Professional Documents
Culture Documents
Summary
Production optimization under uncertainty is complex and computationally demanding, a particularly challenging
process for carbonate reservoirs subject to WAG injection, represented in large ensembles with high simulation
runtimes. Search spaces of optimization are often large, where reservoir models are complex and the number of
decision variables is high. The computational costs of ensemble-based production optimization can be decreased
by reducing the size of the ensemble with representative models (RM). The validity of this method requires that
the RM maintain representativeness throughout the optimization process, where the production strategy changes
at each evaluation. Many techniques of RM selection use production forecasts of the ensemble for an initial
production strategy, which raises questions about the robustness of the RM. This work investigates approaches to
ensure the consistency of RM in ensemble-based long-term optimization. We use a metaheuristic optimization
algorithm that finds sets of RM that represent the ensemble in the probability distribution of uncertain attributes
and the variability of production, injection, and economic indicators (Meira et al., 2020). Our case study is a
benchmark light-oil fractured carbonate with features of Brazilian pre-salt reservoirs and many reservoir and
operational uncertainties. We obtained production, injection and economic indicators using different approaches
to provide valuable insight for RM selection. We inferred about RM fitness for production optimization based on
their adequacy for uncertainty quantification for varying production strategies. Despite the effects of changing
decision variables on RM representativity, our results suggest the possible use of RM for ensemble-based
production optimizations with limitations related to the estimation of the probabilistic objective function due to
mismatches in the probabilities of occurrence. Using production indicators obtained from a base production
strategy decreased RM representativeness when compared to RM selection based on a more robust evaluation of
reservoir performance using a wide-covering well pattern and no restrictions from production facilities. Finally,
our results suggest valid RM selection using production forecasts for intermediate dates of the simulation period,
an important contribution for ensembles with very high simulation runtimes. We also provide a broad theoretical
background on the uncertain reservoir system and on approaches to obtain reduced ensembles and their
applications.
The reservoir simulator (also referred to as flow simulator) is known to be one of the best tools to
evaluate the performance of a production strategy over time for a given reservoir scenario. The physical
system (reservoir) is represented in a mathematical model, which is then solved numerically to predict
fluid behaviour over time. This approach can be classified as physics-based as it incorporates the
physical laws governing fluid flow in porous media. Despite computationally expensive, it has the
unique advantage of modelling the complex integration between the production strategy and the
performance of the reservoir system (certain or uncertain).
Despite undeniably important, performing production optimization using reservoir simulation models
is challenging. Defining a production strategy involves defining a large set of variables related to the
production system, including subsurface and surface facilities. In addition, the problem is often
characterized by large search spaces, which may demand thousands of evaluations of the optimizer's
objective function. Given that each evaluation of the objective function equals to one reservoir
simulation, which may take many hours, a production optimization problem may become unfeasible
depending on the available computational infrastructure. This is particularly relevant for production
optimization under uncertainty, such as robust optimization, where optimization is conducted on an
ensemble of different reservoir scenarios. In such cases, each evaluation of the objective function equals
to multiple reservoir simulations (one for each reservoir scenario).
Added challenges exist in Brazilian pre-salt reservoir, light-oil fractured carbonates subject to water-
alternating-gas (WAG) injection, and with intelligent wells. First, representing these reservoirs into
simulation models leads to high simulation runtimes, due to the inherent heterogeneities of carbonate
reservoirs and the physical phenomena related to WAG recovery. Second, due to difficulties related to
reservoir characterization under uncertainty, large ensembles of scenarios are required to ensure that
uncertainty is fully captured. Lastly, the production optimization problem has added variables related
to the WAG injection strategy and intelligent well design and operation.
Different approaches are available in the literature to reduce the computational runtime of each
evaluation during production optimization processes. These can be classified into three mains
categories: (1) simplifications that capture the physics of the process (physics-based); (2)
simplifications that do not capture the physics of the process (data-driven); and (3) hybrid models that
combine physics-based and data-driven approaches.
The most common simplification in the physics-based category is the use of low-fidelity models,
defined as reservoir simulation models that have strong simplifications in rock and/or fluid properties
(e.g., Wilson and Durlofsky, 2013; Aliyev and Durlofsky, 2015). Examples include the use of upscaled
simulation grids and a reduced number of pseudo-components in fluid models. The prime advantage of
this approach is that it easy to implement. However, sub-grid heterogeneity effects and phenomena
related to gas miscibility may be missed
Another class of simplifications within the physics-based category is the use of reduced ensembles,
where a selected number of models is chosen from a large ensemble of uncertain reservoir scenarios
(typically hundreds) (e.g., Schiozer et al., 2004; Scheidt and Caers, 2009; Shirangi and Durlofsky, 2016;
Mahjour et al., 2020a; Meira et al., 2020). Different approaches exist to obtain reduced ensembles,
which can be regarded as a broad class that includes representative models (RM). The prime advantage
of this approach is that it does not require simplification in reservoir representation in the simulation
model, as we have seen for low-fidelity models. However, ensuring that uncertainty is properly
represented in a reduced ensemble is a difficult and complex process.
