Professional Documents
Culture Documents
MBA CPM
2nd Semester
2021-22
Content
► Tender Process
► Various Types of Tendering
► Single Vs Two Stage Tendering
Tendering: Processes & Various Types
► In construction, the main tender process is generally for the selection of the
contractor that will construct the works. However, as procurement routes have
become more complex, so tenders may be sought for a wide range of goods and
services (for example, on a construction management contract the works are
constructed by a number of different trade contractors each contracted to the client)
and contractors may take on additional functions such as design and management.
► Irrespective of the nature of the goods or services that are being sought, the
process for securing tenders may take a number of different basic forms: refer next
slide.
Procurement Strategy
Procurement Routes
Design & Built Traditional
Route Route
Contracting Models
Compensation Formats
Types of Tendering
Procurement Procedure
Types:
Open tendering,
Selective tendering,
Negotiated tendering,
Serial tendering,
Framework tendering,
Methods:
Single-stage and
Two-stage tendering.
Various Types of Tendering
Open tendering
► Open tendering allows anyone to submit a tender to supply the goods or
services that are required. Generally, an advert will be placed giving
notice that the contract is being tendered and offering an equal
opportunity to any organization to submit a response to tender.
Selective Tendering
Serial Tendering
► Serial tendering involves the preparation of tenders based on a typical or
Framework tendering
► One or more suppliers are then selected and appointed. When specific projects
arise the client is then able to simply select a suitable framework supplier and
instruct them to start work. Where there is more than one suitable supplier on the
framework, the client may introduce a secondary selection process to assess which
supplier is likely to offer best value for a specific project. The advantage of this
process to the client is that they are able instigate a selection procedure for
individual projects without having to undertake a time-consuming pre-qualification
process. This should also reduce tender costs.
Various Types of Tendering
Single-Stage Tendering
► A tender is a submission made by a prospective supplier in response to
an invitation to tender. It makes an offer for the supply of goods or
services.
► Single-stage tendering is the more traditional route, used when all the
information necessary to calculate a realistic price is available when
tendering commences:
An invitation to tender is issued to prospective suppliers (perhaps
Single-Stage Tendering
Tenders are prepared and returned by prospective suppliers (this
may involve questions and answers and a mid-tender interview to
clarify the client’s requirements).
Submitted tenders are then assessed and compared (this may
involve further interviews).
The preferred tenderer is selected and negotiations opened.
Subject to the outcome of those negotiations the preferred tenderer
may then be appointed.
Two-Stage Tendering
► Two stage tendering is used to allow the early appointment of a
contractor, prior to the completion of all the information required to enable
them to offer a fixed price. In the first stage, a limited appointment is
agreed allowing the contractor to begin work and in the second stage a
fixed price is negotiated for the contract.
► In this case, the contractor will tender a fee for designing the building (or
completing the design) along with a schedule of rates that can be used to
establish the construction price for the second stage tender.
Two-Stage Tendering
Two-Stage Tendering
► The first-stage appointment might be made on the basis of a bespoke
agreement, a consultancy agreement or a pre-construction services
agreement (PCSA), with an appendix setting out all tender items to be
applied to the second stage contract, and a clause that makes it clear
there is no obligation to proceed to the second stage, and in such
circumstances the first stage fee would be full and final settlement of the
contractor's costs.
► The basis of the appointment for the first stage may include:
A pre-construction and construction programme.
Method statements.
Detailed preliminaries including staff costs.
Agreed overheads and profit.
A schedule of rates to be applied to the second-stage tender.
Agreed fees for design and other pre-construction services.
CV’s for proposed site and head office staff.
Tendering of any packages that can be broken out and defined.
Agreed contract conditions to be applied to the second-stage construction contract.
It is important that this appointment is based on as much information as possible and that
requirements are well defined, as subsequent changes could prove expensive.
Two-Stage Tendering
Two-Stage Tendering
► The pre-construction services carried out by the contractor in the first
phase might include:
Two-Stage Tendering
► Ideally the second-stage negotiation is simply a mathematical exercise
using the pricing criteria agreed in the first stage agreement. In reality
however, there will be some items not previously considered, around
which negotiations will ensue. In the case of sub-contractors, the second
stage construction contract is negotiated by the main contractor subject to
the approval of the design team.
Two-Stage Tendering
► It is in the client's interests to try to include some packages in the first
phase, and to ensure that they have some means of securing an
alternative bid if negotiations with the preferred contractor fail, albeit this is
likely to result in delays and difficulties regarding design liability. However,
the client may find the competition lose interest once they find out that
another contractor been awarded the first stage tender.
Single-Stage & Two-Stage Tendering
Benefits: Benefits:
► The client benefits from a competitive tendering ► The project doesn’t have to be fully designed
process which can lead to more competitive and costed before they can start procurement
pricing. for the project, thus reducing costs.
► The client can also benefit from a fixed price ► Shorter timescales required to get a contractor
through this tendering process. appointed.
► Due to the shorter timescales, the client would
Risks: benefit from contractor early engagement which
► The number of contractors prepared to bid for could result in project costs being reduced
the project may be low. through a Value Engineering Process.
► The collaborative approach breeds greater
communication with the client and the clients
► The development scheme is generally designed team, which can result in improved outcomes.
and costed up by the contractor in isolation
which can often result in the project budget Risks:
being exceeded. Generally, this is because ► If the client and contractor don’t communicate
contractors may not have been consulted on with each other then it would be unlikely that
the buildability at the outset meaning ever- they would benefit from collaboration and
changing building costs throughout the project. project and cost clarity.
Single-Stage & Two-Stage Tendering
Further Reading…
► https://www.cqsa.co.uk/node/48
► https://www.macfarlanes.com/what-we-think/in-depth/2015/tendering-to-the-two-stage-process/
► http://constructingexcellence.org.uk/wp-
content/uploads/2015/12/Two_Stage_Open_Book_Guidance.pdf
Q&A