You are on page 1of 39

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

1. A Customer has subscribed to Oracle Cloud ERP and HCM Fusion, PBCS (Enterprise performance
management), B2C Service (RightNow), CPQ, and Oracle Marketing Cloud (Responsys), and integrations
using OIC (Integration Cloud). They would like to take the quick win approach to adopt the Cloud
solutions. What would be the Best Practice recommended approach for this Customer?

Global Design Approach

Multi-Release approach

Phased Approach

Parallel Tracking Phased Approach

Big Bang Approach

Incorrect. Please review Project Management Plan and Delivery Approach to find the correct answer.

(0/1) Points

2. A Customer has procured Oracle Cloud ERP and HCM in addition to OCI to lift and shift their Seibel
CRM solution to the Cloud. What would be the Scoping considerations for Seibel solution to move to the
Cloud?

Compute and Database requirements

Number of Instances/Containers required

Storage and Networking requirements

Security and Governance requirements

All of the above

Correct!

(1/1) Points

3. Your Customer comments “Cloud Projects Delivery & Planning approach is same as that of On-
Premise Projects”. Which of the following is an appropriate response?

It’s almost the same with some changes in the scope of work
It is totally different as Cloud Projects are managed differently

The topics covered are almost same, however, the approach of handling each process is different in

Cloud due to the subscription and Entitlements model of Cloud

They are different, as there is no need for a Project Management plan in Cloud Projects

Yes. it’s the same, there is no difference from on-premise or other IT Projects

Correct!

(1/1) Points

4. You are the Project Manager of a Cloud Project with the following scope: Cloud HCM, ERP and
Universal Credits for PaaS/OCI. Which of the following does NOT form part of PaaS Scoping?

Mobile applications development and extensions

Number of Analytical reports, dashboard and complexity, number of instances

Number of SaaS Processes implemented

Custom application Use cases to be developed and Number of App Dev instances required

Number of integration points in the scope + and the instances required

Correct!

(1/1) Points

5. You are planning for a Customer Cloud Multi-pillar Project with SaaS ERP, HCM and CX solutions in
scope. The Customer operates in 12 countries and is keen to standardize their Business processes. What
Best Practice approach would you recommend to this Customer?

Multi-Release approach

Pilot Approach

Big bang Approach

Global Design Approach

Phased Approach

Correct!
(1/1) Points

Page 1 of 18

6. While preparing for a Cloud Project Risk Register what are the important topics that you as a PM need
to familiarize with and reflect in the Register?

Oracle Cloud Sales Agreement

All of the above

Support SLAs with Oracle

Policies, Service Descriptions and Entitlements

Product features and functionalities

Incorrect. Please review Cloud Risk Management to find the correct answer.

(0/1) Points

7. The best approach to get the expected attention for a Service Request is to open all the SRs at Highest
Severity Severity 1 and 24/7

False

True

Correct!

(1/1) Points

8. As you approach Go-Live, you encounter an unexpected issue with the application. You’ve raised an
SR with Support as Sev 2, however you are not getting the expected response – what is the next step as
per the Support Process?

Call the regional support Hub, request an escalation and a Manager call back.

Update the SR every 4 hours

Postpone the Go-Live and inform the Customer to speak to Oracle Sales account Manager.
Call Oracle Sales Account Manager and ask him to escalate the issue.

Correct!

(1/1) Points

9. A Telco industry Customer implementing Fusion Engagement Cloud requires 24/7 high availability and
is concerned of Quarterly patching downtime. Before looking at alternative technical solutions as risk
mitigation, which of the following would you review to educate the Customer about SaaS Updates?

Oracle Professional services contract

CX unity Cloud services policies

Oracle Hosting and Delivery Policies

Oracle Fusion Services Description

Oracle SaaS Services policies

Correct!

(1/1) Points

10. You are engaged in a Project to identify all possible Integration Use Cases for scoping purposes.
Which of the following Use Cases may be eliminated for Integration Scope?

Business Decisions (Business Rules)

None of the options listed may be eliminated– All of them are potential Scope areas.

File Transfers

Stream Processing using Streaming Analytics

Process Automation and Case Management

Correct!
Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

11. Your implementation team has developed 22 integration packages in the DEV environment. In
preparation for UAT, all these integrations will need to move to the TEST Instance. What is the Best
Practice approach that minimises time taken to migrate these Packages?

Create a clone of the Integration instances

Create integration recipes to export and import Integration packages

Postpone the UAT until the import and export is completed. Export individual Integration packages from

DEV and Import them to TEST

Create a package to group integrations together, then Import to TEST

Create new Integration instances to copy the Packages

Correct!

(1/1) Points

12. Which of the following Integration tools provides seamless batch and real time data movement
among Cloud and on-premise data sources, maintaining data consistency along with fault tolerance and
resiliency?

Managed File Transfer Cloud Service

API Platform Cloud Service

SOA Cloud Service

Oracle Integration Cloud

Data Integration Cloud Service

Correct!

(1/1) Points

13. Your Customer Integrations require human intervention, decision making and approvals. Which of
the following Integration tools may be used to address this requirement?