The most common simplification in the data-driven category is the use of data-fit proxy models, defined
as analytical functions that bypass the reservoir simulator when predicting production forecasts (e.g.,
Scheidt et al., 2007; Feraille and Marrel, 2012; Douarche et al., 2014; Panjalizadeh et al., 2014). The
prime advantage of this approach is that it is extremely fast, allowing thousands of evaluations of the
Even though often required, using simplifications bears the risk of adding positive or negative biases to
production forecasts and in decision-making. This is because biases are already inherent to the processes
of reservoir representation in simulation models and production strategy definition (Meddaugh et al.,
2017). Thus, the use of simplifications must be chosen carefully and be treated as case dependent.
However, the validity of solutions obtained for reduced ensembles, such as production optimization,
lays on the premise that the reduced ensemble represents properly the range of uncertainties. Following
the fundamental concept behind RM selection based on percentiles, current methods often base RM
selection on production, injection, and economic indicators obtained for the full lifespan of the reservoir
system, considering an outlined production strategy. However, given that the RM are selected to
perform uncertainty-based analyses (such as ensemble-based production optimization) and not to
evaluate a single production strategy (such as that for the base case), other approaches may be of value.
This includes investigating the need for more robust approaches for evaluating reservoir performance,
such as those related to minimizing potential biases introduced by the use of an outlined production
strategy.
Moreover, during production optimization processes, the production strategy is dynamic, meaning that
different possibilities for the set of variables are sampled at each evaluation. Thus, the RM used for
optimization should maintain the representativity of the uncertain system throughout the process.
Existing RM selection methods must be applied carefully, as not to affect the quality of solutions, i.e.,
the representativeness of the RM may be impaired depending on the input data used for RM selection.
This raises the need for additional studies to investigate the best way to apply existing RM selection
methods aiming to maximize uncertainty representation. Furthermore, despite the increasing number of
works in the literature, further studies are still required looking at current optimization challenges
because most applications consider water flooding and conventional wells.
The main idea behind RMFinder is the selection of a set of RM that represents both the probability
distribution of uncertain attributes and variability of production, injection, and economic indicators of
the full ensemble. Due to the complex integration between reservoir performance and production
strategy, obtaining these indicators is not a straightforward process. This is because they require the
definition of one production strategy (such as number and placement of wells, and subsurface facilities)
and this choice will affect the variability in production, injection, and economic indicators. In this study,
we obtained indicators of reservoir performance using different approaches to provide decision-makers
with valuable insights into the process of RM selection.
The case study presented in this work is an open-source benchmark in the development phase called
UNISIM-II-D (Correia et al., 2015). Added challenges exist depending on the composition of the
injected gas, such as that in WAG-CO2. Despite the target recovery mechanism of the reservoir
UNISIM-II being WAG-CO2, we did not address it in this work. Instead, we used a low-fidelity model
based on a black-oil fluid model but maintaining geological representation (grid properties) to allow
computational feasibility of different evaluations of the full ensemble (composed of hundreds of
scenarios) for varying decision variables. The simulation model is called UNISIM-II-D-BO, where BO
stands for black-oil.
Note that Meira et al. (2020) demonstrated the use of the RMFinder for the same benchmark case used
in this work, the UNISIM-II-D. However, their application considered the use of conventional wells
and the recovery mechanism was water flooding, while our work considers the adequacy of RMFinder
for a production strategy with WAG injection and intelligent wells. Thus, we do not use the results
presented by Meira et al. (2020).
Theoretical background
time
In a typical reservoir system, several reservoir uncertainties exist because reservoir and fluid data are
mainly acquired indirectly (e.g., seismic surveys) and, when directly, sparsely (e.g., well coring).
Additionally, because developing a petroleum field is a long-term project, reservoir systems have added
uncertainties related to operational availability of production facilities (e.g., failures in equipment,
maintenance), economic data (e.g., oil price, capital and operational expenditures), among others. As a
result, instead of having one value for each system input, we may have a range of values characterized
by a probability distribution.
Uncertainty in continuous variables, such as the fluid contacts, is described in probability distribution
functions (PDF) while in discrete variables, such as a structural model and geostatistical realizations, it
is described in probability mass functions (PMF). To bring these properties to the simulation system,
we need to create an ensemble of uncertain scenarios, where a scenario is defined here as a particular
combination of one value for all uncertain variables (the system inputs, i.e., geological, reservoir, fluid,
Scenarios are generated using statistical sampling techniques such as the Monte Carlo and the
discretized Latin Hypercube combined with geostatistical realizations (DLHG) (Schiozer et al., 2017).
