Professional Documents
Culture Documents
Disclaimer: This document has been developed specifically for EPCIC of Pegaga Project
C3 21.07.2020 Approved for Construction (Re-AFC)
C2 26.08.2019 Approved for Construction (Re-AFC)
C1 18.03.2019 Approved for Construction (AFC)
4.4 19.10.2018 Issue for Approval (IFA)
4.3 30.07.2018 Re-Issue for Review (Re-IFR)
4.2 21.03.2018 Issue for Review (IFR)
4.1 19.03.2018 Inter-Discipline Check (IDC)
Rev No.
Date Purpose of Issue
REVISON CHANGE HISTORY
All major changes to the document at this current revision are recorded below.
(Does not include correction of typos or formatting changes)
Re-AFC
Mohd Zaieri Bin Incorporating Re-AFC comments. This
C3 21.07.20
Mohamed document has been reviewed in advance
by COMPANY.
HOLD LIST
Page 2 of 44
TABLE OF CONTENTS
1 INTRODUCTION ............................................................................................................... 6
1.1 Project Background ............................................................................................ 6
1.2 Facility Description ............................................................................................. 6
1.3 Purpose of Document ......................................................................................... 7
1.4 Scope of Document............................................................................................. 7
1.5 Reference............................................................................................................. 7
2 DEFINITIONS AND ABBREVIATIONS ................................................................. 8
2.1 Definitions ........................................................................................................... 8
2.2 Abbreviations ...................................................................................................... 11
3 ASSET INTEGRITY REQUIREMENTS FOR EXECUTE PHASE ........................ 13
3.1 CONTRACTOR Asset Integrity Scope for EPCIC Execute Phase ....................... 13
3.2 Asset Integrity Plan ............................................................................................. 14
3.3 Asset Integrity Road Map .................................................................................... 15
4 ASSET INTEGRITY ACTIVITIES ........................................................................ 17
4.1 Project Validation ................................................................................................ 17
4.2 Leadership and Accountability ............................................................................. 18
4.3 Laws and Regulations ......................................................................................... 19
4.4 Codes and Standards.......................................................................................... 19
4.5 Performance Evaluation ...................................................................................... 19
4.5.1 Key Performance Indicators (KPI) .................................................................... 19
4.5.2 Implementation of Quality Assurance/ Quality Control (QA/QC) ................... 22
4.5.3 Inspections and Audits ........................................................................................ 22
4.5.3.2 Audits ................................................................................................................. 22
4.5.4 Management Review........................................................................................... 22
4.6 Management of Change/ Deviations ................................................................... 23
4.7 Risk Management ............................................................................................... 24
4.8 Barriers for Safety in design ................................................................................ 25
4.8.1 Safety Studies during Detailed Design Engineering (DDE) ............................ 25
4.8.2 Development of Safety Critical Elements (SCE) and PS................................. 26
4.8.2.1 Safety Critical Elements (SCE) ......................................................................... 27
4.8.2.2 Performance Standards (PS) ............................................................................ 27
4.9 Life Cycle Cost (LCC) in Procurement process for Type 1 Equipment ................. 27
5 CORROSION, ASSET INTEGRITY AND INSPECTIONS PROGRAMME ........... 28
5.1 Corrosion Risk Assessment (CRA)...................................................................... 28
5.2 Risk-Based Assessment and Inspection Programme .......................................... 29
Page 3 of 44
5.3 Inspection Requirements/ Baseline Inspection Requirements ............................. 30
5.3.1 Baseline Inspection for Pressure Equipment .................................................................... 30
5.3.2 Underwater Baseline Inspection for Offshore Structure ..................................................... 31
5.3.3 Intelligent Pigging (IP) Inspection ...................................................................................... 31
5.3.4 Underwater Baseline Inspection for Pipeline external ........................................................ 32
5.4 Anomaly Management (during Execute phase) ................................................... 32
5.5 Procedure Development ...................................................................................... 32
5.6 Competency Assurance ...................................................................................... 33
APPENDIX A: ASSET INTEGRITY FOR EXECUTE PHASE ACTIVITIES .................................. 34
APPENDIX B: ORGANIZATION CHART FOR O&M AND ASSET INTEGRITY DURING
EXECUTE PHASE ...................................................................................................................... 43
Page 4 of 44
LIST OF FIGURES
Figure 3.4: The Road map for Asset Integrity requirement in Execute Phase
LIST OF TABLES
Table 4.2: List of KPI according to CONTRACTOR’s Contract Quality Plan (CQP)
Page 5 of 44
1 INTRODUCTION
North Luconia
Delta
SK320
Baram Delta
Central Luconia
Rim
Balingian
Tatau Province
Page 6 of 44
1.3 Purpose of Document
As a derivative of the Mubadala Petroleum Operations Management System and the sub-
set Asset Integrity Management Standard, the Project Asset Integrity requirements for
“EPCIC Execute phase” document has been used in providing the plan of the activities for
the elements required to ensure that all credible integrity threats with the potential to result
in Health, Safety, and Environmental (HSE) impact. Additionally, economic and
reputational aspects must also be covered, ie integrity threats which endanger equipment/
items (COMPANY’s assets) or affect production or reputation. Beyond that, in the project
phase, design Integrity must be verified and inspectability, operability and maintainability
shall be reviewed and validated.