OIC Standard edition as it includes Process Cloud.


The requirement may be addressed through OIC and Visual Cloud Builder

Use OIC which comes with SaaS adapters, technology adapters, and On-Premises Agents

OIC Enterprise Edition that includes Process Cloud to handle Human intervention in the workflows

Standard Edition of OIC (Oracle Integration Tool) will be sufficient to address this requirement

Correct!

(1/1) Points

14. A Customer with several core Banking Systems and frontend CX applications is looking for
automation of manual updates to Customer records across multiple applications and to streamline the
operations. If all the Applications have APIs, which of the following would you leverage to achieve the
outcome?

Oracle Process Cloud

leverage UiPath RPA Adapter

Leverage OIC adapters

Leverage OIC with Process Cloud

Use Robotic Process Automation orchestrated with a process

Correct!

(1/1) Points

15. Your Customer requires the application software to remain up and running during the Data
Migration process. What tool is best suited to perform the Data Migration?

Data Import, Export with Oracle Data Pump or PDB Import/Export

MV2ADB

Oracle SQL Developer

Remote cloning with ADG

Maximum availability Architecture

Incorrect. Please review Data Management and Migration Plan to find the correct answer.
(0/1) Points

Page 3 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

16. Which of the following Use Case Projects is best addressed by the ADW (Autonomous Data
Warehouse) solution?

Internet of Things and Big Data

None of the above

Creating a data warehouse location for long term data retention

To optimize data usage for fast query response and current operations

Integrating both structured and unstructured sets of data to perform advance analytics and reporting

Correct!

(1/1) Points

17. Customer would like to delete certain data from their environments. What guidance would you
provide for the feasibility of the requirement?

Customer can never delete/block any data stored in Cloud environments.

Run the delete Scripts and delete the data for the Customer

Guide the partner through the Cloud hosting and delivery policy documentation for the Customer’s
Services on oracle.com to understand the feasibility

This is a paid service performed by Oracle – so request must be made through My Oracle Support
Engage the Oracle Cloud technologist team with Customer to run a detailed workshop for the

requirements

Correct!

(1/1) Points

18. Which of the following approach fits most of Cloud Data Migration Projects?

Solution Driven

Target Driven

Strategy Driven

Requirement Driven

Innovation Driven

Correct!

(1/1) Points

19. Oracle provides built in Data Sheets for each module within Fusion to simplify the data loading
activity

False

True

Incorrect. Please review Data Management and Migration Plan to find the correct answer.

(0/1) Points

20. Your Customer requires to distribute and share Analytics content (either static or interactive).
Considering Customer has Universal Credits Constraints, which minimum Oracle Analytics Cloud Edition
caters this Use Case?

Essbase Edition

Enterprise Edition

Special Edition

Standard Edition

Professional Edition
Correct!

(1/1) Points

Page 4 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

21. For planning your Oracle Analytics Cloud Implementation Project, which of the following should be
thought through?

All of the above

Data Centre for the Services deployed

Sizing options the Customer has opted for (OCPU or Users)

Name required for the service

The OAC edition required for your Project

Incorrect. Please review Implementation Appraoch for Reporting and Business Analytics to find the
correct answer.

(0/1) Points

22. Your Customer would like to conduct a ‘What-if’ analysis for their Trade Promotions, using the
Volumes, Channels, Marketing Pools, Customer Spend as drivers - for different dimensions including
Product, Promotion type etc. in order to generate a Trade Spend Model. What reporting tool may be
used to meet this requirement?

Business Intelligence Reporting

Operational Reporting

Essbase Business Modelling


None of the above

Enterprise Performance Reporting

Correct!

(1/1) Points

23. As part of an ERP implementation a Customer has the following requirements: Report on
transactions such as invoices, payments, assets, journals and on balances; Real-time online reporting;
Wizard-driven easy-to-use creation tool; Advanced formatting and multiple chart options. Which of the
following reporting tools addresses this requirement?

Account Monitor

BI Publisher reports

Financial Reports Centre

SmartView for Microsoft Office™

OTBI Reports

Correct!

(1/1) Points

24. Augmented Analytics powers deeper insight by embedding-

Data Warehouse and Data Science

Transactional and Analytics

Extract and Transform

Machine Learning and Artificial Intelligence

Enrich and Model

Correct!

(1/1) Points

25. Customer complains of failed integrations from Taleo Recruitment & Learn Applications to their E-
Business HRMS. You delivered this Project including post Go-Live Support to the highest standards two
years ago and therefore called in to rescue. What could have gone wrong?
Post Go-Live support handover had incomplete tasks

Taleo is no longer supported and hence integrations fail.

The Customer has taken a reactive issue resolution approach to maintain the solution instead of

proactively looking at the new updates and releases to maintain the integrations

Taleo Recruit and Learn are no longer positioned on the roadmap of HCM solutions and hence

integrations will not work

All of the above

Correct!