The prime limitation of Monte Carlo sampling, which performs pure random sampling, is that there is
no guarantee that the full range of the distribution is sampled evenly and consistently with a sampling
number lower than many thousands (Mishra, 1998).
Latin Hypercube sampling (LHS) has gain popularity because it incorporates the desirable features of
random sampling and stratified sampling (Helton and Davis, 2003). The DLHG applies the efficient
LHS and integrates all types of uncertainties in the sampling step, i.e., continuous attributes are
discretized and combined with discrete attributes and geostatistical realizations (Figure 2). Thus, the
DLHG appeared as a promising technique to increase the computational efficiency of the sampling
process in reservoir engineering problems, ensuring adequate representation of all uncertainties with
few hundreds of scenarios (Santos et al., 2018a).
• Geostatistical
realizations
Hence, the inputs of the uncertain system are an ensemble of hundreds or thousands of scenarios, each
one characterized by a combination of the possible values of each uncertain variable (system input).
Forecasting reservoir and economic performances of the ensemble, we obtain a range of values for each
system output (Figure 3). These outputs consist of, for example, production and injection curves over
time, estimated recovery factor, and discounted net cash flows. These ranges of possible outputs can be
used to construct, for a given time, risk curves, which are also referred to as descending or
complementary cumulative distribution functions (CCDF) in the statistics literature.
Generating the outputs of an uncertain system using numerical reservoir simulation may be
computationally expensive or prohibitive, especially for procedures related to production optimization
that demand thousands of evaluations. Over the decades, several approaches have been investigated to
reduce such costs, as we have explored in the Introduction section. A promising line of research for
complex reservoirs consists of reducing the size of the ensemble, which we address in this work.
Cum. prob.
production/ injection
(...) indicators
• Time series and
NPV CCDF of well
economic indicators
• …
P90
P50
P10
Figure 4 Risk curve for a system output X, marking the percentiles P10, P50, and P90.
During the past decade, a variety of studies have been published investigating different approaches to
obtain reduced ensembles. The focus shifted from selecting models close to P10, P50, and P90 for one
variable to selecting models that covered the entire variability of one or more variables of the uncertain
system. Today, the literature presents two main approaches to obtain reduced ensembles (Table 1).
Figure 5 Manual selection of representative models based on cross-plots for NPV, Np, RF, and Wp (in
Schiozer et al., 2004).
With the increasing number of criteria for RM selection, the process of manual selection became
extremely time-consuming and difficult to achieve satisfying solutions. This raised the need for
automated procedures for RM selection, which lead to the development of an optimization-based
method implemented in an in-house program called RMFinder (Meira et al., 2016, 2017, 2020).
RMFinder uses a mathematical function that captures the representativeness of a set of models
combined with a metaheuristic optimization algorithm and performs global and local searches. The
main idea behind RMFinder is to select a set of RM that represents both the probability distribution of
the input variables represented by the ensemble (reservoir, operational and economic uncertainties) and
the variability of the main output variables (production, injection and economic indicators) of the
uncertain reservoir system (Figure 6).
Figure 6 Illustrative example of a set of nine RM (in red) selected from an ensemble of 214 scenarios
(in green). Bar charts compare the histograms of two system inputs (uncertain variables) in the set of
RM and the ensemble. Cross-plots (scatterplots) and risk curves (CCDF) make the same comparison
for four system outputs (NPV, RF, Np, and Wp).
Main applications of RM
Different processes related to the management of petroleum fields require probabilistic analysis, from
uncertainty quantification to uncertainty management, and from production strategy optimization to
production strategy selection under uncertain. The RM are an important way to make many of these
processes computationally feasible while ensuring adequate representation of uncertainty.
Today, the main applications of RM are those summarized in Table 2. The examples from the literature
listed in Table 2 used RMFinder to select the RM. All those works selected RM using system outputs
obtained for a base production strategy, despite the different applications for which the RM were
selected for.
Before selecting the RM, it is key to define properly the study objective and for which processes the
RM will be used, as it may affect the RM selection process (number of RM, weights of objective
functions, among other user-defined setups of RMFinder). A prime application of the RM (and the focus
of this work) is production optimization under uncertainty, which we address in the following
subsection.
Reservoir properties and size, limitations in logistics of production systems, among other factors, define
the degree of complexity of production optimization processes. Brazilian giant pre-salt reservoirs,
which are light-oil fractured carbonates with high volumes of CO2-rich associated gas, typically involve
many challenges related to gas treatment and recovery mechanism, which increase significantly the
complexity of optimization problems. These cases are often classified as gas-driven production
optimization, where oil production is limited by restrictions in production units, not by reservoir
productivity.