This document identifies the elements relevant to Asset Integrity requirements in “Execute
phase” and its activities for the preparation of handover to COMPANY’s Operations prior
to Start-up and Commissioning of the Pegaga facilities. CONTRACTOR scope covers the
Asset Integrity plan in “Execute phase” which addresses the Technical Integrity during
Detailed design engineering (DDE), Procurement, Construction, Transportation &
installation, Hook-up, testing and Commissioning.
• Potential functional failures have been identified and assessed, and appropriate
inspection, maintenance and testing regimes are developed for their prevention and
/ or detection prior to start-up.
• Appropriate quality and competency management systems have been established
and applied and are subjected to on-going/ continuous reviews and audits.
• Asset “as-built” design, mechanical completion / acceptance, commissioning
records and safe operating limits have been accurately documented for reference
and handover to COMPANY’s Operations and Productions.
1.5 Reference
Reference Title
Page 7 of 44
Reference Title
2.1 Definitions
Page 8 of 44
Installation and Commissioning (EPCIC)
Site : Site means the location (s) of the offshore facilities and
Pipelines
Page 9 of 44
its intended function in a safe, effective and efficient
manner over its entire life cycle, in order to achieve the
organizational objectives.
Life Cycle Cost : Life Cycle Cost is defined as the total cost throughout its
life including planning, design, acquisition, support costs
and any other costs directly attributable to owning and
using the assets. In calculating the Life Cycle Cost
requirements, the cost associated with removal for onsite
and offsite calibration/ certification shall be taken into
account. It should also consider the cost associated with
Long Term Service Contracts (LTSA) if applicable and
rental/ membership fee of LTSA or spare unit (if
applicable).
Page 10 of 44
diving bell or other subsea chamber used for such
operations;
(d) any other event arising from a work activity involving
death or serious personal injury to five or more persons on
the facilities or engaged in an activity on or in connection
with; or
(e) any major environmental incident resulting from any
event referred to in paragraph (a), (b) or (d) above.
Risk : The product of the consequence and likelihood
associated with hazardous event.
2.2 Abbreviations
Page 11 of 44
EPCIC Engineering, Procurement, Construction, (Transportation &)
Installation and Commissioning
EERA Escape, Evacuation and Rescue Analysis
ESSA Emergency System Survivability Analysis
FEED Front End Engineering Design
FERA Fire and Explosion Risk Assessment
FMD Flooded Member Detection
GTG Gas Turbine Generator
H2S Hydrogen Sulfide
HAZID Hazard Identification
HAZOP Hazard Operability
HC Hydrocarbon
HFE Human Factor Engineering
HUC Hook up and Commissioning
ICPP Integrated Central Processing Platform
ICSS Integrated Control and Safety Systems
IP Intelligent Pigging
IPF Instrumented Protective Function
ITP Inspection Test Plan
IVB Independent Verification Body
KPI Key Performance Indicators
LCC Life Cycle Cost
LCCA Life Cycle Cost Analysis
MAH Major Accident Hazards
MDR Master Deliverable Register
MP Mubadala Petroleum
MOC Management of Change
MWS Marine Warranty Surveyor
NDT Non-destructive Testing
OEM Original Equipment Manufacturer
OMSB Ocean Might Sdn Bhd
OPEX Operation Expenditure
PC Procurement and Construction
PDMS Plant Design Management System
PFD Process Flow Diagram
PMT Project Management Team
POF Probability of Failure
P&ID Piping & Instrument Diagram
PS Performance Standard
QRA Quantitative Risk Analysis
RAM Reliability, Availability and Maintainability
RBI Risk Based Inspection
RCM Reliability-centered maintenance
RFQ Request for Quotation
RT Radiographic Testing
SCE Safety Critical Element
SFSB Sapura Fabrication Sdn Bhd
SGIA Smoke and Gas Ingress Analysis
SIL Safety Integrity Level
SSIV Subsea Isolation Valve
UTTG Ultrasonic Testing Thickness Gauging
T&I Transportation & Installation
TBA To be advised
Page 12 of 44
TBC To be confirmed
TBD To be developed
TEG Triethylene Glycol
TPA Third Party Agency
WHD Wellhead Deck
Within the EPCIC phases of Pegaga Project scope, the term ‘integrity’ refers to the
‘Technical Integrity’ of an equipment/ items which being designed, procured,
fabricated, constructed, inspected, installed and commissioned in a manner that
validates design integrity and ensure that the objectives are being met prior to handover
to COMPANY. Technical Integrity is achieved through the completion of inspection,
testing, witnessing, auditing and examination activities to assure that the technical
criteria set for all equipment/ items shall be met as set by the Performance Standard
(PS) of each SCEs.
