกหรือไม่ /ARE SCAFFOLD SECURE AND TOE BOARD
IN PLACE
แผ่ นกันของตกจะต้ องมีความสูงไม่ น้อยกว่ า 15 ซ.ม. /IS TOE BOARD AT HANDRAIL LEAST 15
CM.? HIGH
มีการยึดโยงนั่งร้ านกับโครงสร้ างที่แข็งแรงหรือไม่
BRACED AND/OR TIED OFF TO THE STRUCTURE
ราวกันตกจะต้ องมีความสูงไม่ น้อยกว่ า 90 –110 ซ.ม.
ARE GUARDS IN PLACE AND IS SAFETY A MINIMUM OF 90-110 M. HIGH
ต้ องมีบันไดขึน้ ลงที่ปลอดภัย (ต้ องมีราวบันไดและราวกันตก)
ARE ACCESS LADDERS IN PLACE (Include handrail and guardrail)
มีการผูกมัดแผ่ นทางเดินหรื อไม่ /IS PLANKING (WALKING SURFACE) SECURE TO THE
SCAFFOLDING
ขณะมีการติดตัง้ รือ้ ถอนนั่งร้ านพนักงานจะต้ องสวมใส่ เข็มขัดนิรภัยและคล้ องเกี่ยว / DURING
ERECTTION OR DISMANTLING ARE WORKERS WEARING SAFETY BELT AND HOOK
UP
นั่งร้ านมีการแขวนใบอนุญาตใช้ งานอยู่หรือไม่ / IS SCAFFOLDING TAGGED PERTAINING TO
ITS OPERATIONAL STATUS
เสาตัง้ ได้ฉากหรือไม่ / Are the standards vertical?
คานตง(เลดเจอร์) และคานแป(ทรานซัม) อยูใ่ นแนวระนาบหรือไม่ /Are the ledgers & Transoms
horizontal?
ข้อต่อห่างจากเสา ไม่เกิน 30 ซ.ม /Are the joints no more than 30 cm from a standard?
Joint Venture of
Engineering Document Petrofac South East Asia Pte. Ltd., Saipem
Singapore Pte. Ltd. and Samsung
Engineering (Thailand) Co., Ltd.
Scaffold register:
่ ดตังนั
Scaffold Location / บริเวณทีติ ้ ่ งร ้าน………………………….Date/วันที:่ …………………...