You are on page 1of 2

Bridge Construction Replacement Program (BCRP) I, Design and Build Bridges in Luzon (CAR and Region II)

Contract Package 3, Contract ID No. 16ZO0010


MALITAO BRIDGE 2, CAR
MATRIX OF QUANTITIES FROM ORIGINAL CONTRACT TO DETAILED ENGINEERING DESIGN

SUMMARY OF QUANTITIES
Total Quantity
PAY ITEM Approach Road Abutment Piers
DESCRIPTION UNIT Superstructure
NO. 1st 2nd A B 1 2
B. OTHER GENERAL REQUIREMENTS
B.11 Provisional Sum (3% EDC) PS 1 1

B.14 Environment Management and Monitoring mos. 11 11

B.7(1) Occupational Safety and Health Program mos. 11 11

B.9 Mobilization/Demobilization ls. 1 1

SPL 2 Detailed Engineering Design (5% EDC) ls. 1 1

C. EARTHWORKS
100(1) Clearing and Grubbing sq.m 3264.12 11213.83 14477.95

100(4) Individual removal of trees each 10.00 20.00 30.00

101(3)b1 Removal of Actual Structures/ Obstruction (150 mm thick PCCP, Reinforced) sq.m 173.97 916.40 1090.37

101(3)b5 Removal of Actual Structures/ Obstruction (280 mm thick PCCP, Reinforced) sq.m 400.46 2077 2477.46

101(4)c Removal of Existing Curb and Gutter sq.m 101.78 628.80 730.58

102(2) Surplus Common Excavation cu.m 6981.06 52472.07 59453.13

103(1)a Structure Excavation (Common Soil) cu.m 107.86 390.18 498.04

104(1)a Embankment from Roadway Excavation cu.m 1626.90 87.81 1714.71

105(1)a Subgrade Preparation (Common Material) sq.m 1582.49 3662.04 5244.53

D. SUBBASE COURSE
200(1) Aggregate Subbase Course cu.m 505.69 893.92 1399.61

E. SURFACING WORKS
300(2) Crushed Aggregate Surface Course cu.m 0.00

311(1)a Portland Cement Concrete Pavement (Unreinforced) (0.15 m thick, 14 days) cu.m 577.29 1120.59 1697.88

311(1)e1 Portland Cement Concrete Pavement (Unreinforced) (0.28 m thick, 14 days) sq.m 1409.10 2502.65 3911.75

F. BRIDGE CONSTRUCTION
101(1) Removal of Structures and Obstruction (Existing Bridge L = 63.80m) ls. 0.00 0.00

102(4) Surplus Unclassified Excavation (Rechannelling/Dredging Excavation at River Bed) cu.m 0.00 0.00 0.00

103(1)a Structural Excavation Above O.W.L. cu.m 252.55 409.84 39.36 19.20 720.95

103(1)b Structural Excavation Below O.W.L. cu.m 241.44 0.00 244.08 191.33 676.85

103(3)a Backfill Above O.W.L. cu.m 126.28 204.92 19.68 9.60 360.48

103(3)b Backfill Below O.W.L. cu.m 62.04 0.00 0.00 0.00 62.04

104(2)a Embankment from Selected Borrow cu.m 59.36 59.36 118.71

200(1) Aggregate Subbase Course cu.m 3.24 3.24 6.49

401(2)a Concrete Railing (Standard) m 127.62 127.62


Bridge Construction Replacement Program (BCRP) I, Design and Build Bridges in Luzon (CAR and Region II)
Contract Package 3, Contract ID No. 16ZO0010
MALITAO BRIDGE 2, CAR
MATRIX OF QUANTITIES FROM ORIGINAL CONTRACT TO DETAILED ENGINEERING DESIGN

SUMMARY OF QUANTITIES
Total Quantity
PAY ITEM Approach Road Abutment Piers
DESCRIPTION UNIT Superstructure
NO. 1st 2nd A B 1 2
404(1)a Reinforcing Steel (Grade 40) kg. 4216.28 4216.28 3727.50 3727.50 38755.00 54642.55

404(1)b Reinforcing Steel (Grade 60) kg. 30222.68 30222.68 37405.73 37405.73 63737.00 198993.80

405(1)a3 Structural Concrete (Class A, 20.68 Mpa, 28 days) cu.m 32.45 32.45 0.00 0.00 168.83 233.74

405(1)b3 Structural Concrete (Class A, 27.58 Mpa, 28 days) cu.m 171.67 171.67 120.62 120.62 117.95 702.52

407(8) Lean Concrete cu.m 1.32 1.32 5.70 5.70 14.04

413(1)/(2) Preformed Sponge Rubber or Cork Joint Expansion (12 mm thick cu.m 30.00 30.00

413(1)a Premolded Expansion Joint Filler with Sealant (12 mm thick) cu.m 0.11 0.11

413(5) Elastomeric , Hot-Applied Expansion Joint Sealant (with Single-Sized Aggregates) cu.m 0.14 0.14 0.28

103(5)b Shoring, cribbing and related works (Cofferdamming) l.s. 1.00 1.00

517(1)a Drain Pipe (Galvanized) (150mm) l.m 15.00 15.00

412(1) Elastomeric Bearing Pad each 4.00 4.00 8.00

G. SLOPE PROTECTION
500(3)b1 Lined Ditch (Concrete, Rectangular) l.m. 179.77 653.53 833.30

505(2)a Grouted Riprap, Class A cu.m 286.40 693.65 217.25 217.25 1414.54

505(1)a Riprap, Class A (Loose Boulder) cu.m 80.15 80.15 160.30

508(1) Hand-laid Rock Embankment cu.m 0.00

511(3) Filter cloth sq.m 394.94 67.33 462.27

622(3)b Vegetation (Vetiver Grass System) sq.m 0.00

H. MISCELLANEOUS WORKS
603(3)a1 Metal Guardrail (Metal Beam) Including Post, (Single) l.m. 72.49 80.1 152.59

603(4) Metal Beam End Piece each 6 4 10.00

605(1)a3 Warning Signs (900 mm, Class W1-1C) ea. 1 1 2.00

605(2)b1 Regulatory Signs (600mm, Class R1-2A)) ea. 1 1 2.00

605(3)a1 Guide or Informatory Signs (Class G1-1) ea. 1 1 2.00

606(1)a1 Pavement Markings (Premixed Reflectorized, White) sq.m 0 0 0.00

606(1)b1 Pavement Markings (Reflectorized Thermoplastic, White) sq.m 64 94 157.91

606(1)b2 Pavement Markings (Reflectorized Thermoplastic, Yellow) sq.m 0 5 5.40

622(1)b Coconet Bio-Engineering Solution - Coco-net sq.m 1188.40 11216.91 12405.31

622(2)c Coconet Bio-Engineering Solution - Coco-logs/Fascine l.m. 125.09 1180.73 1305.82

622(3)b Coconet Bio-Engineering Solution - Vegetation (Vetiver Grass) sq.m 1188.40 11216.91 12405.31

B.5 Project Billboard / Signboard ea. 1 1 2.00

B.15(1) Detour/ Access Road ls. 1.00 1.00

B.8(2) Traffic Management ls. 1.00 1.00