Asset Integrity for each project can be achieved when the risk of a failure occurring which
would endanger the safety of personnel, the natural environment or asset value has
been reduced to is ‘As Low As Reasonably Practicable’ (ALARP). It is derived from the
aggregation of three (3) discrete components/ phases of integrity management which
prevail through the successive phases of the asset development and operations lifecycle
as described in Figure 3.1 below;
Page 13 of 44
CONTRACTOR’S
SCOPE
Asset Integrity Management (AIM) is a continuous process throughout the asset lifecycle.
In general there are five phases in an asset’s lifecycle including identify/ access, evaluate,
concept definition, execute, and operate as illustrated in Figure 3.2. Substantial emphasis on
design integrity has been made at the concept selection and concept definition phases to
establish asset integrity requirements. For Execute phase, the focus will be on Technical
Integrity. However the process will continue as the project progresses from Execute phase to
Operate phase and handed over to COMPANY's Operations. During Operate phase, the focus
is on Operational Integrity (OI) and the assets need to be maintained in order to sustain its
integrity.
The Execute phase is concerned with the realisation of the FEED and ensuring that Regulatory
requirements, COMPANY requirements and Codes & Standards will be applied throughout
the subsequent Detailed Design Engineering (DDE), Procurement, Construction,
Transportation & Installation (T&I), Hook-up and Commissioning (HUC).
Asset integrity (AI) plan for Execute phase has been developed for Pegaga Project to
ensure the process of handover to Operate phase meet its all technical requirements.
The AI plan requires the systematic and continuous monitoring of activities from detail
engineering, procurement, manufacturing, construction, testing, installation,
commissioning, operation, inspection and maintenance to meet asset integrity
objectives. This plan shall demonstrate that all the all credible integrity threats which
could result in HSE impact are proactively identified, assessed and effectively controlled
throughout the execution phase and shall involve COMPANY, CONTRACTOR,
SUBCONTRACTORS, Suppliers, Vendors or other personnel who are performing works
and involved in Pegaga Project.
The entire AI plan/ program is further divided to activities, which being executed by
Page 14 of 44
CONTRACTOR and in collaboration with SUBCONTRACTORs. Each relevant activity
is further detailed in Appendix A of this document.
The timeline of the execution of the asset integrity program is further discussed in
Section 3.3.
Asset Integrity road map has been developed for Execute phase to ensure that key
elements of the Asset Integrity requirement is addressed and delivered in timely manner.
The Asset Integrity Road Map is presented in detail in Figure 3.4 below. For easy
reference, the key dates are presented in Table 3.1;
Expected to Expected to
No. ACTIVITIES
Start Complete
(Actual)
Safety Studies in Detailed Design
1.0 Apr-2018 Feb-2019
Engineering
Major Accident Hazard (MAH)
2.0 29-Jun-2018 23-Nov-2018
Identification
3.0 Bow-tie workshop 28-Aug-18 29-Aug-18
Design and Operational Safety Critical
4.0 Elements (SCE) and Performance 30-Nov-2018 Apr-2019
Standards (PS)
Revision of detail design CMP (WHD
5.0 02-Jun-2019 07-Aug-2019
& CPP)
5.1 Review & update CMP 02-Jun-2019 26-Jul-2019
Expected to Expected to
No. ACTIVITIES
Start Complete
(Actual)
5.2 Submission of draft CMP Review
26-Jul-2019 30-Jul-2019
report
5.3 Submission of final CMP Review
30-Jul-2019 07-Aug-2019
Report
Update Corrosion Management
6.0 02-Jun-2019 05-Aug-2019
Strategies & Procedures
Review & update strategies &
6.1 02-Jun-2019 02-Aug-2019
Procedures
6.2 Submission of comments 02-Aug-2019 05-Aug-2019
7.0 Conduct CRA for Pressure System, 02-Jun-2019 29-Nov-2019
Structures & Pipelines
7.1 CRA Pressure System 02-Jun-2019 10-Oct-2019
7.2 Conduct CRA for Structures As confirmed by MP, CRA for
Structures & Pipeline not required.
8.0
Key-Point Location (or Corrosion 02-Jun-2019 09-Jun-2020
Monitoring Location – CML)
Page 15 of 44
8.1
Define CMLs on Isometric WHD 02-Jun-2019 18-Oct-2019
8.2 Define CMLs on CPP
02-Jun-2019 15-May-2020
8.3 Define CMLs on Pressure Equipment
02-Jun-2019 22-May-2020
9.0 Baseline Inspection
02-Jun-2019 *03-Feb-2021
9.1 Baseline Inspection (UTTG) for WHD
02-Jun-2019 16-Mar-2020
9.2 Baseline Inspection (UTTG) for CPP
01-Jul-2020 *27-Mar-2021
10.0 Baseline Collection 13-Feb-2020 *27-Apr-2021
Page 16 of 44
17.c Management Review No.3 Jan-2020
Table 3.1: Key dates for Asset Integrity Road map (during Project execution)
Not Not
Required Required
Page 17 of 44
Page 18 of 44
All Safety studies have been addressed during the DDE stage and completed on
February 2019 with the last workshop to be conducted is Design HSE Case
presentation. SCEs and PS planned to be conducted after the design HSE case
considering all the elements of technical integrity have been included. SCEs and PS is
envisaged to be completed before the start of Asset register development for RBI and
CMMS database preparation.