(1/1) Points

Page 5 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

26. For a Cloud Project to be successful in the longer run, the Sustainment Plan and Adoption Strategy
should include the following:

A detailed Customer Support plan with detailed SLAs to address issues through tracking tools and ensure
Customer satisfaction

Ensure that KPIs set at the beginning of the Project are met at the end of the Project and the Customer
realized the benefit for their investments

Focus on Business value realization and value assessment with periodical Business review workshops

Oracle provides the needful Customer support for the Cloud services subscribed through MOS - My
Oracle Support and Cloud Portal; A reference to this should be enough.
Proactive and reactive Customer engagement to address issues, help Customer realize value and

progressively update solution to adopt new features and Best Practices

Correct!

(1/1) Points

27. You have successfully delivered a Cloud Project, finishing the final hand-over activities following a
period of post Go-Live support. Your final Business as Usual handover checklist should include all of the
following items EXCEPT:

Ensure the Customer can use the Cloud console to monitor the integration dashboard and set up
notifications

Ensure the Customer Cloud admin understands the Cloud Portal activities to schedule Refresh and sizing
of the environments

Ensure the Customer understands the Updates cycles and the agile testing required during the 2 weeks
period between TEST and PROD

Monitor the OCI Universal Credits Overage, Usage, set limits and Tags

The configuration workbooks and other Project phase deliverables sign-off certificates stored in
Customer Project Repository

Incorrect. Please review Sustainment Plan and Adoption Strategy to find the correct answer.

(0/1) Points

28. You propose implementing Virtual Private Network to restrict Customer employee access outside
their corporate network. What should you consider in the Project Delivery Costs?

Oracle VPN is a free service bundled with Oracle Cloud Service subscriptions. So, there is no additional

costs to budget for.

Oracle VPN comes part of OCI under the Universal Credits subscription – so no additional budget
required.

Oracle VPN is part of the application Services that is configured using the Application Administrator login
access rights. Hence, no additional effort/ Costs to budget for.

Oracle VPN is a subscription based paid service and needs to be budgeted for the Project

Correct!

(1/1) Points
29. Your Customer currently uses Microsoft Active Directory as their Identity Provider. On their
transition to Oracle Infrastructure Cloud (OCI), they intend to restrict OCI resources access initially to the
Project Developers ONLY. Which of the following Cloud Architect’s activity achieves this requirement?

Create a group for developers on OCI and map the group to a similar group in Microsoft Active Directory
during the federation process.

Create a group for developers on OCI, export all the developers from Microsoft Active Directory, and

then import them into the Identity and Access Management (IAM) group.

Federate all Microsoft Active Directory groups with OCI to allow users to use their existing credentials.

Create a new user account for each user, and then create policies to provide access to developers.

Correct!

(1/1) Points

30. Your Customer wants to deploy their application and Data assets on Oracle Cloud Infrastructure.
They would like to isolate different departments, so that visibility and access to resources can be
compartmentalized. Which of the following options helps achieve this isolation layer?

VCN and Subnets

Bare metal instances

Back-end infrastructure

Compartments and IAM policies

Correct!

(1/1) Points

Page 6 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1
31. Your customer would like to enable SSO between EPM Cloud, ERP Cloud and Primavera Cloud
services. Considering there is no Active Directory synchronisation, what is the recommended approach
to achieve this requirement?

This requirement cannot be achieved without OCI subscription.

Enable SSO between EPM, Primavera and ERP

Set up as IDCS as an Identity Provider (IDP) for single point of entry to Oracle Cloud, where EPM, ERP
and Primavera Clouds act as Service providers.

Log an SR to request SAML certificates for all three Cloud services

Correct!

(1/1) Points

32. The Oracle Web Application Firewall builds a secure perimeter around your web applications. Which
TWO options are valid use-cases for OCI WAF?

(Choose all correct answers)

Authorization

Access Control

Provisioning

Bot Management

Multi-Factor Authentication

Correct!

(1/1) Points

33. Oracle Cloud Infrastructure’s security approach is based on seven core pillars. Each pillar has
multiple solutions designed to maximize the security and compliance of the platform. Which of the
following is NOT Considered one of the pillars?

High Availability

Data Encryption

Visibility
Customer Isolation

Disaster Recovery

Correct!

(1/1) Points

34. You are engaged in a Project where the Customer has SSO (Single Sign On) requirement between
their Fusion Application and other third-party vendors. How would you address this requirement?

Customer SSO can’t be integrated with Fusion applications SSO.

Customer need to buy the SSO module, in order to integrate with Fusion SSO.

SSO should be planned and activated at the solution design phase. Customer SSO should be part of the
preapproved list – activation may be requested via a Service Request (SR).

You should raise an SR after Go-Live

SSO should be activated during the UAT phase by logging an SR if it is part of the pre-approved SSO list.
Should it be out of 27 preapproved SSO list, Project Managers should scope an integration effort to build
the solution.

Incorrect. Please review Cloud Security

(0/1) Points

35. Adopting an Agile Testing Mindset & Approach for Cloud Applications Projects means:

Conduct Regression Testing on Application Updates within 2 weeks’ sprints with simplified Test Scripts

Conduct regression testing with simplified Test Scripts in an iterative and incremental phased approach
as you have unlimited time to test the updates prior to progressing the changes to PRODUCTION
Environment

Automated Regression Testing to practice continuous improvement

Exploratory Testing to include Unplanned Consequences besides explicit expectations

Keep it simple and Practice Continuous Improvement

Incorrect. Please review Continuous Testing Strategy and Plan to find the correct answer.