WAG-CO2 injection is an interesting solution for such cases, joining the benefits of increased sweep
efficiency to the ability to safely discarding the CO2-rich associated gas. The decision variables related
to this recovery mechanism include the number of wells operating in the WAG scheme and the
specifications of the injection cycles (per time or injected volume).
The optimization problem under uncertainty using RM can be classified into two main classes (nominal
and robust), as detailed in Table 3. These approaches are not interchangeable, meaning that they are
complementary in the decision-making process under uncertainty and, whenever possible, should be
performed both (Schiozer et al., 2019).
Methodology
In this study, we use RMFinder (Meira et al., 2020) to select the RM and investigate two main aspects
related to the generation of system outputs for RM selection: (1) the decision variables used for
obtaining production, injection, and economic indicators, and (2) the simulation time frame of the
reservoir system. These approaches are detailed in the following subsections.
Obtaining system outputs for RM selection: the decision variables of the reservoir system
We considered two approaches to obtain indicators of reservoir performance under uncertainty (Table
4). First, a base production strategy defined as the best solution found for the base case and obtained
from nominal optimization (an approach called here production strategy zero, or PS0). In the second
approach, we evaluate reservoir performance using a well pattern with wide reservoir coverage and with
no restrictions related to the production system, aiming to assess if this approach ensures unbiased
coverage of the full reservoir system (approach called production evaluation zero, PE0).
Obtaining system outputs for RM selection: the reservoir simulation time frame
We selected RM using system outputs obtained for different dates throughout the lifecycle of the
petroleum reservoir, ranging from the first years of the production phase until field abandonment (Table
5). Here, the focus is on understanding if there is value in using an intermediate date of the simulation
time frame in RM selection. In addition to the evident potential to reduce computational costs, reservoir
performance at field abandonment is strongly dependent on the production strategy, meaning that few
years of production may suffice to predict the productivity of a reservoir scenario.
Due to the reduced number of data points, risk curves for RM are drawn using a stair-step graph. To
quantify the approaches used for RM selection, we determine the area between the RM and the ensemble
risk curve, called absolute error. To allow comparison across different indicators and sets of RM, we
normalize the absolute error by the standard deviation of the ensemble and call it normalized error. An
illustrative example is provided in Figure 7.
At the end of the study, we test the validity of each approach by applying the different sets of RM to a
control production strategy used only for validation (called here production validation, or PV), i.e., not
used for RM selection.
Case study
Our case study is the UNISIM-II-D-BO, an open-access benchmark created by the UNSIM research
group and made available to the scientific community. Using public data, the available literature and
analogues, Correia et al. (2015) constructed a synthetic carbonate fractured reservoir with features found
in Brazilian pre-salt fields, such as high-permeability thin layers, commonly known as super-k.
The case study is in the initial field development phase under uncertainties and has 1.5 years of
production data for the Wildcat. The reservoir is represented in dual-permeability simulation models
with a corner-point grid with 46 x 69 x 30 cells measuring, on average, 100 x 100 x 8 m (total 64,110
active cells). Reservoir depth varies between 5,000 m and 5,500 m from sea level, initial pressure is 450
kgf/cm2, the temperature is 59°C, and oil viscosity is 1.14 cP (28° API).
The case study has a set of geological and reservoir uncertainties that were combined using the DLHG
sampling to generate scenarios that, after ensemble-based data assimilation procedures, resulted in an
ensemble of 199 scenarios (Table 6). These reservoir scenarios were then combined with operational
uncertainties (Table 7) using the DLHG to generate 199 scenarios that include both reservoir and
operational uncertainties. A base case (base0) was selected from the ensemble as the model closest to
P50 for field indicators.
Table 8 shows the economic data used for the NPV calculations. Platform investment (Invplat), in US$
millions, is given by Equation (1) (Santos et al., 2018b) where Cpo is the oil processing capacity (103
m3/day), Cpl is the liquid processing capacity (103 m3/day), Cpw is the water processing capacity (103
m3/day), Ciw is the water injection capacity (103 m3/day), Cpg is the gas processing capacity (106
m3/day), and nw is the number of well slots.
𝐼𝑛𝑣$%&' = 417 + 12.2 × 𝐶𝑝2 + 3.15 × 𝐶𝑝% + 3.15 × 𝐶𝑝5 + 3.15 × 𝐶𝑖5 + 9.61 × 𝐶𝑝9 + 0.1 × 𝑛5 (1)
We calculated the NPV using a simplified net cash flow formulation based on the Brazilian concession
fiscal regime (Equation (2)) where NCF is the net cash flow, Rev is the gross revenue, Roy is the amount
paid in royalties, ST is the amount paid in social taxes, OPEX are operational expenditures, T is the
corporate tax rate, CAPEX are investments on equipment and facilities, and AC is the abandonment
cost.