The management reviews is planned to be held for every 6 monthly. Details can be
referred to Section 4.5.4.
The underwater baseline inspection to be carried out during T&I 2nd campaign which
is approximately in Early June 2021. Meanwhile IP will be carried during T&I campaign
which is scheduled on Early October 2021 (tentative).
To support the confirmation of Design Integrity during the detailed design engineering
(DDE), COMPANY has engaged an Independent Verification Body (IVB) (i.e Bureau
Veritas (BV)) who independently verified the detailed design engineering deliverables
performed by CONTRACTOR.
For the Execute phase, COMPANY and CONTRACTOR have engaged and employed
the independent bodies in validating the following scopes;
Independent
Phases Scope of work Engaged by
Bodies
To review and verify the
entire detailed design
engineering which has
been performed by
CONTRACTOR and
Independent
Detailed design issue a Certificate of
Verification Body COMPANY
engineering (DDE) Fitness for the design of
(IVB)
the facilities to confirm
the adequacy and
correctness according to
the required Codes &
Standards.
Page 17 of 43
Phases Independent Scope of work Engaged by
Bodies
To review all aspects of
marine operations
associated with the load-
Transportation & Marine Warranty
out, transportation and COMPANY
Installation (T&I) Surveyor (MWS)
installation of the Pegaga
facilities.
Page 18 of 43
a) Establishment KPIs, as presented in detailed in Section 4.5.1.
b) Include AIM as part of agenda during a six (6) monthly Management review as
well as during Project Quality Internal Audit (within CONTRACTOR EPCIC
disciplines), Project Quality External Audit (within CONTRACTOR’s
SUBCONTRACTORs, Vendors and Suppliers), COMPANY Audits and Project
Readiness Review Audits (i.e prior to load-out, start-up).
c) Include AIM as part of agenda during programme organized by COMPANY for
management site tours during Construction phase.
Project KPI has been established in accordance with the Scope of Work (Exhibit
3.0) and can be referred to Contract Quality Plan (CQP), PGGA-QM-PLN-0-001,
Clause 5.2, Appendix 3. The respective Discipline Managers are responsible to
report the KPI as per the frequency defined in the CQP.
The Project QA/QC Manager is responsible in collating all relevant data from
process owners and analyse for performance monitoring. The KPI and analysis
report shall be presented to the CONTRACTOR’s Project Director and subsequently
issued to the COMPANY Management.
Page 19 of 43
Page 20 of 43
Table 1.2: List of KPI according to Contract Quality Plan (CQP)
Page 21 of 43
4.5.2 Implementation of Quality Assurance/ Quality Control (QA/QC)
4.5.3.1 Inspections
For Execute phase, all fabrication, inspection, testing and acceptance criteria shall be
conducted in strict accordance with relevant Regulatory and COMPANY requirements
and National / International Codes & Standards.
Specific requirements are identified in CONTRACTOR’s Inspection & Test Plans
(ITPs), Source Inspection Plan, Regulatory Inspection plan and the application of the
stated requirements shall be subject to routine surveillance inspections and audits by
the COMPANY throughout the Execute phase.
4.5.3.2 Audits
CONTRACTOR with the participation of COMPANY will conduct a series of project audits
and reviews during the course of Work. These audits and reviews will be conducted
during Detailed Engineering, Construction, Installation and prior start up
(Commissioning) as required by COMPANY. As mentioned in Section 4.2 above, audits
for AI will be included as part of agenda during Project Quality Internal Audit, Project
Quality External Audit, COMPANY Audits and Project Readiness Review Audits. Details
of the overall audit plan can be referred to Project Audit Schedule as established for this
Pegaga project.
As a commitment towards achieving the objective of ensuring the effective and efficient
implementation of all aspects of the AIM requirements during Execute phase,
CONTRACTOR will include the AIM as part of agenda during a six (6) monthly
Management. Details of the planned date can be referred to Table 3.1 above.
Page 22 of 43
The following inputs will be included as a minimum to the Management Review
agenda;
• Status of KPI relevance to the AI function
• Status of Action arising from previous management reviews.
• Status of planned COMPANY and CONTRACTOR audits and review of any
previously identified non-conformances along with their current status.
• Lesson learned and actions taken to prevent recurrence
• Opportunities for improvement in COMPANY’s Asset Integrity programme.
• Modifications to the Internal Audit/ External Audit Schedule to reflect recent
audit findings
During the Execute phase, any changes initiated by COMPANY and/or proposed by
CONTRACTOR shall be managed using the CONTRACTOR Management of Change
(MOC) Procedure, PGGA-PM-PRC-0-006 with cross-reference to COMPANY
Management of Change (MOC) Procedure, MY-GEN-PF-PM-PRC-0008-R2 and Exhibit
26: Administrative Procedure, clause 3.1 Management of Change.