(0/1) Points
Page 7 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

36. Cloud Services Entitlements impact the Testing Strategy & Plan. What are the key points to take into
consideration for Test activity planning?

All of the above

Lead times for Sizing evaluation & Concurrent patching requests

Lead times for Provisioning ATE (Additional Test Environments)

Lead times to Enable additional Cloud Services e.g. IP Whitelisting, VPN, SSO, etc…

Correct!

(1/1) Points

37. To avoid any delays during the UAT, it’s advised that the partner team runs the testing scenario in a
lab in-front of the Customer. Customer may practice using the application during Training or after Go
live. Is this a Best Practice?

False

True

Correct!

(1/1) Points

38. Oracle SaaS Updates Release Documentation is available 6 weeks prior to the General Availability of
the Update. Which of the following Update activities must be part of your Project Plan?

(1). Review the planned Releases 1 week before actual Update Date (2). Develop Test Scripts for all
Mandatory and Optional New Features (3). Conduct Full Regression Testing after implementing New
Features (4). Plan Test activities to test New features ONLY
(1). Review the planned Releases as soon as they are available (2). Identify Mandatory and Optional New
Features (3). Conduct Full Regression Test before implementing any New Features (4). Plan & Prioritise

Test activities to cover the Regression and Mandatory New items over Optional Features

(1). Review the planned Releases as soon as they are available (2). Develop Test Scripts for Regression
Items ONLY (3). Conduct Full Regression Test - No New Features will require testing (4). Plan & Prioritise

Test activities Regression Items ONLY

(1). Review the planned Releases after the Updates are applied to your Instances (2). No Test Scripts are
necessary, the application will work as before following the Update (3). Prior planning is not necessary -

No Post Update Testing will be required.

Correct!

(1/1) Points

39. A Customer would like to know how to set Project cost control plans through the Budgeting Feature
available in OCI. How can you set up budgets?

Budget can be set at a Tenancy level along with Budget alert rule for a % or $ value.

Budget can be set at a Compartment level along with Budget alert rule for a % or $ value.

Budget can be set at a Subnet level along with Budget alert rule for a $ value ONLY

Budget can be set at a Compartment level along with alert rule for a % value ONLY

Budget can be set at a Network level along with Budget alert rule for a % or $ value.

Correct!

(1/1) Points

40. When a Customer subscribes to Fusion SaaS ERP and HCM, Oracle will provision the following as
standard:

1 unified Production Environment, 1 unified Stage Environment and 1 for Payroll; Total 3

1 Environment for Test and Production

One Global Single Instance (GSI)

1 Production Environment for Fin, 1 HCM Production and 1 Fin and 1 HCM as Stage Environments; Total

of 4

1 unified Production Environment and 1 unified Stage Environment; Total 2


Incorrect. Please review Cloud Environments Provisioning and Management to find the correct answer.

(0/1) Points

Page 8 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

41. What is the Welcome E-mail that Oracle sends to its Cloud Customers?

It’s a declaration sent to Customer administrator informing that Oracle is about to start the provisioning.

It’s a declaration sent to Customer administrator informing that Oracle has received the Order from the
Sales Manager.

It’s a declaration sent to Customer administrator informing that Oracle has completed provisioning and

the instance is ready to be used.

It has important list of action the Cloud admin should do.

It’s a declaration sent to Customer administrator informing that Oracle has initiated the provisioning of
instances

Correct!

(1/1) Points

42. What is the unique name for Cloud Environment called? (Note that User authentication and
authorisation for access to Services is defined and controlled at this level)

Service Instance

Cloud Console

Cloud Portal

Data Centre Regions


Identity Domain

Correct!

(1/1) Points

43. A Customer has completed the UAT of a Cloud Fusion ERP and HCM Project and is close to Go-Live.
The Customer insists to have a Gold Instance - i.e. have a back-up of the Production Instance to restore
from in case PROD Data Migration went wrong. Is this possible?

No need for Gold Instance, conduct a P2T after production configuration and the Test Instance may be

used to restore to PROD if necessary

Ask the Customer to buy an extra environment which will serve as Gold instance, to carry out this

activity

Back-Up and Restore is unavailable for Fusion SaaS Projects as in On-Premise Projects. All activities must
be thoroughly tested prior to Production Migration as instance restore is not a service entitlement.

There are alternative solutions in PaaS/OCI to be explored

This is an on-premise strategy and may be used for Cloud implementations.

Correct!

(1/1) Points

44. The Fusion Cloud Project you are managing is going Live in 5 weeks’ time. You realised that the P2T
refresh immediately following Go-Live is missing in your plan. What is the latest point of time to request
the refresh so that your activities align with Best Practice recommendation?

No need to schedule in advance, just escalate to Oracle whenever a refresh is required

No need to schedule any P2T. You may do it after Go-Live.