The production unit has the following capacities: Cpo and Cpl 180,000 bbl/day, Cpg 8,000,000 m3/day,
Cpw 50,000 bbl /day, Ciw 150,000 bbl/day, and 18 well slots. All gas produced is reinjected without
separation of gas streams. Water injection rates were controlled to maintain the hydrocarbon volume
weighted average at the initial reservoir pressure.
For the approach called PE0, we did not perform optimization. Instead, we placed 56 wells in a 5-spot
well pattern that covered the entire reservoir grid (modified from Mahjour et al., 2020b). To capture the
phenomena related to WAG recovery and the restrictions related to gas recycle, we defined the 28
injection wells as WAG injectors operating in 6-month cycles. Due to the inherent vertical
heterogeneities of carbonate reservoirs and the uncertainty in reservoir top and bottom, we did not place
ICV in the wellbore to permit unconstrained assessments of reservoir performance and reduce potential
biases introduced during ICV placement and operation.
Figure 8 shows the well placement for PS0 and PE0. We used a commercial black-oil reservoir
simulator and an in-house economic calculator to obtain production, injection, and economic forecasts
until field abandonment for the ensemble of 199 scenarios using approaches PS0 and PE0. Then, we
truncated these outputs in different time series based on the timeline of the case study (Figure 9), as
illustrated in Figure 10 for Np. We stored these results in a database and used them for RM selection,
which did not require any additional reservoir simulation runs.
Figure 8 Map of total oil per unit area for the base case, showing the well placement used for obtaining
system outputs in approaches PS0 (left) and PE0 (right).
Figure 9 Timeline of UNISIM-II-D-BO, marking in yellow the intermediate and final dates used for RM
selected. The timeline is not-to-scale.
Selecting the RM
We selected nine RM using the system outputs stored in a database: six field indicators (Np, Wp, Gp,
Wi, RF, NPV) and 18 well indicators for PS0 (one indicator per well), while 56 well indicators for PE0
(again, one per well), totalling 24 system outputs for PS0 and 62 for PE0. The indicator used here for
the well performance is the well economic indicator (WEI) (Ravagnani et al., 2011), which quantifies
the individual contribution of each well to the field NPV (i.e., CAPEX, OPEX, and revenues, if
applicable). It is desired to maximize WEI for producers (reflecting maximum hydrocarbon production)
and to minimize WEI for injectors (reflecting maximum fluid injection).
Given that RMFinder uses a probabilistic optimization method with a random component, we executed
the method five times to selected five different solutions of RM (S1 to S5) to ensure the robustness of
results obtained for each approach. As our analysis focused on risk curve representation, we attributed
a higher weight to this parameter when selecting the RM. We used sets of nine RM, as recommended
by Schiozer et al. (2004).
Despite evaluating different intermediate dates for RM selection, our objective is always to ensure
representativeness for the time frame of production optimization (long-term optimization until field
abandonment, in our case). Thus, we always assessed the representativeness of the RM when compared
to the risk curves of the ensemble at field abandonment (not at the intermediate date).
Figure 11 shows the results for solution S1. We chose this solution blindly without observing the quality
of each solution in representing the targeted risk curves (i.e., risk curves for PS0 at field abandonment).
The blue curve in Figure 11 marks the mean normalized error obtained for the five solutions (S1 to S5).
Risk curves using RM selected from PE0 recorded higher errors than those obtained directly for PS0.
This was expected to a certain degree, given that minimum errors were anticipated for the RM of PS0
in itself. However, understanding the underlying limitations in the RM selected from PE0 is essential
to validate or discard this approach. To understand better these results, we detail analyses in the
following subsections.
To enhance the understanding of the error used to quantify the adequacy of each approach, we show
four examples of RM risk curves for varying degrees of the normalized error (Figure 12). Quantitative
error analysis supported by visual inspection of risk curves reveals that significant mismatches start to
be recorded in normalized errors of around 0.25.
Figure 11 Boxplots characterizing the range of errors in representativity of RM risk curves when
compared to the risk curve of the ensemble of PS0 at field abandonment (2046). To the left, results for
RM selection using system outputs of PS0 at different dates. To the right, results for RM selection using
system outputs of PE0 for the same dates. Boxplots illustrate one of the five solutions (here S1), while
the blue curve marks the mean error obtained for the five solutions (S1 to S5). Crosses mark outliers
and circles the mean of each boxplot.