All changes in the project, such as management being applicable to contract changes,
design concession, field design changes, process changes, technical queries, in people,
equipment and working procedures shall be recorded in proper planning and controlling
to avoid any HSSE and QA/QC consequences. The Change control procedures
(Technical Query Procedure, Concession Request Procedure, and Variation Order
Procedure) address the requirements of various changes.
As a minimum, the reasons for the change may include the following reasons;
Page 23 of 43
• A change in COMPANY business strategy
• A design aspect with the potential to adversely impact upon the Technical
Integrity of the facilities
• A change in technology during Project execution
• Establishment of better engineering or construction solutions during the course of
Project execution.
The CONTRACTOR’s Project Risk Management has been developed to fulfil the
requirement of risk management which has been set in COMPANY’s Operational Risk
Management Standard, Document No. CO-GEN-HS-STD-0004. COMPANY’s
Operational Risk Management Standard has been introduced to support the
Operational Management System to ensure that risks arising from COMPANY’s
activities are continuously assessed throughout the business cycle and that
appropriate action plans are implemented to prevent, or reduce risks to an acceptable
level. Risk Management which includes inspection and maintenance planning, is one
of the requirements to be performed and not a one-time activity but a continuous
process where information and data from the inspection/maintenance/monitoring
activities performed during Execute phase are provided to COMPANY’s planning and
strategy development for maintaining its assets and ensure the following objectives
have been met;
• All risks potentially impacting the project are identified, assessed and pro-
actively are managed.
• A clear and concise process for documenting risks and their controls are
provided.
• Project effectiveness in managing the risks is increased.
• Project management to make risk-based decisions supported by qualitative and
quantitative risk & opportunities analyses is managed.
The core components of the risk management approach will be well monitored and will
be administered during project execution with reference and guidelines to COMPANY’s
Operational Risk Management Standard, COMPANY’s 5x5 Risk Matrix (Figure 5.2) and
CONTRACTOR’s Risk and Opportunities Management Plan (PGGA-PM-PLN-0- 004).
Page 24 of 43
4.8 Barriers for Safety in design
Safety studies addressed and conducted during detailed engineering is very important
to the development of Asset Integrity. Safety studies are the earliest and initial qualitative
risk assessment to be carried out for the facilities to identify any risks to the systems,
subsystems and components including subsea facilities. The importance of safety
studies is very significant to demonstrate to COMPANY that its assets are safe to be
operated and maintained. It is also important to reduce risks for Production or service
losses from equipment/ assets failure which could contribute to loss of life or impact to
the environment.
One of the important activities in Safety studies is the Hazard Identification (HAZID). The
hazard identification process identified that loss of containment and/or loss of pressure
systems, piping, structural integrity as well as pipeline could occur as the result to Internal
& external corrosion, external mechanical damage etc. HAZID study performed during
DDE is significant since it relies on knowledgeable individuals/ personnel contributing
their experience and judgments to the process including the input gained from
COMPANY Operation.
It is usually desirable to list all the potential failure mechanisms that could occur and
subsequently screen out those which are considered unlikely or otherwise inappropriate
of further consideration. Applying a “what if…” approach increases the potential for
capturing all the potential failure mechanisms. This approach to hazard identification
(HAZID) can be further formalized using techniques such as the HAZOP (Hazard and
Operability Study) where guidewords are used to structure the discussions of the hazard
identification team. All the hazards assessed should be recorded so that they too can be
reviewed in the light of the in data and operational experience.
The other selected Safety studies are also important to be developed or further refined
by the CONTRACTOR during Execute phase. These Safety Studies are summarized as
follows; (Note: The list of Safety studies below is not exhaustive).
Page 25 of 43
• Smoke and Gas Ingress Analysis (SGIA)
• Fire and Gas Mapping Study
• SIL Verification Study
• Noise Study
• HAZID for Construction, Installation, Hook-up and Pre-Commissioning
• Safety Critical Element and Performance Standard
• Human Factor Engineering
• Vibration Study (Acoustic & Flow Induced) forms part of the Engineering work-
scope
The combined output of these Safety Studies will be incorporated into the design and
culminate in Operations HSE Case being developed by CONTRACTOR for handover to
the COMPANY Production Operations Group prior to start-up of the facilities.
• Structural Integrity;
• Process Containment;
• Ignition Control;
• Detection Systems;
• Protection Systems;
• Shutdown Systems;
• Emergency Response;
• Life Saving.
The role of SCEs is to prevent or limit the escalation and/or consequences of a MAH.
For each SCE identified at the asset, Performance Standards (PS) are developed which
in turn inform the maintenance, testing and inspection requirements to ensure the
integrity of the system. Technical Integrity on a Pegaga is delivered when PS for SCEs
have been produced and implemented.
Page 26 of 43
4.8.2.1 Safety Critical Elements (SCE)
Any structure, equipment, system or component part whose failure could cause or
contribute substantially to a Major Accident Hazards (MAH) is considered as SCE. SCEs
also include those items that are crucial to the prevention, control or mitigation of MAH.