Latest three weeks in advance avoiding Black-Out periods

Maximum four weeks in advance and it can be rescheduled any time prior to the refresh date.

2 weeks before Go-Live

Correct!

(1/1) Points

45. A Customer would like to know exactly how the Database (DB) instances will be managed in the
Autonomous Database Service. Which of the following options are correct?
Autonomous Database will only self-scale its size

Autonomous DB is managed by Oracle but Back-up and Restore is Customer initiated

Autonomous DB updates are automated and managed by Oracle, but backups are Customer initiated

Autonomous DB updates and Backups are automated and managed by Oracle.

Autonomous DB updates and Backups are Customer initiated.

Correct!

(1/1) Points

Page 9 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

46. You are assigned to a Customer Project in EMEA region who has subscribed to SaaS Applications of
Fusion ERP, SCM, Sales and HCM. Customer has not activated the services yet. What considerations
should be made before activation of the Services?

Language Packs

All of the above

Geographic locations

Timezones

Data Centre location in view of Data Residency requirements

Correct!

(1/1) Points

47. One of the Service entitlements of Cloud applications is Environments refresh (P2T and T2T). A
Customer asks if there is a T2P (Test to Production) as well in order to shorten Production Transition
time for their Oracle Talent Acquisition Cloud - OTAC - (Taleo) and Fusion HCM Applications. What are
the possibilities?
T2P is possible for both environments (Taleo and fusion)

T2P zone refresh may be scheduled as a one-off for OTAC - Taleo as part of Go-Live Transition. The
entitlement however, is unavailable for Fusion HCM – hence a manual configuration will be required.

T2P is possible for Fusion applications but not possible for OTAC - Taleo

T2P is a manual activity of extracting and loading the configuration package

There is no T2P services provided by Oracle for any of its Cloud Application Services

Correct!

(1/1) Points

48. You are documenting the lessons learned following delivery of a Cloud Project. What high level
Project Management ''habits'' would you document as Best Practices for future Projects?

Ensure that there is a proper Change Management Plan driven by the Customer

Integrate the Environment and Instance Management activities with the Project Plan

All of the above

Ensure the Project objectives and the Business goals/KPIs are aligned throughout the Project

Project Delivery in shorter sprints bring quick win benefits to better realise Cloud investment for

Customers – a point to consider for future Project proposals

Correct!

(1/1) Points

49. What is/are the most important Cloud knowledge area(s) for a Project Manager to be familiar with,
for Cloud Projects Delivery readiness?

Cloud Security Management

Cloud Environments Management

The Cloud mindset and Cloud products like Integration, PaaS, Fusion Applications at a high level

All of the above

High level understanding of how the Cloud Services in SaaS/PaaS/OCI work


Correct!

(1/1) Points

50. There are several factors that contribute to the success of Cloud Projects. From a Project Manager's
point of view the following items are the main components EXCEPT:

Proactive issues and Risk tracking

Loosely Defined Scope

Executive Sponsorship

Cloud Instances/Environments Management

Working effectively with Oracle Support

Correct!

(1/1) Points

Page 10 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

51. What are the key principles for Cloud Implementations preparation and readiness to ensure
alignment of Business goals and Project Objectives?

Business value identification; Business process improvement design; User adoption strategies

All of the Above

Trade-off analysis decision-making framework, Efficiency and effectiveness measures and analysis

Business and program strategic alignment; Goals and funding prioritization;

Program success accountability: Enterprise infrastructure and application architecture design and

standards

Correct!
(1/1) Points

52. A Telco Operator has been Live with Oracle CX Services for over six months. When a new product
launch was requested, the delivery turn-around from IT department was more than three months,
which is way too much for the Marketing department. What could have gone wrong during the
implementation that may have resulted in this situation?

Customer Service team is complaining on the lack of a 360degree integrated view of Customer which

should be accessible to the Customer Service Advisors

Marketing team has promotion bundles to be configured in addition to other enhancements and the IT

team is not able to deliver them on Time

IT team is complaining that due to Cloud security they are not able to take back-up to build analytical
reports

Oracle products are not addressing all the Customer requirements and need more commitment from

Oracle to address some of the ER-s

Misalignment between IT and Business KPIs. Business KPIs were set without taking into consideration
the Time to Market T2M KPI of telco services to be developed by IT

Correct!

(1/1) Points

53. A Retail Distribution company has embarked an Oracle Cloud Journey. The CIO expects to leverage
role-based Security and other governance standards to achieve improvements with: -Compliance and
Security; Lesser costs & effort; Reduced Data Breaches and Reduced Security breaches. Which of the
below Project KPIs would you define to align with the CIO’s Business Goals?

(A) Annual Audit and Compliance Costs

(A) and (C) ONLY

(B) % of sensitive records utilizing encryption, data masking, or security policy

(C) Average cost per cybersecurity record and Number of data breaches

(A), (B) and (C)

Incorrect. Please review Transitioning Aligning Business Goals and Cloud Project Objectives to find the
correct answer.

(0/1) Points
54. Which of the following Cloud service is included free of charge with any Application Development
Cloud service?

