Professional Documents
Culture Documents
2
Agenda
3
Aluminum Contributes to Solving some of
the World’s most Challenging Issues
4
The World Will Need
More and More Aluminum
5
Innovation: an Essential Component of
Making Aluminum a Sustainable Product
6
Environmental Benefits of Innovation
• World productivity
benchmark
• Smaller environmental
footprint
7
Stakeholders Economic Benefits
of Innovation
8
AP Technology Evolution
600,000 AP60
550,000
AP60
500,000
AP50
Ampere
450,000
AP40
400,000 AP30 AP39
350,000 AP35 36 37
AP33
AP18 AP30
300,000 AP28
AP24
AP18
250,000 AP3X
AP22 AP40
200,000 AP60
AP18
150,000
1971 1976 1981 1986 1991 1996 2001 2006 2011
Year
9
…. Aluminum
10
AP60 Phase 1
Delivering Superior Results
11
Key Facts
• 38 AP60 pots
– Gas treatment center
– Rodding shop
– Sow caster
• First industrial implementation of AP60 technology
• Built in Arvida City, on the same site where the first
aluminum smelter in Canada was constructed
– Location of demolished Soderberg smelter
• Owner: Rio Tinto Alcan
• EPCM: SNC-Lavalin and Hatch joint venture
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only. 12
Key Figures
• $1.3 B budget
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only. 13
Why Project Efficiency Matters?
14
AP60 Challenges and Complexity
• New technology
– Major change during execution
15
Project Achievements
16
Project Achievements (cont’d)
17
Learning from our Predecessors
18
Learning from our Predecessors (cont’d)
• Key elements
Developing
and using
Labor Project &
Clear value complete &
alignment accurate
relations & operation = SUCCESS!
development integration
engineering
documents
19
Project Objective
FUNCTIONALITY
expenditure and a
realistic schedule.”
SCHEDULING COSTS
20
Developing a Culture
21
Creating the Culture
22
Creating the Culture (cont’d)
23
Project Motto
“Rigor,
Courage
and
Passion”
24
Creating the Culture (cont’d)
• In practice
– No blame culture – Seriously!
– Risk management used as an enabling tool
– Reward pro-activity using recognition program
– Frank discussion on difficult topics when required
25
Risk Management
26
Risk Management (cont’d)
A Key Tool for Culture Creation
“PMI” is a registered trade and service mark of the Project Management Institute, Inc.
©2012 Permission is granted to PMI for PMI® Marketplace use only. 27
Risk Management (cont’d)
A Key Tool for Culture Creation
28
Risk Management (cont’d)
A Key Tool for Culture Creation
Execution
risks
• Multiple
dimension of risks
analyzed
29
Global Financial Crisis
30
Value Improvement Opportunity
Idea Generation
Estimate (Oom)
– Technology–EPCM–Operations
Risk analysis
– Formal sign-off
Documentation
constraints Value
Advisory
Panel
31
Value Improvement Opportunity (cont’d)
32
Zero Harm
Changing the Culture
33
Zero Harm
(cont’d)
HSE Policy
34
Zero Harm (cont’d)
Time Schedule and HSE Impacts
Constructability
DATE input
Design influenced by safety
START ( Materials, configuration)
Ability to
Detailed work plan and risk assessment
influence
DATE
final safety,
START
Performance measurement
quality,
cost & time
DATE
START
DATE
START
DATE
START
Studies
Time – Project schedule
Constructability - Program’s ability to influence HSE results when applied to the Project life cycle.
35
Zero Harm (cont’d)
HSE Performance of AP60
AIFR LTIFR
AP60 Project 0.48 0.27
Quebec’s construction industry
(2003-2009 average) 23.5
36
New Technology Best Practices
Engineering
37
New Technology Best Practices (cont’d)
Engineering
• Engineering completeness
prior to bid
• Specific technology transfer
approach
• Detailed planning of
technology packages with
project requirements
• Early input of EPCM
• Close collaboration
• Confidentiality management
38
New Technology Best Practices (cont’d)
Constructability and Engineering
39
New Technology Best Practices (cont’d)
Constructability and Engineering
40
New Technology Best Practices (cont’d)
Procurement Approach
HOW WOULD YOU DO IT?
1. Lump-sum contracts
41
New Technology Best Practices (cont’d)
Procurement Approach
42
New Technology Best Practices (cont’d)
Procurement Approach
Including Substation
• Local impacts
– Specific effort with local community based Other
countries
Saguenay-
Lac-St-
on competitiveness 25% Jean
50%
43
New Technology Best Practices (cont’d)
Construction
• Early involvement
• New specific AP60 technology
developed methods
– Including modularization
• Constant attention during
engineering
• Strong planning, tracking and
coordination
44
New Technology Best Practices (cont’d)
Construction
Pre-assembly
45
New Technology Best Practices (cont’d)
Lean Principles
• Current practices erect
barriers between parties
• Exchange of information
is often inefficient
• Issues and critical items
are not known by team
– Empowerment
• New issues are not
known in time to act
46
New Technology Best Practices (cont’d)
Lean Principles
If there is a problem,
you move and go
If you cannot see. Collect relevant Each person has A team is
Simple, quick,
justify a situation, information, find the a role to play: stronger than a
root cause, get cheap!
do not accept it! respect him! person
consensus and take
the initiative.
47
New Technology Best Practices (cont’d)
Process Improvement Workshop
• Improving a process by involving all stakeholders to find
ideas to make their job easier through a simple process
HSE
Equipment – Tools
Organization – Productivity
Matérials – Logistics
Studied activity Quality
presentation Various
Current work process
definition/presentation Brainstorming to identify
High Level possible improvements
classified in six differents Define for each possible
areas improvement :
Action to take, Who, When
48
Plan to Learn
• Objectives
– Capture all significant lessons specially linked to technology
– Capture lessons in a structured format
– Capture knowledge before personnel demobilization
– Easy consultation
• We benefited from lessons learned; we must provide
learning for future projects
• First generation new technology creates very important
lessons influencing future implementation
49
Plan to Learn (cont’d)
• Detailed planning
– Is essential
– People do not stay on a project
when the mandate is completed
50
AP60 Take Away
51
52
Contact Information
53