SCEs consisted primarily of hardware equipment (e.g. vessels, instrumentation etc.) but
can also constitute activities (e.g. procedures, tasks) that influence the prevention or
recovery from MAH.
Narrowing the definition of a SCE in the context of asset integrity is deliberate and does
not imply that all other high asset/reputation risk or medium to low risks are in any way
neglected.
4.9 Life Cycle Cost (LCC) in Procurement process for Type 1 Equipment
Life Cycle Cost is defined as the total cost throughout its life including planning, design,
acquisition, support costs and any other costs directly attributable to owning and using
the assets. For procurement exercise of Type 1, LCC analysis shall be carried out as
cross-reference to Exhibit 3.0, Clause 7.9.1, Commercial Bid Evaluation – Equipment
and Material type 1. In calculating the LCC requirements, the cost associated with
removal for onsite and offsite calibration/ certification shall be taken into account. It
should also consider the cost associated with Long Term Service Contracts (LTSA) if
applicable and rental/ membership fee of LTSA or spare unit (if applicable).
Page 27 of 43
For each equipment and materials package with a Equipment and Material Type 1,
RFA report will be prepared accordingly. Each report will cover the following subjects;
• Commercial summary analysis (spreadsheet presentation) of each Bidder who
has been technically approved by COMPANY.
• Incorporate all Life Cycle Costing analyses as above.
• Based on technical compliance and COMPANY acceptance, CONTRACTOR will
proceed with placement of Purchase Order in favour of technically acceptable and
commercially lowest Life Cycle Cost (LCC). The principle of LCC analysis in
Contract Bid Evaluation (CBE) and Recommendation of Award shall be applied
for the equipment listed below;
Page 28 of 43
severity of corrosion risk. It is important to note that CRA mainly contributes to the PoF
assessment in RBI analysis.
RBI methodology will be used to manage the overall risk of a platform/ facilities by
focusing inspection efforts on the process equipment with the highest risk. RBI will
identify and manage the risks associated with the integrity of pressure systems,
structures and pipeline in order to reduce them down to an ALARP (as low as reasonably
practicable) level or mitigate them completely. RBI provides the basis for making
informed decisions on inspection frequency, the extent of inspection, and the most
suitable type of NDT required.
The RBI assessment will be conducted using COMPANY's risk matrix, as presented in
Figure 5.2 to develop an effective inspection plan. Inspection planning is a systematic
process that details out the inspection strategy, frequency, scope and coverage
according to the identified damage mechanisms. Both the probability of failure and the
consequence of failure (COF) should be evaluated by considering all credible damage
mechanisms that could affect the facilities or equipment. In addition, failure scenarios
based on each credible damage mechanism should be developed and considered
Page 29 of 43
Figure 5.2: The COMPANY 5 x 5 Risk Matrix
By using the above Risk Matrix, the final Risk Ranking (the results of the Criticality Analysis) is
obtained by considering the Likelihood rating (on the X-axis) and the Consequence rating (Y-axis)
of the Risk Matrix to determine the risk. If this risk is unacceptable, then other mitigation or
improvement may be required to supplement the inspection plan to reduce the risk. When properly
implemented, risk-based inspection is highly effective in maintaining asset integrity compared to
conventional Inspection programmes.
In general, the objective of inspection strategy is to address all credible failure modes, with the
scope and level of detail determined by the risk rating. In most circumstances this will result in a
limited range of inspection strategies, dependent upon equipment type, deterioration mode and
expected rate (time dependent mechanisms, e.g. general corrosion) or initiation conditions
(stochastic mechanisms, e.g. stress corrosion cracking). A separate inspection procedure will be
established to determine the scope, extent of inspection, technique/ methodology and formatting
report.
Baseline inspection for Pressure Equipment shall be performed once CMLs identification has been
defined. CMLs for Pressure Equipment are designated locations on pressure vessels and piping
where thickness measurements inspections are conducted to monitor the presence and rate of
damage and corrosion. Detailed of Baseline Inspection requirements can be referred to PGGA-
PM-PRC-12-001 Pressure System Baseline Inspection Guidelines.
Page 30 of 43
5.3.2 Underwater Baseline Inspection for Offshore Structure
The scope of the Underwater baseline installation with reference to CIMG Rev.3B
shall include the followings:
As part of inspection requirement, the IP will be carried out for the 4 Km Pipeline
internal. CONTRACTOR plans to perform the IP for the new 4 Km Pipeline in Early
October 2021 after successfully getting Provisional Acceptance (PA) Certificate which
is scheduled on 30-Sep-2021 (based on Schedule C6).
Page 31 of 43
5.3.4 Underwater Baseline Inspection for Pipeline external
Underwater Baseline Inspection for pipeline external will be carried out using ROV
and CP inspection. Baseline data will be uploaded later in COMPANY's Asset Integrity
System. This will also include verification of anode spacing in accordance to pipeline
GA/ anode distribution diagram.
Any anomalies found during baseline inspection will be recorded and reported
immediately to COMPANY and subsequent repairs shall only be executed in strict
accordance with approved procedures.