Oracle Visual Builder Cloud service

Oracle APEX

Oracle API Management Cloud Service

Oracle Developer Cloud Service

Correct!

(1/1) Points

55. Your Customer is interested to implement Blockchain to extend their ledger information and would
like to use bitcoins. Is this possible?

Yes - Oracle provides Permissionless Blockchain platform

No- Oracle provides Permissioned Blockchain platform

Correct!

(1/1) Points

Page 11 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

56. The Continuous integration server that can be used to monitor changes in the source control system
and runs a variety of builds is known as:

Selenium

Maven

Git
Hudson

Eclipse

Correct!

(1/1) Points

57. Which one of the following activities can a Project Manager DO with ODCS (Oracle Developer Cloud
Service)?

Storage of applications dependencies and libraries

Set up and create Wiki Components for documentation and collaboration

User management and adding Team members

All of the above

Continuous Integration and Continuous Deployment (CI/CD)

Correct!

(1/1) Points

58. Oracle’s Application Development Platform allows which of the following Programming languages? :

Phython

Java

All of the above

PHP

Ruby

Correct!

(1/1) Points

59. The software Project management comprehension tool based on the concept of a Project Object
Model (POM) that can manage a Project’s build reporting and documentation from a central location is
called:

Hudson
Eclipse

Maven

Git

Selenium

Correct!

(1/1) Points

60. Your Project scope includes custom build Automotive dealership management solution integrated
with Oracle Cloud ERP Cloud through Oracle Integration Cloud. As ERP Cloud is updated on a quarterly
basis, the Customer wants to ensure that the customizations approach is scalable and won't be affected
by the updates. What approach would you take to ensure that that the custom-built solution is easily
maintained after going live?

Low Code Development in APEX on Bare Metal developed in Agile approach

Microservices approach on containers in the Cloud, managed with DevOps CI/CD approach

Serverless Functions stored on Virtual Machines on the Cloud using CI/CD approach

Monolithic Architecture on Virtual Machines in the Cloud using Agile approach

Correct!

(1/1) Points

Page 12 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

61. You are discussing the benefits of using Oracle Development Cloud Services with your Customer.
Which one of the following is a key differentiator?

It streamlines Deployment; Manages Teams and Developers


It achieves build process agility and Produces better application

All of the above

It enables tracking and reporting including Team Communication

It manages source code and Automates build and deployment of extensions

Correct!

(1/1) Points

62. Which of the Project Management administration activities may NOT be possible within Oracle
Developer Cloud Services (ODCS)

Analysing Usage Metrics and Data

Manage and Mitigate Risks

Import/Export Projects

Define Project Properties

Customize Issue Tracking

Correct!

(1/1) Points

63. Oracle Cloud provides an Open platform for building, integrating, extending, securing and managing
a multi-Cloud infrastructure by leveraging Open Source choice of Technology Stacks such as Java, Ruby,
Python etc.

False

True

Correct!

(1/1) Points

64. Modern Best Practices were used during pre-sales scoping for a Customer’s multi pillar Project (ERP,
HCM and CX). Given the Customer is open to Solution Driven approach, what Business Process related
activity is recommended as a continuation into the implementation phase of the Project?

It will be useful to identify the Customer pains areas and contrast them with improvements possible

with Oracle Modern Best Practice


Better hone/define Customer’s objectives, focus, & obstacles to success, Map processes to capabilities

and craft digital transformation plans

Leverage the MBPs for familiarization training based on the Level 2 diagrams of MBPs and drill down to

Level 3 diagrams during implementation for solution walkthrough workshops/CRP sessions

All of the above

Guide trust-building process/solution driven discussion with the Customer to achieve quick win results

Correct!

(1/1) Points

65. Your Customer refers to an RFP (Request for Proposal) appendix matrix listed with system
requirements for SaaS Finance, HCM and Procurement in 5 countries. Planning and preparing for CRP
(Conference Room Pilot) sessions, what is the Best Practice approach to mitigate any Solution Gaps you
may encounter?

Leverage a Set Up questionnaire mapped to MBP to capture necessary information to Configure the

system activities and identify Gaps.

Conduct detailed Requirements gathering workshops and create a traceability matrix following the
CRPs. Design a global solution based on the traceability Matrix to address Customer requirements.

Engage appropriate key users and stakeholders at the early phases of the Project to reinforce a No
customization approach for SaaS Solutions.

Review the Customer objectives and pain areas. Walk through the Modern Best Practice (MBP) diagrams
during the CRPs to identify solution Gaps.

Correct!

(1/1) Points

Page 13 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.


Section 1

66. One of your PM colleagues informs you that the Oracle Modern Best Practices are just a marketing
tool to use in presales. He suggests conducting an activity level Business Process diagramming exercise
(from scratch) to capture Customer requirements. Which of the following is recommended approach as
guided by Oracle?

Proceed with the detailed mapping approach, as MBPs may only be used in the Sales cycle.

No, MBP is not just marketing tool, you can leverage existing Level 3 (Visio) diagrams in MOS through

iterative and incremental approach during implementation

MBPs are L2/L3 diagrams which can be used to deliver ANY process in the Project why invent the wheel

Ensure conducting a fit/gap analysis of Business Processes and carry out 3 iterations of detailed
diagramming to fully capture the Business Process activities

Correct!