Figure 12 Risk curves for four indicators (field indicators Np and Wp and well economic indicators for
producers PRK061 and the Wildcat) of PS0 at the time of field abandonment (2046). Green circles: risk
curves of the ensemble. Red stair-steps: risk curves for RM selected using system outputs of PS0 at
2046. Grey fill: normalized error between risk curves. Here, we show the RM solution S1.
Overall visual inspection of risk curves (qualitative analysis) reveals that the PE0 approach has
drawbacks in capturing uncertainty for some system outputs, namely for injectors IRK049, IRK050,
and IRK056. These imprecisions were expected given that normalized errors (quantitative analysis)
were higher than 0.30, averaging 0.35 (Figure 11b). In most cases that recorded mismatches, the nine
RM covered the entire spread of the risk curve (evenly and consistently, in some cases), meaning that
they failed to match the correct cumulative probability. The accuracy of the risk curve relies also on the
proper estimate of the probability of occurrence of the RM, which was not the case for these wells as
revealed by the risk curves. This suggests that the RM can be representative of the uncertain system
provided that their probabilities of occurrence be adjusted.
We selected RM using well economic indicators to reflect, in a single value, a combination of Np, Wp
and Gp for producers, and Gi and Wi for WAG injectors, which are important to support production
strategy definition. As our target production optimization is a gas-driven problem, where oil production
is limited by restrictions in gas processing capacity, WAG injection and ICV operations are often aim
to control gas production. As a result, in addition to evaluating RM uncertainty representation for well
economic indicators, we assessed it for indicators obtained per ICV in producers and injectors. Figure
16 shows the gas-oil ratio (GOR) per ICV over time for three illustrative producers and Figure 17 the
cumulative gas injected (Gi) per ICV for three WAG injectors. Results show that RM obtained from
both approaches covered the range of the ensemble, with approach PE0 recording better uncertainty
representation for some cases, namely ICV1 and 2 of producer PRK028 and ICV2 of injector IRK028.
Figure 13 Risk curves for field indicators of PS0 at the time of field abandonment (2046). Green circles:
risk curves of the ensemble. Red stair-steps: risk curves for RM selected using system outputs of PS0 at
2046. Blue stair-steps: risk curves for RM selected using system outputs of PE0 at 2046.
Figure 15 Risk curves for production wells of PS0 at the time of field abandonment (2046). Green
circles: risk curves of the ensemble. Red stair-steps: risk curves for RM selected using system outputs
of PS0 at 2046. Blue stair-steps: risk curves for RM selected using system outputs of PE0 at 2046.
Figure 17 Gi time series per ICV of three injectors of PS0. Grey: ensemble. Red: RM selected using
system outputs of PS0 at 2046. Blue: RM selected using system outputs of PE0 at 2046.
Results obtained for RM selected based on approach PE0 evidence the inherent relation between the
RM and production strategy. On another note, the use of a high number of wells may have been
unfavourable to a fair evaluation of reservoir performance. Moreover, the use of a high number of
system outputs for RM selection may have hampered the procedure. This is because the more variables
we use, the more difficult it is to represent them evenly in one small set of RM. Thus, further
investigations are recommended to improve the application of approach PE0.
As expected, the normalized error is slightly higher for the RM selected for 2023 than for those obtained
directly for 2046 but are highly comparable and averaging less than 0.25. The prime advantage of using
a reduced time frame is the strong reduction of the computational costs required to simulate the
ensemble for generating system outputs for RM selection. While simulating one reservoir scenario of
the ensemble over a lifespan of 30 years takes, on average, around 1 hour and 25 minutes using 12
processors in high-performance computing, the simulation runtime for the reduced time frame takes, on
average, less than 10 minutes using the same computational infrastructure (Figure 22).
Figure 18 Risk curves for field indicators of PS0 at field abandonment (2046). Green circles: risk
curves of the ensemble. Continuous red stair-steps: risk curves for RM selected using system outputs of
PS0 at 2046. Dashed red stair-steps: risk curves for RM selected using outputs of PS0 at 2023.
Figure 20 Risk curves for production wells of PS0 at field abandonment (2046). Green circles: risk
curves of the ensemble. Continuous red stair-steps: risk curves for RM selected using system outputs of
PS0 at 2046. Dashed red stair-steps: risk curves for RM selected using system outputs of PS0 at 2023.
Figure 22 Boxplots characterizing the simulation runtime of the ensemble of 199 scenarios considering
the full lifespan of the field (September 30, 2046) and until the intermediate time (December 31, 2023).
Validation
Results obtained from previous steps were applied to a control production strategy for validation (called
PV), not used for RM selection. This strategy is not an optimized solution, representing an initial guess
of well number and placement in a production optimization procedure. To test fully our approaches, we
ensured that well placement differed from that used in PS0 and PE0.