The anomaly management will also reminds of monitoring requirements and offers a
simple interface for inspection and integrity teams to enter and analyse data.
Depending on the nature of the reported anomaly and type of component requiring
repair, COMPANY have reserve the right to increase the inspection activities on
similar components to ensure no inherent deficiency in the manufacturing and
fabrication process.
During the Operations phase, the maintenance and inspection regime will be
supported by procedures to manage these activities. In this respect, additional
COMPANY procedures shall be developed during Execute phase in conjunction with
Production Operations to reflect industry-wide lesson learned from historical integrity
failures on operational facilities.
The following steps summarise the key stages involved in developing the procedures;
1. Identify the needs based on COMPANY’s Operation requirement
2. Identify the responsible parties
3. Gathering information
4. Draft the procedures
5. Consult/ review with COMPANY’s Operation Team
6. Finalize and getting approval
7. Submission to COMPANY
Further details can be referred to Exhibit 14 Section 6.8.3, Project Asset Integrity
Requirements (Execute phase).
Page 32 of 43
5.6 Competency Assurance (during Execute phase)
All inspection and testing personnel certification shall be subject to continuous review
by the COMPANY.
Page 33 of 43
APPENDIX A: ASSET INTEGRITY FOR EXECUTE PHASE ACTIVITIES
The Asset Integrity for Execute Phase Activities addresses key processes, activities and resources relevant to the contract.
REF. RESPONSIBLE CONTROLLING
NO. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
PARTIES
Refer to CONTRACTOR Contract Quality Plan (CQP), Document No. PGGA-QM-PLN-0-001, Rev.C1- AFC, Section 4.0 Data and Document Control ISO 9001:2015,
Clause 7.5
Refer to CONTRACTOR Contract Quality Plan (CQP), Document No. PGGA-QM-PLN-0-001, Rev.C1- AFC, Section 13.0 Independent Review of Design, Fabrication
and Installation (ISO 9001:2015, Clause 8.4)
Refer to CONTRACTOR Contract Quality Plan (CQP), Document No. PGGA-QM-PLN-0-001, Rev.C1- AFC, Section 5.0 Quality Management (ISO 9001:2015 Clause
4.0,8.0,9.0.10.0)
Refer to CONTRACTOR Contract Quality Plan (CQP), Document No. PGGA-QM-PLN-0-001, Rev.C1- AFC, Section 5.0 Quality Management (ISO 9001:2015 Clause
4.0,8.0,9.0.10.0)
4.0 Interface Management & Regulatory Compliance
Refer to CONTRACTOR Contract Quality Plan (CQP), Document No. PGGA-QM-PLN-0-001, Rev.C1- AFC, Section 3.0 Interface Management& Regulatory
Compliance (ISO 9001:2015 Clause 8.0)
Page 34 of 43
REF. RESPONSIBLE CONTROLLING
NO. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
PARTIES
5.1 HSE Case, Safety Critical Element (SCE) and Performance Standards (PS)
Major Accident Event
Contract
(MAE) Report
Specification and
PGCA-SA-REP-1-025
• Establish the Major Accident Hazard Scope of Work
(MAH) Identification Section B Exhibit
• Carry out a QRA (Quantitative Risk QRA (Quantitative Risk 3.0
PMTs Assessment)
Assessment) and Fire and Explosion PRW Project
PGCA-SA-REP-1-059
Risk Assessment (FERA). Execution Plan
• SCE Identification Development PGGA-PM-PEP-
Project SCE Identification and
1-001
Development of HSE Case, SCE and • Bow-Tie Assessment Engineering Register
5.1.1 PGCA-SA-REP-1-026
PS. • Performance Standard Development Manager PRW Engineering
• Performance Criteria assignment for Quality
Bow-Tie Assessment Management Plan
SCE/HSE items
• Assurance and verification activities Technical Safety PGGA-QA-PQP-
Subcontractor Safety Critical Element
ensures that SCE meet their PS (SCE) and 1-001
• Safety Critical Element (SCE) and Performance Standards MDR
Performance Standards Report Report
Page 35 of 43
REF. RESPONSIBLE CONTROLLING
NO. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
PARTIES
Helideck Turbulence
Study
Noise Study
Vibration Study
(Acoustic & Flow
Induced)
Reliability, Availability
and Maintainability
(RAM) study
HAZID (Construction,
Installation, Hook-up
and Pre-
Commissioning)
6.0 Design Control & Review in Detailed Design Engineering
Refer to CONTRACTOR Contract Quality Plan (CQP), Document No. PGGA-QM-PLN-0-001, Rev.C1- AFC, Section 6.0 Design Control & Review (ISO 9001:2015
Clause 8.3)
Page 36 of 43
REF. RESPONSIBLE CONTROLLING
NO. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
PARTIES
Each Vendor
• Prepare a Life-cycle cost analysis Package for Type
(LCCA) to determine the most cost- I Equipment
Contract
effective option among different Specification and
competing alternatives to purchase, Supply Chain
Manager, Life Cycle Cost Analysis Scope of Work
7.1 Life Cycle Cost for Type 1 Equipment own, operate, maintain and, finally, Section B Exhibit
(LCCA)
dispose of an object or process, when Procurement 3.0
each is equally appropriate to be Manager
implemented on technical grounds.