(1/1) Points

67. Your Project scope includes Cloud ERP, HCM, Payroll, Talent Management with OIC integrations to
On-Premise Time recording System. Oracles Analytics Cloud is used for reporting. The Customer PM
would like to identify Customer Business SMEs that will require training. Who do you classify as Business
trainees?

Identify the impacted departments ONLY and train the key SMEs. Manage the overall Change with
needful communication

Train everyone in the organization on Cloud

Train all HR Key Users for system use. Train IT team to develop the applications, integrations, and build

reporting dashboards.

Train all the Key Users, IT Applications development team, Infrastructure team and Help desk teams

Train the Infrastructure team on migrating E-Business to Cloud and on how to monitor integrations

Incorrect. Please review Training and Knowledge Transfer Strategy and Plan to find the correct answer.

(0/1) Points

68. Your Delivery scope includes training the Administrators, Power Users and End Users. In order for
Training objectives to be met, Product adoption maximised and training is effective, what measures are
suggested that you put in place?
Include a training effectiveness assessment in the delivery plan to ensure the gaps are identified as early

as possible

Ensure all the trainers sign off the trainings they attended and record the sessions for further learning

Establish a train the trainer model to make sure the resistance to Change is addressed from within the

organization

Identify the learning objectives and desired outcomes of the Project.

Subscribe to Oracle Cloud Learning Subscription to maximize learning

Correct!

(1/1) Points

69. The requirements gathering approach with User-Centred design process to understand their needs,
experiences, behaviours and goals for software design is called -

Personas

Use Case Diagrams

Story Mapping

WireFrame

User Stories

Correct!

(1/1) Points

70. Which of the following is NOT Considered as an Agile Principle?

Deliver Value

Structured Teams

Reflect and Adjust

Working Software

Embrace Change
Correct!

(1/1) Points

Page 14 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

71. Which one of the following is NOT considered as a benefit of DevOps?

Environment Management

Process metrics

Increased Release Velocity

Reduced Defects

Shorter Development Cycle

Correct!

(1/1) Points

72. You are assigned to a Project where the scope of work is EPM - Enterprise Performance
Management and Oracle Analytics Cloud. What would be the implementation approach?

Agile approach – As it includes Custom development

EPM - Solution Driven Approach and Analytics Cloud -Requirement Driven

Requirement Driven – As EPM and analytics are Business and Data requirements driven

Solution Driven – As there are standard processes that may be adopted for EPM and Analytics

EPM - Requirement Driven Approach and Analytics Cloud Solution Driven

Correct!

(1/1) Points
73. What is DevOps?

Disciplined Agile

Operations

Methodology

Culture

Framework

Incorrect. Please review Implementation Approach for Solution in Scope to find the correct answer.

(0/1) Points

74. Your Customer Project scope includes Fusion Engagement Cloud, Service Cloud (RightNow), Field
Service (TOA), Commerce (ATG), CPQ, Marketing Eloqua and Responsys, integrated through OIC (Oracle
Integration Cloud) recipes. What implementation approaches apply for this scope?

OIC - Requirement Driven; Marketing - Strategy Driven; Other CX Products - Solution Driven

There is no one-size fit all. It is mostly Solution Driven; Except for OIC, some parts of Service Cloud
extensions and Marketing where configuration is shaped by changing Business Strategy.

Agile - Iterative and incremental approach

Solution Driven approach fits the entire scope as there are OIC recipes which are plug and play

Requirement Driven Approach is appropriate for this scope

Correct!

(1/1) Points

75. Agile is described as:

All of the Above

Adopting Ongoing communication within the Project team and with the client

A flexible, iterative design and build process

Delivering in a dynamic environment with changing or evolving requirements

Approach that emphasises adaptability to changing situations


Correct!

(1/1) Points

Page 15 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

76. The Customer is carrying out Train-the-Trainer activities in parallel to the Project UAT activities.
Which of the following activities must the Super Users be trained in, for them to be equipped with
Business insights on a day to day basis post Go-Live?

It`s Business as usual with a more user-friendly GUI, there is no specific training necessary

Module and screen specific embedded Analytics dashboards, Infolets and AI

Fixed set of Regression test activities (that remain unchanged) that must be repeated every Quarter

Job roles and duties should be revised every Quarter – hence functional training is necessary in this area

Functional training for the system configuration, impact assessment training and patch analysis activities

Correct!

(1/1) Points

77. Your Delivery scope for Cloud Transformation Project includes SaaS/PaaS/OCI components. Change
Management is led by the Customer. Which of the following Change Management activities are
ESSENTIAL in the Customer’s Change planning from the CLOUD Project perspective?

Depict the reasons for resisting Change and prepare mitigation activities

Align corporate vision, mission, objectives and KPIs of the organization with employee goals

Prepare a Change Management and Communication plan


Identify key stakeholders and their roles and responsibilities in the Project

Identify Customer Change agents and Cloud champion(s) from Business and IT to drive the technology

and process Change

Correct!

