Bridge Construction Replacement Program (BCRP) 1 Design and Build Bridges for Prepared by AABR Date: 11/10/20

Region II and CAR Contract Package 3 Checked by JA Date: 11/10/20


MALITAO BRIDGE 2, CAR Reviewed by JA Date: 11/10/20

SUMMARY

ITEM NO. DESCRIPTION BID COST DETAILED DESIGN VARIANCE

(1) (2) (1) - (2)

PART B OTHER GENERAL REQUIREMENTS 4,314,733.20 4,314,733.20 -

PART C EARTHWORKS 3,527,977.51 5,708,663.03 2,180,685.52

PART D SUBBASE 874,289.19 1,089,638.37 215,349.18

PART E SURFACING WORKS 6,451,407.62 7,969,155.87 1,517,748.25

PART F BRIDGE CONSTRUCTION 16,272,646.67 26,764,014.13 10,491,367.46

PART G SLOPE PROTECTION 20,002,089.68 7,398,071.60 (12,604,018.08)

PART H MISCELLANEOUS WORKS 2,108,097.06 2,938,907.80 830,810.74

TOTAL COST 53,551,240.93 56,183,184.01 2,631,943.08

% Variance of Cost
4.91%
(Bid Cost against Detailed Design)