Sub-Contract
Manager
Buyer
For Source Inspection, refer to CONTRACTOR Contract Quality Plan (CQP), Document No. PGGA-QM-PLN-0-001, Section 7.0 Procurement and Sub-Contracting
(ISO 9001 : 2015 Clause 8.2.3, 8.4)
Page 37 of 43
REF RESPONSIBLE CONTROLLING
. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
NO. PARTIES
Page 38 of 43
REF. RESPONSIBLE CONTROLLING
NO. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
PARTIES
Inspection schedule in
spreadsheet and
uploaded in
COMPANY's AI System
and CMMS
• Add baseline readings to Inspection
drawings (i.e. wall thickness reading at PMT
each unique location).
• Compile baseline readings in Excel AI Engineer/ Focal Baseline readings in
spreadsheet format point spreadsheets
Baseline Data
• Collect baseline wall thickness readings
Project QA/QC Collection
Baseline inspection for Pressure at the identified key-point locations Procedure
8.4 Manager Baseline Inspection
Equipment and Piping using CONTRACTOR inspection
Reports PGCA-MT-REP-
personnel. Inspection Anomaly Reports 0002
• Add baseline readings to Inspection SUBCONTRACT
drawings (i.e. wall thickness reading at OR
each unique location).
AI Subcontractor
Page 39 of 43
REF. RESPONSIBLE CONTROLLING
NO. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
PARTIES
Contract
Specification and
Scope of Work
• Visual assessment of the entire Section B Exhibit
structure including appurtenances. 3.0
• FMD on all primary members and Non-
Destructive Test on selected key PMTs
Post installation Exhibit 14.0
structural members and nodes
• Verify overall configurations of structural AI Engineer/ Focal baseline survey report
members against As-Built Drawings point Project
• Check for damage, corrosion, Baseline inspection Transportation &
Interface Manager Installation
anomalies, flooded member testing, multimedia (recordings,
photos, videos, etc) Requirements
anode depletion, scour, debris, marine Project QA/QC
Post Installation Baseline Survey for (MPMY-PM-PRC-
8.5 growth and condition of riser clamps. Manager
Offshore Structure 0008)
• Assessment of coating deterioration on Anomaly reports
entire surface to determine need for T&I Manager
touch up painting or total re-coat. Post Installation
Post Installation Baseline data compiled Baseline Survey
• Cathodic protection reading and Baseline Survey in spreadheets and Procedure
sacrificial anode condition including Subcontractor uploaded in Asset
attachments. Integrity System
• Update in COMPANY’s Risk Based AI Subcontractor Anomaly
Inspection software on the survey Management
findings. Procedure
API RP 2A
API RP 2SIM
PMTs
• ROV inspection of full pipeline length RBI readings in Contract
spreadsheets Specification and
Post installation survey for the • CP survey AI Engineer/ Focal
8.6 Scope of Work
pipeline • IP baseline survey point
Section B Exhibit
Interface Manager 3.0
Page 40 of 43
REF. RESPONSIBLE CONTROLLING
NO. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
PARTIES
ROV inspection report
Project QA/QC CP survey report Exhibit 14.0
Manager
IP baseline survey
T&I Manager report Project
Pipeline RBI report Transportation &
Post installation Installation
Uploaded baseline data
survey of the Requirements
in COMPANY's Asset
pipeline
Integrity System (MPMY-PM-PRC-
Subcontractor
Uploaded RBI 0008)
AI Subcontractor programme for first 5
years in CMMS and AI Pipeline post-
IP Subcontractor System installation
surveys
procedures
IP Procedure
DNVGL-RP-F116
API RP 1160
Page 41 of 43
REF. RESPONSIBLE CONTROLLING
NO. PROCESS (ES) KEY ACTIVITIES DELIVERABLE (S) DOCUMENT (S)
PARTIES
Contract
Specification and
• Launch IP from topside Pegaga Scope of Work
• Perform survey of internal Section B Exhibit
inspection for the 38-inch 3.0
Pegaga pipeline
• Subject to type of IP being used, Project QA/QC IP baseline survey Exhibit 14.0
the IP can either be retrieved Manager report
back to Pegaga or retrieved at
E11R-B T&I Manager Pipeline RBI report
• Process the data obtained from Project
launched IP AI Subcontractor
Uploaded baseline data Transportation &
in COMPANY's Asset Installation
IP Subcontractor
Integrity System Requirements
Intelligent Pigging (IP) Inspection for (MPMY-PM-PRC-
8.7
Pipeline internal 0008)
Uploaded RBI
programme for first 5
years in CMMS and AI
System Anomaly
Management
Procedure
API RP 2A
API RP 2SIM
Page 42 of 43
APPENDIX B: ORGANIZATION CHART FOR O&M AND ASSET INTEGRITY DURING EXECUTE PHASE
Page 43 of 43