(1/1) Points

78. Which of the following activities should be part of a Change Management Plan for Oracle SaaS CX
Project with OIC integration to E-Business Suite?

Conduct organizational impact assessment for shifting from On-Premise to Cloud for the Business and IT

operations departments

Set up of Cloud communication notifications to target audience to embed the new Cloud culture in the

Customer organization

Train the Customer IT team on Cloud Environments Management, Cloud console and portal usage

For the SaaS applications, leverage the Oracle Modern Best Practices to facilitate adoption and process

change. For integrations, leverage integration recipes

All of be above

Correct!

(1/1) Points

79. Enterprise Business Analysis and Architecture processes continuously refine an organization’s:

Internal and external Compliance and Regulatory requirements

All of the Above

Cloud Strategy and Roadmap

Future-State Architecture

Business Strategies and Requirements

Correct!

(1/1) Points

80. To take a systematic and methodical approach for a Project, it is important to conduct a thorough
analysis of which of the following the Enterprise Architecture Layers:
Strategy, Data, Applications, Infrastructure

Business, Data, Software, Technology

Information, Data, Business processes, Technology

Business, Databases, Applications, Technology

Business, Data, Applications, Technology

Correct!

(1/1) Points

Page 16 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

81. Which of the following is a characteristic of Monolithic Architecture?

Decentralized: each service may use its own database.

Consists of loosely coupled services

A failure in any component could affect the availability of the entire application

Can be scaled independently of the other services

Deployed independently, without affecting the other services in the application

Correct!

(1/1) Points

82. The software architecture style that has complex applications composed of small, independent and
self-contained processes which communicate with each other using language agnostic APIs is referred to
as:
Service Oriented Architecture

Monolithic Architecture

Microservices Architecture

Macroservices Architecture

Serverless Function Architecture

Correct!

(1/1) Points

83. What are the TWO initial things to consider when you decide to migrate a legacy application to
Cloud

(Choose all correct answers)

Perform analysis to verify the Cloud compatibility and estimate migration effort

Assess the Business need

Provision the Cloud resources and install the application package

Discard the old legacy application and adopt a new and modern Cloud based application offering the
same functionalities

Correct!

(1/1) Points

84. You are about to start the VALIDATE/TEST phase of a Move and Improve to OCI Project and want to
ensure all the key considerations are taken care of. Which of the following should be considered?

Configure application logic/data approach to transfer to Cloud

Identify and Size the deployment environments with the correct Cloud services

Design the target architecture

Continuously test and validate the application data migrated to Cloud

Correct!

(1/1) Points
85. Identify the THREE key considerations for Move and Improve of an On-Premise packaged application
to OCI

(Choose all correct answers)

What is the vendor`s certified/verified approach?

Is there a certified image available in the OCI Marketplace?

Does the vendor provide any accelerator to speed up the Project?

Is the application certified for ADW?

Correct!

(1/1) Points

Page 17 of 18

Test: 100066 - Oracle Cloud Project Management Assessment

Review your answers, feedback, and question scores below.

Section 1

86. A Customer is moving their On-Premise Forms Application to Application Express on Autonomous.
This is a Move and Improve Project

FALSE

True

Correct!

(1/1) Points

87. Select the TWO knowledge components that are relevant to a MOVE-only Project

(Choose all correct answers)

WebLogic fundamentals

Oracle DB Cloud fundamentals


Fundamentals on High Availability and D/R

Web Application Firewall

All of the above

Incorrect. Please review Implementation Approach for OCI Move and Improve to find the correct
answer.

(0/1) Points

88. In a Move and Improve Project we consider the subject workload mostly as a “black box”. Which of
the follow statements describes this accurately?

All the above

We use the black colour to tag these workloads in the respective architecture diagrams

We do not consider any changes of the functionality encapsulated in the target workload, so that the
end-users will experience no changes in their nature of their work. Any improvements may just be to the

wrapping so as to improve the Quality of Service

The target workloads are boxed into VMs or Containers, so they run on improved environment

Correct!

(1/1) Points

89. You are managing a Move and Improve Project of a bespoke application developed on WebLogic
Server and Oracle Database. The heavily transactional On-Premise System runs on Windows Servers and
has variable workloads across the week. As it is a core system, there is a lot of demand for database
administration to keep the lights-on. Which of the following options serve as a Best Practice
improvement solution to meet the Customer’s needs in an efficient way?

Integrate with Oracle Management Cloud Service to monitor the application

Migrate the database to Autonomous

Deploy the WebLogic workloads on Java Cloud Service

Modernize the application with the use of Containers and microservices

Correct!

(1/1) Points
90. As a PM for a Move and Improve to OCI Project, you’d like to have better visibility of architectural
components as well as better cost control on resources being utilised. Select THREE options that enable
you to achieve your needs

(Choose all correct answers)

Clearly define the detailed target and intermediate architectures

Leverage OCI tagging in order to apply budgeting techniques on OCI consumption

Contact Oracle Sales

Define a proper and detailed inventory of migratable assets

Correct!

(1/1) Points

Page 18 of 18

You might also like