We constructed risk curves for PV at field abandonment using four sets of RM, comparing them to
those obtained for the ensemble. These sets are the RM selected from system outputs of PS0 at 2023
and 2046, and the RM selected from system outputs of PE0 at 2023 and 2046. Similarly to the previous
sections, we show here the best RM solution (S1 to S5) for PS0 and PE0, that is, the one that recorded
the smallest mean error based on PS0 and PE0 alone (i.e., blindly for PV).
Figure 23 reveals comparable mean and range of errors for the RM selected for PS0 and PE0 at the
intermediate time (2023), with the latter recording slightly higher quartiles that PS0. Conversely, RM
selected using outputs for field abandonment (2046) lead to significantly lower errors for PE0. Not only
did the RM for PE0 recorded a smaller mean error, but the error variability was also reduced, revealing
robustness in the degree of risk curve representativeness for the main indicators. Except for two outliers
(field Gp and WEI of producer P01), the RM for PE0 recorded normalized errors lower than 0.35, while
normalized errors for PS0 went up to 0.50.
Another lesson learned from Figure 23 is that the normalized errors for RM selected using outputs of
PS0 at the intermediate date (2023) recorded lower variability than that obtained for the RM selected
using outputs at field abandonment (2046). This suggests the increasing effects of production strategy
Figure 23 Boxplots characterizing the range of errors in representativity of risk curves of PV at field
abandonment (2046) plotted using the RM selected from system outputs of PS0 and PE0. “PS0 2023”
and “PS0 2046”: RM selected from system outputs of PS0 at 2023 and 2046, respectively. “PE0 2023”
and “PE0 2046”: RM selected from system outputs of PE0 at 2023 and 2046, respectively. Crosses
mark outliers and circles the mean of each boxplot.
Figure 24 Risk curves for field indicators of PV at the time of field abandonment (2046). Yellow circles:
risk curves of the ensemble. Red stair-steps: risk curves for RM selected using system outputs of PS0 at
2046. Blue stair-steps: risk curves for RM selected using system outputs of PE0 at 2046.
Figure 26 Risk curves for production wells of PV at the time of field abandonment (2046). Yellow
circles: risk curves of the ensemble. Red stair-steps: risk curves for RM selected using system outputs
of PS0 at 2046. Blue stair-steps: risk curves for RM selected using system outputs of PE0 at 2046.
However, risk curves in Figure 24 to Figure 26 show global indicators either at field and scope level,
raising the need to verify the representativity of the RM for production and injection indicators obtained
per ICV. Visual inspection of Figure 27 and Figure 28 reveals that RM representativity is limited for
both sets in some indicators (e.g. ICV1 for I01), but has good coverage for the remaining, with slight
better representation for PE0.
Figure 28 Gi time series per ICV of WAG injectors of PS0. Grey: ensemble. Red: RM selected using
system outputs of PS0 at 2046. Blue: RM selected using system outputs of PE0 at 2046.
Given that PV has a different number and placement of wells, different ICV design and operation over
time, different WAG injection strategy, and different production unit than PE0, our results suggest that
despite having normalized errors higher than the accepted limit of 0.25, the use of PE0 ensured, to a
certain degree, improved representativity of the RM for varying production strategies, when compared
to the alternative approach that uses the base production strategy.
Conclusions
This work investigated approaches to improve the selection of representative models (RM), aiming to
ensure adequate representation of uncertainty during long-term ensemble-based production
optimization processes. We started by providing a broad theoretical background on the uncertain
reservoir system and on approaches to obtain reduced ensembles and their applications.
We investigated two main aspects related to the generation of system outputs (production, injection,
and economic indicators) for RM selection: (1) the decision variables (production strategy) used for
obtaining these indicators, and (2) the simulation time frame of the reservoir system.
Our results showed that changing decision variables affects the representativity of the RM. However,
in many cases, the RM covered the range of risk curves but failed to attain the correct probabilities of
occurrence. This suggests a possible use of the RM for ensemble-based production optimizations with
limitations related to the estimation of the probabilistic objective function. In cases with weighted
functions based on the probability of each scenario, biases may be introduced to the optimization
process. This suggests an open area for research to quantify the impacts and reduce the effects of this
mismatch on production optimization.
Using production, injection and economic indicators obtained from a base production strategy revealed
some drawbacks in RM representativeness when compared to a more robust approach based on the
evaluation of reservoir performance using a well pattern with wide reservoir and no restrictions from
production facilities. Despite similar errors across indicators, they were higher than the accepted limit,
suggesting the need for further improving this approach. The use of a high number of wells may have
been unfavourable to a fair evaluation of reservoir performance. This also led to a high number of
system outputs for RM selection, which may have hampered the procedure.
Our results also suggest that RM can be selected using production and injection indicators obtained for
an intermediate date of the simulation time frame, without requiring simulating the full lifespan of the
project. This approach benefited the generation of system outputs using an outlined production strategy
by reducing of the effects of this strategy on the forecasts of reservoir performance. Given that running
reservoir simulation of a full ensemble is computationally demanding, these findings show the potential
to accelerate analyses. To improve RM selection, this approach could be combined with data-driven
methods to estimate production and injection indicators for the remaining time frame of the project.
We used a stair-step plot to construct RM risk curves and defined the area between the RM risk curve
and the ensemble risk curve as the error measure for quantitative analyses. The low number of data
points of the RM risk curve has the inherent drawback of reduced precision when compared to the
ensemble risk curve, composed of hundreds or thousands of data points. Moreover, we calculated the
area between percentiles ~P0 and ~P100 (in our case study, cumulative probability of 0.25% and
99.75%, respectively) to capture the precision of the RM risk curve in the less-likely but high-
consequent events, represented by the two ends of the risk curve. However, increased imprecision is
To conclude, this work inferred about the adequacy of RM for ensemble-based production optimization
based on insights of the RM fitness for uncertainty quantification for varying production strategies. Our
RM showed fair uncertainty representation for different placement of wells, ICV design and operations,
and WAG injection strategies, suggesting adequacy for ensemble-based production optimization.
We focused on problems related to reservoir development, where the focus of production optimization
is on design variables and infrastructure. Further studies are suggested focusing on RM selection for
reservoirs in the production phase, where the focus of production optimization is on the management
of equipment over time.
Acknowledgements
We gratefully acknowledge the support of EPIC – Energy Production Innovation Center, hosted by the
University of Campinas (UNICAMP) and sponsored by Equinor Brazil and by FAPESP – São Paulo
Research Foundation (grant number 2017/15736-3). We acknowledge the support of ANP (Brazil’s
National Agency of Oil, Natural Gas and Biofuels) through the R&D levy regulation.
Acknowledgments are extended to the Center for Petroleum Studies (CEPETRO) and School of
Mechanical Engineering (FEM) at UNICAMP. We also acknowledge the funding from Energi
Simulation and thank the Computer Modelling Group Ltd. (CMG) and Mathworks for software licenses
and technical support.
References
Aliyev, E. and Durlofsky, L.J. [2015] Multilevel Field Development Optimization under uncertainty
using a sequence of upscaled models. Mathematical Geosciences, 49(3), 1-33.
Armstrong, M., Ndiaye, A., Razanatsimba, R. and Galli, A. [2013] Scenario reduction applied to
geostatistical simulations. Mathematical Geosciences, 45(2), 165-182.
Botechia, V.E., dos Santos, D.R., Barreto, C.E.A., da Silva Gaspar, A.T.F., da Graça Santos, S.M. and
Schiozer, D.J. [2018] Estimating the chance of success of information acquisition for the Norne
benchmark case. Oil & Gas Science and Technology–Revue d’IFP Energies nouvelles, 73, 54.
Correia, M., Hohendorff, J., Gaspar, A.T.F.S and Schiozer, D. [2015] UNISIM-II-D: Benchmark case
proposal based on a carbonate reservoir. SPE Latin American and Caribbean Petroleum
Engineering Conference, SPE-177140-MS.
Douarche, F., Da Veiga, S., Feraille, M., Enchéry, G., Touzani, S. and Barsalou, R. [2014] Sensitivity
analysis and optimization of surfactant-polymer flooding under uncertainties. Oil and Gas Science
and Technology – Rev. IFP, 69(4), 603-617.
Feraille, M. and Marrel, A. [2012] Prediction under uncertainty on a mature field. Oil and Gas Science
and Technology – Rev. IFP, 67(2), 193-206.
Ferreira, C.J., Davolio, A. and Schiozer, D.J. [2015] Improving the estimation of the chance of success
of a 4D seismic project based on representative models. EUROPEC 2015, SPE-174386-MS.
Gaspar, A.T.F.S., Santos, S.M.G., Ferreira, C.J. and Schiozer, D.J. [2020] Estimation of the chance of
success of a four-dimensional seismic project for a developed oil field. ECMOR XVII.
Helton, J.C., Davis, F.J. [2003] Latin hypercube sampling and the propagation of uncertainty in analyses
of complex systems. Reliability Engineering & System Safety, 81(1), 23-69.
Hutahaean, J., Demyanov, V. and Christie, M. [2019] Reservoir development optimization under
uncertainty for infill well placement in brownfield redevelopment. Journal of Petroleum Science
and Engineering, 175, 444-464.